Professional Documents
Culture Documents
Monthly Report Format
Monthly Report Format
DOCUMENT NO.
AL-HASSAN ENGINEERNG CO. SAOG
PROJECT: AMAL POWER STATION
(PDO CONTRACT NO: C-311333)
TABLE OF CONTENTS
Page
Section 1 Contract Particulars
1.01 Salient Features of the Contract
1.02 Contract Scope of Work in brief
Section 2 Project Summary Report
2.01 Project Progress Statistics
2.02 Narrative Summary Report
2.03 Over-all Progress Curve for the Project
2.04 Areas of Concern
Section 3 Detailed Report
3.01 Health, Safety and Environment (HSE)
3.02 Engineering & Design Documents
3.03 Procurement
3.04 Manufacturing
3.05 Delivery
3.06 Mobilization
3.07 On plot construction and commissioning
3.08 Off Plot construction and Commissioning
3.09 Equipment Deployment
3.10 Manpower Deployment
3.11 Quality Assurance
3.12 Plan for Next month
3.13 Contract Financials
Section 4 Appendices
I Project Milestone Dates
II Project Schedule (Updated)
III Drawing Control Register
IV Material Tracking Register
V Critical Project Material List
VI Health & Safety Statistics (Monthly Return)
VII HSE Audit / Inspection Schedule
VIII HSE Training Matrix
IX Quality internal and external audit schedule
X Summary of progress
XI S-curve for Engineering Progress
XII S-curve for Procurement Progress
XIII S-curve for Construction progress
XIV S-curve for Overall progress
XV S-curve for VOWD
Doc. No: Rev. No : Date: Page 5 of 48
MONTHLY PROGRESS REPORT
SECTION 1
CONTRACT PARTICULARS
HVAC System.
SECTION 2
1.
2.
3.
1.
2.
SECTION 3
DETAILED REPORTS
3.03: Procurement
3.04: Manufacturing
3.05: Delivery
3.06: Mobilization:
Civil
Mechanical
ELECTRICAL
Instrumentation
Testing
1. Station wagon
2. Pickup
3. Potable water tanker 5000 Gallon
4. Tipper
5. Diesel Tanker
6. Shovel/Loader
7. Grader
8. Bucket truck
9. 62 Seat Big bus
10. Crew cab
1. Project Manager
2. Interface Manager
3. Planning Manager
4. Procurement Manager
5. Design Manager
6. Design Electrical Engineer
7. Design Civil Engineer
8. Project Coordinator
9. Cost Accountant
10. Draughts man
11 Secretary
12 Drivers (Omani)
1. Project Manager
2. Civil Discipline
3. Electrical Discipline
4. Mechanical Discipline
5. Process Discipline
6. C & I Discipline
7. Piping Discipline
1. Staff ( Expat)
2. Staff (Omani)
3. JE (Expat)
4. JE (Omani)
5 Sub contract
Mobilization:
Civil
Mechanical
Electrical
Commissioning
Instrumentation
QUALITY ASSURANCE
CONTRACT FINANCIALS:
SECTION 4
APPENDICES
APPENDICES-I
MS-1
MS-2
MS-3
MS-4
MS-5a
MS-5b
MS-6
MS-7
MS-8
MS-9
MS-10
APPENDICES II
APPENDICES-III
APPENDICES-IV
APPENDICES-V
APPENDICES-VI
APPENDICES-VII
HSE AUDIT/INSPECTION
SCHEDULE
APPENDICES-VIII
APPENDICES-IX
APPENDICES-X
SUMMARY OF PROGRESS
ENGINEERING
PROCUREMENT
CONSTRUCTION
OVERALL
APPENDICES-XI
APPENDICES-XII
APPENDICES-XIII
APPENDICES-XIV
APPENDICES-XV
APPENDICES-XVI
APPENDICES-XVII
SUBCONTRACT DETAILS
APPENDICES-XVIII
VARIATION REGISTER
APPENDICES-XIX
OMANISATION R
APPENDICES-XX
SPIR PROGRESS
MATERIALS
APPENDICES-XXI
PROGRESS PHOTOGRAPHS