BSNL-MP Telecom Circle, Bhopal.

1
Enterprise Resource Planning

ERP systems facilitate the flow of real-time


information across departments, so businesses can
make data-driven decisions and manage
performance – live.

BSNL-MP Telecom Circle, Bhopal. 2


SAP stands for Systems, Applications and Products

 SAP Project Systems (PS) helps you to manage


the project life cycle starting from structuring to
planning, execution, until the project completion
( assetisation ).

3
BSNL-MP Telecom Circle, Bhopal.
1. Capital works :- Such as procurement of
ready to use items i.e. office equipments, furniture
etc.

•Process through IO (Internal Order)

2. Capital Projects :- Such as Laying of new OFC


/UG cable, BTS installation etc.

•Process through WBS (In PS-Module)

BSNL-MP Telecom Circle, Bhopal. 4


What is WBS

The WBS (Work Breakdown Structure) is an


important tool which helps you to keep an
overview of the project.

It shows the amount of work, the material and


services required, and the costs involved in the
project.

BSNL-MP Telecom Circle, Bhopal. 5


What is Network:

Material Requirement, Services and the


Overhead cost are aggregated in a Network.

A network is attached to a WBS.

BSNL-MP Telecom Circle, Bhopal. 6


WBS and Network Linking
WBS

Project
Network

Material
Req/Amt Overheads
Exp
Service
Req/Amt
1 2 3

BSNL-MP Telecom Circle, Bhopal. 7


Complex Project/WBS (Cable Laying in
different SLOCs of BA Bhopal (2302))

WBS Element-1 WBS Element-2 WBS Element-3


(Cable Laying in (Cable Laying in (Cable Laying in
Saket Nagar-SLOC-1) MP Nagar -SLOC-2) TT Nagar -SLOC-3)

N/W-1 1.Cable- 4 km
(Detailed 2. Jointing kit-4 nos
Estimate) Mat. Req for Cable 3. etc
Laying near AIIMS
1.Cable- 8 km
Int Proc Mat. Req for Cable
2. Jointing kit-16 nos
(Material Req) Laying near SBI
3. etc

Serv. Req for Cable 1.Trenching cost for 4km


Ext Proc Laying near AIIMS 2. Laying cost
(Service Req)
3. etc
Serv. Req for Cable 1.Trenching cost for 8km
Prim Cost
Laying near SBI 2. Laying cost
(up to 10%
Overheads) BSNL-MP Telecom Circle, Bhopal. 3. etc 8
WBS Creation

N/W Creation

Financial
Concurrence

Project Approval

Budgeting

MIGO
Service-PO Release of N/W (Good Issue to
Creation
SLOC)
Asset Creation

Equipment Creation
BSNL-MP Telecom Circle, Bhopal.
9
WBS Creation WBS Modification N/W Creation
(CJ01) (CJ02) (CN21)

Budget Project Financial N/W


Alloaction Approval Concurrence Modification
(BUDG/AUC) (PEAP) (PEFI) (CN22)

Release of Material MIGO


N/W (Int. Prc) (T&P,
Reservn No Good Issue)

Service
(Ext. Prc) PO Creation Release SES MIRO
PR No

BSNL-MP Telecom Circle, Bhopal. 10


WBS Status Modification WBS Settlement
(OFAT,TKOV,etc) Cost will be shifted from WBS to AUC
(CJ02) (CJ88)

Zero Valued
WBS Status WBS and N/W
Asset Creation
Comm then CLSD Status TECO
Using Template
(CJ02) (CJ02/CN22)
(AS01)

Allocating Final Creation Equipment


Amount to each of Asset Creation thru
Asset from WBS Project settled PM Module
(CJIC) (CJ88) (IE01)

BSNL-MP Telecom Circle, Bhopal. 11


Creation of project

BSNL-MP Telecom Circle, Bhopal. 12


Creation of project (CJ01 )

BSNL-MP Telecom Circle, Bhopal. 13


Creation of project (CJ01 )

