1. Concrete volume
a. Number of 40kg bags of Cement.
b. Volume of sand, gravel, and water.
2. Area of formwork
of the following:
`
A LOCATION MAP
B VICINITY MAP
D D
C' C'
C C
B" B"
B' B'
B B
A'' A''
A'
A A
2
3
D D
C C
B B
A A
A LEFT WING ROOF FRAMING PLAN B RIGHT WING ROOF FRAMING PLAN
1 1a 2 3 4 5
1 1a 2 3 4 5
7 6 5 4
1 1a 2 3 4 5 5 4 3 2 1a 1
D C B'' B A'' A D C B A
D D
SECOND FLOOR
TO
ROOF
GROUND FLOOR
TO
SECOND FLOOR
B' B A''
ADMINISTRATION BUILDING
C
PLAN: F-1
A
D BALCONY DETAILS 1 FOOTING DETAILS PLAN: F-2
B-1 B-8
B-1a B-9
B-1b B-10
B-2 B-11
B-2a B-12
B-2b RB-1
B-2c RB-2
B-2d RB-2a
B-3 RB-3
B-3a RB-4
B-4 RB-5
B-5 RB-6
B-6 RB-7
B-7 RB-8
Y
Y
@SUPPORT @MIDSPAN
SC-1 LB-1
FTB-1
DOOR OPENING WINDOW OPENING
2 FTB-1, SC-1 & LB-1 DETAILS
5 DOOR & WINDOW DETAILS
WF-1 WF-4
A A
Y
ELEVATION ELEVATION
A A
PLAN ELEV.
ELEV.
SECTION A-A
7 RAFTER & STRUT DETAILS 8 & SAG ROD DETAIL 9 CONNECTION DETAIL