HYDERABAD GROWTH CORRIDOR LIMITED

Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Certified Quantitis Bifurcated District Wise For AGGREGATE

Cummulative
IPC Wise IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 Total Quantity of the
Package
Bowrampet (Ranga Reddy District)
3.01 - - - - 6,506.800 10,646.800 18,847.288 708.646 7,583.387 185.564 44,478.485 56,155.485
3.02 - - - - - 2,787.014 19,178.470 1,898.806 9,557.186 2,005.120 35,426.596 44,059.596
4.04 (Maytas) - - - - - - 2,680.926 - - - 2,680.926 2,680.926
4.04 (Ramky) 2,703.224 - 2,703.224 2,703.224
4.04 (GPL) - 6,738.783 6,738.783 6,738.783
5.02 - - - - - - - - - - - 1,832.895
5.05 - - - - - 41.940 132.240 29.116 - - 203.296 705.519
5.06(a) - - - - - 108.000 345.702 31.660 - - 485.362 793.287
5.07(a) - - - - - 102.704 490.216 - - - 592.920 2,065.671
5.08(a) - - - - - 39.965 168.105 - - - 208.070 424.268
6.02 - - - - - - - - - - - 2,630.655
6.05(a) - - - - - 20.022 150.576 - - - 170.598 880.674
6.05(b) - - - - - 133.498 939.817 - - - 1,073.315 5,611.489
6.06(a)(i) - - - - - 249.614 752.328 138.974 - - 1,140.916 3,148.766
6.06(a)(ii) - - - - - - 156.806 - - - 156.806 638.301
6.07(a) - - - - - 526.331 576.732 - - - 1,103.063 1,677.416
8.06(a) - - - - - - 3,220.000 - - - 3,220.000 10,566.000
8.08© - - - - - 15.038 175.618 - - - 190.656 471.076
8.08(d) - - - - - 39.541 53.834 - - - 93.375 1,085.270
8.08(e) - - - - - 20.988 52.121 - - - 73.109 543.041

Gummadidala (Medak District)


3.01 2,332.000 9,345.000 11,677.000
3.02 8,633.000 8,633.000
4.04 (Maytas) -
4.04 (Ramky) -
4.04 (GPL) -
5.02 346.913 - - 145.192 - 329.520 667.445 - 320.131 23.694 1,832.895
5.05 63.429 74.788 58.878 125.479 4.197 25.142 - 21.224 69.123 59.963 502.223
5.06(a) - 26.514 - - 9.190 68.610 - 50.444 130.136 23.031 307.925
5.07(a) - 146.107 41.413 116.065 225.609 183.710 - 25.817 343.642 390.388 1,472.751
5.08(a) - - - 49.476 38.788 - - 3.594 84.563 39.777 216.198
6.02 - 57.969 - 730.370 357.600 - - 45.120 198.654 1,240.942 2,630.655
6.05(a) - 109.659 58.616 83.760 42.496 20.022 - - 216.580 178.943 710.076
6.05(b) - 183.129 949.945 661.072 254.380 133.498 - 66.749 1,002.946 1,286.455 4,538.174
6.06(a)(i) - - 215.282 234.240 416.245 168.113 - 123.782 386.496 463.692 2,007.850
6.06(a)(ii) - - - - - - - 93.236 211.900 176.359 481.495
6.07(a) - - - - 259.162 315.191 - - - - 574.353
8.06(a) - - - - - - - 1,824.000 2,522.000 3,000.000 7,346.000
8.08© - 30.600 - - 10.790 15.000 - 39.838 131.657 52.535 280.420
8.08(d) - - 57.542 - - 27.593 - 169.265 570.624 166.871 991.895
8.08(e) - - 7.193 10.789 10.801 - - - 143.174 297.975 469.932
HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Certified Quantitis Bifurcated District Wise For EARTH WORK/ MORROM MATERIAL

Cummulative
IPC Wise IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 Total Quantity of the
Package
Ranga reddy District
2.03 133,725.51 127,086.91 172,732.93 218,765.59 256,693.10 190,235.83 158,042.31 72,288.21 77,742.37 33,805.96 1,441,118.70 1,441,118.699
2.04 - - - 14,025.72 27,931.70 30,160.82 387.70 13,564.01 10,401.82 96,471.761 96,471.761
2.05 - - - - - - - - - -
2.06(a) 42,559.51 13,849.65 86,615.85 26,604.68 21,816.85 13,646.50 29,870.11 19,715.00 55,914.50 53,820.55 364,413.192 364,413.192
2.06(b) - - - - - 14,839.26 - 5,194.60 19,606.15 39,640.008 39,640.008
2.06© - - - - - 967.44 - 508.74 850.95 2,327.130 2,327.130
2.09 - - - - - 1,453.90 - - 292.95 1,746.850 1,746.850

Medak District
2.03 -
2.04 -
2.05 -
2.06(a) -
2.06(b) -
2.06© -
2.09 -
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 1 IPC-1 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 133,725.510 133,726 - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - m
2.06(a) Eambankment Reuse Cum - - - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - -
3.01 Granular Sub-base Cum - 2.230 - - - - - - -
3.02 Wet mix macadam Cum - 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 133,725.510 - - - - - - ###
-
133,725.510 - ###
-

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum 346.913 1.000 346.913 - - - - -
5.05 PCC M 15 for leveling course Cum 63.429 0.4810 0.6693 0.6693 30.509 - - 42.453 42.453 -
5.06(a) PCC Grade M 20 Cum - 0.4754 0.6560 0.6540 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.4520 0.6244 0.6225 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.4520 0.6244 0.6225 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.4806 0.6631 0.6611 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4806 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum - 0.4806 0.6631 0.6611 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.4450 0.6145 0.6126 - - - - - -
- - - - - -
Total Quantity from Medak District - 377.422 - - 42.453 42.453 - ###
-
- 377.422 ###
84.906
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 2 IPC-2 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 127,086.910 127,087 - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum - - - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum - 2.230 - - - - - - -
3.02 Wet mix macadam Cum - 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 127,086.910 - - - - - - ###
-
127,086.910 - ###
-

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - -
5.05 PCC M 15 for leveling course Cum 74.788 0.4810 0.6631 0.6611 35.973 - - 49.592 49.442 -
5.06(a) PCC Grade M 20 Cum 26.514 0.4750 0.6560 0.6540 12.594 - - 17.393 17.340 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 146.107 0.4520 0.6244 0.6225 66.040 - - 91.222 90.944 -
5.08(a) RCC M 25 superstructure Cum - 0.4520 0.6244 0.6225 - - - - - -
6.02 Granular material Filling in Foundat Cum 57.969 - - - - - -
6.05(a) PCC M15 for foundation Cum 109.659 0.4810 0.6631 0.6611 52.746 - - 72.715 72.496 -
6.05(b) RCC M30 for foundation Cum 183.129 0.4450 0.6145 0.6126 81.492 - - 112.524 112.185 -
6.06a(i) RCC M30 Upto 5m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum 30.600 0.4806 0.6631 0.6611 14.706 - - 20.291 20.230 -
8.08(d) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.4450 0.6145 0.6126 - - - - - -
- - - - - -
Total Quantity from Medak District - 263.552 - - 363.736 362.637 - ###
-
- 263.552 ###
726.373
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 3 IPC-3 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 172,732.928 172,733 - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum - - - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum - 2.230 - - - - - - -
3.02 Wet mix macadam Cum - 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 172,732.928 - - - - - - ###
-
172,732.93 - ###
-

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - -
5.05 PCC M 15 for leveling course Cum 58.878 0.4810 0.6631 0.6611 28.320 - - 39.042 38.924 -
5.06(a) PCC Grade M 20 Cum - 0.4754 0.6560 0.6540 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 41.413 0.4520 0.6244 0.6225 18.719 - - 25.856 25.778 -
5.08(a) RCC M 25 superstructure Cum - 0.4520 0.6244 0.6225 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum 58.616 0.4810 0.6631 0.6611 28.194 - - 38.868 38.751 -
6.05(b) RCC M30 for foundation Cum 949.945 0.4450 0.6145 0.6126 422.726 - - 583.694 581.936 -
6.06a(i) RCC M30 Upto 5m height Cum 215.282 0.4450 0.6145 0.6126 95.800 - - 132.280 131.882 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4806 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum - 0.4806 0.6631 0.6611 - - - - - -
8.08(d) RCC M30 for foundation Cum 57.542 0.4450 0.6145 0.6126 25.606 - - 35.357 35.250 -
8.08(e) RCC M30 for Substructure Cum 7.193 0.4450 0.6145 0.6126 3.201 - - 4.420 4.406 -
- - - - - -
Total Quantity from Medak District - 622.566 - - 859.517 856.928 - ###
-
- 622.566 ###
1,716.444
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 4 IPC-4 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 218,765.588 218,766 - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum - - - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum - 2.230 - - - - - - -
3.02 Wet mix macadam Cum - 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 218,765.588 - - - - - - ###
-
218,765.59 - ###
-

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum 145.192 1.000 145.192 - - - - -
5.05 PCC M 15 for leveling course Cum 125.479 0.4810 0.6631 0.6611 60.355 - - 83.205 82.954 -
5.06(a) PCC Grade M 20 Cum - 0.4754 0.6560 0.6540 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 116.065 0.4520 0.6244 0.6225 52.461 - - 72.465 72.245 -
5.08(a) RCC M 25 superstructure Cum 49.476 0.4520 0.6244 0.6225 22.363 - - 30.890 30.796 -
6.02 Granular material Filling in Foundat Cum 730.370 - - - - - -
6.05(a) PCC M15 for foundation Cum 83.760 0.4810 0.6631 0.6611 40.289 - - 55.541 55.374 -
6.05(b) RCC M30 for foundation Cum 661.072 0.4450 0.6145 0.6126 294.177 - - 406.196 404.973 -
6.06a(i) RCC M30 Upto 5m height Cum 234.240 0.4450 0.6145 0.6126 104.237 - - 143.929 143.495 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum - 0.4810 0.6631 0.6611 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
8.08(e) RCC M30 for Substructure Cum 10.789 0.4450 0.6145 0.6126 4.801 - - 6.629 6.609 -
- - - - - -
Total Quantity from Medak District - 723.875 - - 798.856 796.446 - ###
-
- 723.875 ###
1,595.302
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 5 IPC-5 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 256,693.095 256,693 - - - - - -
2.04 Subgrade with approved material Cum 14,025.715 14,026 - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum 191,446.530 191,447 - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 6,506.800 - - - - - - -
3.02 Wet mix macadam Cum - 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 462,165.340 - - - - - - ###
-
462,165.34 - ###
-

