Republic of the Philippines

Department of Public Works and Highways


QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Dalahican Road, Lucena City

Construction of Three (3) Storey Twelve


(12) Classroom Academic School
Building at San Antonio Central School,
San Antonio, Quezon

CY 2020 BEFF
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City

Date: ______________

EXECUTIVE SUMMARY

For : THE DISTRICT ENGINEER

Project ID :
Project Name : Construction of Three (3) Storey Twelve (12) Classroom
Academic School Building at San Antonio Central
School,
Location of Project : San Antonio, Quezon
2. Project Category : School Building
3. Source of Fund : CY 2020 BEFF
4. Action Recommended: For Aproval
5. Implementing Office
: DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 36,017,970.38
8. ABC : ₱ 35,928,150.00
9. Project Duration : 300 C.D.
10. Mode Implementation
: By Contract

PREPARED BY:

CESAR ANTONIO P. JADER


Architect II

SUBMITTED BY:

FAUSTINO MARK ANTHONY S. DE LA CRUZ


Chief, Planning and Design Section
HAULING DISTANCE

Project Name : Construction of Three (3) Storey Twelve (12) Classroom Academic School Building
Location : at San Antonio Central School,
Hauling Distance : 135 K.M.
UNIT COST ANALYSIS FOR AGGREGATES (SAND and GRAVEL)

Item Description : Aggregates


Assumed Quantity : 100.00 cu.m.
Source : Rizal Quarry
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at
Project :
San Antonio Central School,
Sariaya Sta. K120+000.00 (POBLACION)
C
Total Hauling Distance : 130.00 km
Terrain Condition : **With 5km free hauling distance
Flat/ Rolling, Paved : 130.00 km **From Source of Material to Point of Reference
Flat/ Rolling, Paved : 0.00 km **From Point of Reference to Project Site if Applicable
(Note: Distance established was based on Google Earth)
Working Hours : 8.00 hours

TIME MOTION ANALYSIS :

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
130.00 km x 60 mins/hr
Time when loaded = = 240.00 mins
32.5 kph
130.00 km x 60 mins/hr
Time when empty = = 164.21 mins
47.5 kph

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
0.00 km x 60 mins/hr
Time when loaded = = 0.00 mins
32.5 kph
0.00 km x 60 mins/hr
Time when empty = = 0.00 mins
47.5 kph

Loading Time = 3 mins


Unloading Time = 2 mins
Allowance for Delay:
10% of Total Time = 40.92 mins
TOTAL CYCLE TIME = 450.13 mins/trip

No. of Dumptrucks Used: 1 Dumptruck


Capacity of Dumptruck : 10 cu.m
8.00 hr/day x 60 mins/hr
No. of trips for DT per day = = 1.00 trip/day
450.13 mins/trip
Dumptruck Daily Output = 10 cu.m/trip x 1.00 trip/day = 10.00 cu.m./day
No. of Dump Trucks Used = 1 DT x 10.00 cu.m./day = 10.00 cu.m./day
100 cu.m.
No. of Days of Dumptruck = = 10.00 days
10.00 cu.m./day
Equipment Used
(Rates per Day) (Days)
1 Dumptruck = 10650 x 10.00 = 106,500.00 Php
Sub Total = 106,500.00 Php
Hauling Cost per 106,500.00 Php
= = 1065.00 Php/ cu.m.
cu.m. 100 cu.m.

Barangg Municip
Pick Up ay al Total Cost up to
ITEM Hauling Cost
Price Passwa Passwa Project Site
y y
Gravel 3/4" 750.00 5.00 10.00 1,065.00 1,830.00
Gravel G-1 580.00 5.00 10.00 1,065.00 1,660.00

Common Borrow 150.00 5.00 10.00 1,065.00 1,230.00

Sand 300.00 5.00 10.00 1,065.00 1,380.00


Boulder 720.00 5.00 10.00 1,065.00 1,800.00
COMPUTATION OF ESTIMATED PROJECT DURATION

PROJECT: Construction of Three (3) Storey Twelve (12) Classroom Academic


School Building at San Antonio Central School,

LOCATION: Sariaya

AMOUNT: ₱ 36,017,970.380

PROJECT CATEGORY: Building

Computation of Duration:

Type of Building used as reference: 3 STY 15 CL

Area of Building used as reference: 1,567.50 m²

Building Duration based on the Modified Std. 240 c.d.


DPWH - DepEd School Buildings as of July
31, 2019 (as per memorandum dated August
6, 2019 from DPWH Central Office):

Type of Building: 3 STY 12 CL

Area of Building: 1,311.00 m²

Calendar Days by Ratio: 210 c.d.

Additional Calendar Days due to New Item of 90 c.d.


Works and increase in quantity of Item of
Works due to additional structures and actual
site condition:

PROJECT DURATION : say.. 300.00 c.d.


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : Construction of Three (3) Storey Twelve (12) Classroom Academic School Building Appropriation : Php 36,017,970.38
at San Antonio Central School, Source of Fund : CY 2020 BEFF
Project ID : Target Start Date :
Location : San Antonio, Quezon Total Project Duration : 300 C.D.
Project Description : Construction of 2-Storey 10-Classroom School Buidling (with stairwall 5m
width, steel casement windowat rear portion with security grilles for the front jalousie
windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.32% 91,211.24 0.32% 91211.24
Part II Other General Requirements 5.10% 1,462,788.91 5.10% 1462788.91
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 13.70% 3,930,521.18 13.70% 3,930,521.18
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 37.68% 10,810,869.41 37.68% 10,810,869.41
PART C FINISHING WORKS & OTHER CIVIL WORKS 28.00% 8,033,211.20 28.00% 8,033,211.20
PART D ELECTRICAL WORKS 3.28% 941,474.34 3.28% 941,474.34
PART E MECHANICAL WORKS 11.93% 3,423,535.13 11.93% 3,423,535.13

Total 100% 28,693,611.41 100% 28,693,611.41

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 4,735,882.11 4,735,882.11 A. Total Direct Cost 28,693,611.41 28,693,611.41
2. Materials 21,571,247.63 21,571,247.63 B. OCM and Profit 5,523,674.31 5,523,674.31
3. Rental of Equipment 2,386,481.67 2,386,481.67 C. Value Added Tax (5%) 1,710,864.28 1,710,864.28
4. Provisional Sum / Daywork D. Total Construction Cost 35,928,150.00 35,928,150.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 5,523,674.31 5,523,674.31 E. Eng'g & Administrative Overhead, 0.25% 89,820.38 89,820.38
6. Value Added Tax (5%) 1,710,864.28 1,710,864.28 F. RROW Acquisition
7. EAO, 0.25% 89,820.38 89,820.38 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 36,017,970.38 36,017,970.38 H. TOTAL ESTIMATED COST 36,017,970.38 36,017,970.38

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Architect II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.30% 1.00 L.s. 65,236.44 21,474.80 - 86,711.24 86,711.24 8% 6,936.90 4,682.41 98,330.55
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 0.30% 1.00 L.s. 65,236.44 21,474.80 - 86,711.24 86,711.24 8% 6,936.90 4,682.41 98,330.55
As Submitted 0.02% 300.00 ea. 4,500.00 - - 15.00 4,500.00 8% 360.00 243.00 5,103.00
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.02% 300.00 ea. 4,500.00 - - 15.00 4,500.00 8% 360.00 243.00 5,103.00
As Submitted 69,736.44 21,474.80 - 91,211.24 7,296.90 4,925.41 103,433.55
TOTAL OF PART I
As Evaluated 69,736.44 21,474.80 - 91,211.24 7,296.90 4,925.41 103,433.55
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.29% 1.00 L.s. 82,678.15 - - 82,678.15 82,678.15 0% - 4,133.91 86,812.06
B.3 Permits and Clearances
As Evaluated 0.29% 1.00 L.s. 82,678.15 - - 82,678.15 82,678.15 0% - 4,133.91 86,812.06
As Submitted 0.01% 1.00 Ea 2,815.00 822.36 82.24 3,719.60 3,719.60 20% 743.92 223.18 4,686.70
B.5 Project Billboard/ Sign Board
As Evaluated 0.01% 1.00 Ea 2,815.00 822.36 82.24 3,719.60 3,719.60 20% 743.92 223.18 4,686.70
As Submitted 3.82% 1.00 L.s. 758,175.96 318,000.00 20,215.20 1,096,391.16 1,096,391.16 8% 87,711.29 59,205.12 1,243,307.57
B.7(2) Occupational Safety and Health Program
As Evaluated 3.82% 1.00 L.s. 758,175.96 318,000.00 20,215.20 1,096,391.16 1,096,391.16 8% 87,711.29 59,205.12 1,243,307.57
As Submitted 0.98% 1.00 L.s. - - 280,000.00 280,000.00 280,000.00 0% - 14,000.00 294,000.00
B.9 Mobilization/Demobilization
As Evaluated 0.98% 1.00 L.s. - - 280,000.00 280,000.00 280,000.00 0% - 14,000.00 294,000.00
As Submitted 843,669.11 318,822.36 300,297.44 1,462,788.91 88,455.21 77,562.21 1,628,806.33
TOTAL OF PART II
As Evaluated 843,669.11 318,822.36 300,297.44 1,462,788.91 88,455.21 77,562.21 1,628,806.33

(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III WORKS
PART A EARTHWORKS
As Submitted 0.38% 1.00 l.s. - 26,974.72 82,375.55 109,350.27 109,350.27 20% 21,870.05 6,561.02 137,781.34
800(2) Clearing and Grubbing
As Evaluated 0.38% 1.00 l.s. - 26,974.72 82,375.55 109,350.27 109,350.27 20% 21,870.05 6,561.02 137,781.34
As Submitted 1.04% 1.00 L.s. - 47,205.76 250,224.58 297,430.34 297,430.34 20% 59,486.07 17,845.82 374,762.23
801(1) Removal of Structure and Obstruction
As Evaluated 1.04% 1.00 L.s. - 47,205.76 250,224.58 297,430.34 297,430.34 20% 59,486.07 17,845.82 374,762.23
As Submitted 0.69% 854.76 m³ - 10,297.72 188,094.00 232.10 198,391.72 20% 39,678.34 11,903.50 249,973.56
803(1)a Structure Excavation (Common Soil)
As Evaluated 0.69% 854.76 m³ - 10,297.72 188,094.00 232.10 198,391.72 20% 39,678.34 11,903.50 249,973.56
As Submitted 0.36% 679.57 m³ - 16,640.49 87,646.23 153.46 104,286.72 20% 20,857.34 6,257.20 131,401.26
804(1)a Embankment from Structure Excavation
As Evaluated 0.36% 679.57 m³ - 16,640.49 87,646.23 153.46 104,286.72 20% 20,857.34 6,257.20 131,401.26
As Submitted 0.77% 131.10 m³ 201,566.25 3,210.22 16,908.37 1,690.96 221,684.84 20% 44,336.97 13,301.09 279,322.90
804(1)b Embankment from Borrow
As Evaluated 0.77% 131.10 m³ 201,566.25 3,210.22 16,908.37 1,690.96 221,684.84 20% 44,336.97 13,301.09 279,322.90
As Submitted 0.57% 81.42 m³ 141,915.06 16,348.46 5,807.62 2,015.12 164,071.14 20% 32,814.23 9,844.27 206,729.64
804(4) Gravel Fill
As Evaluated 0.57% 81.42 m³ 141,915.06 16,348.46 5,807.62 2,015.12 164,071.14 20% 32,814.23 9,844.27 206,729.64
As Submitted 9.88% 1.00 L.s. 2,249,552.87 473,084.80 112,668.48 2,835,306.15 2,835,306.15 20% 567,061.23 170,118.37 3,572,485.75
807(1) Site Development
As Evaluated 9.88% 1.00 L.s. 2,249,552.87 473,084.80 112,668.48 2,835,306.15 2,835,306.15 20% 567,061.23 170,118.37 3,572,485.75
As Submitted 2,593,034.18 593,762.17 743,724.83 3,930,521.18 786,104.23 235,831.27 4,952,456.68
TOTAL OF PART A
As Evaluated 2,593,034.18 593,762.17 743,724.83 3,930,521.18 786,104.23 235,831.27 4,952,456.68
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 12.26% 551.26 m³ 3,322,444.02 77,351.26 117,841.90 6,381.09 3,517,637.18 20% 703,527.44 211,058.23 4,432,222.85
900(8) Structural Concrete (27.58 Mpa @ 28 days)
As Evaluated 12.26% 551.26 m³ 3,322,444.02 77,351.26 117,841.90 6,381.09 3,517,637.18 20% 703,527.44 211,058.23 4,432,222.85
As Submitted 6.73% 38,293.18 Kg 1,556,043.37 263,591.53 111,084.16 50.42 1,930,719.06 20% 386,143.81 115,843.14 2,432,706.01
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 6.73% 38,293.18 Kg 1,556,043.37 263,591.53 111,084.16 50.42 1,930,719.06 20% 386,143.81 115,843.14 2,432,706.01
As Submitted 13.62% 75,858.09 Kg 3,164,534.01 522,170.02 220,055.68 51.50 3,906,759.71 20% 781,351.94 234,405.58 4,922,517.23
902(1)b Reinforcing Steel (Deformed), Grade 60
As Evaluated 13.62% 75,858.09 Kg 3,164,534.01 522,170.02 220,055.68 51.50 3,906,759.71 20% 781,351.94 234,405.58 4,922,517.23
As Submitted 5.07% 2,962.35 m² 607,069.94 573,782.18 274,901.34 491.42 1,455,753.46 20% 291,150.69 87,345.21 1,834,249.36
903(2) Formworks & Falseworks
As Evaluated 5.07% 2,962.35 m² 607,069.94 573,782.18 274,901.34 491.42 1,455,753.46 20% 291,150.69 87,345.21 1,834,249.36
As Submitted 8,650,091.34 1,436,894.99 723,883.08 10,810,869.41 2,162,173.88 648,652.16 13,621,695.45
TOTAL OF PART B
As Evaluated 8,650,091.34 1,436,894.99 723,883.08 10,810,869.41 2,162,173.88 648,652.16 13,621,695.45
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART C FACILITIES FOR THE ENGINEER
FINISHING
C.1 Termite Control Works
As Submitted 0.28% 264.64 L 67,483.20 12,538.06 1,253.81 307.12 81,275.07 20% 16,255.01 4,876.50 102,406.58
1000(1) Soil Poisoning
As Evaluated 0.28% 264.64 L 67,483.20 12,538.06 1,253.81 307.12 81,275.07 20% 16,255.01 4,876.50 102,406.58
As Submitted 67,483.20 12,538.06 1,253.81 81,275.07 16,255.01 4,876.50 102,406.58
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.71% 321.70 m² 155,847.57 31,222.14 17,588.20 636.18 204,657.91 20% 40,931.58 12,279.47 257,868.96
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel), 100mm
As Evaluated 0.71% 321.70 m² 155,847.57 31,222.14 17,588.20 636.18 204,657.91 20% 40,931.58 12,279.47 257,868.96
As Submitted 2.69% 812.29 m² 623,188.89 94,825.92 53,417.77 949.70 771,432.58 20% 154,286.52 46,285.96 972,005.06
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 2.69% 812.29 m² 623,188.89 94,825.92 53,417.77 949.70 771,432.58 20% 154,286.52 46,285.96 972,005.06
As Submitted 779,036.46 126,048.06 71,005.97 976,090.49 195,218.10 58,565.43 1,229,874.02
Sub - Total C.2
As Evaluated 779,036.46 126,048.06 71,005.97 976,090.49 195,218.10 58,565.43 1,229,874.02
C.3 Fabricated Materials
As Submitted 0.63% 1.00 L.s. 129,103.80 46,052.16 4,605.22 179,761.18 179,761.18 20% 35,952.24 10,785.67 226,499.09
1010(4) Wooden Doors & Windows
As Evaluated 0.63% 1.00 L.s. 129,103.80 46,052.16 4,605.22 179,761.18 179,761.18 20% 35,952.24 10,785.67 226,499.09
As Submitted 0.17% 34.65 m² 24,255.00 22,261.54 2,226.15 1,406.72 48,742.69 20% 9,748.54 2,924.56 61,415.79
1010(2)a Door (Flush)
As Evaluated 0.17% 34.65 m² 24,255.00 22,261.54 2,226.15 1,406.72 48,742.69 20% 9,748.54 2,924.56 61,415.79
As Submitted 1.13% 51.84 m² 285,120.00 36,840.96 3,684.10 6,281.73 325,645.06 20% 65,129.01 19,538.70 410,312.77
1010(2)b Door (Wooden Panel)
As Evaluated 1.13% 51.84 m² 285,120.00 36,840.96 3,684.10 6,281.73 325,645.06 20% 65,129.01 19,538.70 410,312.77
As Submitted 0.19% 1.00 L.s. 40,800.00 13,157.76 1,315.78 55,273.54 55,273.54 20% 11,054.71 3,316.41 69,644.66
1003(17) Carpentry and Joinery Works
As Evaluated 0.19% 1.00 L.s. 40,800.00 13,157.76 1,315.78 55,273.54 55,273.54 20% 11,054.71 3,316.41 69,644.66
As Submitted 0.07% 3.12 m² 17,160.00 2,467.08 1,419.71 6,745.77 21,046.79 20% 4,209.36 1,262.81 26,518.96
1006(4) Steel Louver Door
As Evaluated 0.07% 3.12 m² 17,160.00 2,467.08 1,419.71 6,745.77 21,046.79 20% 4,209.36 1,262.81 26,518.96
As Submitted 1.89% 142.56 m² 284,407.20 162,827.28 93,700.73 3,794.44 540,935.21 20% 108,187.04 32,456.11 681,578.36
1005(1) Residential Casement Steel Window
As Evaluated 1.89% 142.56 m² 284,407.20 162,827.28 93,700.73 3,794.44 540,935.21 20% 108,187.04 32,456.11 681,578.36
As Submitted 0.63% 57.60 m² 131,826.82 43,859.20 4,385.92 3,126.25 180,071.94 20% 36,014.39 10,804.32 226,890.65
1009(1)a Jalousie Window (Glass)
As Evaluated 0.63% 57.60 m² 131,826.82 43,859.20 4,385.92 3,126.25 180,071.94 20% 36,014.39 10,804.32 226,890.65
As Submitted 0.33% 1.00 L.s. 67,064.37 23,026.08 3,866.61 93,957.06 93,957.06 20% 18,791.41 5,637.42 118,385.89
1005(6) Window Accessory
As Evaluated 0.33% 1.00 L.s. 67,064.37 23,026.08 3,866.61 93,957.06 93,957.06 20% 18,791.41 5,637.42 118,385.89
As Submitted 0.09% 1.00 L.s. 26,860.00 - - 26,860.00 26,860.00 20% 5,372.00 1,611.60 33,843.60
1004(2) Finishing Hardware
As Evaluated 0.09% 1.00 L.s. 26,860.00 - - 26,860.00 26,860.00 20% 5,372.00 1,611.60 33,843.60
As Submitted 1.56% 1.00 L.s. 324,461.34 67,436.80 55,481.68 447,379.82 447,379.82 20% 89,475.96 26,842.79 563,698.57
1051(6) Railing
As Evaluated 1.56% 1.00 L.s. 324,461.34 67,436.80 55,481.68 447,379.82 447,379.82 20% 89,475.96 26,842.79 563,698.57
As Submitted 1,331,058.53 417,928.86 170,685.90 1,919,673.29 383,934.66 115,180.39 2,418,788.34
Sub-Total C.3
As Evaluated 1,331,058.53 417,928.86 170,685.90 1,919,673.29 383,934.66 115,180.39 2,418,788.34
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.4 Finishing Works FACILITIES FOR THE ENGINEER
As Submitted 1.75% 2,836.23 m² 318,395.18 167,777.43 16,777.74 177.33 502,950.35 20% 100,590.07 30,177.02 633,717.44
1027(1) Cement Plaster Finish
As Evaluated 1.75% 2,836.23 m² 318,395.18 167,777.43 16,777.74 177.33 502,950.35 20% 100,590.07 30,177.02 633,717.44
As Submitted 0.50% 1,327.38 m² - 68,285.34 75,986.15 108.69 144,271.49 20% 28,854.30 8,656.29 181,782.08
1021(1)a Cement Floor Finish (Plain)
As Evaluated 0.50% 1,327.38 m² - 68,285.34 75,986.15 108.69 144,271.49 20% 28,854.30 8,656.29 181,782.08
As Submitted 1.35% 455.11 m² 282,910.03 93,672.84 9,367.28 848.04 385,950.15 20% 77,190.03 23,157.01 486,297.19
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
As Evaluated 1.35% 455.11 m² 282,910.03 93,672.84 9,367.28 848.04 385,950.15 20% 77,190.03 23,157.01 486,297.19
As Submitted 0.01% 18.00 Lm 3,420.90 388.35 38.84 213.78 3,848.09 20% 769.62 230.89 4,848.60
1003(11)a1 Fascia Board (19mm, Fiber Cement Board)
As Evaluated 0.01% 18.00 Lm 3,420.90 388.35 38.84 213.78 3,848.09 20% 769.62 230.89 4,848.60
As Submitted 0.29% 436.71 m² 61,903.64 20,094.94 2,009.49 192.37 84,008.07 20% 16,801.61 5,040.48 105,850.16
1038(1) Reflective Insulation
As Evaluated 0.29% 436.71 m² 61,903.64 20,094.94 2,009.49 192.37 84,008.07 20% 16,801.61 5,040.48 105,850.16
As Submitted 1.05% 196.24 m² 196,392.85 95,913.20 9,591.32 1,538.41 301,897.37 20% 60,379.47 18,113.84 380,390.68
1018(1) Glazed Tiles and Trims
As Evaluated 1.05% 196.24 m² 196,392.85 95,913.20 9,591.32 1,538.41 301,897.37 20% 60,379.47 18,113.84 380,390.68
As Submitted 0.27% 82.91 m² 44,910.19 28,365.85 2,836.58 918.01 76,112.62 20% 15,222.52 4,566.76 95,901.90
1018(2) Unlglazed Tiles
As Evaluated 0.27% 82.91 m² 44,910.19 28,365.85 2,836.58 918.01 76,112.62 20% 15,222.52 4,566.76 95,901.90
As Submitted 0.23% 377.62 m² 21,807.56 41,405.28 4,140.53 178.36 67,353.37 20% 13,470.67 4,041.20 84,865.24
1016(1)a Water Proofing Cement Base
As Evaluated 0.23% 377.62 m² 21,807.56 41,405.28 4,140.53 178.36 67,353.37 20% 13,470.67 4,041.20 84,865.24
As Submitted 929,740.35 515,903.23 120,747.93 1,566,391.51 313,278.29 93,983.49 1,973,653.29
Sub-Total C.4
As Evaluated 929,740.35 515,903.23 120,747.93 1,566,391.51 313,278.29 93,983.49 1,973,653.29
C.5 Painting Works
As Submitted 3.30% 3,614.79 m² 434,436.31 466,015.28 46,601.53 261.99 947,053.12 20% 189,410.62 56,823.19 1,193,286.93
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 3.30% 3,614.79 m² 434,436.31 466,015.28 46,601.53 261.99 947,053.12 20% 189,410.62 56,823.19 1,193,286.93
As Submitted 0.26% 292.01 m² 28,557.70 41,828.50 4,182.85 255.36 74,569.05 20% 14,913.81 4,474.14 93,957.00
1032(1)b Painting Works (Wood Painting)
As Evaluated 0.26% 292.01 m² 28,557.70 41,828.50 4,182.85 255.36 74,569.05 20% 14,913.81 4,474.14 93,957.00
As Submitted 0.19% 215.57 m² 22,010.13 29,180.63 2,918.06 251.00 54,108.82 20% 10,821.76 3,246.53 68,177.11
1032(1)c Painting Works (Steel)
As Evaluated 0.19% 215.57 m² 22,010.13 29,180.63 2,918.06 251.00 54,108.82 20% 10,821.76 3,246.53 68,177.11
As Submitted 485,004.14 537,024.41 53,702.44 1,075,730.99 215,146.19 64,543.86 1,355,421.04
Sub-Total C.5
As Evaluated 485,004.14 537,024.41 53,702.44 1,075,730.99 215,146.19 64,543.86 1,355,421.04
C.6 Roof Framing and Roofing Works
As Submitted 0.96% 487.40 m² 209,845.20 60,065.71 6,006.57 566.10 275,917.48 20% 55,183.50 16,555.05 347,656.03
1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
As Evaluated 0.96% 487.40 m² 209,845.20 60,065.71 6,006.57 566.10 275,917.48 20% 55,183.50 16,555.05 347,656.03
As Submitted 1.67% 5,587.70 Kg 368,427.51 32,251.11 78,732.85 85.80 479,411.47 20% 95,882.29 28,764.69 604,058.45
1047(2)a Structural Steel (Trusses)
As Evaluated 1.67% 5,587.70 Kg 368,427.51 32,251.11 78,732.85 85.80 479,411.47 20% 95,882.29 28,764.69 604,058.45
As Submitted 1.74% 6,110.13 Kg 418,299.50 28,472.06 52,971.21 81.79 499,742.77 20% 99,948.55 29,984.57 629,675.89
1047(2)b Structural Steel (Purlins)
As Evaluated 1.74% 6,110.13 kg 418,299.50 28,472.06 52,971.21 81.79 499,742.77 20% 99,948.55 29,984.57 629,675.89
As Submitted 0.25% 862.40 Kg 55,961.14 13,643.77 1,364.38 82.29 70,969.29 20% 14,193.86 4,258.16 89,421.31
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 0.25% 862.40 Kg 55,961.14 13,643.77 1,364.38 82.29 70,969.29 20% 14,193.86 4,258.16 89,421.31
As Submitted 0.03% 157.50 Kgs 6,264.41 2,491.76 249.18 57.18 9,005.35 20% 1,801.07 540.32 11,346.74
1047(7)b Metal Structure Accessories (Sagrods)
As Evaluated 0.03% 157.50 Kgs 6,264.41 2,491.76 249.18 57.18 9,005.35 20% 1,801.07 540.32 11,346.74
As Submitted 0.08% 397.16 Kgs 16,270.54 6,283.35 628.33 58.37 23,182.22 20% 4,636.44 1,390.93 29,209.59
1047(4) Metal Structure Accessories (Crossbracing)
As Evaluated 0.08% 397.16 Kgs 16,270.54 6,283.35 628.33 58.37 23,182.22 20% 4,636.44 1,390.93 29,209.59
As Submitted 0.04% 44.00 ea. 8,800.00 1,356.89 135.69 233.92 10,292.58 20% 2,058.52 617.56 12,968.66
1047(3)c Metal Structure Accessories (Turnbuckle)
As Evaluated 0.04% 44.00 ea. 8,800.00 1,356.89 135.69 233.92 10,292.58 20% 2,058.52 617.56 12,968.66
As Submitted 0.04% 46.00 L.m. 9,558.92 945.71 94.57 230.42 10,599.20 20% 2,119.84 635.95 13,354.99
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
As Evaluated 0.04% 46.00 L.m. 9,558.92 945.71 94.57 230.42 10,599.20 20% 2,119.84 635.95 13,354.99
As Submitted 0.02% 22.32 L.m. 4,517.46 458.88 45.89 225.01 5,022.23 20% 1,004.45 301.33 6,328.01
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
As Evaluated 0.02% 22.32 L.m. 4,517.46 458.88 45.89 225.01 5,022.23 20% 1,004.45 301.33 6,328.01
As Submitted 0.01% 10.00 L.m. 3,285.70 174.23 17.42 347.74 3,477.35 20% 695.47 208.64 4,381.46
1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)
As Evaluated 0.01% 10.00 L.m. 3,285.70 174.23 17.42 347.74 3,477.35 20% 695.47 208.64 4,381.46
As Submitted 1,101,230.38 146,143.47 140,246.09 1,387,619.94 277,523.99 83,257.20 1,748,401.13
Sub-Total C.6
As Evaluated 1,101,230.38 146,143.47 140,246.09 1,387,619.94 277,523.99 83,257.20 1,748,401.13
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.7 Plumbing / Sanitary FACILITIES
Works FOR THE ENGINEER
As Submitted 0.50% 1.00 L.s. 108,876.68 30,700.80 3,070.08 142,647.56 142,647.56 20% 28,529.51 8,558.85 179,735.92
1001(8) Sewer Line Works
As Evaluated 0.50% 1.00 L.s. 108,876.68 30,700.80 3,070.08 142,647.56 142,647.56 20% 28,529.51 8,558.85 179,735.92
As Submitted 0.66% 1.00 L.s. 149,702.46 36,840.96 3,684.10 190,227.52 190,227.52 20% 38,045.50 11,413.65 239,686.67
1002(24) Cold Water lines
As Evaluated 0.66% 1.00 L.s. 149,702.46 36,840.96 3,684.10 190,227.52 190,227.52 20% 38,045.50 11,413.65 239,686.67
As Submitted 0.62% 1.00 L.s. 133,254.43 40,462.08 4,046.21 177,762.72 177,762.72 20% 35,552.54 10,665.76 223,981.02
1001(9) Storm Drainage and Downspout
As Evaluated 0.62% 1.00 L.s. 133,254.43 40,462.08 4,046.21 177,762.72 177,762.72 20% 35,552.54 10,665.76 223,981.02
As Submitted 1.21% 1.00 L.s. 273,623.16 65,788.80 6,578.88 345,990.84 345,990.84 20% 69,198.17 20,759.45 435,948.46
1002(4) Plumbing FIxtures
As Evaluated 1.21% 1.00 L.s. 273,623.16 65,788.80 6,578.88 345,990.84 345,990.84 20% 69,198.17 20,759.45 435,948.46
As Submitted 0.49% 1.00 L.s. 122,079.11 16,306.50 1,630.65 140,016.26 140,016.26 20% 28,003.25 8,400.98 176,420.49
1001(11) Septic Vault (Concrete / CHB)
As Evaluated 0.49% 1.00 L.s. 122,079.11 16,306.50 1,630.65 140,016.26 140,016.26 20% 28,003.25 8,400.98 176,420.49
As Submitted 0.10% 20.00 Ea 20,739.05 8,223.60 822.36 1,489.25 29,785.01 20% 5,957.00 1,787.10 37,529.11
1001(5)b Catch Basin (CHB)
As Evaluated 0.10% 20.00 Ea 20,739.05 8,223.60 822.36 1,489.25 29,785.01 20% 5,957.00 1,787.10 37,529.11
As Submitted 808,274.89 198,322.74 19,832.28 1,026,429.91 205,285.97 61,585.79 1,293,301.67
Sub-Total C.7
As Evaluated 808,274.89 198,322.74 19,832.28 1,026,429.91 205,285.97 61,585.79 1,293,301.67
As Submitted 5,501,827.95 1,953,908.83 577,474.42 8,033,211.20 1,606,642.21 481,992.66 10,121,846.07
TOTAL OF PART C
As Evaluated 5,501,827.95 1,953,908.83 577,474.42 8,033,211.20 1,606,642.21 481,992.66 10,121,846.07
PART D ELECTRICAL WORKS
As Submitted 0.33% 1.00 L.s. 79,099.20 15,348.96 1,534.90 95,983.06 95,983.06 20% 19,196.61 5,758.98 120,938.65
1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in)
As Evaluated 0.33% 1.00 L.s. 79,099.20 15,348.96 1,534.90 95,983.06 95,983.06 20% 19,196.61 5,758.98 120,938.65
As Submitted 0.86% 1.00 L.s. 206,799.00 37,519.68 3,751.97 248,070.65 248,070.65 20% 49,614.13 14,884.24 312,569.02
1101(33) Wires and Wiring Devices
As Evaluated 0.86% 1.00 L.s. 206,799.00 37,519.68 3,751.97 248,070.65 248,070.65 20% 49,614.13 14,884.24 312,569.02
As Submitted 1.21% 1.00 L.s. 334,492.40 10,537.20 1,053.72 346,083.32 346,083.32 20% 69,216.66 20,765.00 436,064.98
1102(1) Panel Board with Main Breaker
As Evaluated 1.21% 1.00 L.s. 334,492.40 10,537.20 1,053.72 346,083.32 346,083.32 20% 69,216.66 20,765.00 436,064.98
As Submitted 0.88% 1.00 L.s. 209,610.00 37,933.92 3,793.39 251,337.31 251,337.31 20% 50,267.46 15,080.24 316,685.01
1103(1) Lighting Fixtures & Lamps
As Evaluated 0.88% 1.00 L.s. 209,610.00 37,933.92 3,793.39 251,337.31 251,337.31 20% 50,267.46 15,080.24 316,685.01
As Submitted 830,000.60 101,339.76 10,133.98 941,474.34 188,294.86 56,488.46 1,186,257.66
TOTAL OF PART D
As Evaluated 830,000.60 101,339.76 10,133.98 941,474.34 188,294.86 56,488.46 1,186,257.66
PART E MECHANICAL WORKS
As Submitted 11.78% 1.00 L.s. 3,046,668.01 303,465.60 30,346.56 3,380,480.17 3,380,480.17 20% 676,096.03 202,828.81 4,259,405.01
1202(1) Automatic Water Sprinkler
As Evaluated 11.78% 1.00 L.s. 3,046,668.01 303,465.60 30,346.56 3,380,480.17 3,380,480.17 20% 676,096.03 202,828.81 4,259,405.01
As Submitted 0.15% 1.00 L.s. 36,220.00 6,213.60 621.36 43,054.96 43,054.96 20% 8,610.99 2,583.30 54,249.25
1208(1) Fire Alarm System
As Evaluated 0.15% 1.00 L.s. 36,220.00 6,213.60 621.36 43,054.96 43,054.96 20% 8,610.99 2,583.30 54,249.25
As Submitted 3,082,888.01 309,679.20 30,967.92 3,423,535.13 684,707.02 205,412.11 4,313,654.26
TOTAL OF PART E
As Evaluated 3,082,888.01 309,679.20 30,967.92 3,423,535.13 684,707.02 205,412.11 4,313,654.26
As Submitted 20,657,842.08 4,395,584.95 2,086,184.23 27,139,611.26 5,427,922.20 1,628,376.66 34,195,910.12
TOTAL OF PART III
As Evaluated 20,657,842.08 4,395,584.95 2,086,184.23 27,139,611.26 5,427,922.20 1,628,376.66 34,195,910.12
As Submitted 20,657,842.08 4,395,584.95 2,086,184.23 27,139,611.26 5,427,922.20 1,628,376.66 34,195,910.12
TOTAL OF (Project ID)
As Evaluated 20,657,842.08 4,395,584.95 2,086,184.23 27,139,611.26 5,427,922.20 1,628,376.66 34,195,910.12
As Submitted 21,571,247.63 4,735,882.11 2,386,481.67 28,693,611.41 5,523,674.31 1,710,864.28 35,928,150.00
GRAND TOTAL
As Evaluated 21,571,247.63 4,735,882.11 2,386,481.67 28,693,611.41 5,523,674.31 1,710,864.28 35,928,150.00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