BSNL-MP Telecom Circle, Bhopal. 14


Creation of project (CJ01 )

BSNL-MP Telecom Circle, Bhopal. 15


Creation of project (CJ01 )

BSNL-MP Telecom Circle, Bhopal. 16


Creation of project (CJ01 )

BSNL-MP Telecom Circle, Bhopal. 17


Creation of project (CJ01 )

Enter project Description,


company code,
Business area,
Plant, Start date and Person Responsible

BSNL-MP Telecom Circle, Bhopal. 18


Creation of project (CJ01 )

Project Definition will be created

BSNL-MP Telecom Circle, Bhopal. 19


Creation of WBS

BSNL-MP Telecom Circle, Bhopal. 20


Creation of WBSs(CJ02 )

BSNL-MP Telecom Circle, Bhopal. 21


Creation of WBSs(CJ02 )

Enter Data for Level 1 and Level 2 WBSs

BSNL-MP Telecom Circle, Bhopal. 22


Creation of WBSs(CJ02 )

BSNL-MP Telecom Circle, Bhopal. 23


Creation of WBSs(CJ02 )

BSNL-MP Telecom Circle, Bhopal. 24


Creation of WBSs(CJ02 )

BSNL-MP Telecom Circle, Bhopal. 25


Creation of WBSs(CJ02 )

BSNL-MP Telecom Circle, Bhopal. 26


Creation of WBSs(CJ02 )

Q. Can we use project typ FA/BB/Cm be used at Level 2 ?

A. No, The project type FA/BB/CM shall be used at Level 1 only.

BSNL-MP Telecom Circle, Bhopal. 27


Creation of WBSs(CJ02 )

WBS will be created.

BSNL-MP Telecom Circle, Bhopal. 28


Tuning WBS data (CJ02)

BSNL-MP Telecom Circle, Bhopal. 29


Tuning WBS data (CJ02)

BSNL-MP Telecom Circle, Bhopal. 30


Tuning WBS data (CJ02)

Asset data recorded.

BSNL-MP Telecom Circle, Bhopal. 31


Movement of notesheet (CJ02)

BSNL-MP Telecom Circle, Bhopal. 32


Movement of notesheet (CJ02)

BSNL-MP Telecom Circle, Bhopal. 33


Movement of notesheet (CJ02)

Note sheet will be received in workflow of SDE concerned

BSNL-MP Telecom Circle, Bhopal. 34


Movement of notesheet (CJ02)

Note sheet will be received in workflow of SDE concerned

BSNL-MP Telecom Circle, Bhopal. 35


Movement of notesheet (CJ02)

BSNL-MP Telecom Circle, Bhopal. 36


Creation of Network

BSNL-MP Telecom Circle, Bhopal. 37


Creation of Detail Estimate (CN21)

BSNL-MP Telecom Circle, Bhopal. 38


Creation of Detail Estimate (CN21)

BSNL-MP Telecom Circle, Bhopal. 39


Creation of Detail Estimate (CN21)

Network profile,
Network type=ZPS2,
Plant ,
MRP controller=001.

BSNL-MP Telecom Circle, Bhopal. 40


Creation of Detail Estimate (CN21)

BSNL-MP Telecom Circle, Bhopal. 41


Creation of Detail Estimate (CN21)

Change scheduling to forward and mention start date

BSNL-MP Telecom Circle, Bhopal. 42


Creation of Detail Estimate (CN21)

BSNL-MP Telecom Circle, Bhopal. 43


Creation of Detail Estimate (CN21)

BSNL-MP Telecom Circle, Bhopal. 44


Creation of Detail Estimate (CN21)

Network number will be created.