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - -
5.05 PCC M 15 for leveling course Cum 4.197 0.4810 0.6631 0.6611 2.019 - - 2.783 2.775 -
5.06(a) PCC Grade M 20 Cum 9.190 0.4754 0.6560 0.6540 4.369 - - 6.029 6.010 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 225.609 0.4520 0.6244 0.6225 101.975 - - 140.859 140.430 -
5.08(a) RCC M 25 superstructure Cum 38.788 0.4520 0.6244 0.6225 17.532 - - 24.217 24.144 -
6.02 Granular material Filling in Foundat Cum 357.600 - - - - - -
6.05(a) PCC M15 for foundation Cum 42.496 0.4810 0.6631 0.6611 20.441 - - 28.179 28.094 -
6.05(b) RCC M30 for foundation Cum 254.380 0.4450 0.6145 0.6126 113.199 - - 156.304 155.833 -
6.06a(i) RCC M30 Upto 5m height Cum 416.245 0.4450 0.6145 0.6126 185.229 - - 255.762 254.992 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum 259.162 0.4450 0.6145 0.6126 115.327 - - 159.242 158.763 -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum 10.790 0.4810 0.6631 0.6611 5.190 - - 7.155 7.133 -
8.08(d) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
8.08(e) RCC M30 for Substructure Cum 10.801 0.4450 0.6145 0.6126 4.806 - - 6.637 6.617 -
- - - - - -
Total Quantity from Medak District - 570.087 - - 787.166 784.790 - ###
-
- 570.087 ###
1,571.957
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 6 IPC-6 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 190,235.830 190,236 - - - - - -
2.04 Subgrade with approved material Cum 27,931.700 27,932 - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum 13,646.500 13,647 - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 10,646.800 2.230 - - - - - - 23,742
3.02 Wet mix macadam Cum 2,787.014 0.729 0.354 0.398 0.729 - - 2,032.569 985.488 1,108.674 2,032.569
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum 41.940 0.3352 0.2301 0.6661 0.5441 14.058 9.650 - 27.936 22.820 -
5.06(a) PCC Grade M 20 Cum 108.000 0.3315 0.2277 0.6594 0.5384 35.802 24.592 - 71.215 58.147 -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 102.704 0.2980 0.2046 0.6448 0.5265 30.606 21.013 - 66.224 54.074 -
5.08(a) RCC M 25 superstructure Cum 39.965 0.2980 0.2046 0.6448 0.5265 11.910 8.177 - 25.769 21.042 -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum 20.022 0.3352 0.2301 0.6661 0.5441 6.711 4.607 - 13.337 10.894 -
6.05(b) RCC M30 for foundation Cum 133.498 0.2850 0.1958 0.6442 0.5261 38.047 26.139 - 85.999 70.233 -
6.06a(i) RCC M30 Upto 5m height Cum 249.614 0.2850 0.1958 0.6442 0.5261 71.140 48.874 - 160.801 131.322 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum 526.331 0.2850 0.1958 0.6442 0.5261 150.004 103.056 - 339.062 276.903 -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum 15.038 0.3352 0.2301 0.6661 0.5441 5.041 3.460 - 10.017 8.182 -
8.08(d) RCC M30 for foundation Cum 39.541 0.2850 0.1958 0.6442 0.5261 11.269 7.742 - 25.472 20.803 -
8.08(e) RCC M30 for Substructure Cum 20.988 0.2850 0.1958 0.6442 0.5261 5.982 4.109 - 13.520 11.042 -
- - - - - -
Total Quantity from Ranga reddy District 231,814.030 584.461 225.657 2,032.569 1,755.370 1,724.663 2,032.569 23,742.364
###
231,814.03 584.461 ###
31,513.192

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum 329.520 1.000 329.520 - - - - -
5.05 PCC M 15 for leveling course Cum 25.142 0.4810 0.6631 0.6611 12.093 - - 16.672 16.621 -
5.06(a) PCC Grade M 20 Cum 68.610 0.4750 0.6560 0.6540 32.590 - - 45.008 44.871 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 183.710 0.4520 0.6244 0.6225 83.037 - - 114.699 114.350 -
5.08(a) RCC M 25 superstructure Cum - 0.4520 0.6244 0.6225 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum 20.022 0.4810 0.6631 0.6611 9.631 - - 13.277 13.237 -
6.05(b) RCC M30 for foundation Cum 133.498 0.4450 0.6145 0.6126 59.407 - - 82.028 81.781 -
6.06a(i) RCC M30 Upto 5m height Cum 168.113 0.4450 0.6145 0.6126 74.810 - - 103.297 102.986 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum 315.191 0.4450 0.6145 0.6126 140.260 - - 193.669 193.086 -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum 15.000 0.4810 0.6631 0.6611 7.215 - - 9.947 9.917 -
8.08(d) RCC M30 for foundation Cum 27.593 0.4450 0.6145 0.6126 12.279 - - 16.955 16.903 -
8.08(e) RCC M30 for Substructure Cum - 0.4450 0.6145 0.6126 - - - - - -
- - - - - -
Total Quantity from Medak District - 760.841 - - 595.551 593.752 - ###
-
- 760.841 ###
1,189.303
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 7 IPC-7 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 158,042.305 158,042 - - - - - -
2.04 Subgrade with approved material Cum 30,160.821 30,161 - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum 29,870.112 29,870 - - - - - -
(
2.06(b) Subgrade Reuse Cum 14,839.258 14,839 - - - - - -
m
2.06© Shoulder Reuse Cum 967.440 967 - - - - -
)
2.09 Filling of median / island with appr Cum 1,453.900 1,454 - - - - - -
3.01 Granular Sub-base Cum 18,847.288 2.230 - - - - - - 42,029
3.02 Wet mix macadam Cum 19,178.470 0.729 0.354 0.398 0.729 - - 13,986.858 6,781.507 7,629.195 13,986.858
4.04 DBM (Mytas mix) Cum 2,680.926 0.437 0.459 0.391 0.988 - - 1,170.413 1,231.742 1,047.110 2,648.761
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum 132.240 0.3352 0.2301 0.6661 0.5441 44.327 30.428 - 88.085 71.952 -
5.06(a) PCC Grade M 20 Cum 345.702 0.3315 0.2277 0.6594 0.5384 114.600 78.716 - 227.956 186.126 -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 490.216 0.2980 0.2046 0.6448 0.5265 146.084 100.298 - 316.091 258.099 -
5.08(a) RCC M 25 superstructure Cum 168.105 0.2980 0.2046 0.6448 0.5265 50.095 34.394 - 108.394 88.507 -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum 150.576 0.3352 0.2301 0.6661 0.5441 50.473 34.648 - 100.299 81.928 -
6.05(b) RCC M30 for foundation Cum 939.817 0.2850 0.1958 0.6442 0.5261 267.848 184.016 - 605.430 494.438 -
6.06a(i) RCC M30 Upto 5m height Cum 752.328 0.2850 0.1958 0.6442 0.5261 214.413 147.306 - 484.650 395.800 -
6.06a(ii) RCC M30 5m - 10m height Cum 156.806 0.2850 0.1958 0.6442 0.5261 44.690 30.703 - 101.014 82.496 -
6.07(a) RCC M30 Super structure Cum 576.732 0.2850 0.1958 0.6442 0.5261 164.369 112.924 - 371.531 303.419 -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 3,220.000 0.0226 0.0241 0.0607 72.772 77.602 - - 195.446 -
8.08© PCC M15 grade Cum 175.618 0.3352 0.2301 0.6661 0.5441 58.867 40.410 - 116.979 95.554 -
8.08(d) RCC M30 for foundation Cum 53.834 0.2850 0.1958 0.6442 0.5261 15.343 10.541 - 34.680 28.322 -
8.08(e) RCC M30 for Substructure Cum 52.121 0.2850 0.1958 0.6442 0.5261 14.854 10.205 - 33.576 27.421 -
- - - - - -
Total Quantity from Ranga reddy District 235,333.836 1,924.775 892.191 15,157.271 10,601.934 10,748.774 16,635.619 42,029.452
###
235,333.84 1,924.775 ###
96,065.242

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum 667.445 1.000 667.445 - - - - -
5.05 PCC M 15 for leveling course Cum - 0.4810 0.6631 0.6611 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.4754 0.6560 0.6540 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.4520 0.6244 0.6225 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.4520 0.6244 0.6225 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.4810 0.6631 0.6611 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0245 0.0672 - - - - - -
8.08© PCC M15 grade Cum - 0.4810 0.6631 0.6611 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.4450 0.6145 0.6126 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.4450 0.6145 0.6126 - - - - - -
- - - - - -
Total Quantity from Medak District - 667.445 - - - - - ###
-
- 667.445 ###
-
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 8 IPC-8 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 72,288.205 72,288 - - - - - -
2.04 Subgrade with approved material Cum 387.700 388 - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum 19,715.000 19,715 - - - - - -
(
2.06(b) Subgrade Reuse Cum - - - - - - - -
m
2.06© Shoulder Reuse Cum - - - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 7,215.446 2.230 - - - - - - 16,090
3.02 Wet mix macadam Cum 1,898.806 0.729 0.354 0.398 0.729 - - 1,384.799 671.418 755.345 1,384.799
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum 29.116 0.3352 0.2301 0.6661 0.5441 9.760 6.700 - 19.394 15.842 -
5.06(a) PCC Grade M 20 Cum 31.660 0.3315 0.2277 0.6594 0.5384 10.495 7.209 - 20.877 17.046 -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum 138.974 0.2850 0.1958 0.6442 0.5261 39.608 27.211 - 89.527 73.114 -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 92,390.905 (1,029.006) 1,119.906 1,384.799 801.216 861.347 1,769.890 16,090.445
###
92,390.905 (1,029.006) ###
22,027.603