PART I FACILITIES FOR THE ENGINEER

I.1.1 Offices and Laboratory for the Engineer


A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 L.s. 86,711.24 86,711.24 86,711.24 86,711.24 98,330.55 98,330.55 0.30% 0.30%

A.1.4(1) Provision of Progress Photographs 300.00 300.00 ea. 4,500.00 4,500.00 15.00 15.00 17.01 17.01 0.02% 0.02%

TOTAL OF PART I 91,211.24

PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances 1.00 1.00 L.s. 82,678.15 82,678.15 82,678.15 82,678.15 86,812.06 86,812.06 0.29% 0.29%

B.5 Project Billboard/ Sign Board 1.00 1.00 Ea 3,719.60 3,719.60 3,719.60 3,719.60 4,686.70 4,686.70 0.01% 0.01%

B.7(2) Occupational Safety and Health Program 1.00 1.00 L.s. 1,096,391.16 1,096,391.16 1,096,391.16 1,096,391.16 1,243,307.57 1,243,307.57 3.82% 3.82%

B.9 Mobilization/Demobilization 1.00 1.00 L.s. 280,000.00 280,000.00 280,000.00 280,000.00 294,000.00 294,000.00 0.98% 0.98%

TOTAL OF PART II 1,462,788.91

Project ID

(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

PART A EARTHWORKS

800(2) Clearing and Grubbing 1.00 1.00 l.s. 109,350.27 109,350.27 109,350.27 109,350.27 137,781.34 137,781.34 0.38% 0.38%

801(1) Removal of Structure and Obstruction 1.00 1.00 L.s. 297,430.34 297,430.34 297,430.34 297,430.34 374,762.23 374,762.23 1.04% 1.04%

803(1)a Structure Excavation (Common Soil) 854.76 854.76 m³ 198,391.72 198,391.72 232.10 232.10 292.45 292.45 0.69% 0.69%

804(1)a Embankment from Structure Excavation 679.57 679.57 m³ 104,286.72 104,286.72 153.46 153.46 193.36 193.36 0.36% 0.36%

804(1)b Embankment from Borrow 131.10 131.10 m³ 221,684.84 221,684.84 1,690.96 1,690.96 2,130.61 2,130.61 0.77% 0.77%

804(4) Gravel Fill 81.42 81.42 m³ 164,071.14 164,071.14 2,015.12 2,015.12 2,539.05 2,539.05 0.57% 0.57%

807(1) Site Development 1.00 1.00 L.s. 2,835,306.15 2,835,306.15 2,835,306.15 2,835,306.15 3,572,485.75 3,572,485.75 9.88% 9.88%

TOTAL OF PART A 3,930,521.18

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(8) Structural Concrete (27.58 Mpa @ 28 days) 551.26 551.26 m³ 3,517,637.18 3,517,637.18 6,381.09 6,381.09 8,040.17 8,040.17 12.26% 12.26%

902(1)a Reinforcing Steel (Deformed) Grade 40 38,293.18 38,293.18 Kg 1,930,719.06 1,930,719.06 50.42 50.42 63.53 63.53 6.73% 6.73%

902(1)b Reinforcing Steel (Deformed), Grade 60 75,858.09 75,858.09 Kg 3,906,759.71 3,906,759.71 51.50 51.50 64.89 64.89 13.62% 13.62%

903(2) Formworks & Falseworks 2,962.35 2,962.35 m² 1,455,753.46 1,455,753.46 491.42 491.42 619.19 619.19 5.07% 5.07%

TOTAL OF PART B 10,810,869.41

PART C FINISHING

C.1 Termite Control Works


1000(1) Soil Poisoning 264.64 264.64 L 81,275.07 81,275.07 307.12 307.12 102,406.58 102,406.58 0.28% 0.28%

Sub-Total C.1 81,275.07


Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

C.2. Masonry Works FACILITIES FOR THE ENGINEER

1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel), 100mm 321.70 321.70 m² 204,657.91 204,657.91 636.18 636.18 801.58 801.58 0.71% 0.71%

1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm 812.29 812.29 m² 771,432.58 771,432.58 949.70 949.70 1,196.62 1,196.62 2.69% 2.69%

Sub-Total C.2 976,090.49

C.3 Fabricated Materials


1010(4) Wooden Doors & Windows 1.00 1.00 L.s. 179,761.18 179,761.18 179,761.18 179,761.18 226,499.09 226,499.09 0.63% 0.63%

1010(2)a Door (Flush) 34.65 34.65 m² 48,742.69 48,742.69 1,406.72 1,406.72 1,772.46 1,772.46 0.17% 0.17%

1010(2)b Door (Wooden Panel) 51.84 51.84 m² 325,645.06 325,645.06 6,281.73 6,281.73 410,312.77 410,312.77 1.13% 1.13%

1003(17) Carpentry and Joinery Works 1.00 1.00 L.s. 55,273.54 55,273.54 55,273.54 55,273.54 69,644.66 69,644.66 0.19% 0.19%

1006(4) Steel Louver Door 3.12 3.12 m² 21,046.79 21,046.79 6,745.77 6,745.77 8,499.67 8,499.67 0.07% 0.07%

1005(1) Residential Casement Steel Window 142.56 142.56 m² 540,935.21 540,935.21 3,794.44 3,794.44 681,578.36 681,578.36 1.89% 1.89%

1009(1)a Jalousie Window (Glass) 57.60 57.60 m² 180,071.94 180,071.94 3,126.25 3,126.25 226,890.65 226,890.65 0.63% 0.63%

1005(6) Window Accessory 1.00 1.00 L.s. 93,957.06 93,957.06 93,957.06 93,957.06 118,385.89 118,385.89 0.33% 0.33%

1004(2) Finishing Hardware 1.00 1.00 L.s. 26,860.00 26,860.00 26,860.00 26,860.00 33,843.60 33,843.60 0.09% 0.09%

1051(6) Railing 1.00 1.00 L.s. 447,379.82 447,379.82 447,379.82 447,379.82 563,698.57 563,698.57 1.56% 1.56%

Sub-Total C.3 1,919,673.29

C.4 Finishing Works


1027(1) Cement Plaster Finish 2,836.23 2,836.23 m² 502,950.35 502,950.35 177.33 177.33 223.44 223.44 1.75% 1.75%

1021(1)a Cement Floor Finish (Plain) 1,327.38 1,327.38 m² 144,271.49 144,271.49 108.69 108.69 136.95 136.95 0.50% 0.50%

1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board) 455.11 455.11 m² 385,950.15 385,950.15 848.04 848.04 1,068.53 1,068.53 1.35% 1.35%

1003(11)a1 Fascia Board (19mm, Fiber Cement Board) 18.00 18.00 Lm 3,848.09 3,848.09 213.78 213.78 269.37 269.37 0.01% 0.01%

1038(1) Reflective Insulation 436.71 436.71 m² 84,008.07 84,008.07 192.37 192.37 242.38 242.38 0.29% 0.29%

1018(1) Glazed Tiles and Trims 196.24 196.24 m² 301,897.37 301,897.37 1,538.41 1,538.41 1,938.40 1,938.40 1.05% 1.05%

1018(2) Unlglazed Tiles 82.91 82.91 m² 76,112.62 76,112.62 918.01 918.01 1,156.70 1,156.70 0.27% 0.27%

1016(1)a Water Proofing Cement Base 377.62 377.62 m² 67,353.37 67,353.37 178.36 178.36 224.74 224.74 0.23% 0.23%

Sub-Total C.4 1,566,391.51

C.5 Painting Works


1032(1)a Painting Works (Masonry/Concrete) 3,614.79 3,614.79 m² 947,053.12 947,053.12 261.99 261.99 330.11 330.11 3.30% 3.30%

1032(1)b Painting Works (Wood Painting) 292.01 292.01 m² 74,569.05 74,569.05 255.36 255.36 321.76 321.76 0.26% 0.26%

1032(1)c Painting Works (Steel) 215.57 215.57 m² 54,108.82 54,108.82 251.00 251.00 316.26 316.26 0.19% 0.19%

Sub-Total C.5 1,075,730.99

C.6 Roof Framing and Roofing Works


1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk 487.40 487.40 m² 275,917.48 275,917.48 566.10 566.10 713.29 713.29 0.96% 0.96%
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

1047(2)a Structural Steel (Trusses) FACILITIES FOR THE ENGINEER 5,587.70 5,587.70 Kg 479,411.47 479,411.47 85.80 85.80 108.11 108.11 1.67% 1.67%

1047(2)b Structural Steel (Purlins) 6,110.13 6,110.13 Kg 499,742.77 499,742.77 81.79 81.79 103.05 103.05 1.74% 1.74%

1047(6) Metal Structure Accessories (Steel Plates) 862.40 862.40 Kg 70,969.29 70,969.29 82.29 82.29 103.69 103.69 0.25% 0.25%

1047(7)b Metal Structure Accessories (Sagrods) 157.50 157.50 Kgs 9,005.35 9,005.35 57.18 57.18 72.04 72.04 0.03% 0.03%

1047(4) Metal Structure Accessories (Crossbracing) 397.16 397.16 Kgs 23,182.22 23,182.22 58.37 58.37 73.55 73.55 0.08% 0.08%

1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 44.00 ea. 10,292.58 10,292.58 233.92 233.92 12,968.66 12,968.66 0.04% 0.04%

1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26) 46.00 46.00 L.m. 10,599.20 10,599.20 230.42 230.42 13,354.99 13,354.99 0.04% 0.04%

1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26) 22.32 22.32 L.m. 5,022.23 5,022.23 225.01 225.01 6,328.01 6,328.01 0.02% 0.02%

1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter) 10.00 10.00 L.m. 3,477.35 3,477.35 347.74 347.74 4,381.46 4,381.46 0.01% 0.01%

Sub-Total C.6 1,387,619.94

TOTAL OF PART C

C.7 PLUMBING/SANITARY WORKS

1001(8) Sewer Line Works 1.00 1.00 L.s. 142,647.56 142,647.56 142,647.56 142,647.56 179,735.92 179,735.92 0.50% 0.50%

1002(24) Cold Water lines 1.00 1.00 L.s. 190,227.52 190,227.52 190,227.52 190,227.52 239,686.67 239,686.67 0.66% 0.66%

1001(9) Storm Drainage and Downspout 1.00 1.00 L.s. 177,762.72 177,762.72 177,762.72 177,762.72 223,981.02 223,981.02 0.62% 0.62%

1002(4) Plumbing FIxtures 1.00 1.00 L.s. 345,990.84 345,990.84 345,990.84 345,990.84 435,948.46 435,948.46 1.21% 1.21%

1001(11) Septic Vault (Concrete / CHB) 1.00 1.00 L.s. 140,016.26 140,016.26 140,016.26 140,016.26 176,420.49 176,420.49 0.49% 0.49%

1001(5)b Catch Basin (CHB) 20.00 20.00 Ea 29,785.01 29,785.01 1,489.25 1,489.25 1,876.46 1,876.46 0.10% 0.10%

Sub-Total C.7 1,026,429.91

TOTAL OF PART C 8,033,211.20

PART D ELECTRICAL WORKS

1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in) 1.00 1.00 L.s. 95,983.06 95,983.06 95,983.06 95,983.06 120,938.65 120,938.65 0.33% 0.33%

1101(33) Wires and Wiring Devices 1.00 1.00 L.s. 248,070.65 248,070.65 248,070.65 248,070.65 312,569.02 312,569.02 0.86% 0.86%

1102(1) Panel Board with Main Breaker 1.00 1.00 L.s. 346,083.32 346,083.32 346,083.32 346,083.32 436,064.98 436,064.98 1.21% 1.21%

1103(1) Lighting Fixtures & Lamps 1.00 1.00 L.s. 251,337.31 251,337.31 251,337.31 251,337.31 316,685.01 316,685.01 0.88% 0.88%

TOTAL OF PART D 941,474.34

PART E MECHANICAL WORKS

1202(1) Automatic Water Sprinkler 1.00 1.00 L.s. 3,380,480.17 3,380,480.17 3,380,480.17 3,380,480.17 4,259,405.01 4,259,405.01 11.78% 11.78%

1208(1) Fire Alarm System 1.00 1.00 L.s. 43,054.96 43,054.96 43,054.96 43,054.96 54,249.25 54,249.25 0.15% 0.15%

TOTAL OF PART D 3,423,535.13

TOTAL OF PART III 27,139,611.26

TOTAL OF (Project ID) 27,139,611.26

GRAND TOTAL 28,693,611.41 100.00% 100.00%


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 91,211.24 8.00% 7,296.90 4,925.41 12,222.31 103,433.55
PART I FACILITIES FOR THE ENGINEER
AS EVALUATED 91,211.24 8.00% 7,296.90 4,925.41 12,222.31 103,433.55
AS SUBMITTED 1,462,788.91 0.00% 88,455.21 77,562.21 166,017.42 1,628,806.33
PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED 1,462,788.91 0.00% 88,455.21 77,562.21 166,017.42 1,628,806.33

