Material QTY Build Up Area Requirement Req in Nos/Tons/Litres Rate Total Amount Brand
Material QTY Build Up Area Requirement Req in Nos/Tons/Litres Rate Total Amount Brand
ULTRA TECH
CEMENT 0.4 3600 1440 1440 450 648000
435 PER BAG (50KG EACH)
TATA TISCON
STEEL 4 3600 14400 14.4 78000 1123200 62000 RS / TON
3240540
FLOOR PLAN,
STRUCTURAL 30000
DRAWINGS, 3D
FRONT ELEVATION
ELECTRICAL MATERIAL
& LABOUR 200000
PLUMBING MATERIAL
& 200000
LABOUR
ROOF WEATHERING
100000
MATERIAL & LABOUR
FRONT ELEVATION
150000
MATERIAL & LABOUR
TOTAL 3165000
MATERIAL QTY BUILD UP AREA REQUIREMENT REQ IN NOS/TONS/LITRES RATE TOTAL AMOUNT BRAND
ULTRA TECH
CEMENT 0.4 1500 600 600 485 291000
435 PER BAG (50KG EACH)
TATA TISCON
STEEL 4 1500 6000 6 78000 468000 62000 RS / TON
1310100
FLOOR PLAN,
STRUCTURAL
DRAWINGS, 3D 30000 FINAL 2875100
FRONT ELEVATION
BOREWELL 100000
ELECTRICAL MATERIAL
100000
& LABOUR
PLUMBING MATERIAL
& 100000
LABOUR
ROOF WEATHERING
100000
MATERIAL & LABOUR
FRONT ELEVATION
100000
MATERIAL & LABOUR
FALSE CEILING /
100000
WOODEN CUPBOARDS
TOTAL 1565000
MATERIAL QTY BUILD UP AREA REQUIREMENT REQ IN NOS/TONS/LITRES RATE TOTAL AMOUNT BRAND
TATA TISCON
STEEL 4 1600 6400 6 78000 468000 62000 RS / TON
1627440
1416.5