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2.230 - - - - - - -
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - -
5.05 PCC M 15 for leveling course Cum 21.224 0.4810 0.6631 0.6611 10.209 - - 14.074 14.031 -
5.06(a) PCC Grade M 20 Cum 50.444 0.4754 0.6560 0.6540 23.981 - - 33.091 32.990 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 25.817 0.4520 0.6244 0.6225 11.669 - - 16.119 16.070 -
5.08(a) RCC M 25 superstructure Cum 3.594 0.4520 0.6244 0.6225 1.624 - - 2.244 2.237 -
6.02 Granular material Filling in Foundat Cum 1,191.059 1.5950 - - - - - 1,899.739
6.05(a) PCC M15 for foundation Cum - 0.4810 0.6631 0.6611 - - - - - -
6.05(b) RCC M30 for foundation Cum 66.749 0.4450 0.6145 0.6126 29.703 - - 41.014 40.890 -
6.06a(i) RCC M30 Upto 5m height Cum 123.782 0.4450 0.6145 0.6126 55.083 - - 76.058 75.829 -
6.06a(ii) RCC M30 5m - 10m height Cum 93.236 0.4450 0.6145 0.6126 41.490 - - 57.289 57.116 -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4810 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 1,824.000 0.0226 0.0245 0.0672 41.222 44.688 - - 122.561 -
8.08© PCC M15 grade Cum 39.838 0.4810 0.6631 0.6611 19.162 - - 26.417 26.337 -
8.08(d) RCC M30 for foundation Cum 169.265 0.4450 0.6145 0.6126 75.323 - - 104.005 103.692 -
8.08(e) RCC M30 for Substructure Cum - 0.4450 0.6145 0.6126 - - - - - -
- - - - - -
Total Quantity from Medak District - 309.467 44.688 - 370.310 491.754 1,899.739 ###
-
- 309.467 ###
2,806.491
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Package-2 from Mallampet R
(Km.35+000) to Dindigal (Km.46+000) being takenup with the loan assistance from Japan International Cooperation Agency under Phase - 1 Programme, Contract Agreement No: CGM(T)/HGCL/27/08-09 C
C
MATERIAL CONSUMPTION STATEMENT FOR ROYALTY
P
i
Interim Payment Certificate No. 9 IPC-9 For the Month of May 2010
p
Factor Material Consumption e
This Bill Gravel 1
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 2
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT)
(Cu.m) 0
Consumed from Ranga Reddy District 0
2.03 Embankment with Borrow Cum 77,742.368 77,742 - - - - - -
2.04 Subgrade with approved material Cum 13,564.010 13,564 - - - - - - m
2.05 Shoulder with approved material Cum - - - - - - - - m
2.06(a) Eambankment Reuse Cum 55,914.500 55,915 - - - - - -
(
2.06(b) Subgrade Reuse Cum 5,194.600 5,195 - - - - - -
m
2.06© Shoulder Reuse Cum 508.740 509 - - - - -
)
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 7,583.387 2.230 - - - - - - 16,911
3.02 Wet mix macadam Cum 9,557.186 0.729 0.354 0.398 0.729 - - 6,970.056 3,379.421 3,801.849 6,970.056
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 2,703.224 0.458 0.482 0.409 1.035 - - 1,236.779 1,301.873 1,106.592 2,799.027
4.04 DBM Cum - 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - -
- - - - - -
Total Quantity from Ranga reddy District 152,924.218 - - 8,206.835 4,681.294 4,908.441 9,769.083 16,910.953
###
152,924.22 - ###
44,476.605

Consumed from Medak District


2.03 Embankment with Borrow Cum - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - -
3.01 Granular Sub-base Cum 2,332.000 2.230 - - - - - - 5,200
3.02 Wet mix macadam Cum 0.729 0.354 0.398 0.729 - - - - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - -
5.02 Sand filling in Foundation Cum 320.131 1.000 320.131 - - - - -
5.05 PCC M 15 for leveling course Cum 69.123 0.4806 0.6631 0.6611 33.221 - - 45.835 45.697 -
5.06(a) PCC Grade M 20 Cum 130.136 0.4754 0.6560 0.6540 61.867 - - 85.369 85.109 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 343.642 0.4520 0.6244 0.6225 155.326 - - 214.553 213.900 -
5.08(a) RCC M 25 superstructure Cum 84.563 0.4520 0.6244 0.6225 38.222 - - 52.797 52.636 -
6.02 Granular material Filling in Foundat Cum 198.654 1.5950 - - - - - 316.853
6.05(a) PCC M15 for foundation Cum 216.580 0.4806 0.6631 0.6611 104.088 - - 143.614 143.181 -
6.05(b) RCC M30 for foundation Cum 1,002.946 0.4450 0.6145 0.6126 446.311 - - 616.260 614.405 -
6.06a(i) RCC M30 Upto 5m height Cum 386.496 0.4450 0.6145 0.6126 171.991 - - 237.482 236.767 -
6.06a(ii) RCC M30 5m - 10m height Cum 211.900 0.4450 0.6145 0.6126 94.296 - - 130.202 129.810 -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - -
6.08 M15 for Approach slab Cum - 0.4806 0.6631 0.6611 - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 2,522.000 0.0226 0.0245 0.0607 56.997 61.789 - - 153.079 -
8.08© PCC M15 grade Cum 286.883 0.4806 0.6631 0.6611 137.876 - - 190.232 189.658 41.363
8.08(d) RCC M30 for foundation Cum 570.624 0.4450 0.6145 0.6126 253.928 - - 350.620 349.564 76.178
8.08(e) RCC M30 for Substructure Cum 143.174 0.4450 0.6145 0.6126 63.712 - - 87.973 87.708 18.087
- - - - - -
Total Quantity from Medak District - 1,937.966 61.789 - 2,154.939 2,301.516 452.481 5,200.360
###
- 1,937.966 ###
10,171.084
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT FOR ROYALTY

Interim Payment Certificate No. 10 IPC-10 For the Month of May 2010
Factor Material Consumption
Void
This Bill Gravel RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel formers
Quantity Sand 40mm 20mm 10mm Dust GSB /Morrum GSB (MT) 600 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) 1000mm
(Cu.m) (m)
dia (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 33,805.960 33,806 - - - - - - - - -
2.04 Subgrade with approved material Cum 10,401.815 10,402 - - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 53,820.550 53,821 - - - - - - - - -
2.06(b) Subgrade Reuse Cum 19,606.150 19,606 - - - - - - - - -
2.06© Shoulder Reuse Cum 850.950 851 - - - - - - - -
2.09 Filling of median / island with appr Cum 292.950 293 - - - - - - - - -
3.01 Granular Sub-base Cum 185.564 2.230 - - - - - - 414 - - -
3.02 Wet mix macadam Cum 2,005.120 0.729 0.354 0.398 0.729 - - 1,462.334 709.010 797.637 1,462.334 - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 - - - - - - - - - -
4.04 DBM(Ramky mix) Cum - 0.458 0.482 0.409 1.035 - - - - - - - - - -
4.04 DBM Cum 6,738.783 0.971 0.428 0.834 - - - 6,541.889 2,880.978 5,618.703 721.040 - 154.395 -
5.02 Sand filling in Foundation Cum - 1.0000 - - - - - - - - -
5.05 PCC M 15 for leveling course Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - - - - -
5.06(a) PCC Grade M 20 Cum - 0.3315 0.2277 0.6594 0.5384 - - - - - - - - -
5.06(b) PCC Grade M 25 Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - - - - -
5.08(a) RCC M 25 superstructure Cum - 0.2980 0.2046 0.6448 0.5265 - - - - - - - - -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - - - - -
6.03 Back filling with granular material Cum - - - - - - - - - -
6.04 Filter media behind abutments Cum - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - - - - -
6.05(b) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
6.06a(i) RCC M30 Upto 5m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
6.06a(ii) RCC M30 5m - 10m height Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
6.07(a) RCC M30 Super structure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - - - - -
6.08 M15 for Approach slab Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - - - - -
6.09 M30 for Approach slab Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
8.06(a) M-20 Median Kerb "A" Lm - 0.0226 0.0241 0.0607 - - - - - - - - -
8.08© PCC M15 grade Cum - 0.3352 0.2301 0.6661 0.5441 - - - - - - - - -
8.08(d) RCC M30 for foundation Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
8.08(e) RCC M30 for Substructure Cum - 0.2850 0.1958 0.6442 0.5261 - - - - - - - - -
- - - - - - - - -
Total Quantity from Ranga reddy District 118,778.375 - - 1,462.334 7,250.900 3,678.615 4,890.716 413.808 721.040 - 154.395 - - -
118,778.38 - 17,696.372 721.040 - 154.395 - - -
in No.s
Consumed from Medak District
2.03 Embankment with Borrow Cum - - - - - - - - - - -
2.04 Subgrade with approved material Cum - - - - - - - - - - -
2.05 Shoulder with approved material Cum - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum - - - - - - - - - - -
2.06© Shoulder Reuse Cum - - - - - - - - - -
2.09 Filling of median / island with appr Cum - - - - - - - - - - -
3.01 Granular Sub-base Cum 9,345.000 2.230 - - - - - - 20,839 - - -
3.02 Wet mix macadam Cum 8,633.000 0.729 0.354 0.398 0.729 - - 6,296.047 3,052.629 3,434.207 6,296.047 - - -
4.04 DBM (Mytas mix) Cum 0.437 0.459 0.391 0.988 - - - - - - - - - -
4.04 DBM(Ramky mix) Cum 0.451 0.427 0.427 0.923 - - - - - - - - - -
4.04 DBM Cum 0.971 0.428 0.834 - - - - - - - - - -
5.02 Sand filling in Foundation Cum 23.694 1.000 23.694 - - - - - - - -
5.05 PCC M 15 for leveling course Cum 59.963 0.4806 0.6631 0.6611 28.818 - - 39.761 39.642 - - 16.190 -
5.06(a) PCC Grade M 20 Cum 23.031 0.4754 0.6560 0.6540 10.949 - - 15.108 15.062 - - 6.449 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 - - - - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 390.388 0.4520 0.6244 0.6225 176.455 - - 243.739 242.997 - - 136.636 -
5.08(a) RCC M 25 superstructure Cum 39.777 0.4520 0.6244 0.6225 17.979 - - 24.835 24.759 - - 13.922 -
6.02 Granular material Filling in Foundat Cum 1,240.942 1.5950 - - - - - 1,979.302 - - -
6.03 Back filling with granular material Cum - - - - - - - - - -
6.04 Filter media behind abutments Cum - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 178.943 0.4806 0.6631 0.6611 86.000 - - 118.657 118.299 - - 48.315 -
6.05(b) RCC M30 for foundation Cum 1,286.455 0.4450 0.6145 0.6126 572.472 - - 790.462 788.082 - - 488.853 -
6.06a(i) RCC M30 Upto 5m height Cum 463.692 0.4450 0.6145 0.6126 206.343 - - 284.916 284.058 - - 176.203 -
6.06a(ii) RCC M30 5m - 10m height Cum 176.359 0.4450 0.6145 0.6126 78.480 - - 108.364 108.038 - - 67.016 -
6.07(a) RCC M30 Super structure Cum - 0.4450 0.6145 0.6126 - - - - - - - - -
6.07(b) RCC M35 Super structure Cum - - - - - - - - - -
6.08 M15 for Approach slab Cum - 0.4806 0.6631 0.6611 - - - - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 - - - - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 3,000.000 0.0226 0.0245 0.0607 67.800 73.500 - - 182.093 - - 59.520 -
8.08© PCC M15 grade Cum 286.883 0.4806 0.6631 0.6611 137.876 - - 190.232 189.658 41.363 - 77.458 -
8.08(d) RCC M30 for foundation Cum 166.871 0.4450 0.6145 0.6126 74.258 - - 102.534 102.225 76.178 - 63.411 -
8.08(e) RCC M30 for Substructure Cum 297.975 0.4450 0.6145 0.6126 132.599 - - 183.091 182.539 18.087 - 113.231 -
- - - - - - - - -
Total Quantity from Medak District - 1,613.723 73.500 6,296.047 5,154.328 5,711.660 8,410.977 20,839.350 - - 1,267.203 - - -
- 1,613.723 46,485.862 - - 1,267.203 - - -
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No. 11 For the Month of June 2010