(Project ID)
(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

AS SUBMITTED 3,930,521.18 20.00% 786,104.23 235,831.27 1,021,935.50 4,952,456.68


PART A EARTHWORKS
AS EVALUATED 3,930,521.18 20.00% 786,104.23 235,831.27 1,021,935.50 4,952,456.68
AS SUBMITTED 10,810,869.41 20.00% 2,162,173.88 648,652.16 2,810,826.04 13,621,695.45
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS EVALUATED 10,810,869.41 20.00% 2,162,173.88 648,652.16 2,810,826.04 13,621,695.45
AS SUBMITTED 8,033,211.20 20.00% 1,606,642.21 481,992.66 2,088,634.87 10,121,846.07
PART C FINISHING
AS EVALUATED 8,033,211.20 20.00% 1,606,642.21 481,992.66 2,088,634.87 10,121,846.07
AS SUBMITTED 941,474.34 20.00% 188,294.86 56,488.46 244,783.32 1,186,257.66
PART D ELECTRICAL WORKS
AS EVALUATED 941,474.34 20.00% 188,294.86 56,488.46 244,783.32 1,186,257.66
AS SUBMITTED 3,423,535.13 20.00% 684,707.02 205,412.11 890,119.13 4,313,654.26
PART E MECHANICAL WORKS
AS EVALUATED 3,423,535.13 20.00% 684,707.02 205,412.11 890,119.13 4,313,654.26
AS SUBMITTED 27,139,611.26 20.00% 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
TOTAL OF PART III
AS EVALUATED 27,139,611.26 20.00% 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
AS SUBMITTED 27,139,611.26 20.00% 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
TOTAL OF (Project ID)
AS EVALUATED 27,139,611.26 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
AS SUBMITTED 28,693,611.41 5,523,674.31 1,710,864.28 7,234,538.59 35,928,150.00
TOTAL
AS EVALUATED 28,693,611.41 5,523,674.31 1,710,864.28 7,234,538.59 35,928,150.00

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Evaluated by: Approved:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Architect II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART I FACILITIES FOR THE ENGINEER
AS SUBMITTED 1.00 L.s. 86,711.24 8.00% 6,936.90 4,682.41 11,619.31 98,330.55 98,330.55
A.1.1(3) Construction of Field Office for the Engineer
AS EVALUATED 1.00 L.s. 86,711.24 8.00% 6,936.90 4,682.41 11,619.31 98,330.55 98,330.55
AS SUBMITTED 300.00 ea. 4,500.00 8.00% 360.00 243.00 603.00 5,103.00 17.01
A.1.4(1) Provision of Progress Photographs
AS EVALUATED 300.00 ea. 4,500.00 8.00% 360.00 243.00 603.00 5,103.00 17.01
AS SUBMITTED 91,211.24 7,296.90 4,925.41 12,222.31 103,433.55
TOTAL OF PART I
AS EVALUATED 91,211.24 7,296.90 4,925.41 12,222.31 103,433.55
PART II OTHER GENERAL REQUIREMENTS
AS SUBMITTED 1.00 L.s. 82,678.15 0.00% - 4,133.91 4,133.91 86,812.06 86,812.06
B.3 Permits and Clearances
AS EVALUATED 1.00 L.s. 82,678.15 0.00% - 4,133.91 4,133.91 86,812.06 86,812.06
AS SUBMITTED 1.00 Ea 3,719.60 20.00% 743.92 223.18 967.10 4,686.70 4,686.70
B.5 Project Billboard/ Sign Board
AS EVALUATED 1.00 Ea 3,719.60 20.00% 743.92 223.18 967.10 4,686.70 4,686.70
AS SUBMITTED 1.00 L.s. 1,096,391.16 8.00% 87,711.29 59,205.12 146,916.41 1,243,307.57 1,243,307.57
B.7(2) Occupational Safety and Health Program
AS EVALUATED 1.00 L.s. 1,096,391.16 8.00% 87,711.29 59,205.12 146,916.41 1,243,307.57 1,243,307.57
AS SUBMITTED 1.00 L.s. 280,000.00 0.00% - 14,000.00 14,000.00 294,000.00 294,000.00
B.9 Mobilization/Demobilization
AS EVALUATED 1.00 L.s. 280,000.00 0.00% - 14,000.00 14,000.00 294,000.00 294,000.00
AS SUBMITTED 1,462,788.91 88,455.21 77,562.21 166,017.42 1,628,806.33
TOTAL OF PART II
AS EVALUATED 1,462,788.91 88,455.21 77,562.21 166,017.42 1,628,806.33
Project ID
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
AS SUBMITTED 1.00 l.s. 109,350.27 20.00% 21,870.05 6,561.02 28,431.07 137,781.34 137,781.34
800(2) Clearing and Grubbing
AS EVALUATED 1.00 l.s. 109,350.27 20.00% 21,870.05 6,561.02 28,431.07 137,781.34 137,781.34
AS SUBMITTED 1.00 L.s. 297,430.34 20.00% 59,486.07 17,845.82 77,331.89 374,762.23 374,762.23
801(1) Removal of Structure and Obstruction
AS EVALUATED 1.00 L.s. 297,430.34 20.00% 59,486.07 17,845.82 77,331.89 374,762.23 374,762.23
AS SUBMITTED 854.76 m³ 198,391.72 20.00% 39,678.34 11,903.50 51,581.84 249,973.56 292.45
803(1)a Structure Excavation (Common Soil)
AS EVALUATED 854.76 m³ 198,391.72 20.00% 39,678.34 11,903.50 51,581.84 249,973.56 292.45
AS SUBMITTED 679.57 m³ 104,286.72 20.00% 20,857.34 6,257.20 27,114.54 131,401.26 193.36
804(1)a Embankment from Roadway/Structure Excavation
AS EVALUATED 679.57 m³ 104,286.72 20.00% 20,857.34 6,257.20 27,114.54 131,401.26 193.36
AS SUBMITTED 131.10 m³ 221,684.84 20.00% 44,336.97 13,301.09 57,638.06 279,322.90 2,130.61
804(1)b Embankment from Borrow
AS EVALUATED 131.10 m³ 221,684.84 20.00% 44,336.97 13,301.09 57,638.06 279,322.90 2,130.61
AS SUBMITTED 81.42 m³ 164,071.14 20.00% 32,814.23 9,844.27 42,658.50 206,729.64 2,539.05
804(4) Gravel Fill
AS EVALUATED 81.42 m³ 164,071.14 20.00% 32,814.23 9,844.27 42,658.50 206,729.64 2,539.05
AS SUBMITTED 1.00 l.s. 2,835,306.15 20.00% 567,061.23 170,118.37 737,179.60 3,572,485.75 3,572,485.75
807(1) Site Development
AS EVALUATED 1.00 l.s. 2,835,306.15 20.00% 567,061.23 170,118.37 737,179.60 3,572,485.75 3,572,485.75
AS SUBMITTED 3,930,521.18 786,104.23 235,831.27 1,021,935.50 4,952,456.68
TOTAL OF PART A
AS EVALUATED 3,930,521.18 786,104.23 235,831.27 1,021,935.50 4,952,456.68
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS SUBMITTED 551.26 m³ 3,517,637.18 20.00% 703,527.44 211,058.23 914,585.67 4,432,222.85 8,040.17
900(8) Structural Concrete (27.58 Mpa @ 28 days)
AS EVALUATED 551.26 m³ 3,517,637.18 20.00% 703,527.44 211,058.23 914,585.67 4,432,222.85 8,040.17
AS SUBMITTED 38,293.18 Kg 1,930,719.06 20.00% 386,143.81 115,843.14 501,986.95 2,432,706.01 63.53
902(1)a Reinforcing Steel (Deformed) Grade 40
AS EVALUATED 38,293.18 Kg 1,930,719.06 20.00% 386,143.81 115,843.14 501,986.95 2,432,706.01 63.53
AS SUBMITTED 75,858.09 Kg 3,906,759.71 20.00% 781,351.94 234,405.58 1,015,757.52 4,922,517.23 64.89
902(1)b Reinforcing Steel (Deformed), Grade 60
AS EVALUATED 75,858.09 Kg 3,906,759.71 20.00% 781,351.94 234,405.58 1,015,757.52 4,922,517.23 64.89
AS SUBMITTED 2,962.35 m² 1,455,753.46 20.00% 291,150.69 87,345.21 378,495.90 1,834,249.36 619.19
903(2) Formworks & Falseworks
AS EVALUATED 2,962.35 m² 1,455,753.46 20.00% 291,150.69 87,345.21 378,495.90 1,834,249.36 619.19
AS SUBMITTED 10,810,869.41 2,162,173.88 648,652.16 2,810,826.04 13,621,695.45
TOTAL OF PART B
AS EVALUATED 10,810,869.41 2,162,173.88 648,652.16 2,810,826.04 13,621,695.45

Preparation and Submission: Evaluation:


Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART C FACILITIES FOR THE
FINISHING ENGINEER
WORKS
AS SUBMITTED 264.64 L 81,275.07 20.00% 16,255.01 4,876.50 21,131.51 102,406.58 386.97
1000(1) Soil Poisoning
AS EVALUATED 264.64 L 81,275.07 20.00% 16,255.01 4,876.50 21,131.51 102,406.58 386.97
AS SUBMITTED 321.70 m² 204,657.91 20.00% 40,931.58 12,279.47 53,211.05 257,868.96 801.58
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel), 100mm
AS EVALUATED 321.70 m² 204,657.91 20.00% 40,931.58 12,279.47 53,211.05 257,868.96 801.58
AS SUBMITTED 812.29 m² 771,432.58 20.00% 154,286.52 46,285.96 200,572.48 972,005.06 1,196.62
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm
AS EVALUATED 812.29 m² 771,432.58 20.00% 154,286.52 46,285.96 200,572.48 972,005.06 1,196.62
AS SUBMITTED 1.00 L.s. 179,761.18 20.00% 35,952.24 10,785.67 46,737.91 226,499.09 226,499.09
1010(4) Wooden Doors & Windows
AS EVALUATED 1.00 L.s. 179,761.18 20.00% 35,952.24 10,785.67 46,737.91 226,499.09 226,499.09
AS SUBMITTED 34.65 m² 48,742.69 20.00% 9,748.54 2,924.56 12,673.10 61,415.79 1,772.46
1010(2)a Door (Flush)
AS EVALUATED 34.65 m² 48,742.69 20.00% 9,748.54 2,924.56 12,673.10 61,415.79 1,772.46
AS SUBMITTED 51.84 m² 325,645.06 20.00% 65,129.01 19,538.70 84,667.71 410,312.77 7,914.98
1010(2)b Door (Wooden Panel)
AS EVALUATED 51.84 m² 325,645.06 20.00% 65,129.01 19,538.70 84,667.71 410,312.77 7,914.98
AS SUBMITTED 1.00 L.s. 55,273.54 20.00% 11,054.71 3,316.41 14,371.12 69,644.66 69,644.66
1003(17) Carpentry and Joinery Works
AS EVALUATED 1.00 L.s. 55,273.54 20.00% 11,054.71 3,316.41 14,371.12 69,644.66 69,644.66
AS SUBMITTED 3.12 m² 21,046.79 20.00% 4,209.36 1,262.81 5,472.17 26,518.96 8,499.67
1006(4) Steel Louver Door
AS EVALUATED 3.12 m² 21,046.79 20.00% 4,209.36 1,262.81 5,472.17 26,518.96 8,499.67
AS SUBMITTED 142.56 m² 540,935.21 20.00% 108,187.04 32,456.11 140,643.15 681,578.36 4,780.99
1005(1) Residential Casement Steel Window
AS EVALUATED 142.56 m² 540,935.21 20.00% 108,187.04 32,456.11 140,643.15 681,578.36 4,780.99
AS SUBMITTED 1.00 L.s. 93,957.06 20.00% 18,791.41 5,637.42 24,428.83 118,385.89 118,385.89
1005(6) Window Accessory
AS EVALUATED 1.00 L.s. 93,957.06 20.00% 18,791.41 5,637.42 24,428.83 118,385.89 118,385.89
AS SUBMITTED 57.60 m² 180,071.94 20.00% 36,014.39 10,804.32 46,818.71 226,890.65 3,939.07
1009(1)a Jalousie Window (Glass)
AS EVALUATED 57.60 m² 180,071.94 20.00% 36,014.39 10,804.32 46,818.71 226,890.65 3,939.07
AS SUBMITTED 1.00 L.s. 26,860.00 20.00% 5,372.00 1,611.60 6,983.60 33,843.60 33,843.60
1004(2) Finishing Hardware
AS EVALUATED 1.00 L.s. 26,860.00 20.00% 5,372.00 1,611.60 6,983.60 33,843.60 33,843.60
AS SUBMITTED 1.00 L.s. 447,379.82 20.00% 89,475.96 26,842.79 116,318.75 563,698.57 563,698.57
1051(6) Railing
AS EVALUATED 1.00 L.s. 447,379.82 20.00% 89,475.96 26,842.79 116,318.75 563,698.57 563,698.57
AS SUBMITTED 2,836.23 m² 502,950.35 20.00% 100,590.07 30,177.02 130,767.09 633,717.44 223.44
1027(1) Cement Plaster Finish
AS EVALUATED 2,836.23 m² 502,950.35 20.00% 100,590.07 30,177.02 130,767.09 633,717.44 223.44
AS SUBMITTED 1,327.38 m² 144,271.49 20.00% 28,854.30 8,656.29 37,510.59 181,782.08 136.95
1021(1)a Cement Floor Finish (Plain)
AS EVALUATED 1,327.38 m² 144,271.49 20.00% 28,854.30 8,656.29 37,510.59 181,782.08 136.95
AS SUBMITTED 455.11 m² 385,950.15 20.00% 77,190.03 23,157.01 100,347.04 486,297.19 1,068.53
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
AS EVALUATED 455.11 m² 385,950.15 20.00% 77,190.03 23,157.01 100,347.04 486,297.19 1,068.53
AS SUBMITTED 18.00 Lm 3,848.09 20.00% 769.62 230.89 1,000.51 4,848.60 269.37
1003(11)a1 Fascia Board (19mm, Fiber Cement Board)
AS EVALUATED 18.00 Lm 3,848.09 20.00% 769.62 230.89 1,000.51 4,848.60 269.37
AS SUBMITTED 436.71 m² 84,008.07 20.00% 16,801.61 5,040.48 21,842.09 105,850.16 242.38
1038(1) Reflective Insulation
AS EVALUATED 436.71 m² 84,008.07 20.00% 16,801.61 5,040.48 21,842.09 105,850.16 242.38
AS SUBMITTED 196.24 m² 301,897.37 20.00% 60,379.47 18,113.84 78,493.31 380,390.68 1,938.40
1018(1) Glazed Tiles and Trims
AS EVALUATED 196.24 m² 301,897.37 20.00% 60,379.47 18,113.84 78,493.31 380,390.68 1,938.40
AS SUBMITTED 82.91 m² 76,112.62 20.00% 15,222.52 4,566.76 19,789.28 95,901.90 1,156.70
1018(2) Unlglazed Tiles
AS EVALUATED 82.91 m² 76,112.62 20.00% 15,222.52 4,566.76 19,789.28 95,901.90 1,156.70
AS SUBMITTED 377.62 m² 67,353.37 20.00% 13,470.67 4,041.20 17,511.87 84,865.24 224.74
1016(1)a Water Proofing Cement Base
AS EVALUATED 377.62 m² 67,353.37 20.00% 13,470.67 4,041.20 17,511.87 84,865.24 224.74
AS SUBMITTED 3,614.79 m² 947,053.12 20.00% 189,410.62 56,823.19 246,233.81 1,193,286.93 330.11
1032(1)a Painting Works (Masonry/Concrete)
AS EVALUATED 3,614.79 m² 947,053.12 20.00% 189,410.62 56,823.19 246,233.81 1,193,286.93 330.11

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
FACILITIES FOR THE ENGINEER AS SUBMITTED 292.01 m² 74,569.05 20.00% 14,913.81 4,474.14 19,387.95 93,957.00 321.76
1032(1)b Painting Works (Wood Painting)
AS EVALUATED 292.01 m² 74,569.05 20.00% 14,913.81 4,474.14 19,387.95 93,957.00 321.76
AS SUBMITTED 215.57 m² 54,108.82 20.00% 10,821.76 3,246.53 14,068.29 68,177.11 316.26
1032(1)c Painting Works (Steel)
AS EVALUATED 215.57 m² 54,108.82 20.00% 10,821.76 3,246.53 14,068.29 68,177.11 316.26
AS SUBMITTED 487.40 m² 275,917.48 20.00% 55,183.50 16,555.05 71,738.55 347,656.03 713.29
1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
AS EVALUATED 487.40 m² 275,917.48 20.00% 55,183.50 16,555.05 71,738.55 347,656.03 713.29
AS SUBMITTED 5,587.70 Kg 479,411.47 20.00% 95,882.29 28,764.69 124,646.98 604,058.45 108.11
1047(2)a Structural Steel (Trusses)
AS EVALUATED 5,587.70 Kg 479,411.47 20.00% 95,882.29 28,764.69 124,646.98 604,058.45 108.11
AS SUBMITTED 6,110.13 Kg 499,742.77 20.00% 99,948.55 29,984.57 129,933.12 629,675.89 103.05
1047(2)b Structural Steel (Purlins)
AS EVALUATED 6,110.13 Kg 499,742.77 20.00% 99,948.55 29,984.57 129,933.12 629,675.89 103.05
AS SUBMITTED 862.40 Kg 70,969.29 20.00% 14,193.86 4,258.16 18,452.02 89,421.31 103.69
1047(6) Metal Structure Accessories (Steel Plates)
AS EVALUATED 862.40 Kg 70,969.29 20.00% 14,193.86 4,258.16 18,452.02 89,421.31 103.69
AS SUBMITTED 157.50 Kgs 9,005.35 20.00% 1,801.07 540.32 2,341.39 11,346.74 72.04
1047(7)b Metal Structure Accessories (Sagrods)
AS EVALUATED 157.50 Kgs 9,005.35 20.00% 1,801.07 540.32 2,341.39 11,346.74 72.04
AS SUBMITTED 397.16 Kgs 23,182.22 20.00% 4,636.44 1,390.93 6,027.37 29,209.59 73.55
1047(4) Metal Structure Accessories (Crossbracing)
AS EVALUATED 397.16 Kgs 23,182.22 20.00% 4,636.44 1,390.93 6,027.37 29,209.59 73.55
AS SUBMITTED 44.00 ea. 10,292.58 20.00% 2,058.52 617.56 2,676.08 12,968.66 294.74
1047(3)c Metal Structure Accessories (Turnbuckle)
AS EVALUATED 44.00 ea. 10,292.58 20.00% 2,058.52 617.56 2,676.08 12,968.66 294.74
AS SUBMITTED 46.00 L.m. 10,599.20 20.00% 2,119.84 635.95 2,755.79 13,354.99 290.33
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
AS EVALUATED 46.00 L.m. 10,599.20 20.00% 2,119.84 635.95 2,755.79 13,354.99 290.33
AS SUBMITTED 22.32 L.m. 5,022.23 20.00% 1,004.45 301.33 1,305.78 6,328.01 283.51
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
AS EVALUATED 22.32 L.m. 5,022.23 20.00% 1,004.45 301.33 1,305.78 6,328.01 283.51
AS SUBMITTED 10.00 L.m. 3,477.35 20.00% 695.47 208.64 904.11 4,381.46 438.15
1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)
AS EVALUATED 10.00 L.m. 3,477.35 20.00% 695.47 208.64 904.11 4,381.46 438.15
AS SUBMITTED 1.00 L.s. 142,647.56 20.00% 28,529.51 8,558.85 37,088.36 179,735.92 179,735.92
1001(8) Sewer Line Works
AS EVALUATED 1.00 L.s. 142,647.56 20.00% 28,529.51 8,558.85 37,088.36 179,735.92 179,735.92
AS SUBMITTED 1.00 L.s. 190,227.52 20.00% 38,045.50 11,413.65 49,459.15 239,686.67 239,686.67
1002(24) Cold Water lines
AS EVALUATED 1.00 L.s. 190,227.52 20.00% 38,045.50 11,413.65 49,459.15 239,686.67 239,686.67
AS SUBMITTED 1.00 L.s. 177,762.72 20.00% 35,552.54 10,665.76 46,218.30 223,981.02 223,981.02
1001(9) Storm Drainage and Downspout
AS EVALUATED 1.00 L.s. 177,762.72 20.00% 35,552.54 10,665.76 46,218.30 223,981.02 223,981.02
AS SUBMITTED 1.00 L.s. 345,990.84 20.00% 69,198.17 20,759.45 89,957.62 435,948.46 435,948.46
1002(4) Plumbing FIxtures
AS EVALUATED 1.00 L.s. 345,990.84 20.00% 69,198.17 20,759.45 89,957.62 435,948.46 435,948.46
AS SUBMITTED 1.00 L.s. 140,016.26 20.00% 28,003.25 8,400.98 36,404.23 176,420.49 176,420.49
1001(11) Septic Vault (Concrete / CHB)
AS EVALUATED 1.00 L.s. 140,016.26 20.00% 28,003.25 8,400.98 36,404.23 176,420.49 176,420.49
AS SUBMITTED 20.00 Ea 29,785.01 20.00% 5,957.00 1,787.10 7,744.10 37,529.11 1,876.46
1001(5)b Catch Basin (CHB)
AS EVALUATED 20.00 Ea 29,785.01 20.00% 5,957.00 1,787.10 7,744.10 37,529.11 1,876.46
AS SUBMITTED 8,033,211.20 1,606,642.21 481,992.66 2,088,634.87 10,121,846.07
TOTAL OF PART C AS EVALUATED 8,033,211.20 1,606,642.21 481,992.66 2,088,634.87 10,121,846.07

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART D FACILITIES FOR THE
ELECTRICAL ENGINEER
WORKS
AS SUBMITTED 1.00 L.s. 95,983.06 20.00% 19,196.61 5,758.98 24,955.59 120,938.65 120,938.65
1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in)
AS EVALUATED 1.00 L.s. 95,983.06 20.00% 19,196.61 5,758.98 24,955.59 120,938.65 120,938.65
AS SUBMITTED 1.00 L.s. 248,070.65 20.00% 49,614.13 14,884.24 64,498.37 312,569.02 312,569.02
1101(33) Wires and Wiring Devices AS EVALUATED 1.00 L.s. 248,070.65 20.00% 49,614.13 14,884.24 64,498.37 312,569.02 312,569.02
AS SUBMITTED 1.00 L.s. 346,083.32 20.00% 69,216.66 20,765.00 89,981.66 436,064.98 436,064.98
1102(1) Panel Board with Main Breaker
AS EVALUATED 1.00 L.s. 346,083.32 20.00% 69,216.66 20,765.00 89,981.66 436,064.98 436,064.98
AS SUBMITTED 1.00 L.s. 251,337.31 20.00% 50,267.46 15,080.24 65,347.70 316,685.01 316,685.01
1103(1) Lighting Fixtures & Lamps
AS EVALUATED 1.00 L.s. 251,337.31 20.00% 50,267.46 15,080.24 65,347.70 316,685.01 316,685.01
AS SUBMITTED 941,474.34 188,294.86 56,488.46 244,783.32 1,186,257.66
TOTAL OF PART D
AS EVALUATED 941,474.34 188,294.86 56,488.46 244,783.32 1,186,257.66
PART E MECHANICAL WORKS
AS SUBMITTED 1.00 L.s. 3,380,480.17 20.00% 676,096.03 202,828.81 878,924.84 4,259,405.01 4,259,405.01
1202(1) Automatic Water Sprinkler
AS EVALUATED 1.00 L.s. 3,380,480.17 20.00% 676,096.03 202,828.81 878,924.84 4,259,405.01 4,259,405.01
AS SUBMITTED 1.00 L.s. 43,054.96 20.00% 8,610.99 2,583.30 11,194.29 54,249.25 54,249.25
1208(1) Fire Alarm System
AS EVALUATED 1.00 L.s. 43,054.96 20.00% 8,610.99 2,583.30 11,194.29 54,249.25 54,249.25
AS SUBMITTED 3,423,535.13 684,707.02 205,412.11 890,119.13 4,313,654.26
TOTAL OF PART E
AS EVALUATED 3,423,535.13 684,707.02 205,412.11 890,119.13 4,313,654.26
AS SUBMITTED 27,139,611.26 5,427,922.20 1,628,376.66 7,946,417.99 39,399,683.51
TOTAL OF PART III
AS EVALUATED 27,139,611.26 5,427,922.20 1,628,376.66 7,946,417.99 39,399,683.51
AS SUBMITTED 27,139,611.26 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
TOTAL OF (Project ID)
AS EVALUATED 27,139,611.26 5,427,922.20 1,628,376.66 7,056,298.86 34,195,910.12
AS SUBMITTED 28,693,611.41 5,523,674.31 1,710,864.28 7,234,538.59 35,928,150.00
GRAND TOTAL
AS EVALUATED 28,693,611.41 5,523,674.31 1,710,864.28 7,234,538.59 35,928,150.00