BSNL-MP Telecom Circle, Bhopal. 45


Creation of Detail Estimate (CN22)

BSNL-MP Telecom Circle, Bhopal. 46


Creation of Detail Estimate (CN22)

BSNL-MP Telecom Circle, Bhopal. 47


Creation of Detail Estimate (CN22)

BSNL-MP Telecom Circle, Bhopal. 48


Creation of Detail Estimate (CN22)

(a) Internal processing (All the materials to be issued from BSNL stores)
(b) External Processing (Services to be hired from External Vendor)
(c) Primary costs (All other costs).
(d) Primary cost should be 10-20% of the total project cost.

BSNL-MP Telecom Circle, Bhopal. 49


Creation of Detail Estimate (CN22)

(a) Internal processing (All the materials to be issued from BSNL stores)

BSNL-MP Telecom Circle, Bhopal. 50


Creation of Detail Estimate (CN22)

BSNL-MP Telecom Circle, Bhopal. 51


Creation of Detail Estimate (CN22)

Internal activities created

BSNL-MP Telecom Circle, Bhopal. 52


Creation of Detail Estimate (CN22)

BSNL-MP Telecom Circle, Bhopal. 53


Creation of Detail Estimate (CN22)

(a) External Processing (Services to be hired from External Vendor)

BSNL-MP Telecom Circle, Bhopal. 54


Creation of Detail Estimate (CN22)

External activities created

BSNL-MP Telecom Circle, Bhopal. 55


Creation of Detail Estimate (CN22)

(a) Primary costs (All other costs).


(b) Primary cost should be 10-20% of the total project cost.

Misc cost activities created.

BSNL-MP Telecom Circle, Bhopal. 56


Earlier Primary Cost was calculated automatically.

BSNL-MP Telecom Circle, Bhopal. 57


Creation of Detail Estimate (CN22)

When saved OCP000 in CN41 will be populated.


PS Clearing G/L will be linked to these activities

BSNL-MP Telecom Circle, Bhopal. 58


Changing Status (CJ02)

BSNL-MP Telecom Circle, Bhopal. 59


Changing Status of WBS

BSNL-MP Telecom Circle, Bhopal. 60


Changing Status (CJ02)

BSNL-MP Telecom Circle, Bhopal. 61


Changing Status (CJ02)

BSNL-MP Telecom Circle, Bhopal. 62


Initiating approval of Detailed estimate using
Workflow and Notesheet functionality

WBS would reach AGM PLG. With user status PECT.

BSNL-MP Telecom Circle, Bhopal. 63


Sending for Financial Concurrence using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 64


Sending for Financial Concurrence using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 65


Sending for Financial Concurrence using
Workflow and Notesheet functionality

Q. Can an additional WBS be created at Level 2 after approval(PEAP/AAES) ?


A. No, It should be planned before approval of estimate.
BSNL-MP Telecom Circle, Bhopal. 66
Sending for Financial Concurrence using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 67


Sending for Financial Concurrence using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 68


Sending for Financial Concurrence using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 69


Initiating approval of Detailed estimate using
Workflow and Notesheet functionality

BSNL-MP Telecom Circle, Bhopal. 70


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 71


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 72


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 73


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 74


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 75


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 76


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 77


IM node assignment and other activities by AO Plg.

BSNL-MP Telecom Circle, Bhopal. 78


Approval of Estimate

BSNL-MP Telecom Circle, Bhopal. 79


Note sheet would reach GMTD.

BSNL-MP Telecom Circle, Bhopal. 80


Sanction of estimate

Note sheet would reach GMTD.

BSNL-MP Telecom Circle, Bhopal. 81


Sanction of estimate

BSNL-MP Telecom Circle, Bhopal. 82


Sanction of estimate

Q. Can the user status be set to PEAP/AAES through user status updation tab ?

A. No, The Project should be approved (PEAP/AAES) through notesheet ("approve


project estimate" tab) only i.e. status change from PEFI to PEAP/AAES should not be
done manually.
BSNL-MP Telecom Circle, Bhopal. 83
Sanction of estimate

BSNL-MP Telecom Circle, Bhopal. 84


Sanction of estimate

BSNL-MP Telecom Circle, Bhopal. 85


Sanction of estimate

BSNL-MP Telecom Circle, Bhopal. 86


Sanction of estimate

BSNL-MP Telecom Circle, Bhopal. 87


Sanction of estimate

Estimate will be approved.