Factor Material Consumption
This Bill Gravel RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT)
(Cu.m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,503,284.523 1,503,285 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 112,274.390 112,274 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 417.000 417 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 385,986.067 385,986 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 2,327.130 2,327 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 1,746.850 1,747 - - - - - - - - - - -
3.01 Granular Sub-base Cum 44,478.485 2.2300 - - - - - - 99,187 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 183,279.490 0.001 - - - - - - - - 137.460 - -
4.02(a) Tack coat over granular surface Sqm 66,191.450 0.000 - - - - - - - - 18.203 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 13,395.366 0.9708 0.4275 0.8338 0.107 0.0229 - - - 13,003.980 5,726.814 11,168.869 - 1,433.285 - 306.907 -
5.02 Sand filling in Foundation Cum 1,841.067 1.000 1,841.067 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 210 - - - - - - - - - - -
5.04 Filter media Cum 81.989 0.6810 0.9080 0.6810 - - - 55.835 74.446 55.835 - - - - -
5.05 PCC M 15 for leveling course Cum 203.296 0.3352 0.2301 0.6661 0.5441 0.2700 68.145 46.778 - 135.415 110.613 - - - - 54.890 -
5.06(a) PCC Grade M 20 Cum 497.350 0.3315 0.2277 0.6594 0.5384 0.2800 164.872 113.247 - 327.953 267.773 - - - - 139.258 -
5.07(a) RCC M 25 foundations & Substructu Cum 782.103 0.2980 0.2046 0.6448 0.5265 0.3500 233.067 160.018 - 504.300 411.777 - - - - 273.736 -
5.08(a) RCC M 25 superstructure Cum 208.070 0.2980 0.2046 0.6448 0.5265 0.3500 62.005 42.571 - 134.164 109.549 - - - - 72.825 -
5.09(a) TMT for Foundation MT 114.580 1.0000 - - - - - - - - - - 114.580
5.09(b) TMT for Substructure MT 110.424 1.0000 - - - - - - - - - - 110.424
5.09(c) TMT for Superstructure MT 42.466 1.0000 - - - - - - - - - - 42.466
5.10 H.P NP-4, 1200 mm Dia Lm 324.300 - - - - - - - - - - -
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 219.256 0.3352 0.2301 0.6661 0.5441 0.2700 73.495 50.451 - 146.046 119.297 - - - - 59.199 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 1,495.617 0.2850 0.1958 0.6442 0.5261 0.3800 426.251 292.842 - 963.476 786.844 - - - - 568.334 -
6.06a(ii) RCC M30 5m - 10m height Cum 157.111 0.2850 0.1958 0.6442 0.5261 0.3800 44.777 30.762 - 101.211 82.656 - - - - 59.702 -
6.07(a) RCC M30 Super structure Cum 1,103.063 0.2850 0.1958 0.6442 0.5261 0.3800 314.373 215.980 - 710.593 580.321 - - - - 419.164 -
6.15(a) TMT for Foundation MT 548.219 1.0000 - - - - - - - - - - 548.219
6.15(b) TMT for Substructure MT 248.199 1.0000 - - - - - - - - - - 248.199
6.15© TMT for Superstructure MT 101.679 1.0000 - - - - - - - - - - 101.679
8.06(a) M-20 Median Kerb "A" Lm 3,530.000 0.0226 0.0241 0.0607 0.0198 79.778 85.073 - - 214.263 - - - - 70.035 -
8.08(b) filter material behind retaining wall Cum 27.000 0.6810 0.9080 0.6810 - - - 18.387 24.516 18.387 - - - - -
8.08© PCC M15 grade Cum 225.756 0.3352 0.2301 0.6661 0.5441 0.2700 75.673 51.946 - 150.376 122.834 - - - - 60.954 -
8.08(d) RCC M30 for foundation Cum 141.318 0.2850 0.1958 0.6442 0.5261 0.3800 40.276 27.670 - 91.037 74.347 - - - - 53.701 -
8.08(e) RCC M30 for Substructure Cum 126.156 0.2850 0.1958 0.6442 0.5261 0.3800 35.954 24.701 - 81.270 66.371 - - - - 47.939 -
8.08(f) TMT For foundation & substruc. Cum 123.307 1.0000 - - - - - - - - - - 123.307
9.17(a) NP2 600mm Dia Pipe Lm 271.030 - - - - - - - - - - - 271.030
- - - - - - - - - - -
2056763.046 - - - - - - - - -
Total Cumulative Quantity 2,049,362.6 3,985.236 6,324.499 28,242.943 33,399.130 27,193.439 43,117.938 99,187.022 2,026.815 160.261 3,014.009 1,288.87 271.000
Upto Previous Bill Quantity 1,945,813.6 1,480.230 2,237.754 28,243.808 25,090.713 21,921.840 35,097.877 99,187.022 1,314.570 115.840 3,147.575 1,057.57 111.000
Balance Quantities 103,549.06 2,505.006 4,086.745 (0.865) 8,308.417 5,271.599 8,020.061 - 712.245 44.421 (133.566) 231.303 64.000
2,505.0 4,086.7 in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No. 11 For the Month of June 2010


Factor Material Consumption
This Bill Gravel RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT)
(Cu.m) (m)

Consumed from Medak District


3.01 Granular Sub-base Cum 19,453.956 2.230 - - - - - - 43,382 - - - -
3.02 Wet mix macadam Cum 18,935.558 0.729 0.354 0.398 0.729 - - 13,809.702 6,695.613 7,532.565 13,809.702 - - - - -
4.03 BM Cum - 0.110 0.0231 - - - - - - - - - - -
4.04 DBM (Mytas mix) Cum - 0.437 0.459 0.391 0.988 0.110 0.023 - - - - - - - - - - -
4.04 DBM(Ramky mix) Cum - 0.451 0.427 0.427 0.923 0.109 0.024 - - - - - - - - - - -
4.04 DBM Cum 0.001 0.971 0.428 0.834 0.107 0.023 - - - 0.000 0.000 0.000 - 0.000 - 0.000 -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - - - - - - -
5.03 Back filling behind abutments Cum - - - - - - - - - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 502.222 0.4806 0.6693 0.6693 0.2700 241.368 - - 336.137 336.137 - - - - 135.600 -
5.06(a) PCC Grade M 20 Cum 307.915 0.4754 0.6560 0.6540 0.2800 146.383 - - 201.992 201.376 - - - - 86.216 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,510.796 0.4524 0.6244 0.6225 0.3500 683.484 - - 943.265 940.395 - - - - 528.779 -
5.08(a) RCC M 25 superstructure Cum 237.379 0.4524 0.6244 0.6225 0.3500 107.390 - - 148.208 147.757 - - - - 83.083 -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - - - - - - -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,273.768 0.4452 0.6145 0.6126 0.3800 2,347.882 - - 3,240.467 3,230.710 - - - - 2,004.032 -
6.06a(i) RCC M30 Upto 5m height Cum 2,406.069 0.4452 0.6145 0.6126 0.3800 1,071.182 - - 1,478.409 1,473.958 - - - - 914.306 -
6.06a(ii) RCC M30 5m - 10m height Cum 503.745 0.4452 0.6145 0.6126 0.3800 224.267 - - 309.526 308.594 - - - - 191.423 -
6.07(a) RCC M30 Super structure Cum 577.651 0.4452 0.6145 0.6126 0.3800 257.170 - - 354.938 353.869 - - - - 219.507 -
8.06(a) M-20 Median Kerb "A" Lm 6,586.000 0.0226 0.0245 0.0672 0.0198 148.844 161.357 - - 442.537 - - - - 130.666 -
8.08(b) filter material behind retaining wall Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
8.08© PCC M15 grade Cum 318.369 0.4806 0.6631 0.6611 0.2700 153.008 - - 211.110 210.474 - - - - 85.960 -
8.08(d) RCC M30 for foundation Cum 1,093.506 0.4452 0.6145 0.6126 0.3800 486.829 - - 671.905 669.882 - - - - 415.532 -
8.08(e) RCC M30 for Substructure Cum 543.451 0.4452 0.6145 0.6126 0.3800 241.944 - - 333.923 332.918 - - - - 206.511 -
Extra M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0117 21.507 23.326 - - 63.986 - - - - 12.519 -
- - - - - - - - -
Total Cumulative Quantity - 6,495.906 184.68 13,809.70 15,428.61 16,746.76 13,809.70 43,382.32 - - 5,218.99 - -
Upto Previous Bill Quantity - 8,276.299 179.97 6,296.05 11,126.86 11,942.14 10,763.20 26,039.52 - - 3,811.117 - -
Balance Quantities - (1,780.393) 4.713 7,513.655 4,301.755 4,804.622 3,046.506 17,342.805 - - 1,407.876 - -
- - 1,407.9 - in No.s
Balance Quantity in This Month 103,549.06 724.613 4,091.458 58,608.555 712.245 44.421 1,274.310 231.303 64.000
erabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

For the Month of June 2010


Material Consumption
RCC Pipe
1200 mm
(m)

324.300

324.300

324.300

-
in No.s
erabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

For the Month of June 2010


Material Consumption
RCC Pipe
1200 mm
(m)

