Professional Documents
Culture Documents
01 - Earth Works
01 - Earth Works
01 1993
Table of Contents
0100 - GENERAL.....................................................................................................................2
0103 - QUARRYING................................................................................................................9
0100 - General
01000 - General
010001 - Scope
These specifications refer to common earthworks for building constructions. Special
preparation works such as building, demolition or special supports required due to proximity
of buildings or work under the level of the aquifer shall be specified in the particular
specifications.
01002 - Definitions
Earth and soil - the terms refer to any type of natural material, including rock.
Layer thickness - is the thickness after the compression and compaction, to be
carried out according to the specifications pertaining to that layer.
Back-fill (borrowed fill) - soil taken from the building site for filling purposes.
Brought up fill - fill brought from places out of the building site for filling
purposes.
Surplus soil - excavated soil not used in the construction.
01003 - Standards
Tthe following is the main standard pertaining to this chapter:
Sorting of soils according to AASHTO ASTM-D-3282 - Classification of Soils
and Soil-Aggregate Mixtures for Highway Construction Purposes.
01004 - Collapse
In the event of a collapse due to insufficient support, or any other reason, the contractor shall
re-excavate the pit and repair the casing and support. Moreover, the contractor shall bear the
3
cost of all damages to people or property incurred by the collapse, and he hereby absolves the
manager of any claims, which may arise in this context.
01005 - Drainage
All excavations described above shall be protected against the penetration of rainwater, by the
adoption of appropriate means such as excavation of drainage trenches, or the creation of
temporary earth banks. If rainwater or sewage water have accumulated in the excavated pits,
despite the means adopted by the contractor, the contractor shall remove the water from the
excavations and allow the bottom to dry sufficiently, to the supervisor's satisfaction, before he
resumes work. These instructions also apply to back- fill.
The excavation and fill and excavation in back-fill areas etc. shall be carried out in such a way
as to allow constant drainage of the water during all the stages of work. The means of
drainage shall include works as excavation of temporary trenches, building of banks, pumping
of water, blocking of pits, etc.
01012 9 Exposure
Exposure includes removal of existing vegetation (shrubs and weeds) and the upper soil layer,
up to a thickness of 20 cm., and then disposal and distribution of this layer as described in
section 01017. Exposure shall be carried out according to a plan, or after the CO has approved
the execution and its scope in advance.
01015 – Dismantling
010151 – Dismantling of Buildings
Wherever required to do so, at whatever length and depth, the contractor shall dismantle both
surface and underground buildings, such as; existing concrete trenches, drainage lines
containing concrete pipes and stone fill, acquaducts, control-cells, embankments and the like.
Foundations or surface buildings shall only be dismantled down to a depth of 1.0 meter below
the subgrade surface. The work includes removal of concrete and stone pieces, etc. as detailed
in section 01017 below.
required density is obtained. When dismantling concrete plates, the plates shall be broken into
parts small enough to be loaded and disposed of.
01022 - Excavation
010221 - Area Excavations
Excavation in the area shall be carried out according to the details of the plans, or as required
in order to lower the level of the existing soil surface, down to the levels determined by the
CO. In the case of soil surpluses, the best excavated soil, which in the CO's opinion conforms
to the requirements and may serve as an appropriate fill, shall be transferred to the planned fill
areas and distributed there as provided in the section concerning fill.
Excavation of aqueducts and excavation of pits (trenches) shall be discussed below.
7
placed, pockets shall be excavated at the bottom of the trench, so as to accommodate pipe
fixtures or connectors. Each trench in a pipeline shall be excavated in a single session along
its entire length and to its entire depth, between one cell and another - and this shall be done
before the pipes are placed in it. Special care shall be taken to thoroughly compact the
bedding or the back-fill below the pipe and up to half its height.
Moreover, special attention shall be given to compacting the pipelines below the concrete
surfaces or tiled areas. The excavation for cables shall be carried out as required in the
appropriate chapter, i.e., chapter 08 - electrical installation, 43 - external lighting, etc.
010227 - Workspaces
Workspaces for the purpose of casing, formworks, sealing or any other purpose, in all types of
excavation and quarrying works, shall be determined by the contractor according to need, as
stated above.