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
3
2 Dump Truck 12 yd 2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 2 34
5 Pumpcrete - 1 35
6 One (1) Bagger Mixer - 1 36
7 Bar Cutter - 1 37
8 Bar Bender - 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit - 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drilling Machine - 1 42
13 Power Throwel - 1 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
25 55
26 56
27 57
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.1(3) Construction of Field Office for the Engineer


Unit of Measurement : l.s.
Output per Hour - As Evaluated : 1.00
Output per Hour - As Submitted : 1.00

No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor
a. Construction Foreman 1 40.00 90.20 3,608.00
b. Skilled Laborer 3 40.00 65.14 7,816.80
c. Unskilled Laborer 5 40.00 50.25 10,050.00

Labor Sub - Total for A1 (As Submitted) 21,474.80


A2. Labor
a. Construction Foreman 1 40.00 90.20 3,608.00
b. Skilled Laborer 3 40.00 65.14 7,816.80
c. Unskilled Laborer 5 40.00 50.25 10,050.00

Labor Sub - Total for A2 (As Evaluated) 21,474.80


No of No. of
Name and Capacity Monthly Rate Amount (PhP)
B1. Unit/s Hr/s
Equipment

Equipment Sub - Total for B1 (As Submitted)


Equipment
B2.
Equipment Sub - Total for B2 (As Evaluated)
C1. Total (A1 + B1) 21,474.80
C2. Total (A2 + B2) 21,474.80
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 21,474.80
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 21,474.80
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1. Materials
a. Plywood Marine (0.00625m x pc. 15.00 500.00 7,500.00
b. Good Lumber bd.ft. 309.55 60.00 18,572.83
c. Corrugated roofing gauge 26 (0.551 mm x 2.44) sq.m. 13.00 255.00 3,315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Door Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel G-1 cu.m. 3.00 1,660.00 4,980.00
h. Sand cu.m. 2.00 1,380.00 2,760.00
i. Reinforcing Steel Bar Grade 40 kg. 95.82 37.50 3,593.10
j. CHB Ordinary (101mm x 203mm x 406mm) pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 W Flourescent LF set 1.00 255.00 255.00
n. Duplex Conv. Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board Cabinet set 1.00 500.00 500.00
q. #16 GI Tie Wire kgs. 2.00 80.00 160.00
r. Misc. (Forms, CWN, Bolts, Electrical Wires, Chairs, Table etc.) lot 1.00 10,000.00 10,000.00

Equipment Sub - Total for F1 (As Submitted) 65,236.44


F2. Materials
a. Plywood Marine (0.00625m x pc. 15.00 500.00 7,500.00
b. Good Lumber bd.ft. 309.55 60.00 18,572.83
c. Corrugated roofing gauge 26 sq.m. 13.00 255.00 3,315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Door Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel G-1 cu.m. 3.00 1,660.00 4,980.00
h. Sand cu.m. 2.00 1,380.00 2,760.00
i. Reinforcing Steel Bar Grade kg. 95.82 37.50 3,593.10
j. CHB Ordinary (101mm x pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 W Flourescent LF set 1.00 255.00 255.00
n. Duplex Conv. Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board Cabinet set 1.00 500.00 500.00
q. #16 GI Tie Wire kgs. 2.00 80.00 160.00
r. Misc. (Forms, CWN, Bolts, Electrical Wires, Chairs, Table etc.) lot 1.00 10,000.00 10,000.00

Materials Sub - Total for F2 (As Evaluated) 65,236.44


G1. Direct Unit Cost (E1 + F1) - As Submitted 86,711.24
G2. Direct Unit Cost (E2 + F2) - As Evaluated 86,711.24
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6,936.90
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6,936.90
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4,682.41
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4,682.41
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 98,330.55
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 98,330.55

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : ea.
Output per Hour - As Evaluated : 1.00
Output per Hour - As Submitted : 1.00

No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor

Labor Sub - Total for A1 (As Submitted) -


A2. Labor

Labor Sub - Total for A2 (As Evaluated) -


No of No. of
Name and Capacity Monthly Rate Amount (PhP)
B1. Unit/s Hr/s
Equipment

Equipment Sub - Total for B1 (As Submitted)


Equipment
B2.
Equipment Sub - Total for B2 (As Evaluated)
C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 ea.
D2. Output per our - As Evaluated = 1 ea.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1. Materials

a. Developing pc. 1.00 15.00 15.00

Equipment Sub - Total for F1 (As Submitted) 15.00


F2. Materials

a. Developing pc. 1.00 15.00 15.00

Materials Sub - Total for F2 (As Evaluated) 15.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 15.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 15.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 1.20
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 1.20
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 0.81
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 0.81
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 17.01
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 17.01

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.3 Permits and Clearances


Unit of Measurement : L.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Labor -
b. Skilled Laborer -
c. Unskilled Laborer -
-
Sub - Total for A1 (As Submitted) -
A2. Labor
a. Construction Foreman -
b. Skilled Laborer -
c. Unskilled Laborer -

Sub - Total for A2 (As Evaluated) -


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Sub - Total for B1 (As Submitted) -


B2
Equipment

Sub - Total for B2 (As Evaluated) -


C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1
Materials

a. Fire Safety Evaluation Clearance Fee L.s. 1.00 35,928.15 35,928.15


b. Brgy. Clearance For Construction Fee L.s. 1.00 500.00 500.00
c. Professional Fee L.s. 1.00 20,000.00 20,000.00
d. Blue Print 20" x 30 " Sheet 250.00 25.00 6,250.00
e. Business Tax L.s. 1.00 20,000.00 20,000.00

Sub - Total for F1 (As Submitted) 82,678.15


Materials
F2
a. Fire Safety Evaluation Clearance Fee L.s. 1.00 35,928.15 35,928.15
b. Brgy. Clearance For Construction Fee L.s. 1.00 500.00 500.00
c. Professional Fee L.s. 1.00 20,000.00 20,000.00
d. Blue Print 20" x 30 " Sheet 250.00 25.00 6,250.00
e. Business Tax L.s. 1.00 20,000.00 20,000.00

Sub - Total for F2 (As Evaluated) 82,678.15


G1. Direct Unit Cost (E1 + F1) - As Submitted 82,678.15
G2. Direct Unit Cost (E2 + F2) - As Evaluated 82,678.15
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 0% of G1 -
I2. Contractor's Profit (CP) - As Evaluated 0% of G2 -
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4,133.91
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4,133.91
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 86,812.06
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 86,812.06

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.5 Project Billboard/ Sign Board


Unit of Measurement : ea
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 4.00 90.20 360.80


b. Skilled Laborer 1 4.00 65.14 260.56
c. Unskilled Laborer 1 4.00 50.25 201.00
.
Sub - Total for A1 (As Submitted) 822.36
A2. Labor
a. Construction Foreman 1 4.00 90.20 360.80
b. Skilled Laborer 1 4.00 65.14 260.56
c. Unskilled Laborer 1 4.00 50.25 201.00

Sub - Total for A2 (As Evaluated) 822.36


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of labor cost) 82.24

Sub - Total for B1 (As Submitted) 82.24


B2
Equipment

Minor Tools (10% of labor cost) 82.24

Sub - Total for B2 (As Evaluated) 82.24


C1. Total (A1 + B1) 904.60
C2. Total (A2 + B2) 904.60
D1. Output per our - As Submitted = 1 ea
D2. Output per our - As Evaluated = 1 ea
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 904.60
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 904.60
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1
Materials

a. Plywood Marine (0.00625m x 1.2m x 2.44m) pc. 1.00 500.00 500.00


b. Coco Lumber bd.ft. 41.00 35.00 1,435.00
c. Project Sign ( tarpaulin) sq.ft. 32.00 25.00 800.00
d. CWN Assorted kl. 1.00 80.00 80.00

Sub - Total for F1 (As Submitted) 2,815.00


Materials
F2
a. Plywood Marine (0.00625m x 1.2m x 2.44m) pc. 1.00 500.00 500.00
b. Coco Lumber bd.ft. 41.00 35.00 1,435.00
c. Project Sign ( tarpaulin) sq.ft. 32.00 25.00 800.00
d. CWN Assorted kl. 1.00 80.00 80.00

Sub - Total for F2 (As Evaluated) 2,815.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,719.60
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,719.60
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 446.35
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 446.35
I1. Contractor's Profit (CP) - As Submitted 8% of G1 297.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 297.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 223.18
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 223.18
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,686.69
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,686.69

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s Man - Days Daily Rate Amount (PhP)


A1.
Labor
DURATION: 300
a. Safety Practitioner / Officer (Part Time) 1 300 500.00 150,000.00
b. Health Personnel - First Aider (Full Time) 1 300 280.00 84,000.00
c. Health Personnel - Sanitation Aide (Full Time) 1 300 280.00 84,000.00

Sub - Total for A1 (As Submitted) 318,000.00


A2. Labor
DURATION: 300
a. Safety Practitioner / Officer (Part Time) 1 300 500.00 150,000.00
b. Health Personnel (Full Time) 1 300 280.00 84,000.00
c. Health Personnel - Sanitation Aide (Full Time) 1 300 280.00 84,000.00

Sub - Total for A2 (As Evaluated) 318,000.00


Name and Capacity Unit Quantity Daily Rate Amount (PhP)
B1.
Equipment
a. G.I pipe barricades 4.5 m x 1.2 m 7 80 21.93 12,280.80
b. G.I pipe barricades 9.5 m x 1.2 m 2 80 49.59 7,934.40

Sub - Total for B1 (As Submitted) 20,215.20


B2. Equipment
a. G.I pipe barricades 4.5 m x 1.2 m 7 80 21.93 12,280.80
b. G.I pipe barricades 9.5 m x 1.2 m 2 80 49.59 7,934.40

Sub - Total for B2 (As Evaluated) 20,215.20


C1. Total (A1 + B1) 338,215.20
C2. Total (A2 + B2) 20,215.20
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 338,215.20
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 338,215.20
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Materials and Facilities for regular disinfection, l.s. 1.00 150,000.00 150,000.00
temperature check and COVID 19 Rapid Test
First Aid Kit
Testing Facilities (Movable Tent, Tables, Chairs)
Rapid Testing Kit for COVID19 x no. of personnel
Thermometer
Alchohol 70% Solutiion
Automatic Alchohol Sanitizer

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 16,048.80 0.27 4,396.93
b. Safety Shoes man-days 10,553.31 3.29 34,695.81
c. Working Gloves man-days 16,048.80 26.67 427,968.00
d. Safety Vest man-days 16,048.80 0.83 13,374.00
e. Rain Coats man-days 4,814.64 0.83 4,012.20
f. Dust Mask man-days 1,335.95 0.34 448.37
i. Body Harness and Lanyard man-days 413.57 1.73 716.02
j. Rubber Boots man-days 5,585.05 1.37 7,650.75
j. Face Mask man-days 16,048.80 5.00 80,244.00
j. Face Shield man-days 16,048.80 1.67 26,748.00

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') set 23.00 123.68 2,844.64
d. Caution Tape, 100ft roll 1.00 800.00 800.00
e. Safety Net (1/8" x 2.7m x 90m.) roll 1.00 3,500.00 3,500.00

Sub - Total for F1 (As Submitted) 758,175.96


F2. Materials

a. Materials and Facilities for regular disinfection, l.s. 1.00 150,000.00 150,000.00
temperature check and COVID 19 Rapid Test
First Aid Kit
Testing Facilities (Movable Tent, Tables, Chairs)
Rapid Testing Kit for COVID19 x no. of personnel
Thermometer
Alchohol 70% Solutiion
Automatic Alchohol Sanitizer

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 16,048.80 0.27 4,396.93
b. Safety Shoes man-days 10,553.31 3.29 34,695.81
c. Working Gloves man-days 16,048.80 26.67 427,968.00
d. Safety Vest man-days 16,048.80 0.83 13,374.00
e. Rain Coats man-days 4,814.64 0.83 4,012.20
f. Dust Mask man-days 1,335.95 0.34 448.37
i. Body Harness and Lanyard man-days 413.57 1.73 716.02
j. Rubber Boots man-days 5,585.05 1.37 7,650.75
j. Face Mask man-days 16,048.80 5.00 80,244.00
j. Face Shield man-days 16,048.80 1.67 26,748.00

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') set 23.00 123.68 2,844.64
d. Caution Tape, 100ft roll 1.00 800.00 800.00
e. Safety Net (1/8" x 2.7m x 90m.) roll 1.00 3,500.00 3,500.00

Sub - Total for F2 (As Evaluated) 758,175.96


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,096,391.16
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,096,391.16
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 87,711.29
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 87,711.29
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 59,205.12
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 59,205.12
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,243,307.57
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,243,307.57

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.9 Mobilization/Demobilization


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

Sub - Total for A1 (As Submitted) -


A2. Labor

Sub - Total for A2 (As Evaluated) -


Name and Capacity No of Unit/s NO. of Trips Rate Amount (PhP)
B1.
Equipment

a. (Not to Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 1 14.00 20,000.00 280,000.00
(Service Truck, Low Bed Trailer)

Sub - Total for B1 (As Submitted) 280,000.00


B2. Equipment

a. (Not to Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 1 14.00 20,000.00 280,000.00
(Service Truck, Low Bed Trailer)

Sub - Total for B2 (As Evaluated) 280,000.00


C1. Total (A1 + B1) 280,000.00
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 280,000.00
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 280,000.00
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 280,000.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 280,000.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 0% of G1 -
I2. Contractor's Profit (CP) - As Evaluated 0% of G2 -
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14,000.00
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14,000.00
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 294,000.00
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 294,000.00

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(2) Clearing and Grubbing


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
Removal of Trees and other Obstruction (Mahogany etc.)
a. Construction Foreman 1 64.00 90.20 5,772.80
b. Skilled Laborer 2 64.00 65.14 8,337.92
c. Unskilled Laborer 4 64.00 50.25 12,864.00

Sub - Total for A1 (As Submitted) 26,974.72


A2. Labor
Removal of Trees and other Obstruction (Mahogany etc.)
a. Construction Foreman 1 64.00 90.20 5,772.80
b. Skilled Laborer 2 64.00 65.14 8,337.92
b. Unskilled Laborer 4 64.00 50.25 12,864.00

Sub - Total for A2 (As Evaluated) 26,974.72


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 16.00 1,537.00 24,592.00


b. Dump Truck (12yd³) 2 16.00 1,420.00 45,440.00
c Chainsaw 2 64.00 75.36 9,646.08
Minor Tools (10% of Labor Cost) 2,697.47

Sub - Total for B1 (As Submitted) 82,375.55


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 16.00 1,537.00 24,592.00


b. Dump Truck (12yd³) 2 16.00 1,420.00 45,440.00
c Chainsaw 2 64.00 75.36 9,646.08
Minor Tools (10% of Labor Cost) 2,697.47

Sub - Total for B2 (As Evaluated) 82,375.55


C1. Total (A1 + B1) 109,350.27
C2. Total (A2 + B2) 109,350.27
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 109,350.27
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 109,350.27
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 109,350.27
G2. Direct Unit Cost (E2 + F2) - As Evaluated 109,350.27
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 13,122.03
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 13,122.03
I1. Contractor's Profit (CP) - As Submitted 8% of G1 8,748.02
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 8,748.02
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 6,561.02
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 6,561.02
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 137,781.34
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 137,781.34

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 801(1) Removal of Structure and Obstruction


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
Demolition of Existing Walkways, Gazebo and other
Obstruction
a. Construction Foreman 1 112.00 90.20 10,102.40
b. Skilled Laborer 2 112.00 65.14 14,591.36
c. Unskilled Laborer 4 112.00 50.25 22,512.00

Sub - Total for A1 (As Submitted) 47,205.76


A2. Labor
Demolition of Existing Walkways, Gazebo and other
Obstruction
a. Construction Foreman 1 112.00 90.20 10,102.40
b. Skilled Laborer 2 112.00 65.14 14,591.36
c. Unskilled Laborer 4 112.00 50.25 22,512.00

Sub - Total for A2 (As Evaluated) 47,205.76


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 112.00 1,537.00 172,144.00


b. Dump Truck (12yd³) 1 28.00 1,420.00 39,760.00
c. Jackhammer 2 112.00 150.00 33,600.00
Minor Tools (10% of Labor Cost) 4,720.58

Sub - Total for B1 (As Submitted) 250,224.58


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 112.00 1,537.00 172,144.00


b. Dump Truck (12yd³) 1 28.00 1,420.00 39,760.00
c. Jackhammer 2 112.00 150.00 33,600.00
Minor Tools (10% of Labor Cost) 4,720.58

Sub - Total for B2 (As Evaluated) 250,224.58


C1. Total (A1 + B1) 297,430.34
C2. Total (A2 + B2) 297,430.34
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 297,430.34
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 297,430.34
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 297,430.34
G2. Direct Unit Cost (E2 + F2) - As Evaluated 297,430.34
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 35,691.64
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 35,691.64
I1. Contractor's Profit (CP) - As Submitted 8% of G1 23,794.43
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 23,794.43
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 17,845.82
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 17,845.82
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 374,762.22
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 374,762.22

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)a Structure Excavation (Common Soil)


Unit of Measurement : m³
Output per hour : 20.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 240.95


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 240.95


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12yd³) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B1 (As Submitted) 4,401.10


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12yd³) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B2 (As Evaluated) 4,401.10


C1. Total (A1 + B1) 4,642.05
C2. Total (A2 + B2) 4,642.05
D1. Output per our - As Submitted = 20 m³
D2. Output per our - As Evaluated = 20 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 232.10
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 232.10
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 232.10
G2. Direct Unit Cost (E2 + F2) - As Evaluated 232.10
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 27.85
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 27.85
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13.93
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13.93
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 292.45
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 292.45

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)a Embankment from Structure Excavation


Unit of Measurement : m³
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 240.95


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 240.95


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B1 (As Submitted) 1,269.10


B2. Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Dump Truck (12yd³) 1 0.75 1,420.00 1,065.00
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B2 (As Evaluated) 1,181.35


C1. Total (A1 + B1) 1,510.05
C2. Total (A2 + B2) 1,422.30
D1. Output per our - As Submitted = 9.84 m³
D2. Output per our - As Evaluated = 9.84 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 153.46
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 144.54
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 153.46
G2. Direct Unit Cost (E2 + F2) - As Evaluated 144.54
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 18.42
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 17.35
I1. Contractor's Profit (CP) - As Submitted 8% of G1 12.28
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11.56
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 9.21
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 9.21
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 193.36
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 193.36

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)b Embankment from Borrow


Unit of Measurement : m³
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 240.95


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 240.95


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B1 (As Submitted) 1,269.10


B2. Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B2 (As Evaluated) 1,269.10


C1. Total (A1 + B1) 1,510.05
C2. Total (A2 + B2) 1,510.05
D1. Output per our - As Submitted = 9.84 m³
D2. Output per our - As Evaluated = 9.84 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 153.46
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 153.46
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Common Borrow m³ 1.25 1,230.00 1,537.50


(w/ 25% Shrinkage Factor)

Sub - Total for F1 (As Submitted) 1,537.50


F2. Materials

a. Common Borrow m³ 1.25 1,230.00 1,537.50


(w/ 25% Shrinkage Factor)

Sub - Total for F2 (As Evaluated) 1,537.50


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,690.96
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,690.96
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 202.92
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 202.92
I1. Contractor's Profit (CP) - As Submitted 8% of G1 135.28
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 135.28
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 101.46
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 101.46
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 2,130.61
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 2,130.61

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(4) Gravel Fill


Unit of Measurement : m³
Output per hour : 1.200

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 240.95


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 240.95


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.50 123.00 61.50


b. Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B1 (As Submitted) 85.60


B2. Equipment

a. Plate Compactor (5hp) 1 0.50 123.00 61.50


b. Minor Tools (10% of Labor Cost) 24.10

Sub - Total for B2 (As Evaluated) 85.60


C1. Total (A1 + B1) 326.55
C2. Total (A2 + B2) 326.55
D1. Output per our - As Submitted = 1.20 m³
D2. Output per our - As Evaluated = 1.20 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 272.12
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 272.12
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Gravel G-1 m³ 1.05 1,660.00 1,743.00


(w/ 5% Srinkage Factor)

Sub - Total for F1 (As Submitted) 1,743.00


F2. Materials

a. Gravel G-1 m³ 1.05 1,660.00 1,743.00


(w/ 5% Srinkage Factor)

Sub - Total for F2 (As Evaluated) 1,743.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 2,015.12
G2. Direct Unit Cost (E2 + F2) - As Evaluated 2,015.12
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 241.81
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 241.81
I1. Contractor's Profit (CP) - As Submitted 8% of G1 161.21
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 161.21
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 120.91
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 120.91
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 2,539.05
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 2,539.05

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 807(1) Site Development


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
a. Construction Foreman 1 760.00 90.20 68,552.00
b. Skilled Laborer 2 760.00 65.14 99,012.80
c. Unskilled Laborer 8 760.00 50.25 305,520.00

Sub - Total for A1 (As Submitted) 473,084.80


A2. Labor
a. Construction Foreman 1 760.00 90.20 68,552.00
b. Skilled Laborer 2 760.00 65.14 99,012.80
c. Unskilled Laborer 8 760.00 50.25 305,520.00

Sub - Total for A2 (As Evaluated) 473,084.80


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
a. Minor Tools (10% of Labor Cost) 47,308.48
b. One bagger mixer 1 380.00 172.00 65,360.00

Sub - Total for B1 (As Submitted) 112,668.48


B2. Equipment
a. Minor Tools (10% of Labor Cost) 47,308.48
b. One bagger mixer 1 380.00 172.00 65,360.00

Sub - Total for B2 (As Evaluated) 112,668.48


C1. Total (A1 + B1) 585,753.28
C2. Total (A2 + B2) 585,753.28
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 585,753.28
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 585,753.28
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials
a. Electrical System Improvement
Meralco Service Utility Lines and Accessories l.s. 1.00 10,000.00 10,000.00
b. Restoration of Covered Walkway w/ Slab on Fill (1.5m l.m. 180.00 10,000.00 1,800,000.00
Width) and walk Guide Plant Box on Both Side
c. Restoration of Gazebo (2 Unit) l.s. 1.00 400,000.00 400,000.00
d. Restoration of Gate/ Fence
CHB 100 mm thk. Inc RSB and Mortar sq.m. 14.75 484.45 7,145.64
Plastering sq.m. 29.50 112.26 3,311.67
Cement bags 9.00 250.00 2,250.00
Gravel cu.m. 0.99 1,660.00 1,643.40
Sand cu.m. 0.50 1,380.00 690.00
10mm dia. RSB kgs. 37.02 40.64 1,504.31
12mm dia. RSB kgs. 42.63 40.64 1,732.27
e. Landscaping (Plant Boxes and Ornamental Plants) l.s. 1.00 15,000.00 15,000.00
f. Misc. Items (Forms, CWN, etc.) l.s. 1.00 6,275.58 6,275.58

Sub - Total for F1 (As Submitted) 2,249,552.87


F2. Materials
a. Electrical System Improvement
Meralco Service Utility Lines and Accessories l.s. 1.00 10,000.00 10,000.00
b. Restoration of Covered Walkway w/ Slab on Fill (1.5m l.m. 180.00 10,000.00 1,800,000.00
Width) and walk Guide Plant Box on Both Side
c. Restoration of Gazebo (2 Unit) l.s. 1.00 400,000.00 400,000.00
d. Restoration of Gate/ Fence
CHB 100 mm thk. Inc RSB and Mortar sq.m. 14.75 484.45 7,145.64
Plastering sq.m. 29.50 112.26 3,311.67
Cement bags 9.00 250.00 2,250.00
Gravel cu.m. 0.99 1,660.00 1,643.40
Sand cu.m. 0.50 1,380.00 690.00
10mm dia. RSB kgs. 37.02 40.64 1,504.31
12mm dia. RSB kgs. 42.63 40.64 1,732.27
e. Landscaping (Plant Boxes and Ornamental Plants) l.s. 1.00 15,000.00 15,000.00
f. Misc. Items (Forms, CWN, etc.) l.s. 1.00 6,275.58 6,275.58

Sub - Total for F2 (As Evaluated) 2,249,552.87


G1. Direct Unit Cost (E1 + F1) - As Submitted 2,835,306.15
G2. Direct Unit Cost (E2 + F2) - As Evaluated 2,835,306.15
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 340,236.74
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 340,236.74
I1. Contractor's Profit (CP) - As Submitted 8% of G1 226,824.49
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 226,824.49
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 170,118.37
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 170,118.37
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 3,572,485.74
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 3,572,485.74