-
in No.s
-
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag R
C
C
MATERIAL CONSUMPTION STATEMENT
P
Interim Payment Certificate No. 12 For the Month of July 2010 i
Factor Material Consumption p
e
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel 6
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) 0
(Cu.m) (m) (m)
0
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,528,615.606 1,528,616 - - - - - - - - - - - m
2.04 Subgrade with approved material Cum 113,803.790 113,804 - - - - - - - - - - - m
2.05 Shoulder with approved material Cum 2,395.860 2,396 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614 - - - - - - - - - - - (
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - - m
2.06© Shoulder Reuse Cum 3,573.450 3,573 - - - - - - - - - - - )
2.06(d) Median filling Reuse Cum 804.420 804 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 2,355.070 2,355 - - - - - - - - - - -
3.01 Granular Sub-base Cum 46,360.245 2.2300 - - - - - - 103,383 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 214,663.840 0.001 - - - - - - - - 160.998 - -
4.02(a) Tack coat over granular surface Sqm 80,238.050 0.000 - - - - - - - - 22.065 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 17,365.340 0.9708 0.4275 0.8338 0.107 0.0229 - - - 16,857.959 7,424.065 14,478.977 - 1,858.067 - 397.864 -
5.02 Sand filling in Foundation Cum 1,841.067 1.0000 1,841.067 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 81.989 0.6810 0.9080 0.6810 - - - 55.835 74.446 55.835 - - - - -
5.05 PCC M 15 for leveling course Cum 216.151 0.3352 0.2301 0.6661 0.5441 0.2700 72.454 49.736 - 143.978 117.608 - - - - 58.361 -
5.06(a) PCC Grade M 20 Cum 509.344 0.3315 0.2277 0.6594 0.5384 0.2800 168.848 115.978 - 335.861 274.231 - - - - 142.616 -
5.07(a) RCC M 25 foundations & Substructu Cum 809.433 0.2980 0.2046 0.6448 0.5265 0.3500 241.211 165.610 - 521.922 426.166 - - - - 283.302 -
5.08(a) RCC M 25 superstructure Cum 253.186 0.2980 0.2046 0.6448 0.5265 0.3500 75.449 51.802 - 163.254 133.302 - - - - 88.615 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.678
5.09(b) TMT for Substructure MT 121.442 1.0000 - - - - - - - - - - 121.442
5.09(c) TMT for Superstructure MT 52.902 1.0000 - - - - - - - - - - 52.902
5.10 H.P NP-4, 1200 mm Dia Lm 354.908 - - - - - - - - - - - 354.908
6.02 Granular material Filling in Foundati Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 1,842.781 0.2850 0.1958 0.6442 0.5261 0.3800 525.193 360.817 - 1,187.120 969.487 - - - - 700.257 -
6.06a(ii) RCC M30 5m - 10m height Cum 287.175 0.2850 0.1958 0.6442 0.5261 0.3800 81.845 56.229 - 184.998 151.083 - - - - 109.127 -
6.07(a) RCC M30 Super structure Cum 1,557.698 0.2850 0.1958 0.6442 0.5261 0.3800 443.944 304.997 - 1,003.469 819.505 - - - - 591.925 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.704
6.15(b) TMT for Substructure MT 281.610 1.0000 - - - - - - - - - - 281.610
6.15© TMT for Superstructure MT 142.510 1.0000 - - - - - - - - - - 142.510
8.05© Lined surface Toe drains Lm 200.000 0.1103 0.0757 0.2191 0.1790 0.0888 22.056 15.141 - 43.829 35.802 - - - - 17.766 -
8.06(a) M-20 Median Kerb "A" Lm 4,003.115 0.0226 0.0241 0.0607 0.0198 90.470 96.475 - - 242.979 - - - - 79.422 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.08(b) filter material behind retaining wall Cum 224.100 0.6810 0.9080 0.6810 - - - 152.612 203.483 152.612 - - - - -
8.08© PCC M15 grade Cum 235.296 0.3352 0.2301 0.6661 0.5441 0.2700 78.871 54.142 - 156.731 128.025 - - - - 63.530 -
8.08(d) RCC M30 for foundation Cum 149.766 0.2850 0.1958 0.6442 0.5261 0.3800 42.683 29.324 - 96.479 78.792 - - - - 56.911 -
8.08(e) RCC M30 for Substructure Cum 152.792 0.2850 0.1958 0.6442 0.5261 0.3800 43.546 29.917 - 98.429 80.384 - - - - 58.061 -
8.08(f) TMT For foundation & substruc. Cum 129.347 1.0000 - - - - - - - - - - 129.347
9.17(a) NP2 600mm Dia Pipe Lm 271.030 - - - - - - - - - - - 271.0
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,082,488.9 4,339.713 6,574.208 28,242.94 38,138.36 29,726.91 46,562.27 103,383.346 2,451.596 187.662 3,545.263 1,409.193 271.00 354.908
###
Upto Previous Bill Quantity 2,049,362.6 3,985.236 6,324.499 28,242.94 33,399.13 27,193.44 43,117.94 99,187.022 2,026.815 160.261 3,014.009 1,288.87 271.00 324.300
Balance Quantities 33,126.30 354.477 249.709 - 4,739.228 2,533.468 3,444.334 4,196.324 424.781 27.401 531.254 120.319 - 12.000
###
354.5 249.7 in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag R
C
C
MATERIAL CONSUMPTION STATEMENT
P
Interim Payment Certificate No. 12 For the Month of July 2010 i
Factor Material Consumption p
e
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel 6
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) 0
(Cu.m) (m) (m)
0

Consumed from Medak District m


3.01 Granular Sub-base Cum 22,222.048 2.230 - - - - - - 49,555 - - - - m
3.02 Wet mix macadam Cum 23,512.866 0.729 0.354 0.398 0.729 - - 17,147.933 8,314.149 9,353.418 17,147.933 - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - - (
5.05 PCC M 15 for leveling course Cum 502.222 0.4806 0.6693 0.6693 0.2700 241.368 - - 336.137 336.137 - - - - 135.600 - m
5.06(a) PCC Grade M 20 Cum 307.915 0.4754 0.6560 0.6540 0.2800 146.383 - - 201.992 201.376 - - - - 86.216 - )
5.07(a) RCC M 25 foundations & Substructu Cum 1,660.124 0.4524 0.6244 0.6225 0.3500 751.040 - - 1,036.498 1,033.344 - - - - 581.043 -
5.08(a) RCC M 25 superstructure Cum 298.015 0.4524 0.6244 0.6225 0.3500 134.822 - - 186.066 185.499 - - - - 104.305 -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,474.697 0.4452 0.6145 0.6126 0.3800 1,101.735 - - 1,520.578 1,515.999 - - - - 940.385 -
6.06a(ii) RCC M30 5m - 10m height Cum 554.601 0.4452 0.6145 0.6126 0.3800 246.908 - - 340.775 339.749 - - - - 210.748 -
6.07(a) RCC M30 Super structure Cum 577.651 0.4452 0.6145 0.6126 0.3800 257.170 - - 354.938 353.869 - - - - 219.507 -
8.05© Lined surface Toe drains Lm - 0.1581 0.2182 0.2175 0.0888 - - - - - - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 6,976.000 0.0226 0.0245 0.0672 0.0198 157.658 170.912 - - 468.743 - - - - 138.404 -
8.06(b) M-20 Median Kerb "L" Lm - 0.0385 0.0417 0.1144 0.0338 - - - - - - - - - - -
8.08© PCC M15 grade Cum 328.569 0.4806 0.6631 0.6611 0.2700 157.910 - - 217.874 217.217 - - - - 88.714 -
8.08(d) RCC M30 for foundation Cum 1,138.361 0.4452 0.6145 0.6126 0.3800 506.798 - - 699.466 697.360 - - - - 432.577 -
8.08(e) RCC M30 for Substructure Cum 555.455 0.4452 0.6145 0.6126 0.3800 247.289 - - 341.299 340.272 - - - - 211.073 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -
- - - - - - - - -
Total Cumulative Quantity - 6,748.874 194.24 17,147.93 17,384.11 18,929.76 17,147.93 49,555.17 - - 5,432.53 - - ###
-
Upto Previous Bill Quantity - 6,495.906 184.68 13,809.70 15,428.61 16,746.76 13,809.70 43,382.32 - - 5,218.993 - - -
Balance Quantities - 252.968 9.555 3,338.231 1,955.500 2,183.004 3,338.231 6,172.845 - - 213.535 - - ###
-
- - 213.5 - in No.s in No.s
Balance Quantity in This Month 33,126.30 607.445 259.264 31,901.165 424.781 27.401 744.789 120.319 - 12.000
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No. 13 For the Month of August 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,542,006.051 1,542,006 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 124,151.453 124,151 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 2,732.670 2,733 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 932 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 3,198.730 3,199 - - - - - - - - - - -
3.01 Granular Sub-base Cum 51,455.653 2.2300 - - - - - - 114,746 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 230,961.540 0.001 - - - - - - - - 173.221 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.000 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 19,299.395 0.9708 0.4275 0.8338 0.107 0.0229 - - - 18,735.505 8,250.916 16,091.565 - 2,065.008 - 442.176 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 81.989 0.6810 0.9080 0.6810 - - - 55.835 74.446 55.835 - - - - -
5.05 PCC M 15 for leveling course Cum 216.151 0.3352 0.2301 0.6661 0.5441 0.2700 72.454 49.736 - 143.978 117.608 - - - - 58.361 -
5.06(a) PCC Grade M 20 Cum 531.876 0.3315 0.2277 0.6594 0.5384 0.2800 176.317 121.108 - 350.719 286.362 - - - - 148.925 -
5.07(a) RCC M 25 foundations & Substructu Cum 904.736 0.2980 0.2046 0.6448 0.5265 0.3500 269.611 185.109 - 583.374 476.344 - - - - 316.658 -
5.08(a) RCC M 25 superstructure Cum 253.186 0.2980 0.2046 0.6448 0.5265 0.3500 75.449 51.802 - 163.254 133.302 - - - - 88.615 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.678
5.09(b) TMT for Substructure MT 136.353 1.0000 - - - - - - - - - - 136.353
5.09(c) TMT for Superstructure MT 58.976 1.0000 - - - - - - - - - - 58.976
5.10 H.P NP-4, 1200 mm Dia Lm 395.576 - - - - - - - - - - - 395.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,197.760 0.2850 0.1958 0.6442 0.5261 0.3800 626.362 430.321 - 1,415.797 1,156.242 - - - - 835.149 -
6.06a(ii) RCC M30 5m - 10m height Cum 372.891 0.2850 0.1958 0.6442 0.5261 0.3800 106.274 73.012 - 240.216 196.178 - - - - 141.699 -
6.07(a) RCC M30 Super structure Cum 1,939.451 0.2850 0.1958 0.6442 0.5261 0.3800 552.744 379.745 - 1,249.394 1,020.345 - - - - 736.991 -
6.07(b) RCC M35 Super structure Cum 197.146 0.4389 0.5450 0.6640 0.4000 86.522 - - 107.445 130.905 - - - - 78.858 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.704
6.15(b) TMT for Substructure MT 322.393 1.0000 - - - - - - - - - - 322.393
6.15© TMT for Superstructure MT 219.712 1.0000 - - - - - - - - - - 219.712
8.05© Lined surface Toe drains Lm 560.000 0.1103 0.0757 0.2191 0.1790 0.0888 61.757 42.394 - 122.722 100.245 - - - - 49.745 -
8.06(a) M-20 Median Kerb "A" Lm 4,543.115 0.0226 0.0241 0.0607 0.0198 102.674 109.489 - - 275.756 - - - - 90.135 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.08(b) filter material behind retaining wall Cum 224.100 0.6810 0.9080 0.6810 - - - 152.612 203.483 152.612 - - - - -
8.08© PCC M15 grade Cum 284.360 0.3352 0.2301 0.6661 0.5441 0.2700 95.317 65.431 - 189.412 154.720 - - - - 76.777 -
8.08(d) RCC M30 for foundation Cum 185.432 0.2850 0.1958 0.6442 0.5261 0.3800 52.848 36.308 - 119.455 97.556 - - - - 70.464 -
8.08(e) RCC M30 for Substructure Cum 178.980 0.2850 0.1958 0.6442 0.5261 0.3800 51.009 35.044 - 115.299 94.161 - - - - 68.012 -
8.08(f) TMT For foundation & substruc. Cum 133.396 1.0000 - - - - - - - - - - 133.396
9.17(a) NP2 600mm Dia Pipe Lm 299.504 - - - - - - - - - - - 299.5
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 1,010.000 8,080
9.18(b) Dia 110mm (Main Carriageway) Rm - -
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,107,535.05 4,793.777 6,823.540 28,242.94 40,880.90 31,336.12 48,174.86 114,746.106 2,658.538 200.789 4,100.073 1,552.212 300.00 395.576 8,080
Upto Previous Bill Quantity 2,082,488.94 4,339.713 6,574.208 28,242.94 38,138.36 29,726.91 46,562.27 103,383.346 2,451.596 187.662 3,545.263 1,409.19 271.00 354.908
Balance Quantities 25,046.11 454.064 249.332 - 2,742.541 1,609.212 1,612.588 11,362.760 206.942 13.127 554.810 143.019 12.000 17.000 8,080
454.1 249.3 in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No. 13 For the Month of August 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)