OCP001 in CN41 will be populated.
PDF of Estimate will be Generated.
Level 1 Notesheet would reach AGM Plg/FI whoever had sent it.
BSNL-MP Telecom Circle, Bhopal. 88
CN41 status

BSNL-MP Telecom Circle, Bhopal. 89


User can’t Release WBS without Budget Allocation

Q. At what user/system status the WBS shall be released ?

A. It should compulsorily be released at PEAP/DEAP user status and BUDG,AVAC


system status only.

BSNL-MP Telecom Circle, Bhopal. 90


Budget Allocation

BSNL-MP Telecom Circle, Bhopal. 91


User can’t Release WBS without Budget Allocation

Q. In case of WBS of Project type CI/CW/EW/EC/EE ,why WBS is not getting released
even status is PEAP/AAES,BUDG and AVAC ?

A. In case of CI/CW/EW/EC/EE it will be released when status is DEAP in addition to


BUDG and AVAC.
BSNL-MP Telecom Circle, Bhopal. 92
Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 93


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 94


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 95


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 96


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 97


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 98


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 99


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 100


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 101


Allocating budget and check Availability control (IM52,CJBV )

BSNL-MP Telecom Circle, Bhopal. 102


Allocating budget and check Availability control (IM52,CJBV )

System status of WBS changed to BUDG and AVAC (Budgetary check).

BSNL-MP Telecom Circle, Bhopal. 103


Release of each Level 2 WBS

AGM Plg. Or Concerned SDE will release WBS.

System status will be set to REL.


Cost postings can be done on this WBS now.
BSNL-MP Telecom Circle, Bhopal. 104
Release of WBS and Network

BSNL-MP Telecom Circle, Bhopal. 105


Release of each Level 2 WBS

BSNL-MP Telecom Circle, Bhopal. 106


Release of each Level 2 WBS

BSNL-MP Telecom Circle, Bhopal. 107


Release of each Level 2 WBS

BSNL-MP Telecom Circle, Bhopal. 108


Release of each Level 2 WBS

BSNL-MP Telecom Circle, Bhopal. 109


Release of each Network

BSNL-MP Telecom Circle, Bhopal. 110


Release of each Network

Network activities will be released.


Material Reservation number and Purchase requisitions number will be
generated.
PR will create commitment also.
BSNL-MP Telecom Circle, Bhopal. 111
Execution of work starts now

BSNL-MP Telecom Circle, Bhopal. 112


MIGO (Transfer/Posting and Goods Issue)

BSNL-MP Telecom Circle, Bhopal. 113


Reserving Inventory in store exclusively for Level 2 WBS
MIGO (Mvt type 415)

Materials will be reserved and cannot be issued to any other work.

BSNL-MP Telecom Circle, Bhopal. 114


Inventory Issue as per requirement MIGO (Mvt type 281Q)

BSNL-MP Telecom Circle, Bhopal. 115


Inventory Issue as per requirement MIGO (Mvt type 281Q)

Goods will be issued to Project.


Can be seen through CN41 report,actual cost coloumn
BSNL-MP Telecom Circle, Bhopal. 116
Release of PR for external services. (Workflow/Inbox)

In actual scenario. PR will be released by workflow

BSNL-MP Telecom Circle, Bhopal. 117


PO Creation and MIRO

BSNL-MP Telecom Circle, Bhopal. 118


Creation of PO using PR (ME21N, Need based order)

PO will be Generated

BSNL-MP Telecom Circle, Bhopal. 119


Release of PO (Workflow/Inbox)

PO will be released through workflow

BSNL-MP Telecom Circle, Bhopal. 120


Create SES (ML81N)

1.Enter ref PO number

2.Click on Create new entry sheet

BSNL-MP Telecom Circle, Bhopal. 121


Create SES (ML81N)

