Professional Documents
Culture Documents
Chapter 7 Questions
Chapter 7 Questions
3.Give examples of when you would prepare rough order of magnitude (ROM), bu
dgetary, and definitive cost estimates for an information technology project. Give
an example of using each of the following techniques for creating a cost estimate
: analogous, parametric, and bottom-up.
Answers will vary. A rough order of magnitude estimate for providing new laptops for 10
0 people might be $250,000. A budgetary estimate would break down the estimate to in
clude hardware, software, detailed assumptions (for example, if the estimate is just for t
he purchase cost or is for a 2 to 4 year project life), and so on. A definitive estimate wo
uld be much more detailed and accurate than a rough estimate or budgetary estimate a
nd would include vendor quotes.
Using the example of providing new laptops for 100 people, one possible response for
examples of each type of estimating techniques follows:
• Analogous estimate: You could research similar organizations that recently purc
hased about the same number and type of laptops.
• Parametric estimate: You could decide on key factors, such as the basic catego
ry of laptop required and other requirements, and estimate costs using those pa
rameters. For example, you might estimate that the laptops would cost about $2
,000 each and that another $500 per unit would be required for support costs.
• Bottom-
up estimate: You could determine detailed hardware and software requirements
, training, and support costs to create an estimate.
4.Explain what happens during the process to determine the project budget.
Project cost budgeting involves allocating the project cost estimate to individual work ite
ms over time to create a cost baseline. For example, you may need to break down cost
s into specific categories like travel, compensation, etc. for each month so funds can be
allocated and tracked.
5.Explain how earned value management (EVM) can be used to control costs and
measure project performance and speculate as to why it is not used more often.
What are some general rules of thumb for deciding if cost variance, schedule vari
ance, cost performance index, and schedule performance index numbers are goo
d or bad?
Earned value analysis is a project performance technique that integrates scope, time, a
nd cost data. It is the preferred method for measuring project performance because it in
cludes all three dimensions of the triple constraint. It is not used more often because it i
s difficult to create a good baseline for cost, time, and scope estimates, and it is difficult
to enter actual information (percentage of work complete and actual time and cost numb
ers) in a timely manner. Negative variance numbers are bad. For example, a cost varia
nce of -
$1000 means it cost more than planned. A performance index below 100 percent is ba
d. For example, a schedule performance index of 80 percent means the project or activi
ty is behind schedule.
6.What is project portfolio management? Can project managers use it with earned
value management?
Project portfolio management is when organizations collect and control an entire suite of
projects or investments as one set of interrelated activities. Yes, you can use earned v
alue management along with project portfolio management.
7.Describe several types of software that project managers can use to support pr
oject cost management.
Spreadsheet software is often used to develop cost estimates, budgets, and other cost
management information. There are also specialized financial applications software pa
ckages, project management software, and portfolio management software to assist wit
h project cost management.
Assignment Name: Schwalbe, Information Technology Project Management 6e, Chapter 7
The ________ is the additional percentage or dollar amount by which actual costs exceed estimates.
a. cost baseline
b. sunk cost
1
c. cost overrun
d. profit margin
Which of the following processes of project cost management involves allocating the overall cost estimate to individual work items to establish a baseline for measuring
performance?
a. cost estimating
b. cost control
2
d. cost budgeting
Which of the following processes of project cost management involves developing an approximation of the costs of the resources needed to complete a project?
a. cost control
c. cost budgeting
d. cost estimating
The main outputs of the ________ process are work performance measurements, budget forecasts, organizational process asset updates, change requests, project
management plan updates, and project document updates.
a. cost estimating
b. cost budgeting
4
c. cost control
To increase ________, a company can increase revenues, decrease expenses, or try to do both.
a. rate of performance
b. profits
5
c. cost baselines
d. reserves
6 A company might complete a project to develop and implement a new customer service system in one or two years, but the new system could be in place for ten years.
Project managers should create estimates of the costs and benefits of the project for ten years. This is an example of ________.
a. cash flow analysis
b. cost budgeting
d. parametric modeling
b. indirect costs
7
c. sunk costs
d. direct costs
________ for projects often include items like goodwill, prestige, and general statements of improved productivity that an organization cannot easily translate into dollar
amounts.
a. Sunk cost
b. Direct costs
8
c. Indirect costs
d. Intangible costs
________ are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.
a. Budgetary estimates
b. Definitive estimates
9
c. Analogous estimates
Which type of estimate is done very early in a project or even before a project is officially started?
a. rough order of magnitude (ROM) estimate
b. definitive estimate
10
c. budgetary estimate
d. analogous estimate
The drawback with ________ is that they are usually time-intensive and therefore expensive to develop.
a. parametric modeling
b. definitive estimates
11
c. top-down estimates
d. bottom-up estimates
12 A ________ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using, the level of
expertise of the programmers, the size and complexity of the data involved, and so on.
a. bottom-up estimate
b. parametric model
c. definitive estimate
d. top-down estimate
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
a. definitive estimate
b. bottom-up estimate
13
c. parametric model
d. top-down estimate
A(n) ________ is a time-phased budget that project managers use to measure and monitor cost performance.
a. cost baseline
b. actual cost
14
c. baseline
The ________ is an estimate of the value of the physical work actually completed.
a. actual cost (AC)
Suppose a project included a summary activity of purchasing and installing a new Web server. Suppose further that, according to the plan, it would take one week and
cost a total of $10,000 for the labor hours, hardware, and software involved. The ________ for that activity that week is, therefore, $10,000.
a. planned value (PV)
17 Which of the following is the earned value minus the actual cost?
Which of the following is the earned value minus the planned value?
a. cost of performance index (CPI)
Which of the following is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project?
a. cost of performance index (CPI)