Consumed from Medak District


3.01 Granular Sub-base Cum 22,964.848 2.230 - - - - - - 51,212 - - - -
3.02 Wet mix macadam Cum 27,516.747 0.729 0.354 0.398 0.729 - - 20,067.964 9,729.922 10,946.132 20,067.964 - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 502.222 0.4806 0.6693 0.6693 0.2700 241.368 - - 336.137 336.137 - - - - 135.600 -
5.06(a) PCC Grade M 20 Cum 312.696 0.4754 0.6560 0.6540 0.2800 148.656 - - 205.129 204.503 - - - - 87.555 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,726.249 0.4524 0.6244 0.6225 0.3500 780.955 - - 1,077.784 1,074.504 - - - - 604.187 -
5.08(a) RCC M 25 superstructure Cum 374.448 0.4524 0.6244 0.6225 0.3500 169.400 - - 233.787 233.075 - - - - 131.057 -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,623.015 0.4452 0.6145 0.6126 0.3800 1,167.766 - - 1,611.712 1,606.859 - - - - 996.746 -
6.06a(ii) RCC M30 5m - 10m height Cum 601.538 0.4452 0.6145 0.6126 0.3800 267.805 - - 369.615 368.502 - - - - 228.584 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
6.07(b) RCC M35 Super structure Cum - - - - - - - - - - - -
8.06(a) M-20 Median Kerb "A" Lm 7,161.000 0.0226 0.0245 0.0672 0.0198 161.839 175.445 - - 481.173 - - - - 142.074 -
8.06(b) M-20 Median Kerb "L" Lm - 0.0385 0.0417 0.1144 0.0338 - - - - - - - - - - -
8.08© PCC M15 grade Cum 328.569 0.4806 0.6631 0.6611 0.2700 157.910 - - 217.874 217.217 - - - - 88.714 -
8.08(d) RCC M30 for foundation Cum 1,138.361 0.4452 0.6145 0.6126 0.3800 506.798 - - 699.466 697.360 - - - - 432.577 -
8.08(e) RCC M30 for Substructure Cum 556.827 0.4452 0.6145 0.6126 0.3800 247.899 - - 342.142 341.112 - - - - 211.594 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -
- - - - - - - - -
Total Cumulative Quantity - 7,073.780 198.77 20,067.96 19,242.53 20,976.22 20,067.96 51,211.61 - - 5,704.20 - - - -
Upto Previous Bill Quantity - 6,748.874 194.24 17,147.93 17,384.11 18,929.76 17,147.93 49,555.17 - - 5,432.528 - - -
Balance Quantities - 324.906 4.533 2,920.031 1,858.419 2,046.456 2,920.029 1,656.444 - - 271.671 - - - -
- - 271.7 - in No.s in No.s
Balance Quantity in This Month 25,046.1 778.970 253.865 28,728.480 206.942 13.127 826.481 143.019 12.000 17.000 8,080
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:14 For the Month of September 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,544,472.526 1,544,473 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 132,147.298 132,147 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 6,938.270 6,938 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 932 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 4,493.823 4,494 - - - - - - - - - - -
3.01 Granular Sub-base Cum 54,824.253 2.2300 - - - - - - 122,258 - - - -
3.02 Wet mix macadam Cum 35,426.597 0.7293 0.3536 0.3978 0.7293 - - 25,836.617 12,526.845 14,092.700 25,836.617 - - - - -
4.01 Prime Coat Sqm 234,429.040 0.001 - - - - - - - - 175.822 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.000 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 19,512.920 0.9708 0.4275 0.8338 0.107 0.0229 - - - 18,942.791 8,342.202 16,269.599 - 2,087.855 - 447.068 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 81.989 0.6810 0.9080 0.6810 - - - 55.835 74.446 55.835 - - - - -
5.05 PCC M 15 for leveling course Cum 216.151 0.3352 0.2301 0.6661 0.5441 0.2700 72.454 49.736 - 143.978 117.608 - - - - 58.361 -
5.06(a) PCC Grade M 20 Cum 531.876 0.3315 0.2277 0.6594 0.5384 0.2800 176.317 121.108 - 350.719 286.362 - - - - 148.925 -
5.07(a) RCC M 25 foundations & Substructu Cum 904.736 0.2980 0.2046 0.6448 0.5265 0.3500 269.611 185.109 - 583.374 476.344 - - - - 316.658 -
5.08(a) RCC M 25 superstructure Cum 253.186 0.2980 0.2046 0.6448 0.5265 0.3500 75.449 51.802 - 163.254 133.302 - - - - 88.615 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.678
5.09(b) TMT for Substructure MT 153.569 1.0000 - - - - - - - - - - 153.569
5.09(c) TMT for Superstructure MT 61.143 1.0000 - - - - - - - - - - 61.143
5.10 H.P NP-4, 1200 mm Dia Lm 395.576 - - - - - - - - - - - 395.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,197.760 0.2850 0.1958 0.6442 0.5261 0.3800 626.362 430.321 - 1,415.797 1,156.242 - - - - 835.149 -
6.06a(ii) RCC M30 5m - 10m height Cum 372.891 0.2850 0.1958 0.6442 0.5261 0.3800 106.274 73.012 - 240.216 196.178 - - - - 141.699 -
6.07(a) RCC M30 Super structure Cum 1,939.451 0.2850 0.1958 0.6442 0.5261 0.3800 552.744 379.745 - 1,249.394 1,020.345 - - - - 736.991 -
6.07(b) RCC M35 Super structure Cum 985.944 0.4389 0.5450 0.6640 0.4000 432.703 - - 537.339 654.667 - - - - 394.378 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.704
6.15(b) TMT for Substructure MT 342.763 1.0000 - - - - - - - - - - 342.763
6.15© TMT for Superstructure MT 292.659 1.0000 - - - - - - - - - - 292.659
8.05© Lined surface Toe drains Lm 560.000 0.1103 0.0757 0.2191 0.1790 0.0888 61.757 42.394 - 122.722 100.245 - - - - 49.745 -
8.06(a) M-20 Median Kerb "A" Lm 4,543.115 0.0226 0.0241 0.0607 0.0198 102.674 109.489 - - 275.756 - - - - 90.135 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.08(b) filter material behind retaining wall Cum 224.100 0.6810 0.9080 0.6810 - - - 152.612 203.483 152.612 - - - - -
8.08© PCC M15 grade Cum 284.360 0.3352 0.2301 0.6661 0.5441 0.2700 95.317 65.431 - 189.412 154.720 - - - - 76.777 -
8.08(d) RCC M30 for foundation Cum 185.432 0.2850 0.1958 0.6442 0.5261 0.3800 52.848 36.308 - 119.455 97.556 - - - - 70.464 -
8.08(e) RCC M30 for Substructure Cum 178.980 0.2850 0.1958 0.6442 0.5261 0.3800 51.009 35.044 - 115.299 94.161 - - - - 68.012 -
8.08(f) TMT For foundation & substruc. Cum 137.461 1.0000 - - - - - - - - - - 137.461
9.17(a) NP2 600mm Dia Pipe Lm 299.504 - - - - - - - - - - - 299.5
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 2,750.000 22,000
9.18(b) Dia 110mm (Main Carriageway) Rm 1,770.000 1,770
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,123,498.06 5,139.957 6,823.540 28,242.94 41,518.08 31,951.17 48,352.90 122,258.084 2,681.384 203.390 4,420.484 1,668.977 300.00 395.576 23,770
Upto Previous Bill Quantity 2,107,535.05 4,793.777 6,823.540 28,242.94 40,880.90 31,336.12 48,174.86 114,746.106 2,658.538 200.789 4,100.073 1,552.21 300.00 395.576 8,080
Balance Quantities 15,963.01 346.180 - 0.001 637.181 615.048 178.035 7,511.978 22.846 2.601 320.411 116.765 - - 23,770
346.2 - in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:14 For the Month of September 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)