1.Enter SLOC

2.Adopt Services which are to be verified

BSNL-MP Telecom Circle, Bhopal. 122


Create SES (ML81N)

1.Enter Quantity to be verified

2.Save

BSNL-MP Telecom Circle, Bhopal. 123


Release SES (Workflow/Inbox)

SES will be released through workflow

BSNL-MP Telecom Circle, Bhopal. 124


Payment to vendor,Misc cost postings. (MIRO, FB60)

BSNL-MP Telecom Circle, Bhopal. 125


Payment to vendor,Misc cost postings. (MIRO, FB60)

Vendor payment will be done and Misc cost postings will be done.

BSNL-MP Telecom Circle, Bhopal. 126


Changing user statuses of WBSs as per current situations.
(CJ02)

Monitoring of project will be carried out


AGM Plg. Or Concerned SDE will chang the user status as per work done
i.e RECR,REAP, OFAT,PFCO, TKOV etc.

BSNL-MP Telecom Circle, Bhopal. 127


Changing WBS Status

BSNL-MP Telecom Circle, Bhopal. 128


Changing user statuses of WBSs as per current situations.
(CJ02)

AGM Plg. Or Concerned SDE will chang the user status as per work done
i.e RECR,REAP, OFAT,PFCO, TKOV etc.

BSNL-MP Telecom Circle, Bhopal. 129


Changing user statuses of WBSs as per current situations.
(CJ02)

AGM Plg. Or Concerned SDE will chang the user status as per work done
i.e RECR,REAP, OFAT,PFCO, TKOV etc.

BSNL-MP Telecom Circle, Bhopal. 130


AUC Settelement (CJ88)

a) Cost will be shifted from network to WBS


b) Cost will be shifted from WBS to AUC G/L 2191000.Itcan be seen through CJI3
report.

BSNL-MP Telecom Circle, Bhopal. 131


AUC Settlement & Asset Creation

BSNL-MP Telecom Circle, Bhopal. 132


AUC Settelement (CJ88)

a) Cost will be shifted from network to WBS


b) Cost will be shifted from WBS to AUC G/L 2191000.Itcan be seen
through CJI3 report.

BSNL-MP Telecom Circle, Bhopal. 133


Asset master Creation (AS01)

Zero value asset will be created

Enter Asset class, Company code

BSNL-MP Telecom Circle, Bhopal. 134


Asset master Creation Template

BSNL-MP Telecom Circle, Bhopal. 135


Asset master Creation Template

BSNL-MP Telecom Circle, Bhopal. 136


Asset master Creation (AS01)

Zero value asset will be created


Enter Asset sub class,services,Region and components, BA, Cost element,Location
(BSNL) etc

BSNL-MP Telecom Circle, Bhopal. 137


Allocating amount to each asset from the total amount in WBS.
(CJIC)

Settlement rule Finalized

BSNL-MP Telecom Circle, Bhopal. 138


Allocating amount to each asset from the total amount in WBS.
(CJIC)

Settlement rule Finalized

BSNL-MP Telecom Circle, Bhopal. 139


Allocating amount to each asset from the total amount in WBS.
(CJIC)

Settlement rule Finalized

BSNL-MP Telecom Circle, Bhopal. 140


Final creation of asset (CJ88)

Project setteled. It can be seen through ZPS_PROJ report.

BSNL-MP Telecom Circle, Bhopal. 141


Final creation of asset (CJ88)

Project setteled. It can be seen through ZPS_PROJ report.

BSNL-MP Telecom Circle, Bhopal. 142


Equipment Creation (IE01)

PM MDM Team will create respective equipment on the Basis of Template. Avb
at portal 10.197.216.213 under PM Module->PM BDC files->Equipment creation.

Equipment will be created

BSNL-MP Telecom Circle, Bhopal. 143


Neccesity of Asset and Equipment Linking

BSNL-MP Telecom Circle, Bhopal. 144


BSNL-MP Telecom Circle, Bhopal. 145