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(8) Structural Concrete (27.58 Mpa @ 28 days)


Unit of Measurement : m³
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 6 1.00 50.25 301.50
. - -
Sub - Total for A1 (As Submitted) 521.98
A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 6 1.00 50.25 301.50

Sub - Total for A2 (As Evaluated) 521.98


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 52.20

Sub - Total for B1 (As Submitted) 795.22


B2. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 52.20

Sub - Total for B2 (As Evaluated) 795.22


C1. Total (A1 + B1) 1,317.20
C2. Total (A2 + B2) 1,317.20
D1. Output per our - As Submitted = 3.72 m³
D2. Output per our - As Evaluated = 3.72 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 354.09
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 354.09
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F1 (As Submitted) 6,027.00


F2. Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F2 (As Evaluated) 6,027.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,381.09
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,381.09
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 765.73
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 765.73
I1. Contractor's Profit (CP) - As Submitted 8% of G1 510.49
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 510.49
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 382.87
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 382.87
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,040.17
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,040.17

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(8) Structural Concrete (27.58 Mpa @ 28 days)


Unit of Measurement : m³
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 6 1.00 50.25 301.50
. - -
Sub - Total for A1 (As Submitted) 521.98
A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 6 1.00 50.25 301.50

Sub - Total for A2 (As Evaluated) 521.98


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 52.20

Sub - Total for B1 (As Submitted) 795.22


B2. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 52.20

Sub - Total for B2 (As Evaluated) 795.22


C1. Total (A1 + B1) 1,317.20
C2. Total (A2 + B2) 1,317.20
D1. Output per our - As Submitted = 3.72 m³
D2. Output per our - As Evaluated = 3.72 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 354.09
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 354.09
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F1 (As Submitted) 6,027.00


F2. Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F2 (As Evaluated) 6,027.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,381.09
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,381.09
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 765.73
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 765.73
I1. Contractor's Profit (CP) - As Submitted 8% of G1 510.49
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 510.49
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 382.87
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 382.87
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,040.17
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,040.17

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)a Reinforcing Steel (Deformed), Grade 40


Unit of Measurement : Kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 3 1.00 65.14 195.42
c. Unskilled Laborer 12 1.00 50.25 603.00

Sub - Total for A1 (As Submitted) 888.62


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 3 1.00 65.14 195.42
c. Unskilled Laborer 12 1.00 50.25 603.00

Sub - Total for A2 (As Evaluated) 888.62


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 88.86

Sub - Total for B1 (As Submitted) 374.49


B2. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 88.86

Sub - Total for B2 (As Evaluated) 374.49


C1. Total (A1 + B1) 1,263.11
C2. Total (A2 + B2) 1,263.11
D1. Output per our - As Submitted = 129.09 Kg
D2. Output per our - As Evaluated = 129.09 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 9.78
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 9.78
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reinforcing Steel Bars Deformed Grade 40 kg 1.000 37.50 37.50


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. c. Consumables (5% of Materials Cost) 1.94 1.94

Sub - Total for F1 (As Submitted) 40.64


F2. Materials

a. Reinforcing Steel Bars Deformed Grade 40 kg 1.000 37.50 37.50


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. c. Consumables (5% of Materials Cost) 1.94 1.94

Sub - Total for F2 (As Evaluated) 40.64


G1. Direct Unit Cost (E1 + F1) - As Submitted 50.42
G2. Direct Unit Cost (E2 + F2) - As Evaluated 50.42
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6.05
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.05
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.03
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.03
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.03
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.03
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 63.53
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 63.53

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)b Reinforcing Steel (Deformed), Grade 60


Unit of Measurement : Kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 3 1.00 65.14 195.42
c. Unskilled Laborer 12 1.00 50.25 603.00

Sub - Total for A1 (As Submitted) 888.62


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 3 1.00 65.14 195.42
c. Unskilled Laborer 12 1.00 50.25 603.00

Sub - Total for A2 (As Evaluated) 888.62


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 88.86

Sub - Total for B1 (As Submitted) 374.49


B2. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 88.86

Sub - Total for B2 (As Evaluated) 374.49


C1. Total (A1 + B1) 1,263.11
C2. Total (A2 + B2) 1,263.11
D1. Output per our - As Submitted = 129.09 Kg
D2. Output per our - As Evaluated = 129.09 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 9.78
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 9.78
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reinforcing Steel Bars Deformed Grade 60 kg 1.000 38.53 38.53


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99 1.99

Sub - Total for F1 (As Submitted) 41.72


F2. Materials

a. Reinforcing Steel Bars Deformed Grade 60 kg 1.000 38.53 38.53


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99 1.99

Sub - Total for F2 (As Evaluated) 41.72


G1. Direct Unit Cost (E1 + F1) - As Submitted 51.50
G2. Direct Unit Cost (E2 + F2) - As Evaluated 51.50
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6.18
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.18
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.12
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.12
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.09
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.09
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 64.89
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 64.89

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 903(2) Formworks & Falseworks


Unit of Measurement : m²
Output per hour : 4.500

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 4 1.00 65.14 260.56
c. Unskilled Laborer 6 1.00 50.25 301.50
Stripping
a. Construction Foreman 1 0.56 90.20 50.51
b. Unskilled Laborer 6 0.56 50.25 168.84
Sub - Total for A1 (As Submitted) 871.61
A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 4 1.00 65.14 260.56
c. Unskilled Laborer 6 1.00 50.25 301.50
Stripping
a. Construction Foreman 1 0.56 90.20 50.51
b. Unskilled Laborer 6 0.56 50.25 168.84
Sub - Total for A2 (As Evaluated) 871.61
Name and Capacity No of Unit/s No. of Day/s Daily R. Rate Amount (PhP)
B1.
Equipment
Area = 205.01 m²
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2pcs H-frames
4pcs diagonal cross braces
4pcs Horizontal cross braces
8pcs joint pins
b. Shoring Jack,3.8 m full extension 62 14.00 4.50 3,906.00
c. Adj. U-Head Jack, 0.60m 80 14.00 0.85 952.00
d. Adj. Base Jack, 0.60m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Not 558 14.00 0.15 1,171.80

Sub - Total for B1 (As Submitted) 19,024.60


B2. Equipment
Area = 205.01 m²
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2pcs H-frames
4pcs diagonal cross braces
4pcs Horizontal cross braces
8pcs joint pins
b. Shoring Jack,3.8 m full extension 62 14.00 4.50 3,906.00
c. Adj. U-Head Jack, 0.60m 80 14.00 0.85 952.00
d. Adj. Base Jack, 0.60m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Not 558 14.00 0.15 1,171.80

Sub - Total for B2 (As Evaluated) 19,024.60


C1. Sub-Total for C1 (B1/Area) 92.80
C2. Sub-Total for C2 (B2/Area) 92.80
D1. Output per our - As Submitted = 4.50 m²
D2. Output per our - As Evaluated = 4.50 m²
E1. Direct Unit Cost (A1 ÷ D1) + C1 - As Submitted 286.49
E2. Direct Unit Cost (A2 ÷ D2) + C2 - As Submitted 286.49
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses pc. 0.347 1,450.00 100.63
b. Good Lumber - 3 Uses bd.ft. 4.727 60.00 94.54
d. Consumables (5% of Material Cost) 9.76

Sub - Total for F1 (As Submitted) 204.93


F2. Materials
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses pc. 0.347 1,450.00 100.63
b. Good Lumber - 3 Uses bd.ft. 4.727 60.00 94.54
d. Consumables (5% of Material Cost) 9.76

Sub - Total for F2 (As Evaluated) 204.93


G1. Direct Unit Cost (E1 + F1) - As Submitted 491.42
G2. Direct Unit Cost (E2 + F2) - As Evaluated 491.42
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 58.97
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 58.97
I1. Contractor's Profit (CP) - As Submitted 8% of G1 39.31
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 39.31
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 29.49
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 29.49
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 619.19
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 619.19
Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : L
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A1 (As Submitted) 255.84


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 255.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B1 (As Submitted) 25.58


B2. Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B2 (As Evaluated) 25.58


C1. Total (A1 + B1) 281.42
C2. Total (A2 + B2) 281.42
D1. Output per our - As Submitted = 5.40 L
D2. Output per our - As Evaluated = 5.40 L
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 52.12
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 52.12
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Soil Poisoning L 1.00 255.00 255.00

Sub - Total for F1 (As Submitted) 255.00


F2. Materials

a. Soil Poisoning L 1.00 255.00 255.00

Sub - Total for F2 (As Evaluated) 255.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 307.12
G2. Direct Unit Cost (E2 + F2) - As Evaluated 307.12
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 36.85
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 36.85
I1. Contractor's Profit (CP) - As Submitted 8% of G1 24.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 24.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 18.43
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 18.43
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 386.97
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 386.97

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
Unit of Measurement : m2
Output per hour : 3.825
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 371.23


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 371.23


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment
a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00
b. Minor Tools (10% of Labor Cost) 37.12

Sub - Total for B1 (As Submitted) 209.12


B2. Equipment

a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00


b. Minor Tools (10% of Labor Cost) 37.12

Sub - Total for B2 (As Evaluated) 209.12


C1. Total (A1 + B1) 580.35
C2. Total (A2 + B2) 580.35
D1. Output per our - As Submitted = 3.83 m2
D2. Output per our - As Evaluated = 3.83 m2
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 151.73
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 151.73
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. CHB Ordinary (101mm x 203mm x 406mm) pcs 13.00 15.00 195.00


b. Portland Cement bag 0.525 250.00 131.25
c. Sand cu.m 0.04 1,380.00 55.20
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F1 (As Submitted) 484.45


F2. Materials

a. CHB Ordinary (101mm x 203mm x 406mm) pcs 13.00 15.00 195.00


b. Portland Cement bag 0.525 250.00 131.25
c. Sand cu.m 0.04 1,380.00 55.20
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F2 (As Evaluated) 484.45


G1. Direct Unit Cost (E1 + F1) - As Submitted 636.18
G2. Direct Unit Cost (E2 + F2) - As Evaluated 636.18
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 76.34
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 76.34
I1. Contractor's Profit (CP) - As Submitted 8% of G1 50.89
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 50.89
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 38.17
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 38.17
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 801.58
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 801.58

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
Unit of Measurement : m2
Output per hour : 3.18
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 371.23


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 371.23


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00


b. Minor Tools (10% of Labor Cost) 37.12

Sub - Total for B1 (As Submitted) 209.12


B2. Equipment
a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00
b. Minor Tools (10% of Labor Cost) 37.12

Sub - Total for B2 (As Evaluated) 209.12


C1. Total (A1 + B1) 580.35
C2. Total (A2 + B2) 580.35
D1. Output per our - As Submitted = 3.18 m2
D2. Output per our - As Evaluated = 3.18 m2
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 182.50
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 182.50
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. CHB Ordinary (150mm x 230mm x 406mm) pcs 13.00 18.00 234.00


b. Portland Cement bag 1.50 250.00 375.00
c. Sand cu.m 0.04 1,380.00 55.20
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F1 (As Submitted) 767.20


F2. Materials

a. CHB Ordinary (150mm x 230mm x 406mm) pcs 13.000 18.000 234.00


b. Portland Cement bag 1.500 250.000 375.00
c. Sand cu.m 0.04 1380.000 55.20
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.640 37.500 99.00
e. GI Tie Wire #16 kg 0.050 80.000 4.00

Sub - Total for F2 (As Evaluated) 767.20


G1. Direct Unit Cost (E1 + F1) - As Submitted 949.70
G2. Direct Unit Cost (E2 + F2) - As Evaluated 949.70
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 113.96
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 113.96
I1. Contractor's Profit (CP) - As Submitted 8% of G1 75.98
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 75.98
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 56.98
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 56.98
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,196.62
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,196.62

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors & Windows


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 224.00 90.20 20,204.80


b. Skilled Laborer 1 224.00 65.14 14,591.36
c. Unskilled Laborer 1 224.00 50.25 11,256.00

Sub - Total for A1 (As Submitted) 46,052.16


A2. Labor

a. Construction Foreman 1 224.00 90.20 20,204.80


b. Skilled Laborer 1 224.00 65.14 14,591.36
c. Unskilled Laborer 1 224.00 50.25 11,256.00

Sub - Total for A2 (As Evaluated) 46,052.16


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 4,605.22

Sub - Total for B1 (As Submitted) 4,605.22


B2. Equipment

a. Minor Tools (10% of Labor Cost) 4,605.22

Sub - Total for B2 (As Evaluated) 4,605.22


C1. Total (A1 + B1) 50,657.38
C2. Total (A2 + B2) 50,657.38
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 50,657.38
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 50,657.38
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Door Jamb (D-1) bd.ft. 402.000 100.00 40,200.00


b. Door Jamb (D-2) bd.ft. 131.200 100.00 13,120.00
c. Door Jamb (D-3) bd.ft. 34.160 100.00 3,416.00
d. Door Jamb (D-3a) bd.ft. 65.600 100.00 6,560.00
e. Door Jamb (BD-1) bd.ft. 111.80 100.00 11,180.00
f. Window Jamb (W-2) bd.ft. 484.80 100.00 48,480.00
g. Consumables (5% of Materials Cost) . 6,147.80

Sub - Total for F1 (As Submitted) 129,103.80


F2. Materials

a. Door Jamb (D-1) bd.ft. 402.000 100.00 40,200.00


b. Door Jamb (D-2) bd.ft. 131.200 100.00 13,120.00
c. Door Jamb (D-3) bd.ft. 34.160 100.00 3,416.00
d. Door Jamb (D-3a) bd.ft. 65.600 100.00 6,560.00
e. Door Jamb (BD-1) bd.ft. 111.800 100.00 11,180.00
f. Window Jamb (W-2) bd.ft. 484.800 100.00 48,480.00
g. Consumables (5% of Materials Cost) 6,147.80

Sub - Total for F2 (As Evaluated) 129,103.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 179,761.18
G2. Direct Unit Cost (E2 + F2) - As Evaluated 179,761.18
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 21,571.34
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 21,571.34
I1. Contractor's Profit (CP) - As Submitted 8% of G1 14,380.89
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 14,380.89
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 10,785.67
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 10,785.67
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 226,499.08
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 226,499.08

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)a Door (Flush)


Unit of Measurement : m²
Output per hour : 0.320

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 0.32 m²
D2. Output per our - As Evaluated = 0.32 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 706.72
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 706.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Flush hollow core door m² 1.000 700.00 700.00

Sub - Total for F1 (As Submitted) 700.00


F2. Materials

a. Flush hollow core door m² 1.000 700.00 700.00

Sub - Total for F2 (As Evaluated) 700.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,406.72
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,406.72
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 168.81
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 168.81
I1. Contractor's Profit (CP) - As Submitted 8% of G1 112.54
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 112.54
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 84.40
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 84.40
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,772.46
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,772.46

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Door (Wooden Panel)


Unit of Measurement : m²
Output per hour : 0.360

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A1 (As Submitted) 255.84


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 255.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B1 (As Submitted) 25.58


B2. Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B2 (As Evaluated) 25.58


C1. Total (A1 + B1) 281.42
C2. Total (A2 + B2) 281.42
D1. Output per our - As Submitted = 0.36 m²
D2. Output per our - As Evaluated = 0.36 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 781.73
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 781.73
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Wooden Panel Door m² 1.000 5,500.00 5,500.00

Sub - Total for F1 (As Submitted) 5,500.00


F2. Materials

a. Wooden Panel Door m² 1.000 5,500.00 5,500.00

Sub - Total for F2 (As Evaluated) 5,500.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,281.73
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,281.73
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 753.81
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 753.81
I1. Contractor's Profit (CP) - As Submitted 8% of G1 502.54
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 502.54
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 376.90
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 376.90
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 7,914.98
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 7,914.98

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(17) Carpentry and Joinery Works


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 64.00 90.20 5,772.80


b. Skilled Laborer 1 64.00 65.14 4,168.96
c. Unskilled Laborer 1 64.00 50.25 3,216.00

Sub - Total for A1 (As Submitted) 13,157.76


A2. Labor

a. Construction Foreman 1 64.00 90.20 5,772.80


b. Skilled Laborer 1 64.00 65.14 4,168.96
c. Unskilled Laborer 1 64.00 50.25 3,216.00

Sub - Total for A2 (As Evaluated) 13,157.76


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 1,315.78

Sub - Total for B1 (As Submitted) 1,315.78


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1,315.78

Sub - Total for B2 (As Evaluated) 1,315.78


C1. Total (A1 + B1) 14,473.54
C2. Total (A2 + B2) 14,473.54
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 14,473.54
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 14,473.54
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Blackboard Set 12.000 3,400.00 40,800.00

Sub - Total for F1 (As Submitted) 40,800.00


F2. Materials

a. Blackboard Set 12.000 3,400.00 40,800.00

Sub - Total for F2 (As Evaluated) 40,800.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 55,273.54
G2. Direct Unit Cost (E2 + F2) - As Evaluated 55,273.54
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6,632.82
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6,632.82
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4,421.88
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4,421.88
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3,316.41
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3,316.41
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 69,644.66
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 69,644.66

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006(4) Steel Louver Door


Unit of Measurement : m²
Output per hour : 0.260

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 118.31


B2. Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 118.31


C1. Total (A1 + B1) 323.90
C2. Total (A2 + B2) 323.90
D1. Output per our - As Submitted = 0.26 m²
D2. Output per our - As Evaluated = 0.26 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,245.77
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,245.77
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Steel Louver Door m² 1.000 5,500.00 5,500.00

Sub - Total for F1 (As Submitted) 5,500.00


F2. Materials

a. Steel Louver Door m² 1.000 5,500.00 5,500.00

Sub - Total for F2 (As Evaluated) 5,500.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,745.77
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,745.77
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 809.49
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 809.49
I1. Contractor's Profit (CP) - As Submitted 8% of G1 539.66
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 539.66
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 404.75
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 404.75
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,499.66
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,499.66

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(1) Residential Casement Steel Window


Unit of Measurement : m²
Output per hour : 0.180

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


b. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 118.31


B2. Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


b. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 118.31


C1. Total (A1 + B1) 323.90
C2. Total (A2 + B2) 323.90
D1. Output per our - As Submitted = 0.18 m²
D2. Output per our - As Evaluated = 0.18 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,799.44
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,799.44
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Steel Casement Window m² 1.000 1,900.00 1,900.00


b. Consumables (5% of Materials Cost) 95.00

Sub - Total for F1 (As Submitted) 1,995.00


F2. Materials

a. Steel Casement Window m² 1.000 1,900.00 1,900.00


b. Consumables (5% of Materials Cost) 95.00

Sub - Total for F2 (As Evaluated) 1,995.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,794.44
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,794.44
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 455.33
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 455.33
I1. Contractor's Profit (CP) - As Submitted 8% of G1 303.56
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 303.56
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 227.67
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 227.67
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,780.99
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,780.99

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(6) Window Accessory


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 112.00 90.20 10,102.40


b. Skilled Laborer 1 112.00 65.14 7,295.68
c. Unskilled Laborer 1 112.00 50.25 5,628.00

Sub - Total for A1 (As Submitted) 23,026.08


A2. Labor

a. Construction Foreman 1 112.00 90.20 10,102.40


b. Skilled Laborer 1 112.00 65.14 7,295.68
c. Unskilled Laborer 1 112.00 50.25 5,628.00

Sub - Total for A2 (As Evaluated) 23,026.08


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 4.00 391.00 1,564.00


b. Minor Tools (10% of Labor Cost) 2,302.61

Sub - Total for B1 (As Submitted) 3,866.61


B2. Equipment

a. Welding Machine (500) 1 4.00 391.00 1,564.00


b. Minor Tools (10% of Labor Cost) 2,302.61

Sub - Total for B2 (As Evaluated) 3,866.61


C1. Total (A1 + B1) 26,892.69
C2. Total (A2 + B2) 26,892.69
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 26,892.69
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 26,892.69
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Window Grill
a. 12 mm x 12 mm Sq. Bar Kg 1,085.184 60.00 65,111.04
c. Consumables (3% of Materials Cost) 1,953.33

Sub - Total for F1 (As Submitted) 67,064.37


F2. Materials

Window Grill
a. 12 mm x 12 mm Sq. Bar Kg 1,085.184 60.00 65,111.04
c. Consumables (3% of Materials Cost) 1,953.33

Sub - Total for F2 (As Evaluated) 67,064.37


G1. Direct Unit Cost (E1 + F1) - As Submitted 93,957.06
G2. Direct Unit Cost (E2 + F2) - As Evaluated 93,957.06
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 11,274.85
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 11,274.85
I1. Contractor's Profit (CP) - As Submitted 8% of G1 7,516.56
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 7,516.56
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 5,637.42
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 5,637.42
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 118,385.89
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 118,385.89

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1009(1)a Jalousie Window (Glass)


Unit of Measurement : m²
Output per hour : 0.270

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 0.27 m²
D2. Output per our - As Evaluated = 0.27 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 837.59
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 837.59
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Jalousie Window (Glass, Inc. Jalousie Casing) m² 1.000 2,222.00 2,222.00


b. Consumables (3% of Materials Cost) 66.66

Sub - Total for F1 (As Submitted) 2,288.66


F2. Materials

a. Jalousie Window (Glass, Inc. Jalousie Casing) m² 1.000 2,222.00 2,222.00


b. Consumables (3% of Materials Cost) 66.66

Sub - Total for F2 (As Evaluated) 2,288.66


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,126.25
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,126.25
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 375.15
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 375.15
I1. Contractor's Profit (CP) - As Submitted 8% of G1 250.10
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 250.10
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 187.57
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 187.57
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 3,939.07
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 3,939.07

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2) Finishing Hardware


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.

Sub - Total for A1 (As Submitted)


A2. Labor

a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.