Consumed from Medak District


3.01 Granular Sub-base Cum 22,964.848 2.230 - - - - - - 51,212 - - - -
3.02 Wet mix macadam Cum 31,590.918 0.729 0.354 0.398 0.729 - - 23,039.256 11,170.549 12,566.867 23,039.256 - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 594.108 0.4452 0.6145 0.6126 0.3800 264.497 - - 365.050 363.951 - - - - 225.761 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -
- - - - - - - - -
Total Cumulative Quantity - 7,531.365 203.30 23,039.26 21,308.87 23,233.21 23,039.26 51,211.61 - - 6,038.9150 - - - -
Upto Previous Bill Quantity - 7,073.780 198.77 20,067.96 19,242.53 20,976.22 20,067.96 51,211.61 - - 5,704.1990 - - - -
Balance Quantities - 457.585 4.532 2,971.292 2,066.335 2,256.989 2,971.293 - - - 334.7160 - - - -
- - 334.7 - in No.s in No.s
Balance Quantity in This Month 15,963.0 803.765 4.532 19,208.152 22.846 2.601 655.127 116.765 - - 23,770
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:15 For the Month of October 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,593,414.531 1,593,415 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 150,354.128 150,354 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 15,198.430 15,198 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 932 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 8,978.683 8,979 - - - - - - - - - - -
3.01 Granular Sub-base Cum 63,282.777 2.2300 - - - - - - 141,121 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 277,048.540 0.001 - - - - - - - - 207.786 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.000 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 23,248.977 0.9708 0.4275 0.8338 0.107 0.0229 - - - 22,569.688 9,939.449 19,384.671 - 2,487.608 - 532.667 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 81.989 0.6810 0.9080 0.6810 - - - 55.835 74.446 55.835 - - - - -
5.05 PCC M 15 for leveling course Cum 218.299 0.3352 0.2301 0.6661 0.5441 0.2700 73.174 50.231 - 145.409 118.776 - - - - 58.941 -
5.06(a) PCC Grade M 20 Cum 539.394 0.3315 0.2277 0.6594 0.5384 0.2800 178.809 122.820 - 355.676 290.410 - - - - 151.030 -
5.07(a) RCC M 25 foundations & Substructu Cum 951.562 0.2980 0.2046 0.6448 0.5265 0.3500 283.565 194.690 - 613.567 500.997 - - - - 333.047 -
5.08(a) RCC M 25 superstructure Cum 333.726 0.2980 0.2046 0.6448 0.5265 0.3500 99.450 68.280 - 215.187 175.707 - - - - 116.804 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.678
5.09(b) TMT for Substructure MT 158.936 1.0000 - - - - - - - - - - 158.936
5.09(c) TMT for Superstructure MT 69.369 1.0000 - - - - - - - - - - 69.369
5.10 H.P NP-4, 1200 mm Dia Lm 395.576 - - - - - - - - - - - 395.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,409.165 0.2850 0.1958 0.6442 0.5261 0.3800 686.612 471.715 - 1,551.984 1,267.462 - - - - 915.483 -
6.06a(ii) RCC M30 5m - 10m height Cum 457.817 0.2850 0.1958 0.6442 0.5261 0.3800 130.478 89.641 - 294.926 240.858 - - - - 173.970 -
6.07(a) RCC M30 Super structure Cum 2,458.648 0.2850 0.1958 0.6442 0.5261 0.3800 700.715 481.403 - 1,583.861 1,293.495 - - - - 934.286 -
6.07(b) RCC M35 Super structure Cum 1,188.198 0.4389 0.5450 0.6640 0.4000 521.466 - - 647.568 788.963 - - - - 475.279 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.704
6.15(b) TMT for Substructure MT 364.464 1.0000 - - - - - - - - - - 364.464
6.15© TMT for Superstructure MT 368.459 1.0000 - - - - - - - - - - 368.459
8.05© Lined surface Toe drains Lm 1,450.000 0.1103 0.0757 0.2191 0.1790 0.0888 159.907 109.769 - 317.763 259.563 - - - - 128.804 -
8.06(a) M-20 Median Kerb "A" Lm 6,098.115 0.0226 0.0241 0.0607 0.0198 137.817 146.965 - - 370.141 - - - - 120.987 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.08(b) filter material behind retaining wall Cum 224.100 0.6810 0.9080 0.6810 - - - 152.612 203.483 152.612 - - - - -
8.08© PCC M15 grade Cum 354.270 0.3352 0.2301 0.6661 0.5441 0.2700 118.751 81.518 - 235.979 192.758 - - - - 95.653 -
8.08(d) RCC M30 for foundation Cum 445.998 0.2850 0.1958 0.6442 0.5261 0.3800 127.109 87.326 - 287.312 234.640 - - - - 169.479 -
8.08(e) RCC M30 for Substructure Cum 217.832 0.2850 0.1958 0.6442 0.5261 0.3800 62.082 42.652 - 140.327 114.601 - - - - 82.776 -
8.08(f) TMT For foundation & substruc. Cum 157.155 1.0000 - - - - - - - - - - 157.155
9.15(a) W-Beam Crash Barrier Lm 4,873.000 0.0275 0.0380 0.0379 0.0162 133.963 - - 185.408 184.843 - - - - 79.138 -
9.17(a) NP2 600mm Dia Pipe Lm 299.504 - - - - - - - - - - - 299.5
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 4,085.000 32,680
9.18(b) Dia 110mm (Main Carriageway) Rm 5,640.000 5,640
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,203,391.92 5,878.338 7,191.049 28,242.94 46,488.98 34,818.14 51,467.97 141,120.593 3,081.137 235.354 5,265.850 1,799.765 300.00 395.576 38,320
Upto Previous Bill Quantity 2,123,498.06 5,139.957 6,823.540 28,242.94 41,518.08 31,951.17 48,352.89 122,258.084 2,681.384 203.390 4,420.484 1,668.98 300.00 395.576 23,770
Balance Quantities 79,893.86 738.381 367.509 - 4,970.903 2,866.974 3,115.072 18,862.509 399.753 31.964 845.366 130.790 - - 14,550
738.4 367.5 in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:15 For the Month of October 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)

Consumed from Medak District


3.01 Granular Sub-base Cum 23,823.588 2.230 - - - - - - 53,127 - - - -
3.02 Wet mix macadam Cum 39,227.705 0.729 0.354 0.398 0.729 - - 28,608.765 13,870.916 15,604.781 28,608.765 - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 603.621 0.4452 0.6145 0.6126 0.3800 268.732 - - 370.895 369.778 - - - - 229.376 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -
- - - - - - - - -
Total Cumulative Quantity - 7,535.600 203.30 28,608.77 24,015.08 26,276.95 28,608.77 53,126.60 - - 6,042.5300 - - - -
Upto Previous Bill Quantity - 7,531.365 203.30 23,039.26 21,308.87 23,233.21 23,039.26 51,211.61 - - 6,038.9150 - - - -
Balance Quantities - 4.235 - 5,569.509 2,706.214 3,043.742 5,569.509 1,914.990 - - 3.6150 - - - -
- - 3.6 - in No.s in No.s
Balance Quantity in This Month 79,893.9 742.616 367.509 48,619.422 399.753 31.964 848.981 130.790 - - 14,550
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:16 For the Month of November 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,678,366.896 1,678,367 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 179,359.251 179,359 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 19,190.000 19,190 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 932 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 14,014.423 14,014 - - - - - - - - - - -
3.01 Granular Sub-base Cum 63,282.777 2.2300 - - - - - - 141,121 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 328,037.816 0.001 - - - - - - - - 246.028 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.000 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 20,440.000 0.000 - - - - - - - - 4.599 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 29,331.589 0.9708 0.4275 0.8338 0.107 0.0229 - - - 28,474.578 12,539.899 24,456.268 - 3,138.439 - 672.028 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 182.933 0.6810 0.9080 0.6810 - - - 124.577 166.103 124.577 - - - - -
5.05 PCC M 15 for leveling course Cum 218.299 0.3352 0.2301 0.6661 0.5441 0.2700 73.174 50.231 - 145.409 118.776 - - - - 58.941 -
5.06(a) PCC Grade M 20 Cum 539.394 0.3315 0.2277 0.6594 0.5384 0.2800 178.809 122.820 - 355.676 290.410 - - - - 151.030 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,023.963 0.2980 0.2046 0.6448 0.5265 0.3500 305.141 209.503 - 660.251 539.117 - - - - 358.387 -
5.08(a) RCC M 25 superstructure Cum 400.275 0.2980 0.2046 0.6448 0.5265 0.3500 119.282 81.896 - 258.097 210.745 - - - - 140.096 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.68
5.09(b) TMT for Substructure MT 166.728 1.0000 - - - - - - - - - - 166.73
5.09(c) TMT for Superstructure MT 75.531 1.0000 - - - - - - - - - - 75.53
5.10 H.P NP-4, 1200 mm Dia Lm 395.576 - - - - - - - - - - - 395.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,819.149 0.2850 0.1958 0.6442 0.5261 0.3800 803.457 551.989 - 1,816.096 1,483.154 - - - - 1,071.277 -
6.06a(ii) RCC M30 5m - 10m height Cum 637.401 0.2850 0.1958 0.6442 0.5261 0.3800 181.659 124.803 - 410.614 335.337 - - - - 242.212 -

6.07(a) RCC M30 Super structure Cum 3,663.285 0.2850 0.1958 0.6442 0.5261 0.3800 1,044.036 717.271 - 2,359.888 1,927.254 - - - - 1,392.048 -
6.07(b) RCC M35 Super structure Cum 1,631.538 0.4389 0.5450 0.6640 0.4000 716.035 - - 889.188 1,083.341 - - - - 652.615 -
6.08 M15 for Approach slab Cum 68.745 0.3352 0.2301 0.6661 0.5441 0.2700 23.043 15.818 - 45.791 37.404 - - - - 18.561 -
6.09 M30 for Approach slab Cum 222.744 0.2850 0.1958 0.6442 0.5261 0.3800 63.482 43.613 - 143.492 117.186 - - - - 84.643 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.70
6.15(b) TMT for Substructure MT 415.183 1.0000 - - - - - - - - - - 415.18
6.15© TMT for Superstructure MT 529.530 1.0000 - - - - - - - - - - 529.53
8.05© Lined surface Toe drains Lm 2,555.000 0.1103 0.0757 0.2191 0.1790 0.0888 281.767 193.421 - 559.920 457.368 - - - - 226.961 -
8.06(a) M-20 Median Kerb "A" Lm 8,113.115 0.0226 0.0241 0.0607 0.0198 183.356 195.526 - - 492.447 - - - - 160.964 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.08(b) filter material behind retaining wall Cum 355.050 0.6810 0.9080 0.6810 - - - 241.789 322.385 241.789 - - - - -
8.08© PCC M15 grade Cum 535.516 0.3352 0.2301 0.6661 0.5441 0.2700 179.505 123.222 - 356.707 291.374 - - - - 144.589 -
8.08(d) RCC M30 for foundation Cum 825.403 0.2850 0.1958 0.6442 0.5261 0.3800 235.240 161.614 - 531.725 434.245 - - - - 313.653 -
8.08(e) RCC M30 for Substructure Cum 448.131 0.2850 0.1958 0.6442 0.5261 0.3800 127.717 87.744 - 288.686 235.762 - - - - 170.290 -
8.08(f) TMT For foundation & substruc. Cum 184.541 1.0000 - - - - - - - - - - 184.54
9.15(a) W-Beam Crash Barrier Lm 7,979.000 0.0275 0.0380 0.0379 0.0162 219.350 - - 303.585 302.659 - - - - 129.579 -
9.17(a) NP2 600mm Dia Pipe Lm 299.504 - - - - - - - - - - - 299.5
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 5,159.000 41,272
9.18(b) Dia 110mm (Main Carriageway) Rm 9,240.000 9,240
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,326,376.72 7,199.493 7,923.513 28,242.94 55,101.95 39,952.52 56,697.48 141,120.593 3,731.968 273.596 6,885.381 2,052.90 300.00 395.576 50,512
Upto Previous Bill Quantity 2,203,391.92 5,878.338 7,191.049 28,242.94 46,488.98 34,818.14 51,467.97 141,120.593 3,081.137 235.354 5,265.850 1,799.77 300.00 395.576 38,320
Balance Quantities 122,984.80 1,321.155 732.464 - 8,612.969 5,134.375 5,229.517 - 650.831 38.242 1,619.531 253.13 - - 12,192
1,321.2 732.5 in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment Certificate No:16 For the Month of November 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)

