Professional Documents
Culture Documents
Concrete Rates
Concrete Rates
Laying of 2" thick Cement Concrete screed 1:3:6 (1 1/2) in foundation at depth not exceed in 5' 0"
Analysis for 1 Sqr
Laying of 2" thick Cement Concrete screed 1:3:6 (1 1/2) in foundation at depth not exceed in 5' 0"
Analysis for 1 Sqr
No Item Description Item Ref Unit Quantity Rate Amount
Ready mixed Concrete 1:3:6(1
1.01 05.A.02 Cube 0.17 31,130.00 5,292.10
1/2")
1.02 SK Labour L-003 Hr 4 187.50 750.00
1.03 U / SK Labourer L-007 Hr 4 150.00 600.00
Total for 6,642.10
Rate for 6,642.10
Rate(Say) 1 Sqr 6,640.00
Rate(Say) 1ft 2
66.40
Rate(Say) 1m2 714.46
Labour
1.03 Mason L-009 Hr 1 187.50 187.50
1.04 U / SK Labourer L-007 Hr 1 150.00 150.00
1.05 SK Labourer (Vibrator) L-004 Hr 0.5 187.50 93.75
1.08 U / SK Labourer (curing) L-007 Hr 0.5 150.00 75.00 506.25
Labour
1.03 Mason L-009 Hr 2 187.50 375.00
1.04 U / SK Labourer L-007 Hr 1 150.00 150.00
1.05 SK Labourer (Vibrator) L-004 Hr 1 187.50 187.50
1.08 U / SK Labourer (curing) L-007 Hr 1 150.00 150.00 862.50
Cement concrete 1:11/2 : 3(3/4") in column base & stub in ground floor.
Labour
1.03 Mason L-009 Hr 1.5 187.50 281.25
1.04 U / SK Labourer L-007 Hr 1 150.00 150.00
1.05 SK Labourer (Vibrator) L-004 Hr 1 187.50 187.50
1.08 U / SK Labourer (curing) L-007 Hr 0.7 150.00 105.00 723.75
#REF!
Rate(Say) 1m #REF!
Rate-BOQ 1m #REF!
Project : Proposed Factory Building for Navesta Pharmaceutical (Pvt) Ltd at Millewa.
2B Concrete Works.
2B - 02 Gr.25 Ready mixed Concrete for m3 224 17,100 3,830,400.00 350.76 28% 501.46
column foundations
2B - 05 Gr.25 Ready mixed Concrete for Lm 270 3,818 1,030,860.00 27% 597.59
300x300 plinth beam
BOQ Percentage of
Description of work Unit Proposed Rate
Item No RNC Markup
2B Concrete Works.
Menaka Weerasinghe
Project Quantity Surveyor
2B - 02)Gr.25 Ready mixed Concrete for column foundations
Analysis for 1 m3
Materials
Ready mixed Concrete 1:1 1/2 : 3 (3/4") m3 1 12,050.00 12,050.00
including transport
Allow 3% for Wastage 361.50 12,411.50
Labour 675.00
2B-16 )175mm thk. Gr.25 Ready mixed Floor Concrete for internal G.F floor area including Platform
Analysis for 1 m3
Materials
Ready mixed Concrete 1:1 1/2 : 3 (3/4") m3 1 12,050.00 12,050.00
including transport
Allow 3% for Wastage 361.50 12,411.50
Labour 893.00
Analysis for 1 m3
Materials
Ready mixed Concrete 1:1 1/2 : 3 (3/4") m3 1 12,050.00 12,050.00
including transport
Allow 3% for Wastage 361.50 12,411.50
Labour 1,060.00
Analysis for 1 m3
Materials
Ready mixed Concrete 1:1 1/2 : 3 (3/4") m3 1 12,050.00 12,050.00
including transport
Allow 3% for Wastage 361.50 12,411.50
Labour 690.00
Rate(Say) 1m #REF!
Rate-BOQ 1m #REF!
2B - 02)Gr.25 Ready mixed Concrete for column foundations
Analysis for 1 m3
Materials
Ready mixed Concrete 1:1 1/2 : 3 (3/4") m3 1 12,050.00 12,050.00
including transport
Allow 3% for Wastage 361.50 12,411.50
Labour
Sk Hr 4.5 125.00 562.50 982.02
Usk Hr 4 100.00 400.00 962.50
Project : Proposed Factory Building for Navesta Pharmaceutical (Pvt) Ltd at Millewa.
Qty as per RNC Labour Rate As Proposed Amount as per Amount as per
Boq Item No Description Unit
BOQ Markup per BOQ Labour rate BOQ proposed rate
2B Concrete Works.
2B - 02 Gr.25 Ready mixed Concrete for column foundations m3 #REF! 30% 675.00 500 #REF! #REF!
2B - 02 Gr.25 Ready mixed Concrete for column stubs m3 #REF! 30% 675.00 600 #REF! #REF!
2B - 05 Gr.25 Ready mixed Concrete for 300x300 Plinth beam m3 24.3 30% 675.00 600 16,402.50 14,580.00
2B-16 175mm thk. Gr.25 Ready mixed Floor Concrete for internal m3 534.275 30% 893.00 250 477,107.58 133,568.75
G.F floor area including Platform
2B-17 100mm thk. Gr.25 Readymixed Floor Concrete for internal m3 61.8 30% 1,060.00 250 65,508.00 15,450.00
G.F floor facility and office area
2B-18 150mm thick Gr.25 Concrete for mezzanine floor area m3 151.2 30% 690.00 250 104,328.00 37,800.00
#REF! #REF!