Sub - Total for A2 (As Evaluated)


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Sub - Total for B1 (As Submitted) -


B2. Equipment

Sub - Total for B2 (As Evaluated) -


C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. door locks (schlage or equivalent) Set 34.00 510.00 17,340.00


b. hinge (50mm x 101mm) pc 136.00 70.00 9,520.00

Sub - Total for F1 (As Submitted) 26,860.00


F2. Materials

a. door locks (schlage or equivalent) Set 34.00 510.00 17,340.00


b. hinge (50mm x 101mm) pc 136.00 70.00 9,520.00

Sub - Total for F2 (As Evaluated) 26,860.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 26,860.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 26,860.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 3,223.20
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 3,223.20
I1. Contractor's Profit (CP) - As Submitted 8% of G1 2,148.80
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 2,148.80
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 1,611.60
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 1,611.60
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 33,843.60
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 33,843.60

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1051(6) Railing


Unit of Measurement : L.s.
Output per hour : 1.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 160.00 90.20 14,432.00


b. Skilled Laborer 2 160.00 65.14 20,844.80
c. Unskilled Laborer 4 160.00 50.25 32,160.00

Sub - Total for A1 (As Submitted) 67,436.80


A2. Labor

a. Construction Foreman 1 160.00 90.20 14,432.00


b. Skilled Laborer 2 160.00 65.14 20,844.80
c. Unskilled Laborer 4 160.00 50.25 32,160.00

Sub - Total for A2 (As Evaluated) 67,436.80


No. of
B1. Name and Capacity No of Unit/s Hourly Rate Amount (PhP)
Hour/s
Equipment

a. Welding Machine (500) 1 120.00 391.00 46,920.00


b. Cutting Outfit 1 40.00 45.45 1,818.00
c. Minor Tools (10% of Labor Cost) 6,743.68

Sub - Total for B1 (As Submitted) 55,481.68


B2. Equipment

a. Welding Machine (500) 1 120.00 391.00 46,920.00


b. Cutting Outfit 1 40.00 45.45 1,818.00
c. Minor Tools (10% of Labor Cost) 6,743.68

Sub - Total for B2 (As Evaluated) 55,481.68


C1. Total (A1 + B1) 122,918.48
C2. Total (A2 + B2) 122,918.48
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 122,918.48
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 122,918.48
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. 50 mm Ø G.I. Pipe (Stainless) pc. 15.00 2,480.00 37,200.00


b. G.I Pipes (50mm D) pc 27.00 1,500.00 40,500.00
c. 19 mm bar kg. 3,406.00 60.00 204,360.00
d. 12 mm dia. bar kg. 346.00 60.00 20,760.00
e. Welding Rod kg. 56.28 110.00 6,190.80
f. Consumables (5% of material cost) 15,450.54

Sub - Total for F1 (As Submitted) 324,461.34


F2. Materials

a. 50 mm Ø G.I. Pipe (Stainless) pc. 15.00 2,480.00 37,200.00


b. G.I Pipes (50mm D) pc 27.00 1,500.00 40,500.00
c. 19 mm bar kg. 3,406.00 60.00 204,360.00
d. 12 mm dia. bar kg. 346.00 60.00 20,760.00
e. Welding Rod kg. 56.28 110.00 6,190.80
f. Consumables (5% of material cost) 15,450.54

Sub - Total for F2 (As Evaluated) 324,461.34


G1. Direct Unit Cost (E1 + F1) - As Submitted 447,379.82
G2. Direct Unit Cost (E2 + F2) - As Evaluated 447,379.82
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 53,685.58
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 53,685.58
I1. Contractor's Profit (CP) - As Submitted 8% of G1 35,790.39
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 35,790.39
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 26,842.79
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 26,842.79
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 563,698.57
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 563,698.57

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1027(1) Cement Plaster Finish


Unit of Measurement : m²
Output per hour : 7.125

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 4 1.00 50.25 201.00

Sub - Total for A1 (As Submitted) 421.48


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 4 1.00 50.25 201.00

Sub - Total for A2 (As Evaluated) 421.48


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 42.15

Sub - Total for B1 (As Submitted) 42.15


B2. Equipment

a. Minor Tools (10% of Labor Cost) 42.15

Sub - Total for B2 (As Evaluated) 42.15


C1. Total (A1 + B1) 463.63
C2. Total (A2 + B2) 463.63
D1. Output per our - As Submitted = 7.125 m²
D2. Output per our - As Evaluated = 7.125 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 65.07
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 65.07
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Portland Cement Bag 0.300 250.00 75.00


b. Sand m³ 0.027 1,380.00 37.26

Sub - Total for F1 (As Submitted) 112.26


F2. Materials

a. Portland Cement Bag 0.300 250.00 75.00


b. Sand m³ 0.027 1,380.00 37.26

Sub - Total for F2 (As Evaluated) 112.26


G1. Direct Unit Cost (E1 + F1) - As Submitted 177.33
G2. Direct Unit Cost (E2 + F2) - As Evaluated 177.33
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 21.28
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 21.28
I1. Contractor's Profit (CP) - As Submitted 8% of G1 14.19
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 14.19
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 10.64
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 10.64
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 223.44
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 223.44

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(1)a Cement Floor Finish (Plain)


Unit of Measurement : m²
Output per hour : 5.950

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A1 (As Submitted) 306.09


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 3 1.00 50.25 150.75

Sub - Total for A2 (As Evaluated) 306.09


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Power Throwel 1 1.00 310.00 310.00


b. Minor Tools (10% of Labor Cost) 30.61

Sub - Total for B1 (As Submitted) 340.61


B2. Equipment

a. Power Throwel 1 1.00 310.00 310.00


b. Minor Tools (10% of Labor Cost) 30.61

Sub - Total for B2 (As Evaluated) 340.61


C1. Total (A1 + B1) 646.70
C2. Total (A2 + B2) 646.70
D1. Output per our - As Submitted = 5.950 m²
D2. Output per our - As Evaluated = 5.950 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 108.69
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 108.69
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 108.69
G2. Direct Unit Cost (E2 + F2) - As Evaluated 108.69
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 13.04
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 13.04
I1. Contractor's Profit (CP) - As Submitted 8% of G1 8.70
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 8.70
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 6.52
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 6.52
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 136.95
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 136.95

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
Unit of Measurement : m²
Output per hour : 1.243

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A1 (As Submitted) 255.84


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 255.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B1 (As Submitted) 25.58


B2. Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B2 (As Evaluated) 25.58


C1. Total (A1 + B1) 281.42
C2. Total (A2 + B2) 281.42
D1. Output per our - As Submitted = 1.243 m²
D2. Output per our - As Evaluated = 1.243 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 226.41
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 226.41
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 4.5mm Fiber Cement Board pc 0.365 450.00 164.25


b. Metal Furring pc 1.131 130.00 147.03
c. and specifications
Carrying Channels) 3m length pc 0.357 150.00 53.55
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 20.00 120.00
f. Wall Angle pc 0.238 100.00 23.80
g. Rivets pc 14 1.50 21.00
h. 1" Metal Screw pc 4 3.00 12.00

Sub - Total for F1 (As Submitted) 621.63


F2. Materials

a. 4.5mm Fiber Cement Board pc 0.365 450.00 164.25


b. Metal Furring pc 1.131 130.00 147.03
c. Carrying Channels pc 0.357 150.00 53.55
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 20.00 120.00
f. Wall Angle pc 0.238 100.00 23.80
g. Rivets pc 14 1.50 21.00
h. 1" Metal Screw pc 4 3.00 12.00

Sub - Total for F2 (As Evaluated) 621.63


G1. Direct Unit Cost (E1 + F1) - As Submitted 848.04
G2. Direct Unit Cost (E2 + F2) - As Evaluated 848.04
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 101.76
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 101.76
I1. Contractor's Profit (CP) - As Submitted 8% of G1 67.84
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 67.84
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 50.88
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 50.88
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,068.53
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,068.53

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(11)a1 Fascia Board (19mm, Fiber Cement Board)


Unit of Measurement : Lm
Output per hour : 3.600

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 0.50 90.20 45.10


b. Skilled Laborer 1 0.50 65.14 32.57

Sub - Total for A1 (As Submitted) 77.67


A2. Labor

a. Construction Foreman 1 0.50 90.20 45.10


b. Skilled Laborer 1 0.50 65.14 32.57

Sub - Total for A2 (As Evaluated) 77.67


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 7.77

Sub - Total for B1 (As Submitted) 7.77


B2. Equipment

a. Minor Tools (10% of Labor Cost) 7.77

Sub - Total for B2 (As Evaluated) 7.77


C1. Total (A1 + B1) 85.44
C2. Total (A2 + B2) 85.44
D1. Output per our - As Submitted = 3.600 Lm
D2. Output per our - As Evaluated = 3.600 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 23.73
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 23.73
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 2-12 x 300mm Fiber Cement Board m 1.000 145.00 145.00


b. 1" Metal Screws pc 12.000 3.00 36.00
c. Consumables (5% of Materials Cost) 9.05

Sub - Total for F1 (As Submitted) 190.05


F2. Materials

a. 2-12 x 300mm Fiber Cement Board m 1.000 145.00 145.00


b. 1" Metal Screws m³ 12.000 3.00 36.00
c. Consumables (5% of Materials Cost) 9.05

Sub - Total for F2 (As Evaluated) 190.05


G1. Direct Unit Cost (E1 + F1) - As Submitted 213.78
G2. Direct Unit Cost (E2 + F2) - As Evaluated 213.78
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 25.65
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 25.65
I1. Contractor's Profit (CP) - As Submitted 8% of G1 17.10
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 17.10
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 12.83
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 12.83
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 269.37
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 269.37

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


Unit of Measurement : m²
Output per hour : 5.560

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A1 (As Submitted) 255.84


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 255.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B1 (As Submitted) 25.58


B2. Equipment

a. Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B2 (As Evaluated) 25.58


C1. Total (A1 + B1) 281.42
C2. Total (A2 + B2) 281.42
D1. Output per our - As Submitted = 5.560 m²
D2. Output per our - As Evaluated = 5.560 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 50.62
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 50.62
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reflective Insulation, 10 mm thk m² 1.000 135.00 135.00


b. Consumable Materials (5% of Mat'l. Cost) 6.75

Sub - Total for F1 (As Submitted) 141.75


F2. Materials

a. Reflective Insulation, 10 mm thk m² 1.000 135.00 135.00


b. Consumable Materials (5% of Mat'l. Cost) 6.75

Sub - Total for F2 (As Evaluated) 141.75


G1. Direct Unit Cost (E1 + F1) - As Submitted 192.37
G2. Direct Unit Cost (E2 + F2) - As Evaluated 192.37
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 23.08
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 23.08
I1. Contractor's Profit (CP) - As Submitted 8% of G1 15.39
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 15.39
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11.54
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11.54
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 242.38
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 242.38

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(1) Glazed Tiles and Trims


Unit of Measurement : m²
Output per hour : 1.365

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 5 1.00 65.14 325.70
c. Unskilled Laborer 5 1.00 50.25 251.25

Sub - Total for A1 (As Submitted) 667.15


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 5 1.00 65.14 325.70
c. Unskilled Laborer 5 1.00 50.25 251.25

Sub - Total for A2 (As Evaluated) 667.15


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% Labor Cost) 66.72

Sub - Total for B1 (As Submitted) 66.72


B2. Equipment

a. Minor Tools (10% Labor Cost) 66.72

Sub - Total for B2 (As Evaluated) 66.72


C1. Total (A1 + B1) 733.87
C2. Total (A2 + B2) 733.87
D1. Output per our - As Submitted = 1.365 m²
D2. Output per our - As Evaluated = 1.365 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 537.63
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 537.63
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ceramic Glazed Tiles m² 1.05 750.00 787.50


c. Portland Cement bags 0.325 250.00 81.25
d. Sand m³ 0.026 1,380.00 35.88
e. Tile Grout bags 0.125 250.00 31.25
f. Tile Adhesive (25kg) bags 0.143 250.00 35.75
g. Consumables (3% of Material Cost) 29.15

Sub - Total for F1 (As Submitted) 1,000.78


F2. Materials

a. Ceramic Glazed Tiles m² 1.05 750.00 787.50


c. Portland Cement bags 0.325 250.00 81.25
d. Sand m³ 0.026 1,380.00 35.88
e. Tile Grout bags 0.125 250.00 31.25
f. Tile Adhesive (25kg) bags 0.143 250.00 35.75
g. Consumables (3% of Material Cost) 29.15

Sub - Total for F2 (As Evaluated) 1,000.78


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,538.41
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,538.41
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 184.61
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 184.61
I1. Contractor's Profit (CP) - As Submitted 8% of G1 123.07
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 123.07
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 92.30
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 92.30
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,938.40
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,938.40

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(2) Unlglazed Tiles


Unit of Measurement : m²
Output per hour : 1.950

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 5 1.00 65.14 325.70
c. Unskilled Laborer 5 1.00 50.25 251.25

Sub - Total for A1 (As Submitted) 667.15


A2. Labor

a. Construction Foreman 1 1 90.20 90.20


b. Skilled Laborer 5 1 65.14 325.70
c. Unskilled Laborer 5 1 50.25 251.25

Sub - Total for A2 (As Evaluated) 667.15


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% Labor Cost) 66.72

Sub - Total for B1 (As Submitted) 66.72


B2. Equipment

a. Minor Tools (10% Labor Cost) 66.72

Sub - Total for B2 (As Evaluated) 66.72


C1. Total (A1 + B1) 733.87
C2. Total (A2 + B2) 733.87
D1. Output per our - As Submitted = 1.95 m²
D2. Output per our - As Evaluated = 1.95 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 376.34
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 376.34
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ceramic Unglazed Tiles m² 1.05 350.00 367.50


b. Portland Cement bags 0.325 250.00 81.25
c. Sand m³ 0.026 1,380.00 35.88
d. Tile Grout bags 0.125 250.00 31.25
e. Consumable (3% of Materials Cost) 25.79

Sub - Total for F1 (As Submitted) 541.67


F2. Materials

a. Ceramic Unglazed Tiles m² 1.05 350.00 367.50


b. Portland Cement bags 0.325 250.00 81.25
c. Sand m³ 0.026 1,380.00 35.88
d. Tile Grout bags 0.125 250.00 31.25
e. Consumable (3% of Materials Cost) 25.79

Sub - Total for F2 (As Evaluated) 541.67


G1. Direct Unit Cost (E1 + F1) - As Submitted 918.02
G2. Direct Unit Cost (E2 + F2) - As Evaluated 918.02
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 110.16
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 110.16
I1. Contractor's Profit (CP) - As Submitted 8% of G1 73.44
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 73.44
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 55.08
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 55.08
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,156.70
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,156.70

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(1)a Water Proofing Cement Base


Unit of Measurement : m²
Output per hour : 1.875

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 1.88 m²
D2. Output per our - As Evaluated = 1.88 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 120.61
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 120.61
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Cement - Based Water Proofing m² 1.05 55.00 57.75

Sub - Total for F1 (As Submitted) 57.75


F2. Materials

a. Cement - Based Water Proofing m² 1.05 55.00 57.75

Sub - Total for F2 (As Submitted) 57.75


G1. Direct Unit Cost (E1 + F1) - As Submitted 178.36
G2. Direct Unit Cost (E2 + F2) - As Evaluated 178.36
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 21.40
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 21.40
I1. Contractor's Profit (CP) - As Submitted 8% of G1 14.27
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 14.27
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 10.70
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 10.70
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 224.74
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 224.74

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)a Painting Works (Masonry/Concrete)


Unit of Measurement : m²
Output per hour : 2.100

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 270.73


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 270.73


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B1 (As Submitted) 27.07


B2. Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B2 (As Evaluated) 27.07


C1. Total (A1 + B1) 297.80
C2. Total (A2 + B2) 297.80
D1. Output per our - As Submitted = 2.100 m²
D2. Output per our - As Evaluated = 2.100 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 141.81
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 141.81
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Concrete Neutralizer gal 0.02 540.00 10.80


b. Concrete Sealer/Primer gal 0.04 644.00 25.76
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats only) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.72

Sub - Total for F1 (As Submitted) 120.18


F2. Materials

a. Concrete Neutralizer gal 0.02 540.00 10.80


b. Concrete Sealer/Primer gal 0.04 644.00 25.76
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats only) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.72

Sub - Total for F2 (As Evaluated) 120.18


G1. Direct Unit Cost (E1 + F1) - As Submitted 261.99
G2. Direct Unit Cost (E2 + F2) - As Evaluated 261.99
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 31.44
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 31.44
I1. Contractor's Profit (CP) - As Submitted 8% of G1 20.96
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 20.96
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 15.72
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 15.72
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 330.11
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 330.11

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)b Painting Works (Wood Painting)


Unit of Measurement : m²
Output per hour : 1.890

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 270.73


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 270.73


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B1 (As Submitted) 27.07


B2. Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B2 (As Evaluated) 27.07


C1. Total (A1 + B1) 297.80
C2. Total (A2 + B2) 297.80
D1. Output per our - As Submitted = 1.890 m²
D2. Output per our - As Evaluated = 1.890 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 157.57
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 157.57
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Glazzing Putty gal 0.05 550.00 27.50


b. Flat Wall Enamel gal 0.04 600.00 24.00
c. Enamel Quick Dry gal 0.04 600.00 24.00
d. Paint Thinner gal 0.063 280.00 17.64
e. Consumables (5% of Materials Cost) 4.66

Sub - Total for F1 (As Submitted) 97.80


F2. Materials

a. Glazzing Putty gal 0.05 550.00 27.50


b. Flat Wall Enamel gal 0.04 600.00 24.00
c. Enamel Quick Dry gal 0.04 600.00 24.00
d. Paint Thinner gal 0.063 280.00 17.64
e. Consumables (5% of Materials Cost) 4.66

Sub - Total for F2 (As Evaluated) 97.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 255.36
G2. Direct Unit Cost (E2 + F2) - As Evaluated 255.36
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 30.64
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 30.64
I1. Contractor's Profit (CP) - As Submitted 8% of G1 20.43
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 20.43
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 15.32
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 15.32
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 321.76
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 321.76

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)c Painting Works (Steel)


Unit of Measurement : m²
Output per hour : 2.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 270.73


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 270.73


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B1 (As Submitted) 27.07


B2. Equipment

a. Minor Tools (10% of Labor Cost) 27.07

Sub - Total for B2 (As Evaluated) 27.07


C1. Total (A1 + B1) 297.80
C2. Total (A2 + B2) 297.80
D1. Output per our - As Submitted = Area = 2 m²
D2. Output per our - As Evaluated = Area = 2 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 148.90
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 148.90
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Flat Wall Enamel gal 0.10 600.00 60.00
c. Paint Thinner gal 0.063 280.00 17.64
d. Consumable Materials (5% Material Cost) 4.86 4.86

Sub - Total for F1 (As Submitted) 102.10


F2. Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Flat Wall Enamel gal 0.10 600.00 60.00
c. Paint Thinner gal 0.063 280.00 17.64
d. Consumable Materials (5% Material Cost) 4.86 4.86

Sub - Total for F2 (As Evaluated) 102.10


G1. Direct Unit Cost (E1 + F1) - As Submitted 251.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 251.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 30.12
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 30.12
I1. Contractor's Profit (CP) - As Submitted 8% of G1 20.08
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 20.08
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 15.06
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 15.06
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 316.26
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 316.26

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
Unit of Measurement : m²
Output per hour : 2.076

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A1 (As Submitted) 255.84


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 2 1.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 255.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B1 (As Submitted) 25.58


B2. Equipment

Minor Tools (10% of Labor Cost) 25.58

Sub - Total for B2 (As Evaluated) 25.58


C1. Total (A1 + B1) 281.42
C2. Total (A2 + B2) 281.42
D1. Output per our - As Submitted = Area = 2.076 m²
D2. Output per our - As Evaluated = Area = 2.076 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 135.56
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 135.56
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54

Sub - Total for F1 (As Submitted) 430.54


F2. Materials

a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54

Sub - Total for F2 (As Evaluated) 430.54


G1. Direct Unit Cost (E1 + F1) - As Submitted 566.10
G2. Direct Unit Cost (E2 + F2) - As Evaluated 566.10
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 67.93
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 67.93
I1. Contractor's Profit (CP) - As Submitted 8% of G1 45.29
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 45.29
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 33.97
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 33.97
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 713.29
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 713.29

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)a Structural Steel (Trusses)


Unit of Measurement : Kg
Output per hour : 85.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor
Fabrication
a. Construction Foreman 1 1.00 90.20 90.20
b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 2 1.00 50.25 100.50
Erection
b. Skilled Laborer 3 0.49 65.14 95.76
c. Unskilled Laborer 3 0.49 50.25 73.87

Sub - Total for A1 (As Submitted) 490.60


A2. Labor
Fabrication
a. Construction Foreman 1 1.00 90.20 90.20
b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 2 1.00 50.25 100.50
Erection
b. Skilled Laborer 3 0.49 65.14 95.76
c. Unskilled Laborer 3 0.49 50.25 73.87

Sub - Total for A2 (As Evaluated) 490.60


No. of
Name and Capacity No of Unit/s Hourly Rate Amount (PhP)
B1. Hour/s
Equipment

a. Welding Machine (300) 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
d. Minor Tools (10 % of Labor Cost) 108.88

Sub - Total for B1 (As Submitted) 1,197.68


B2. Equipment

a. Welding Machine (300) 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
d. Minor Tools (10 % of Labor Cost) 108.88

Sub - Total for B2 (As Evaluated) 1,197.68


C1. Total (A1 + B1) 1,688.29
C2. Total (A2 + B2) 1,688.29
D1. Output per our - As Submitted = 85.000 Kg
D2. Output per our - As Evaluated = 85.000 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 19.86
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 19.86
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Structural Steel Truss Kg 1.00 60.00 60.00


b. Acetylene Kg 0.011 65.00 0.72
c. Oxygen Kg 0.022 50.00 1.10
d. Welding Rod Kg 0.020 110.00 2.20
e. Consumables Materials (3% of Matl. Cost) 1.92

Sub - Total for F1 (As Submitted) 65.94


F2. Materials

a. Structural Steel Truss Kg 1.000 60.00 60.00


b. Acetylene Kg 0.011 65.00 0.72
c. Oxygen Kg 0.022 50.00 1.10
d. Welding Rod Kg 0.020 110.00 2.20
e. Consumables Materials (3% of Matl. Cost) 1.92

Sub - Total for F2 (As Evaluated) 65.94


G1. Direct Unit Cost (E1 + F1) - As Submitted 85.80
G2. Direct Unit Cost (E2 + F2) - As Evaluated 85.80
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 10.30
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 10.30
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.86
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.86
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 5.15
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 5.15
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 108.11
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 108.11

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)b Structural Steel (Purlins)


Unit of Measurement : Kg
Output per hour : 90.450
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 4 1.00 50.25 201.00

Sub - Total for A1 (As Submitted) 421.48


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 2 1.00 65.14 130.28
c. Unskilled Laborer 4 1.00 50.25 201.00

Sub - Total for A2 (As Evaluated) 421.48


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Welding Machine (300) 2 1.00 371.00 742.00


b. Minor Tools (10% of Labor Cost) 42.15

Sub - Total for B1 (As Submitted) 784.15


B2. Equipment

a. Welding Machine (300) 2 1.00 371.00 742.00


b. Minor Tools (10% of Labor Cost) 42.15

Sub - Total for B2 (As Evaluated) 784.15


C1. Total (A1 + B1) 1,205.63
C2. Total (A2 + B2) 1,205.63
D1. Output per our - As Submitted = 90.45 Kg
D2. Output per our - As Evaluated = 90.45 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 13.33
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 13.33
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Structural Steel Purlins Kgs 1.05 60.00 63.00


b. Welding Rod Kgs 0.02 110.00 2.20
c. Consumables (5% of Materials Cost) 3.26

Sub - Total for F1 (As Submitted) 68.46


F2. Materials

a. Structural Steel Purlins Kgs 1.05 60.00 63.00


b. Welding Rod Kgs 0.02 110.00 2.20
c. Consumables (5% of Materials Cost) 3.26

Sub - Total for F2 (As Evaluated) 68.46


G1. Direct Unit Cost (E1 + F1) - As Submitted 81.79
G2. Direct Unit Cost (E2 + F2) - As Evaluated 81.79
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 9.81
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 9.81
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.54
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.54
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4.91
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4.91
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 103.05
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 103.05

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)


Unit of Measurement : Kg
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 12.995 Kg
D2. Output per our - As Evaluated = 12.995 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 17.40
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 17.40
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Steel Plates Kg 1.05 60.00 63.00


b. Consumables Materials (3% of Matl. Cost) 1.89

Sub - Total for F1 (As Submitted) 64.89


F2. Materials

a. Steel Plates kgs 1.05 60.00 63.00


b. Consumables Materials (3% of Matl. Cost) 1.89

Sub - Total for F2 (As Evaluated) 64.89


G1. Direct Unit Cost (E1 + F1) - As Submitted 82.29
G2. Direct Unit Cost (E2 + F2) - As Evaluated 82.29
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 9.88
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 9.88
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.58
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.58
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4.94
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4.94
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 103.69
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 103.69

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(7)b Metal Structure Accessories (Sagrods)


Unit of Measurement : Kgs
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 12.995 Kgs
D2. Output per our - As Evaluated = 12.995 Kgs
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 17.40
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 17.40
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Sagrod with nuts & Bolts kg 1.05 37.88 39.77

Sub - Total for F1 (As Submitted) 39.77


F2. Materials

a. Sagrod with nuts & Bolts kgs 1.05 37.88 39.77

Sub - Total for F2 (As Evaluated) 39.77


G1. Direct Unit Cost (E1 + F1) - As Submitted 57.18
G2. Direct Unit Cost (E2 + F2) - As Evaluated 57.18
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6.86
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.86
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.43
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.43
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 72.04
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 72.04

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : Kgs
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

a. Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 12.995 Kgs
D2. Output per our - As Evaluated = 12.995 Kgs
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 17.40
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 17.40
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Cross Bracing kg 1.05 37.88 39.77


b. Consumables 1.19

Sub - Total for F1 (As Submitted) 40.97


F2. Materials

a. Cross Bracing kg 1.05 37.88 39.77


b. Consumables

Sub - Total for F2 (As Evaluated) 39.77


G1. Direct Unit Cost (E1 + F1) - As Submitted 58.37
G2. Direct Unit Cost (E2 + F2) - As Evaluated 57.18
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 7.00
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.86
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.67
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.50
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.50
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 73.55
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 73.55