0103 - Quarrying
01030 - General
If not noted otherwise, quarrying shall be defined as an excavation that may only be carried
out with the use of penetrometers, compressors, wedges or the use of explosives.
Any work that can be carried out with tractors of any kind, even when operated in their
strongest gear position, shall not be considered quarrying. Such quarrying shall not be
commenced unless the CO has reached the conclusion that the work cannot be carried out
10
except through the above detailed means, and after the CO has given his written authorization
to quarry the rock as above. The material approved for usage as fill shall be transferred and
distributed as detailed in section 01032.
The surpluses shall be transferred and distributed as detailed above in section 01023 (the void
created following the quarrying shall hereinafter be termed "excavation", as it is termed when
he soil is excavated). When an excavation has been approved as a quarry, the CO shall
indicate the appropriate quarrying gradients, in contrary to the markings in the plan.
The bottom of trenches and pits below foundations shall be leveled to the required levels and
inclines by means of a layer of lean concrete whose average thickness shall not exceed 5.0
cm. The bottom of the trenches excavated for pipes, etc., shall be leveled with a layer of
course gravel or aggregates (at an average thickness of 5.0 cm.) compacted as specified in
paragraph 0104, unless another requirement has been noted in the plans or in one of the other
contract documents, or if the CO has so required.
01031 - Blasting
The use of explosives requires the written consent of the CO. The contractor shall obtain all
the licenses and permits required for blasting operations.
The blasts shall be confined to the planned volumes, and no extra blasting shall be permitted.
Loose rocks, or those whose stability has been lessened following the blast, shall be removed
from the site.
Before compaction of each layer, it must be leveled to the supervisor's satisfaction. The
finish of the upper layer compaction shall be within the allowed deviation limits.
D. The compaction work includes preservation of the finished layer surface and its
edges, at the appropriate density and humidity and at the proper height until it is spread
and compacted onto the next and proximate layer. The preservation of the layer surface
also means repeated wetting and compaction if required to this end.
01042 - Density
Unless otherwise specified, the range of density allowed at the site shall be as follows;
Controlled tamping
Type of soil according to the Depth of layer below the Minimum tamping rate
AASHO classification method subgrade surface
A-3 (maximum 5% passing At any depth 98%
mesh 200)
A-1 * , A-2-4, A-3 (More than At any depth 95%
5% passing mesh 200
A-2-5,A-2-6,A-2-7,A-4,A-5 Less than 100 cm 95%
A-2-5,A-2-6,A-2-7,A-4,A-5 More than 100 cm 93%
A-6 to A-7-6(5) At any depth 93%
A-7-6(5)** At any depth 90%
* The compaction rate required for an A-1 type subgrade is at least 98%.
** In swelling clays, the CO is entitled to demand a different compaction rate (for example 89
2%).
Regular compaction
The compaction of each of the layers of fill in quarried material which in the opinion of the
CO, because it contains large stones, the extent of its compaction cannot be measured by
means of a density test - shall be carried out by means of a vibration roller with a minimum
force of 15 tons/blow and the number of vibrations per minute shall be no less than 1000.
The compaction shall be carried out along the entire width of the layer, until the sinking of the
soil or its movement under the rollshall stop, and each point has been covered with a
minimum of 8 roller passes - where the thickness of the layer is up to 30 cm, or double the
number of passes when the layer thickness is more than 30 cm (up to 60 cm).
The contractor is entitled to suggest compaction with a vibration roller with a greater
minimum force (more than 18 tons/blow), the minimum number of passes in this case shall be
decided by the CO following the compaction of a trial patch.
12
If in the course of compaction, it becomes evident that in some places the rate of compaction
can be tested to the entire depth of the layer, the CO is entitled to demand the compaction rate
required for the controlled compaction.
from an authorized source and shall be course sand, free of all stones, clay, silt, organic
materials or any other damaging materials.
The sand must be spread in layers whose thickness does not exceed 20 cm., and compacted as
detailed in paragraph 0104. The layers shall be spread in parallel with the final surface of the
cast or tiled area, and the bedding surface shall be shaped according to the required levels and
gradients. Bedding made of another material shall be carried out according to the particular
specifications.