Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Contingency-Constrained Transmission Expansion

Planning Considering a Representative Daily Demand


Curve

J. Isai Garcia-Mercado, G. Gutierrez-Alcaraz N. Gonzalez-Cabrera


Department of Electrical Engineering Department of Electrical Engineering
Instituto Tecnológico de Morelia Instituto Tecnológico Superior de Irapuato
Morelia Michoacán, México Irapuato Guanajuato, México
email: ggutiera@gmail.com email: nestorgc@ieee.org

Abstract The Transmission Expansion Planning (TEP) ERCOT case is used to solve the systematic planning aspect of
problem determines the optimal investments for certain the TEP problem; different operation times are used to obtain
n an electric power system. The the simulation results, which are then compared with and
TEP problem considers and implements the N-1 security criterion without contingencies. In [11], an algorithm is presented that
in all periods of planning and operation. This paper introduces a considers the load duration curve (LDC) compared to the
novel approach to reduce the computation time and memory used chronological model studies that provide similar measurements
when modeling the TEP problem considering the security criterion of generation values for utility; the LDC model provides more
N-1. Several popular commercial solvers are used to evaluate the accurate results.
computational efficiency of the proposed TEP approach.
In this paper we use a Representative Daily Load Curve
Keywords Transmission Expansion Planning; Security (RDLC) instead of LDC, so that we can better evaluate the
criterion; Investment; Transmission lines variability and spatiality of the demand and obtain a closer
estimate of the operating cost. Normally, the TEP problem with
I. INTRODUCTION security constraint N-1 considers the same contingency for all
The Transmission Expansion Planning (TEP) problem planning horizons, but this is a mistaken consideration, because
network energy flows change continually due to changing
transmission lines in an electric power system. Several methods demand. For this reason, our novel approach implements the N-
to solve the TEP problem with and without considering security 1 security criterion to solve the TEP problem.
criteria have been published in the literature. A comparison The remainder of this paper is organized as follows. Section
between the classical nonlinear formulation and the mixed -
integer disjunctive model, an alternative method, is studied in stage TEP. Section II numerically evaluates the efficiency of the
[1], where the mixed integer disjunctive formulation guarantees proposed approach, based on simulating a Garver 6-bus and an
to obtain the optimal solution, which the classical nonlinear IEEE 24-bus reliability test system (RTS). Section III concludes.
formulation does not. In [2], the contingency criterion (N-k) is
considered as a singular contingency with k components of II. TRANSMISSION EXPANSION PLANNING MODEL
simultaneous faults, and the objective function considers the
investment costs, operating costs and standby generation costs. This section explains our TEP modelling with the N-1
The modification of the security criterion can be used security criterion implemented.
effectively for the planning of the TEP in electrical markets A. Representative Daily Load Curve
where a more flexible security criterion can be taken as a Traditionally, solving the TEP problem uses the load
criterion of coverage contingencies, considering transmission duration curve (LDC) to quantify future power production costs.
lines and generators, as a way to find more reliable planning The LDC depicts the energy demand discretized from low to
than the criterion (N-1) with mixed integer linear programming high against the respective time intervals. Use of the LDC can
(MILP) [3] at less cost than (N-2) [4]. Other factors of interest also provide the sub-optimal solutions. The use of a RDLC,
are the environmental constraints, such as the cost of CO2 which is a better method of incorporating the chronological data,
emission with a loss model [5], and the high penetration of obtains closer evaluations of the variability and spatiality of
renewables, which are modeled by hour, load level, and system
demand, i.e., closer estimations of the operating cost.
state area studied in [6] - [10]. A model considering the
integration of contingency analysis is studied in [9], where the

You might also like