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : ea.
Output per hour : 1.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 0.15 90.20 13.53


b. Skilled Laborer 1 0.15 65.14 9.77
c. Unskilled Laborer 1 0.15 50.25 7.54

Sub - Total for A1 (As Submitted) 30.84


A2. Labor

a. Construction Foreman 1 0.15 90.20 13.53


b. Skilled Laborer 1 0.15 65.14 9.77
c. Unskilled Laborer 1 0.15 50.25 7.54

Sub - Total for A2 (As Evaluated) 30.84


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 3.08

Sub - Total for B1 (As Submitted) 3.08


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3.08

Sub - Total for B2 (As Evaluated) 3.08


C1. Total (A1 + B1) 33.92
C2. Total (A2 + B2) 33.92
D1. Output per our - As Submitted = 1 ea.
D2. Output per our - As Evaluated = 1 ea.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 33.92
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 33.92
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. 16mm Ø turn buckles Pc 1.00 200.00 200.00

Sub - Total for F1 (As Submitted) 200.00


F2. Materials

a. 16mm Ø turn buckles kgs 1.00 200.00 200.00

Sub - Total for F2 (As Evaluated) 200.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 233.92
G2. Direct Unit Cost (E2 + F2) - As Evaluated 233.92
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 28.07
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 28.07
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.71
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.71
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14.04
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14.04
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 294.74
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 294.74

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
Unit of Measurement : L.m.
Output per hour : 10.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 10.00 Lm
D2. Output per our - As Evaluated = 10.00 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 22.61
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 22.61
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted ridge roll, ga.24 (0.701mm) x 2.44mm m 1.05 165.00 173.25


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.05

Sub - Total for F1 (As Submitted) 207.80


F2. Materials

a. pre-painted ridge roll, ga.24 (0.701mm) x 2.44mm m 1.05 165.00 173.25


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.05

Sub - Total for F2 (As Evaluated) 207.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 230.42
G2. Direct Unit Cost (E2 + F2) - As Evaluated 230.42
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 27.65
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 27.65
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.43
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.43
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13.83
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13.83
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 290.33
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 290.33

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
Unit of Measurement : L.m.
Output per hour : 10.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 10.00 Lm
D2. Output per our - As Evaluated = 10.00 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 22.61
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 22.61
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted flashing, ga.24 (0.701mm) x 2.44mm m 1.05 160.00 168.00


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 5.90

Sub - Total for F1 (As Submitted) 202.40


F2. Materials

a. pre-painted flashing, ga.24 (0.701mm) x 2.44mm m 1.05 160.00 168.00


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 5.90

Sub - Total for F2 (As Evaluated) 202.40


G1. Direct Unit Cost (E1 + F1) - As Submitted 225.01
G2. Direct Unit Cost (E2 + F2) - As Evaluated 225.01
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 27.00
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 27.00
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.00
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.00
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13.50
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13.50
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 283.51
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 283.51

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)


Unit of Measurement : L.m.
Output per hour : 11.800

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A1 (As Submitted) 205.59


A2. Labor

a. Construction Foreman 1 1.00 90.20 90.20


b. Skilled Laborer 1 1.00 65.14 65.14
c. Unskilled Laborer 1 1.00 50.25 50.25

Sub - Total for A2 (As Evaluated) 205.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B1 (As Submitted) 20.56


B2. Equipment

Minor Tools (10% of Labor Cost) 20.56

Sub - Total for B2 (As Evaluated) 20.56


C1. Total (A1 + B1) 226.15
C2. Total (A2 + B2) 226.15
D1. Output per our - As Submitted = 11.80 L.m.
D2. Output per our - As Evaluated = 11.80 L.m.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 19.17
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 19.17
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted gutter, ga.24 (0.701mm) x 2.44mm m 1.00 175.00 175.00


b. 12" x 1" Plain GI Strap pc 3.00 40.00 120.00
c. Blind Rivets pc 16.00 1.50 24.00
d. Consumables (3% of Materials Cost) 9.57

Sub - Total for F1 (As Submitted) 328.57


F2. Materials

a. pre-painted gutter, ga.24 (0.701mm) x 2.44mm m 1.00 175.00 175.00


b. 12" x 1" Plain GI Strap pc 3.00 40.00 120.00
c. Blind Rivets pc 16.00 1.50 24.00
d. Consumables (3% of Materials Cost) 9.57

Sub - Total for F2 (As Evaluated) 328.57


G1. Direct Unit Cost (E1 + F1) - As Submitted 347.74
G2. Direct Unit Cost (E2 + F2) - As Evaluated 347.74
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 41.73
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 41.73
I1. Contractor's Profit (CP) - As Submitted 8% of G1 27.82
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 27.82
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 20.86
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 20.86
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 438.15
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 438.15

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 120.00 90.20 10,824.00


b. Skilled Laborer 1 120.00 65.14 7,816.80
c. Unskilled Laborer 2 120.00 50.25 12,060.00

Sub - Total for A1 (As Submitted) 30,700.80


A2. Labor

a. Construction Foreman 1 120.00 90.20 10,824.00


b. Skilled Laborer 1 120.00 65.14 7,816.80
c. Unskilled Laborer 2 120.00 50.25 12,060.00

Sub - Total for A2 (As Evaluated) 30,700.80


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 3,070.08

Sub - Total for B1 (As Submitted) 3,070.08


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3,070.08

Sub - Total for B2 (As Evaluated) 3,070.08


C1. Total (A1 + B1) 33,770.88
C2. Total (A2 + B2) 33,770.88
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 33,770.88
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 33,770.88
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. a. PVC pipe, 150mm dia. x 3m, S-1000 pc 26.000 1,975.29 51,357.54


b. e. PVC pipe, 50mm dia. x 3m, S-1000 (vent) pc 52.000 270.00 14,040.00
c. f. Elbow, 150mm dia. - 90 deg bend pc 4.000 140.00 560.00
d. f. Elbow, 100mm dia. - 90 deg bend pc 14.000 85.00 1,190.00
e. g. Elbow, 50mm dia. - 90 deg bend pc 115.000 26.00 2,990.00
f. g. Elbow, 150mm dia. - 45 deg bend pc 2.000 140.00 280.00
g. g. Elbow, 50mm dia. - 45 deg bend pc 46.000 30.00 1,380.00
h. h. Wye, 150mm dia. pc 4.000 260.00 1,040.00
i. h. Wye, 100mm dia. pc 8.000 173.00 1,384.00
j. i. Wye, 50mm dia. pc 12.000 85.00 1,020.00
k. j. Wye Reducer, 150mm dia. - 100mm dia. pc 2.000 807.29 1,614.58
l. k.Wye, Reducer, 100mm dia. - 50mm dia. pc 63.000 163.00 10,269.00
m. m. PVC Tee, 150mm dia. x 50mm dia. pc 4.000 926.89 3,707.56
n. n. PVC Tee, 50mm dia. x 50mm dia. pc 59.000 40.00 2,360.00
o. o. Clean Out with cover, 150mm dia. pc 6.000 627.90 3,767.40
p. p. Clean Out with cover, 100mm dia. pc 14.000 26.00 364.00
r. q. Clean Out with cover, 50mm dia. pc 4.000 17.00 68.00
s. r. PVC P-trap, 50mm dia. pc 46.000 110.00 5,060.00
t. s. Solvent Cement can 8.000 155.00 1,240.00
u. Consumables (5% of Materials) Lot 5,184.60 5,184.60

Sub - Total for F1 (As Submitted) 108,876.68


F2. Materials

a. a. PVC pipe, 150mm dia. x 3m, S-1000 pc 26.000 1,975.29 51,357.54


b. e. PVC pipe, 50mm dia. x 3m, S-1000 (vent) pc 52.000 270.00 14,040.00
c. f. Elbow, 150mm dia. - 90 deg bend pc 4.000 140.00 560.00
d. f. Elbow, 100mm dia. - 90 deg bend pc 14.000 85.00 1,190.00
e. g. Elbow, 50mm dia. - 90 deg bend pc 115.000 26.00 2,990.00
f. g. Elbow, 150mm dia. - 45 deg bend pc 2.000 140.00 280.00
g. g. Elbow, 50mm dia. - 45 deg bend pc 46.000 30.00 1,380.00
h. h. Wye, 150mm dia. pc 4.000 260.00 1,040.00
i. h. Wye, 100mm dia. pc 8.000 173.00 1,384.00
j. i. Wye, 50mm dia. pc 12.000 85.00 1,020.00
k. j. Wye Reducer, 150mm dia. - 100mm dia. pc 2.000 807.29 1,614.58
l. k.Wye, Reducer, 100mm dia. - 50mm dia. pc 63.000 163.00 10,269.00
m. m. PVC Tee, 150mm dia. x 50mm dia. pc 4.000 926.89 3,707.56
n. n. PVC Tee, 50mm dia. x 50mm dia. pc 59.000 40.00 2,360.00
o. o. Clean Out with cover, 150mm dia. pc 6.000 627.90 3,767.40
p. p. Clean Out with cover, 100mm dia. pc 14.000 26.00 364.00
r. q. Clean Out with cover, 50mm dia. pc 4.000 17.00 68.00
s. r. PVC P-trap, 50mm dia. pc 46.000 110.00 5,060.00
t. s. Solvent Cement can 8.000 155.00 1,240.00
u. Consumables (5% of Materials) Lot 5,184.60 5,184.60

Sub - Total for F2 (As Evaluated) 108,876.68


G1. Direct Unit Cost (E1 + F1) - As Submitted 142,647.56
G2. Direct Unit Cost (E2 + F2) - As Evaluated 142,647.56
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 17,117.71
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 17,117.71
I1. Contractor's Profit (CP) - As Submitted 8% of G1 11,411.81
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11,411.81
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 8,558.85
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 8,558.85
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 179,735.93
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 179,735.93

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(24) Cold Water lines


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 144.00 90.20 12,988.80


b. Skilled Laborer 1 144.00 65.14 9,380.16
c. Unskilled Laborer 2 144.00 50.25 14,472.00

Sub - Total for A1 (As Submitted) 36,840.96


A2. Labor

a. Construction Foreman 1 144.00 90.20 12,988.80


b. Skilled Laborer 1 144.00 65.14 9,380.16
c. Unskilled Laborer 2 144.00 50.25 14,472.00

Sub - Total for A2 (As Evaluated) 36,840.96


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 3,684.10

Sub - Total for B1 (As Submitted) 3,684.10


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3,684.10

Sub - Total for B2 (As Evaluated) 3,684.10


C1. Total (A1 + B1) 40,525.06
C2. Total (A2 + B2) 40,525.06
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 40,525.06
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 40,525.06
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. PPRC Pipe, 75mm dia. X 4m, PN 16 pcs 14.000 4,039.27 56,549.78


b. PPRC Pipe, 32mm dia. X 4m, PN 16 pcs 48.000 736.28 35,341.44
c. PPRC Pipe, 65mm dia. X 4m, PN 16 pcs 14.000 2,765.00 38,710.00
d. PPRC Pipe, 50mm dia. X 4m, PN 16 pcs 8.000 1,753.80 14,030.40
e. PP-R Coupling Reducer 32x25mm dia. pcs 4.000 15.80 63.20
f. PP-R Coupling Reducer 32x20mm dia. pcs 8.000 14.22 113.76
g. PP-R Elbow 25mm dia.-90 deg pcs 2.000 20.54 41.08
h. PP-R Elbow 20mm dia.- 90 deg pcs 6.000 12.64 75.84
i. PP-R Tee 20mm dia. pcs 7.000 14.80 103.60
j. PPR-Tee Reducer 32x20mm dia. pcs 4.000 32.52 130.08
k. PPR-Tee Reducer 25x20mm dia. pcs 4.000 26.86 107.44
k. Consumables (5% of Materials) 4,435.84

Sub - Total for F1 (As Submitted) 149,702.46


F2. Materials

a. PPRC Pipe, 75mm dia. X 4m, PN 16 pcs 14.000 4,039.27 56,549.78


b. PPRC Pipe, 32mm dia. X 4m, PN 16 pcs 48.000 736.28 35,341.44
c. PPRC Pipe, 65mm dia. X 4m, PN 16 pcs 14.000 2,765.00 38,710.00
d. PPRC Pipe, 50mm dia. X 4m, PN 16 pcs 8.000 1,753.80 14,030.40
e. PP-R Coupling Reducer 32x25mm dia. pcs 4.000 15.80 63.20
f. PP-R Coupling Reducer 32x20mm dia. pcs 8.000 14.22 113.76
g. PP-R Elbow 25mm dia.-90 deg pcs 2.000 20.54 41.08
h. PP-R Elbow 20mm dia.- 90 deg pcs 6.000 12.64 75.84
i. PP-R Tee 20mm dia. pcs 7.000 14.80 103.60
j. PPR-Tee Reducer 32x20mm dia. pcs 4.000 32.52 130.08
k. PPR-Tee Reducer 25x20mm dia. pcs 4.000 26.86 107.44
k. Consumables (5% of Materials) 4,435.84

Sub - Total for F2 (As Evaluated) 149,702.46


G1. Direct Unit Cost (E1 + F1) - As Submitted 190,227.52
G2. Direct Unit Cost (E2 + F2) - As Evaluated 190,227.52
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 22,827.30
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 22,827.30
I1. Contractor's Profit (CP) - As Submitted 8% of G1 15,218.20
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 15,218.20
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11,413.65
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11,413.65
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 239,686.67
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 239,686.67

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 96.00 90.20 8,659.20


b. Skilled Laborer 2 96.00 65.14 12,506.88
c. Unskilled Laborer 4 96.00 50.25 19,296.00

Sub - Total for A1 (As Submitted) 40,462.08


A2. Labor

a. Construction Foreman 1 96.00 90.20 8,659.20


b. Skilled Laborer 2 96.00 65.14 12,506.88
c. Unskilled Laborer 4 96.00 50.25 19,296.00

Sub - Total for A2 (As Evaluated) 40,462.08


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 4,046.21

Sub - Total for B1 (As Submitted) 4,046.21


B2. Equipment

a. Minor Tools (10% of Labor Cost) 4,046.21

Sub - Total for B2 (As Evaluated) 4,046.21


C1. Total (A1 + B1) 44,508.29
C2. Total (A2 + B2) 44,508.29
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 44,508.29
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 44,508.29
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. PVC Drain Pipe, 150mm dia. x 3m pc 6.00 1,975.29 11,851.74


b. PVC Drain Pipe, 75mm dia. x 3m pc 6.00 480.00 2,880.00
c. Roof Drain (Dome-type strainer) pc 20.00 1,500.00 30,000.00
d. uPVC Sanitary Pipe,100mm dia. x 3m,S-1000 pc 95.00 700.00 66,500.00
e. uPVC Sanitary Pipe,75mm dia. x 3m,S-1000 pc 4.00 480.00 1,920.00
f. Elbow, 100mm dia. - 45 deg bend pc 34.00 83.00 2,822.00
g. coupling 150mm dia pc 2.00 100.00 200.00
h. coupling 100mm dia pc 18.00 63.00 1,134.00
i. PVC wye 100mm pc 34.00 173.00 5,882.00
j. PVC wye 75mm pc 4.00 85.00 340.00
k. Elbow, 75mm dia. - 45 deg bend pc 4.00 54.00 216.00
l. Elbow, 100mm dia. - 90 deg bend pc 34.00 85.00 2,890.00
m. Elbow, 75mm dia. - 90 deg bend pc 4.00 50.00 200.00
n. PVC Solvent, 400cc can 4.00 155.00 620.00
o Consumables 5% 5,798.69

Sub - Total for F1 (As Submitted) 133,254.43


F2. Materials

a. PVC Drain Pipe, 150mm dia. x 3m pc 6.00 1,975.29 11,851.74


b. PVC Drain Pipe, 75mm dia. x 3m pc 6.00 480.00 2,880.00
c. Roof Drain (Dome-type strainer) pc 20.00 1,500.00 30,000.00
d. uPVC Sanitary Pipe,100mm dia. x 3m,S-1000 pc 95.00 700.00 66,500.00
e. uPVC Sanitary Pipe,75mm dia. x 3m,S-1000 pc 4.00 480.00 1,920.00
f. Elbow, 100mm dia. - 45 deg bend pc 34.00 83.00 2,822.00
g. coupling 150mm dia pc 2.00 100.00 200.00
h. coupling 100mm dia pc 18.00 63.00 1,134.00
i. PVC wye 100mm pc 34.00 173.00 5,882.00
j. PVC wye 75mm pc 4.00 85.00 340.00
k. Elbow, 75mm dia. - 45 deg bend pc 4.00 54.00 216.00
l. Elbow, 100mm dia. - 90 deg bend pc 34.00 85.00 2,890.00
m. Elbow, 75mm dia. - 90 deg bend pc 4.00 50.00 200.00
n. PVC Solvent, 400cc can 4.00 155.00 620.00
o Consumables 5% 5,798.69

Sub - Total for F2 (As Evaluated) 133,254.43


G1. Direct Unit Cost (E1 + F1) - As Submitted 177,762.72
G2. Direct Unit Cost (E2 + F2) - As Evaluated 177,762.72
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 21,331.53
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 21,331.53
I1. Contractor's Profit (CP) - As Submitted 8% of G1 14,221.02
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 14,221.02
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 10,665.76
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 10,665.76
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 223,981.03
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 223,981.03

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(4) Plumbing FIxtures


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 320.00 90.20 28,864.00


b. Skilled Laborer 1 320.00 65.14 20,844.80
c. Unskilled Laborer 1 320.00 50.25 16,080.00

Sub - Total for A1 (As Submitted) 65,788.80


A2. Labor

a. Construction Foreman 1 320.00 90.20 28,864.00


b. Skilled Laborer 1 320.00 65.14 20,844.80
c. Unskilled Laborer 1 320.00 50.25 16,080.00

Sub - Total for A2 (As Evaluated) 65,788.80


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
a. Minor Tools (10% of Labor Cost) 6,578.88

Sub - Total for B1 (As Submitted) 6,578.88


B2. Equipment

a. Minor Tools (10% of Labor Cost) 6,578.88

Sub - Total for B2 (As Evaluated) 6,578.88


C1. Total (A1 + B1) 72,367.68
C2. Total (A2 + B2) 72,367.68
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 72,367.68
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 72,367.68
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Water Closet complete w/ fittings & accs. sets 15.00 7,500.00 112,500.00
b. Urinal (trough) sets 3.00 4,600.00 13,800.00
e. Concrete Counter Sink (3 Faucet) sets 6.00 6,028.00 36,168.00
f. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 4,600.00 9,200.00
g. Gate Valve, 32mm dia pcs 32.00 627.00 20,064.00
i. Gate Valve, 50mm dia pcs 4.00 980.00 3,920.00
j. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k. S.S. Floor Drain 4'x4'' pcs 44.00 250.00 11,000.00
l. Mirror m² 5.10 7,530.88 38,407.49
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 36.00 155.00 5,580.00
p. Consumables 5% 13,029.67

Sub - Total for F1 (As Submitted) 273,623.16


F2. Materials

a. Water Closet complete w/ fittings & accs. sets 15.00 7,500.00 112,500.00
b. Urinal (trough) sets 3.00 4,600.00 13,800.00
e. Concrete Counter Sink (3 Faucet) sets 6.00 6,028.00 36,168.00
f. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 4,600.00 9,200.00
g. Gate Valve, 32mm dia pcs 32.00 627.00 20,064.00
i. Gate Valve, 50mm dia pcs 4.00 980.00 3,920.00
j. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k. S.S. Floor Drain 4'x4'' pcs 44.00 250.00 11,000.00
l. Mirror m² 5.10 7,530.88 38,407.49
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 36.00 155.00 5,580.00
p. Consumables 5% 13,029.67

Sub - Total for F2 (As Evaluated) 273,623.16


G1. Direct Unit Cost (E1 + F1) - As Submitted 345,990.84
G2. Direct Unit Cost (E2 + F2) - As Evaluated 345,990.84
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 41,518.90
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 41,518.90
I1. Contractor's Profit (CP) - As Submitted 8% of G1 27,679.27
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 27,679.27
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 20,759.45
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 20,759.45
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 435,948.46
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 435,948.46

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(11) Septic Vault (Concrete / CHB)


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 25.00 90.20 2,255.00


b. Skilled Laborer 4 25.00 65.14 6,514.00
c. Unskilled Laborer 6 25.00 50.25 7,537.50

Sub - Total for A1 (As Submitted) 16,306.50


A2. Labor

a. Construction Foreman 1 25.00 90.20 2,255.00


b. Skilled Laborer 4 25.00 65.14 6,514.00
c. Unskilled Laborer 6 25.00 50.25 7,537.50

Sub - Total for A2 (As Evaluated) 16,306.50


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 1,630.65

Sub - Total for B1 (As Submitted) 1,630.65


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1,630.65

Sub - Total for B2 (As Evaluated) 1,630.65


C1. Total (A1 + B1) 17,937.15
C2. Total (A2 + B2) 17,937.15
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 17,937.15
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 17,937.15
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 13.71 5,225.00 71,634.75


b. Reinforcement Steel Bars, Gr. 40 kgs 933.94 37.50 35,022.75
c. Plaster Finish m2 12.16 84.25 1,024.48
d. Cement - Based Water Proofing m2 170.00 55.00 9,350.00
e. 6" CHB m2 5.00 767.20 3,836.00
f. 4"CHB m2 2.50 484.45 1,211.13

Sub - Total for F1 (As Submitted) 122,079.11


F2. Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 13.71 5,225.00 71,634.75


b. Reinforcement Steel Bars, Gr. 40 kgs 933.94 37.50 35,022.75
c. Plaster Finish m2 12.16 84.25 1,024.48
d. Cement - Based Water Proofing m2 170.00 55.00 9,350.00
e. 6" CHB m2 5.00 767.20 3,836.00
f. 4"CHB m2 2.50 484.45 1,211.13

Sub - Total for F2 (As Evaluated) 122,079.11


G1. Direct Unit Cost (E1 + F1) - As Submitted 140,016.26
G2. Direct Unit Cost (E2 + F2) - As Evaluated 140,016.26
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 16,801.95
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 16,801.95
I1. Contractor's Profit (CP) - As Submitted 8% of G1 11,201.30
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11,201.30
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 8,400.98
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 8,400.98
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 176,420.49
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 176,420.49

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(5)b Catch Basin (CHB)


Unit of Measurement : Ea
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 2.00 90.20 180.40


b. Skilled Laborer 1 2.00 65.14 130.28
c. Unskilled Laborer 1 2.00 50.25 100.50

Sub - Total for A1 (As Submitted) 411.18


A2. Labor

a. Construction Foreman 1 2.00 90.20 180.40


b. Skilled Laborer 1 2.00 65.14 130.28
c. Unskilled Laborer 1 2.00 50.25 100.50

Sub - Total for A2 (As Evaluated) 411.18


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 41.12

Sub - Total for B1 (As Submitted) 41.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 41.12

Sub - Total for B2 (As Evaluated) 41.12


C1. Total (A1 + B1) 452.30
C2. Total (A2 + B2) 452.30
D1. Output per our - As Submitted = 1.000 Ea
D2. Output per our - As Evaluated = 1.000 Ea
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 452.30
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 452.30
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 0.07 5,225.00 365.75


b. Reinforcing Steel Bars Deformed kgs 8.63 37.50 323.63
c. Grade 40
Masonry m2 0.80 187.50 150.00
d. Plaster Finish m2 1.76 112.26 197.58

Sub - Total for F1 (As Submitted) 1,036.95


F2. Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 0.070 5,225.00 365.75


b. Reinforcing Steel Bars Deformed Grade 40 kgs 8.630 37.50 323.63
c. Masonry m2 0.800 187.50 150.00
d. Plaster Finish m2 1.760 112.26 197.58

Sub - Total for F2 (As Evaluated) 1,036.95


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,489.25
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,489.25
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 178.71
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 178.71
I1. Contractor's Profit (CP) - As Submitted 8% of G1 119.14
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 119.14
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 89.36
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 89.36
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,876.46
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,876.46

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Unit of Measurement : L.s.
Output per hour : 1.000

No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor

a. Construction Foreman 1 72.00 90.20 6,494.40


b. Electrician 1 72.00 72.73 5,236.56
c. Unskilled Laborer 1 72.00 50.25 3,618.00

Sub - Total for A1 (As Submitted) 15,348.96


A2. Labor

a. Construction Foreman 1 72.00 90.20 6,494.40


b. Electrician 1 72.00 72.73 5,236.56
c. Unskilled Laborer 1 72.00 50.25 3,618.00

Sub - Total for A2 (As Evaluated) 15,348.96


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 1,534.90

Sub - Total for B1 (As Submitted) 1,534.90


B2. Equipment

Minor Tools (10% of Labor Cost) 1,534.90

Sub - Total for B2 (As Evaluated) 1,534.90


C1. Total (A1 + B1) 16,883.86
C2. Total (A2 + B2) 16,883.86
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 16,883.86
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 16,883.86
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 20mmØ PVC conduit length 460.00 98.00 45,080.00


b. 25mmØ PVC conduit length 9.00 125.00 1,125.00
c. 40mmØ RSC conduit length 2.00 1,069.50 2,139.00
d. 20mmØ PVC adpater pc 710.00 14.00 9,940.00
e. 25mmØ PVC adapter pc 8.00 17.00 136.00
f. 20mmØ locknut and bushing pc 710.00 10.00 7,100.00
g. 40mmØ RSC Elbow pc 4.00 289.80 1,159.20
i. 25mmØ locknut and bushing pc 8.00 15.00 120.00
i. 20mmØ liquidtight flexible metal conduit m 6.00 20.00 120.00
j. 20mmØ connector pc 4.00 10.00 40.00
k. Utility box, deep type pc 116.00 35.00 4,060.00
l. junction box, deep type pc 168.00 32.00 5,376.00
m. 40mmØ entrance cap pc 1.00 304.00 304.00
n. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F1 (As Submitted) 79,099.20


F2. Materials

a. 20mmØ PVC conduit length 460.00 98.00 45,080.00


b. 25mmØ PVC conduit length 9.00 125.00 1,125.00
c. 40mmØ RSC conduit length 2.00 1,069.50 2,139.00
d. 20mmØ PVC adpater pc 710.00 14.00 9,940.00
e. 25mmØ PVC adapter pc 8.00 17.00 136.00
f. 20mmØ locknut and bushing pc 710.00 10.00 7,100.00
g. 40mmØ RSC Elbow pc 4.00 289.80 1,159.20
. 25mmØ locknut and bushing pc 8.00 15.00 120.00
i. 20mmØ liquidtight flexible metal conduit m 6.00 20.00 120.00
j. 20mmØ connector pc 4.00 10.00 40.00
k. Utility box, deep type pc 116.00 35.00 4,060.00
l. junction box, deep type pc 168.00 32.00 5,376.00
m. 40mmØ entrance cap pc 1.00 304.00 304.00
n. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F2 (As Evaluated) 79,099.20


G1. Direct Unit Cost (E1 + F1) - As Submitted 95,983.06
G2. Direct Unit Cost (E2 + F2) - As Evaluated 95,983.06
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 11,517.97
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 11,517.97
I1. Contractor's Profit (CP) - As Submitted 8% of G1 7,678.64
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 7,678.64
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 5,758.98
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 5,758.98
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 120,938.66
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 120,938.66

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101(33) Wires and Wiring Devices


Unit of Measurement : L.s.
Output per hour : 1.000
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
a. Construction Foreman 1 176.00 90.20 15,875.20
b. Electrician 1 176.00 72.73 12,800.48
c. Unskilled Laborer 1 176.00 50.25 8,844.00

Sub - Total for A1 (As Submitted) 37,519.68


A2. Labor
a. Construction Foreman 1 176.00 90.20 15,875.20
b. Electrician 1 176.00 72.73 12,800.48
c. Unskilled Laborer 1 176.00 50.25 8,844.00

Sub - Total for A2 (As Evaluated) 37,519.68


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 3,751.97

Sub - Total for B1 (As Submitted) 3,751.97


B2. Equipment

Minor Tools (10% of Labor Cost) 3,751.97

Sub - Total for B2 (As Evaluated) 3,751.97


C1. Total (A1 + B1) 41,271.65
C2. Total (A2 + B2) 41,271.65
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 41,271.65
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 41,271.65
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
a. 3.5mm2 THHN wire,stranded m 2920.00 35.00 102,200.00
b. 5.5mm2 THHN wire,stranded m 60.00 45.00 2,700.00
c. 38.0mm2 THHN, wire, stranded m 30.00 292.60 8,778.00
d. 2.0mm2 TW wire, stranded m 240.00 22.00 5,280.00
e. 3.5mm2 TW wire, stranded m 1458.00 35.00 51,030.00
f. 5.5mm2 TW wire stranded m 36.00 45.00 1,620.00
g. 14.0mm2 TW wire stranded m 6.00 86.00 516.00
h. one gang switch set 20.00 95.00 1,900.00
i. two gang switch set 23.00 130.00 2,990.00
j. three gang switch set 51.00 175.00 8,925.00
j. one gang three way switch set 24.00 165.00 3,960.00
k. Duplex C.O. grounding type, 15A, 250V set 24.00 330.00 7,920.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 9.00 420.00 3,780.00
n. KWHR meter set 1.00 2,200.00 2,200.00
o. Tape, bolt&nut, mica tube, terminal lugs, JB cover clamps, screwlot
and anchors 1.00 3,000.00 3,000.00

Sub - Total for F1 (As Submitted) 206,799.00


F2. Materials
a. 3.5mm2 THHN wire,stranded m 2920.00 35.00 102,200.00
b. 5.5mm2 THHN wire,stranded m 60.00 45.00 2,700.00
c. 38.0mm2 THHN, wire, stranded m 30.00 292.60 8,778.00
d. 2.0mm2 TW wire, stranded m 240.00 22.00 5,280.00
e. 3.5mm2 TW wire, stranded m 1458.00 35.00 51,030.00
f. 5.5mm2 TW wire stranded m 36.00 45.00 1,620.00
g. 14.0mm2 TW wire stranded m 6.00 86.00 516.00
h. one gang switch set 20.00 95.00 1,900.00
i. two gang switch set 23.00 130.00 2,990.00
j. three way switch set 51.00 175.00 8,925.00
k. Duplex C.O. grounding type, 15A, 250V set 24.00 330.00 7,920.00
l. Duplex C.O. grounding type, 250 C, weatherproof set 9.00 420.00 3,780.00
n. KWHR meter set 1.00 2,200.00 2,200.00
o. Tape, bolt&nut, mica tube, terminal lugs, JB cover lot 1.00 3,000.00 3,000.00

Sub - Total for F2 (As Evaluated) 202,839.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 248,070.65
G2. Direct Unit Cost (E2 + F2) - As Evaluated 244,110.65
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 29,768.48
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 29,293.28
I1. Contractor's Profit (CP) - As Submitted 8% of G1 19,845.65
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 19,528.85
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14,884.24
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14,884.24
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 312,569.02
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 312,569.02

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(1) Panel Board with Main Breaker


Unit of Measurement : L.s.
Output per hour : 1.000

No. of
A1. Designation No. of Hour/s Hourly Rate Amount (PhP)
Person/s
Labor

a. Construction Foreman 1 40.00 90.20 3,608.00


b. Electrician 1 40.00 72.73 2,909.20
c. Unskilled Laborer 2 40.00 50.25 4,020.00

Sub - Total for A1 (As Submitted) 10,537.20


A2. Labor

a. Construction Foreman 1 40.00 90.20 3,608.00


b. Electrician 1 40.00 72.73 2,909.20
c. Unskilled Laborer 2 40.00 50.25 4,020.00

Sub - Total for A2 (As Evaluated) 10,537.20

B1. Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
Equipment

Minor Tools (10% of Labor Cost) 1,053.72

Sub - Total for B1 (As Submitted) 1,053.72


B2. Equipment

Minor Tools (10% of Labor Cost) 1,053.72

Sub - Total for B2 (As Evaluated) 1,053.72


C1. Total (A1 + B1) 11,590.92
C2. Total (A2 + B2) 11,590.92
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 11,590.92
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 11,590.92
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Terminalset 1.00 115,731.20 115,731.20
Main: 700at, 800af, 3p, 240v, 65 kaic
Branches: 1 - 60at, 50af, 2p, 240v
2 - 50at, 50af, 2p, 240v
1 - 600at, 600af, 3p, 240v

b. FPP set 1.00 57,605.60 57,605.60


Main: 600at, 600af, 3p, 240v, 22KAIC
Branches: 3 - 40at, 50af, 2p, 240v
1 - 40at, 50af, 3p, 240v
1 - 600at, 600af, 3p, 240v

c. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p LUGS ONLY
Branches: 3 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v
2 - 40at, 50af, 2p, 240v

LPB &LPC set 1.00 14,346.80 14,346.80


b. Main: 50at, 50af, 2p, 240v, 10kaic
c. Branches: 3 - 15at, 50af, 2p, 240v
d. 7 - 20at, 50af, 2p, 240v

Automatic Transfer Switch set 1.00 128,000.00 128,000.00


Main: 700at, 800af, 2p, 260v in nema 3R enclosure

40at, 50af, 2p, 240v in NEMA 3R enclosure set 2.00 1,200.00 2,400.00
40at, 50af, 3p, 240v in NEMA 3R enclosure 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v in NEMA 3R enclosure 1.00 1,200.00 1,200.00

Sub - Total for F1 (As Submitted) 334,492.40


F2. Materials

a. MDP - Flush Mounted, NEMA 1 Enclosure w/ Ground Terminalset 1.00 115,731.20 115,731.20
Main: 700at, 800af, 3p, 240v, 65 kaic
Branches: 1 - 60at, 50af, 2p, 240v
2 - 50at, 50af, 2p, 240v
1 - 600at, 600af, 3p, 240v

b. FPP set 1.00 57,605.60 57,605.60


Main: 600at, 600af, 3p, 240v, 22KAIC
Branches: 3 - 40at, 50af, 2p, 240v
1 - 40at, 50af, 3p, 240v
1 - 600at, 600af, 3p, 240v

c. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p LUGS ONLY
Branches: 3 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v
2 - 40at, 50af, 2p, 240v

LPB &LPC set 1.00 14,346.80 14,346.80


b. Main: 50at, 50af, 2p, 240v, 10kaic
c. Branches: 3 - 15at, 50af, 2p, 240v
d. 7 - 20at, 50af, 2p, 240v

Automatic Transfer Switch set 1.00 128,000.00 128,000.00


Main: 700at, 800af, 2p, 260v in nema 3R enclosure

40at, 50af, 2p, 240v in NEMA 3R enclosure set 2.00 1,200.00 2,400.00
40at, 50af, 3p, 240v in NEMA 3R enclosure 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v in NEMA 3R enclosure 1.00 1,200.00 1,200.00

Sub - Total for F2 (As Evaluated) 334,492.40


G1. Direct Unit Cost (E1 + F1) - As Submitted 346,083.32
G2. Direct Unit Cost (E2 + F2) - As Evaluated 346,083.32
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 41,530.00
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 41,530.00
I1. Contractor's Profit (CP) - As Submitted 8% of G1 27,686.6656
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 27,686.67
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 20,765.00
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 20,765.00
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 436,064.98
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 436,064.98
Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures & Lamps


Unit of Measurement : L.s.
Output per hour : 1.000

No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor

a. Construction Foreman 1 144.00 90.20 12,988.80


b. Electrician 1 144.00 72.73 10,473.12
c. Unskilled Laborer 2 144.00 50.25 14,472.00
.

Sub - Total for A1 (As Submitted) 37,933.92


A2. Labor

a. Construction Foreman 1 144.00 90.20 12,988.80


b. Electrician 1 144.00 72.73 10,473.12
c. Unskilled Laborer 2 144.00 50.25 14,472.00

Sub - Total for A2 (As Evaluated) 37,933.92


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 3,793.39

Sub - Total for B1 (As Submitted) 3,793.39


B2. Equipment

Minor Tools (10% of Labor Cost) 3,793.39

Sub - Total for B2 (As Evaluated) 3,793.39


C1. Total (A1 + B1) 41,727.31
C2. Total (A2 + B2) 41,727.31
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 41,727.31
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 41,727.31
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 2 x 28 watts FL fixture, box type set 72.00 1,180.00 84,960.00


b. 1 x 28 watts FL fixture box type. set 58.00 325.00 18,850.00
c. 1 - 18 watts CFL w/ medium base keyless type porcelain set 8.00 325.00 2,600.00
d. receptacle
Ceiling fan w/ control switch set 48.00 1,800.00 86,400.00
e. Exhaust fan w/ control switch set 12.00 1,400.00 16,800.00

Sub - Total for F1 (As Submitted) 209,610.00


F2. Materials

a. 2 x 36 watts FL fixture, box type set 72.00 1,180.00 84,960.00


b. 1 x 36 watts FL fixture box type. set 58.00 325.00 18,850.00
c. 1 - 18 watts CFL w/ medium base keyless type porcelain set 8.00 320.00 2,560.00
d. Ceiling fan w/ control switch set 48.00 1,800.00 86,400.00
e. Exhaust fan w/ control switch set 12.00 1,400.00 16,800.00

Sub - Total for F2 (As Evaluated) 209,570.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 251,337.31
G2. Direct Unit Cost (E2 + F2) - As Evaluated 251,297.31
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 30,160.48
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 30,155.68
I1. Contractor's Profit (CP) - As Submitted 8% of G1 20,106.98
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 20,103.78
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 15,080.24
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 15,080.24
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 316,685.01
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 316,685.01
Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(5) Fire Hose Cabinet Assembly


Unit of Measurement : Set
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 60.00 90.20 5,412.00


b. Skilled Laborer 2 60.00 65.14 7,816.80
c. Unskilled Laborer 4 60.00 50.25 12,060.00

Sub - Total for A1 (As Submitted) 25,288.80


A2. Labor

a. Construction Foreman 1 60.00 90.20 5,412.00


b. Skilled Laborer 2 60.00 65.14 7,816.80
c. Unskilled Laborer 4 60.00 50.25 12,060.00

Sub - Total for A2 (As Evaluated) 25,288.80


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 2,528.88

Sub - Total for B1 (As Submitted) 2,528.88


B2. Equipment

a. Minor Tools (10% of Labor Cost) 2,528.88

Sub - Total for B2 (As Evaluated) 2,528.88


C1. Total (A1 + B1) 27,817.68
C2. Total (A2 + B2) 27,817.68
D1. Output per our - As Submitted = 1.000 Set
D2. Output per our - As Evaluated = 1.000 Set
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 27,817.68
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 27,817.68
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. B.I. Pipe 50mm dia lm 23.00 708.00 16,284.00


b. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,628.40 1,628.40
c. Fire Hose Cabinet with Fire Extinguisher set 2.00 24,000.00 48,000.00
d. Fire Extinguisher, 10 lbs Capacity, Wall Mounted, HCFC 123 set 6.00 6,825.00 40,950.00
e. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Concrete m³ 33.02 5,740.00 189,534.80
h. Rebar , Gr40 kg 648.90 41.00 26,604.90
i. Plaster Finish m² 93.55 84.25 7,881.59
j. Cement Based Waterproofing bag 159.00 55.00 8,745.00
k. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
l. End-Suction Centrifugal Water Pump, TDH 9m, 0.5HP, unit 2.00 23,500.00 47,000.00

Sub - Total for F1 (As Submitted) 602,128.69


F2. Materials

a. B.I. Pipe 50mm dia lm 23.00 708.00 16,284.00


b. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,628.40 1,628.40
c. Fire Hose Cabinet with Fire Extinguisher set 2.00 24,000.00 48,000.00
d. Fire Extinguisher, 10 lbs Capacity, Wall Mounted, HCFC 123 set 6.00 6,825.00 40,950.00
e. Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Concrete m³ 33.02 5,740.00 189,534.80
h. Rebar , Gr40 kg 648.90 41.00 26,604.90
i. Plaster Finish m² 93.55 84.25 7,881.59
j. Cement Based Waterproofing bag 159.00 55.00 8,745.00
k. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
l. End-Suction Centrifugal Water Pump, TDH 9m, 0.5HP, unit 2.00 23,500.00 47,000.00

Sub - Total for F2 (As Evaluated) 602,128.69


G1. Direct Unit Cost (E1 + F1) - As Submitted 629,946.37
G2. Direct Unit Cost (E2 + F2) - As Evaluated 629,946.37
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 75,593.56
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 75,593.56
I1. Contractor's Profit (CP) - As Submitted 8% of G1 50,395.71
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 50,395.71
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 37,796.78
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 37,796.78
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 793,732.42
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 793,732.42

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Automatic Water Sprinkler


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
a. Construction Foreman 1 720.00 90.20 64,944.00
b. Skilled Laborer 2 720.00 65.14 93,801.60
c. Unskilled Laborer 4 720.00 50.25 144,720.00

Sub - Total for A1 (As Submitted) 303,465.60


A2. Labor
a. Construction Foreman 1 720.00 90.20 64,944.00
b. Skilled Laborer 2 720.00 65.14 93,801.60
c. Unskilled Laborer 4 720.00 50.25 144,720.00

Sub - Total for A2 (As Evaluated) 303,465.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
a. Minor Tools (10% of Labor Cost) 30,346.56

Sub - Total for B1 (As Submitted) 30,346.56


B2. Equipment
a. Minor Tools (10% of Labor Cost) 30,346.56

Sub - Total for B2 (As Evaluated) 30,346.56


C1. Total (A1 + B1) 333,812.16
C2. Total (A2 + B2) 333,812.16
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 333,812.16
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 333,812.16
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. B.I. Pipe 100mm dia lm 20.00 1,889.00 37,780.00


b. B.I. Pipe 75mm dia lm 140.00 984.00 137,760.00
c. B.I. Pipe 65mm dia lm 54.00 708.00 38,232.00
d. B.I. Pipe 50mm dia lm 20.00 425.00 8,500.00
e. B.I. Pipe 40mm dia lm 330.00 317.00 104,610.00
f. B.I. Pipe 25mm dia lm 56.00 192.00 10,752.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 135,053.60 135,053.60
h. Pendent 12mm dia pc 106.00 503.00 53,318.00
i. Side Wall 12mm dia pc 6.00 518.00 3,108.00
j. Fire Hose Cabinet with Fire Extinguisher set 6.00 24,000.00 144,000.00
k. Fire Extinguisher, 10 lbs Capacity, Wall Mounted,
set 12.00 6,825.00 81,900.00
HCFC 123
l. FP-1, Horizontal Split Case Centrifugal Pump with A.C.
Motor & Controller, UL/FM Approved, 350 GPM, 100psi, assy 1.00 887,692.31 887,692.31
30 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC Motor assy 1.00 180,000.00 180,000.00
& Controller, UL/FM Approved, 10GPM, 3HP, 100psi,
230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 33,763.40 33,763.40
dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00
ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00
ff. Testing and Commissioning l.s. 1.00 57,062.62 57,062.62
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 7000 US gal unit 1.00 103,703.70 103,703.70
jj. Concrete m³ 15.45 3,475.00 53,688.75
kk. Rebar kg 648.90 31.00 20,115.90
ll. Plaster Finish m² 66.00 84.25 5,560.50
mm. Cement Based Waterproofing bag 159.00 55.00 7,155.00
nn. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
oo. End-Suction Centrifugal Water Pump, TDH 22m, 2.0HP, 60GPM
unit 2.00 36,780.00 73,560.00

Sub - Total for F1 (As Submitted) 3,046,668.01


F2. Materials

a. B.I. Pipe 100mm dia lm 20.00 1,889.00 37,780.00


b. B.I. Pipe 75mm dia lm 140.00 984.00 137,760.00
c. B.I. Pipe 65mm dia lm 54.00 708.00 38,232.00
d. B.I. Pipe 50mm dia lm 20.00 425.00 8,500.00
e. B.I. Pipe 40mm dia lm 330.00 317.00 104,610.00
f. B.I. Pipe 25mm dia lm 56.00 192.00 10,752.00
g. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 135,053.60 135,053.60
h. Pendent 12mm dia pc 106.00 503.00 53,318.00
i. Side Wall 12mm dia pc 6.00 518.00 3,108.00
j. Fire Hose Cabinet with Fire Extinguisher set 6.00 24,000.00 144,000.00
k. Fire Extinguisher, 10 lbs Capacity, Wall Mounted,
set 12.00 6,825.00 81,900.00
HCFC 123
l. FP-1, Horizontal Split Case Centrifugal Pump with A.C.
Motor & Controller, UL/FM Approved, 350 GPM, 100psi, assy 1.00 887,692.31 887,692.31
30 HP, 230/3/60
m. JP-1 Vertical In-Line Centrifugal Pump with AC Motor assy 1.00 180,000.00 180,000.00
& Controller, UL/FM Approved, 10GPM, 3HP, 100psi,
230, 3/60
n. Gate Valve (OS & Y), 100mm dia unit 1.00 31,680.00 31,680.00
o. Y-Strainer unit 1.00 36,118.45 36,118.45
p.Check Valve unit 1.00 17,500.00 17,500.00
q. Alarm Check Valve Assembly unit 1.00 63,360.00 63,360.00
r. Globe Valve unit 1.00 9,114.00 9,114.00
s. Pressure Reducing Valve unit 1.00 104,099.33 104,099.33
t. Float Valve unit 1.00 77,396.68 77,396.68
u. Water Flow Switch unit 1.00 6,468.00 6,468.00
v.Floor Control Valve unit 1.00 8,303.00 8,303.00
w. Pressure Gauge unit 1.00 971.13 971.13
x. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
y. Isolation Valve unit 1.00 18,000.00 18,000.00
z. Water Flow Meter unit 1.00 58,084.99 58,084.99
aa. Drain Off Valve unit 1.00 19,557.51 19,557.51
bb. Roof Manifold unit 1.00 16,199.14 16,199.14
cc. Hangers and Support l.s. 1.00 33,763.40 33,763.40
dd. Electrical Works for Pumps from Main Breaker l.s. 1.00 15,000.00 15,000.00
ee. Miscellaneous and Consumables l.s. 1.00 5,000.00 5,000.00
ff. Testing and Commissioning l.s. 1.00 57,062.62 57,062.62
gg. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
hh. Fire Reserve Tank 7000 US gal unit 1.00 103,703.70 103,703.70
jj. Concrete m³ 15.45 3,475.00 53,688.75
kk. Rebar kg 648.90 31.00 20,115.90
ll. Plaster Finish m² 66.00 84.25 5,560.50
mm. Cement Based Waterproofing bag 159.00 55.00 8,745.00
nn. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
oo. End-Suction Centrifugal Water Pump, TDH 22m, unit 2.00 36,780.00 73,560.00

Sub - Total for F2 (As Evaluated) 3,048,258.01


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,380,480.17
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,382,070.17
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 405,657.62
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 405,848.42
I1. Contractor's Profit (CP) - As Submitted 8% of G1 270,438.41
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 270,565.61
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 202,828.81
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 202,828.81
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,259,405.01
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,259,405.01

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Three (3) Storey Twelve (12) Classroom Academic School Building at San Antonio Central School,
San Antonio, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 40.00 90.20 3,608.00


b. Skilled Laborer 1 40.00 65.14 2,605.60

Sub - Total for A1 (As Submitted) 6,213.60


A2. Labor

a. Construction Foreman 1 40.00 90.20 3,608.00


b. Skilled Laborer 1 40.00 65.14 2,605.60

Sub - Total for A2 (As Evaluated) 6,213.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 621.36

Sub - Total for B1 (As Submitted) 621.36


B2. Equipment

a. Minor Tools (10% of Labor Cost) 621.36

Sub - Total for B2 (As Evaluated) 621.36


C1. Total (A1 + B1) 6,834.96
C2. Total (A2 + B2) 6,834.96
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 6,834.96
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 6,834.96
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Fire Alarm Control Panel set 1.00 18,850.00 18,850.00


b. Manual Pull Switch set 2.00 1,610.00 3,220.00
c. Bell, Vibrating Type set 2.00 2,800.00 5,600.00
d. Smoke Detector set 9.00 950.00 8,550.00

Sub - Total for F1 (As Submitted) 36,220.00


F2. Materials

a. Fire Alarm Control Panel set 1.00 18,850.00 18,850.00


b. Manual Pull Switch set 2.00 1,610.00 3,220.00
c. Bell, Vibrating Type set 2.00 2,800.00 5,600.00
d. Smoke Detector set 9.00 950.00 8,550.00

Sub - Total for F2 (As Evaluated) 36,220.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 43,054.96
G2. Direct Unit Cost (E2 + F2) - As Evaluated 43,054.96
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 5,166.60
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 5,166.60
I1. Contractor's Profit (CP) - As Submitted 8% of G1 3,444.40
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 3,444.40
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 2,583.30
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 2,583.30
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 54,249.25
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 54,249.25

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II