Consumed from Medak District


3.01 Granular Sub-base Cum 36,594.220 2.230 - - - - - - 81,605 - - - -
3.02 Wet mix macadam Cum 51,744.349 0.729 0.354 0.398 0.729 - - 37,737.154 18,296.802 20,583.902 37,737.154 - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
6.07(b) RCC M35 Super structure Cum - - - - - - - - - - - -
6.08 M15 for Approach slab Cum - 0.4806 0.6631 0.6611 0.2700 - - - - - - - - - - -
6.09 M30 for Approach slab Cum - 0.4450 0.6145 0.6126 0.3800 - - - - - - - - - - -
8.02(a) Granular filter material underneath Cum - - - - - - - - - - - -
8.05(a) Covered drain with 100 mm M25 RC Lm - - - - - - - - - - - -
8.05(b) Median Transverse chutes with M15 Lm - - - - - - - - - - - -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 603.621 0.4452 0.6145 0.6126 0.3800 268.732 - - 370.895 369.778 - - - - 229.376 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -
- - - - - - - - -
Total Cumulative Quantity - 7,535.600 203.30 37,737.15 28,440.96 31,256.07 37,737.15 81,605.11 - - 6,042.5300 - - - -
Upto Previous Bill Quantity - 7,535.600 203.30 28,608.77 24,015.08 26,276.95 28,608.77 53,126.60 - - 6,042.5300 - - - -
Balance Quantities - - - 9,128.389 4,425.887 4,979.122 9,128.389 28,478.510 - - - - - - -
- - - - in No.s in No.s
Balance Quantity in This Month 122,984.8 1,321.155 732.464 75,117.158 650.831 38.242 1,619.531 253.130 - - 12,192
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment certificate -17 For the Month of December 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,722,374.435 1,722,374.44 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 203,841.191 203,841.19 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 22,455.480 22,455.48 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614.07 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949.04 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573.45 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 931.95 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 16,469.563 16,469.56 - - - - - - - - - - -
3.01 Granular Sub-base Cum 63,282.777 2.2300 - - - - - - 141,121 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 360,355.497 0.001 - - - - - - - - 270.267 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.000 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 26,645.000 0.000 - - - - - - - - 5.995 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.110 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.109 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 33,143.661 0.9708 0.4275 0.8338 0.107 0.0229 - - - 32,175.269 14,169.644 27,634.720 - 3,546.325 - 759.368 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 182.933 0.6810 0.9080 0.6810 - - - 124.577 166.103 124.577 - - - - -
5.05 PCC M 15 for leveling course Cum 222.477 0.3352 0.2301 0.6661 0.5441 0.2700 74.574 51.192 - 148.192 121.050 - - - - 60.069 -
5.06(a) PCC Grade M 20 Cum 628.516 0.3315 0.2277 0.6594 0.5384 0.2800 208.353 143.113 - 414.443 338.393 - - - - 175.984 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,108.265 0.2980 0.2046 0.6448 0.5265 0.3500 330.263 226.751 - 714.609 583.502 - - - - 387.893 -
5.08(a) RCC M 25 superstructure Cum 596.337 0.2980 0.2046 0.6448 0.5265 0.3500 177.708 122.011 - 384.518 313.971 - - - - 208.718 -
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,256.456 0.6810 0.9080 0.6810 - - - 855.647 1,140.862 855.647 - - - - -
6.05(a) PCC M15 for foundation Cum 241.397 0.3352 0.2301 0.6661 0.5441 0.2700 80.916 55.545 - 160.795 131.344 - - - - 65.177 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,878.840 0.2850 0.1958 0.6442 0.5261 0.3800 820.469 563.677 - 1,854.549 1,514.558 - - - - 1,093.959 -
6.06a(ii) RCC M30 5m - 10m height Cum 668.233 0.2850 0.1958 0.6442 0.5261 0.3800 190.446 130.840 - 430.476 351.557 - - - - 253.929 -
6.07(a) RCC M30 Super structure Cum 4,148.012 0.2850 0.1958 0.6442 0.5261 0.3800 1,182.183 812.181 - 2,672.149 2,182.269 - - - - 1,576.245 -
6.07(b) RCC M35 Super structure Cum - 0.4389 0.5450 0.6640 0.4000 - - - - - - - - - - -
6.08 M15 for Approach slab Cum 68.745 0.3352 0.2301 0.6661 0.5441 0.2700 23.043 15.818 - 45.791 37.404 - - - - 18.561 -
6.09 M30 for Approach slab Cum 222.744 0.2850 0.1958 0.6442 0.5261 0.3800 63.482 43.613 - 143.492 117.186 - - - - 84.643 -
8.05(b) Median Transverse chutes with M15 Lm - - - - - - - - - - - -
8.05© Lined surface Toe drains Lm 3,605.000 0.1103 0.0757 0.2191 0.1790 0.0888 397.562 272.909 - 790.025 645.327 - - - - 320.232 -
8.06(a) M-20 Median Kerb "A" Lm 8,983.115 0.0226 0.0241 0.0607 0.0198 203.018 216.493 - - 545.254 - - - - 178.225 -
8.06(b) M-20 Median Kerb "L" Lm 146.885 0.0385 0.0411 0.1034 0.0338 5.655 6.037 - - 15.188 - - - - 4.965 -
8.07 Water chutes PCC M15 Lm - - - - - - - - - - - -
8.08(b) filter material behind retaining wall Cum 391.500 0.6810 0.9080 0.6810 - - - 266.612 355.482 266.612 - - - - -
8.08© PCC M15 grade Cum 652.141 0.3352 0.2301 0.6661 0.5441 0.2700 218.598 150.058 - 434.391 354.830 - - - - 176.078 -
8.08(d) RCC M30 for foundation Cum 1,020.680 0.2850 0.1958 0.6442 0.5261 0.3800 290.894 199.849 - 657.522 536.980 - - - - 387.858 -
8.08(e) RCC M30 for Substructure Cum 739.472 0.2850 0.1958 0.6442 0.5261 0.3800 210.750 144.789 - 476.368 389.036 - - - - 280.999 -
8.08(f) TMT For foundation & substruc. Cum 222.396 1.0000 - - - - - - - - - - 222.40
8.09 Water harvesting unit Nr - - - - - - - - - - - -
8.10(a) Facia panals sloped surcharge Sqm 66.209 0.4389 0.5450 0.6640 0.4000 29.057 - - 36.084 43.963 - - - - 26.484 -
8.10(b) Facia panals Vertical surcharge Sqm 11.676 0.4389 0.5450 0.6640 0.4000 5.124 - - 6.363 7.753 - - - - 4.670 -
8.11 granular soil behind reinforced eart Cum 300.720 300.720 - - - - - - - - - - -
9.13 Chain link fencing Sqm 30.780 0.4806 0.6631 0.6611 0.2700 14.793 - - 20.410 20.349 - - - - 8.311 -
9.15(a) W-Beam Crash Barrier Lm 10,781.000 0.0275 0.0380 0.0379 0.0162 296.379 - - 410.195 408.945 - - - - 175.083 -
9.17(a) NP2 600mm Dia Pipe Lm 327.984 - - - - - - - - - - - 328.0
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 7,946.000 63,568
9.18(b) Dia 110mm (Main Carriageway) Rm 11,325.000 11,325
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,400,887.53 7,201.14 8,337.34 28,242.94 59,341.92 41,771.10 59,900.76 141,120.59 4,139.86 299.23 7,074.82 2,176.12 327.98 420.58 74,893.00
Upto Previous Bill Quantity 2,326,376.72 7,199.493 7,923.513 28,242.94 55,101.95 39,952.52 56,697.48 141,120.593 3,731.968 273.596 6,885.381 2,052.90 300.00 395.576 50,512
Balance Quantities 74,510.82 1.644 413.822 - 4,239.965 1,818.588 3,203.274 - 407.887 25.635 189.435 123.222 12.000 10.000 24,381.0
1.6 413.8 in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT

Interim Payment certificate -17 For the Month of December 2010


Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Medak District
3.01 Granular Sub-base Cum 45,361.195 2.230 - - - - - - 101,155 - - - -
3.02 Wet mix macadam Cum 60,492.520 0.729 0.354 0.398 0.729 - - 44,117.195 21,390.155 24,063.924 44,117.195 - - - - -
5.02 Sand filling in Foundation Cum - 1.000 - - - - - - - - - - -
5.03 Back filling behind abutments Cum - - - - - - - - - - - - -
5.04 Filter media Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.06(b) PCC Grade M 25 Cum - 0.4520 0.6244 0.6225 0.3500 - - - - - - - - - - -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.02 Granular material Filling in Foundat Cum - 1.5950 - - - - - - - - - - -
6.03 Back filling with granular material Cum - - - - - - - - - - - - -
6.04 Filter media behind abutments Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
6.07(b) RCC M35 Super structure Cum 1,631.538 0.4389 0.5450 0.6640 0.4000 716.035 - - 889.188 1,083.341 - - - - 652.615 -
8.05(b) Median Transverse chutes with M15 Lm - - - - - - - - - - - -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.06(b) M-20 Median Kerb "L" Lm - 0.0385 0.0417 0.1144 0.0338 - - - - - - - - - - -
8.07 Water chutes PCC M15 Lm - - - - - - - - - - - -
8.08(b) filter material behind retaining wall Cum - 0.6810 0.9080 0.6810 - - - - - - - - - - - -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 603.621 0.4452 0.6145 0.6126 0.3800 268.732 - - 370.895 369.778 - - - - 229.376 -
9.17(a) NP2 600mm Dia Pipe Lm - - - - - - - - - - - -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -

- - - - - - - - -
Total Cumulative Quantity - 8,251.636 203.30 44,117.20 32,423.51 35,819.43 44,117.20 101,155.47 - - 6,695.145 - - - -
Upto Previous Bill Quantity - 7,535.600 203.30 37,737.15 28,440.96 31,256.07 37,737.15 81,605.11 - - 6,042.530 - - - -
Balance Quantities - 716.036000 - 6,380.04 3,982.54 4,563.36 6,380.04 19,550.35 - - 652.62 - - - -
- - 652.6 - in No.s in No.s
Balance Quantity in This Month 74,510.8 717.680 413.822 50,118.168 407.887 25.635 842.050 123.222 12.000 10.000 24,381.0
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT


0.058
Interim Payment certificate -18 For the Month of January 2011
Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,772,366.302 1,772,366.30 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 223,166.873 223,166.87 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 22,730.700 22,730.70 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 387,614.067 387,614.07 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949.04 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573.45 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 931.950 931.95 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 16,469.563 16,469.56 - - - - - - - - - - -
3.01 Granular Sub-base Cum 63,282.777 2.2300 - - - - - - 141,121 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 368,357.047 0.0008 - - - - - - - - 276.268 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.0003 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 179,992.650 0.0002 - - - - - - - - 40.498 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.1103 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.1103 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.1086 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 34,402.419 0.9708 0.4275 0.8338 0.1070 0.0229 - - - 33,397.249 14,707.791 28,684.255 - 3,681.011 - 788.208 -
4.06 BC Cum 7,939.178 0.8938 0.4469 0.8490 0.1226 0.0441 - - - 7,095.834 3,547.917 6,740.294 - 973.057 - 349.926 -
4.07 DLC Cum 192.592 0.5382 0.5723 0.6132 0.1703 103.653 - - 110.220 118.097 - - - - 32.798 -
4.08 PQC Cum 266.284 0.4364 0.4290 0.6360 0.4250 116.197 - - 114.236 169.357 - - - - 113.171 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 188.927 0.6810 0.9080 0.6810 - - - 128.659 171.546 128.659 - - - - -
5.05 PCC M 15 for leveling course Cum 282.425 0.3352 0.2301 0.6661 0.5441 0.2700 94.669 64.986 - 188.123 153.667 - - - - 76.255 -
5.06(a) PCC Grade M 20 Cum 655.462 0.3315 0.2277 0.6594 0.5384 0.2800 217.286 149.249 - 432.212 352.901 - - - - 183.529 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,132.405 0.2980 0.2046 0.6448 0.5265 0.3500 337.457 231.690 - 730.175 596.211 - - - - 396.342 -
5.08(a) RCC M 25 superstructure Cum 614.747 0.2980 0.2046 0.6448 0.5265 0.3500 183.195 125.777 - 396.389 323.664 - - - - 215.161 -
5.09(a) TMT for Foundation MT 124.678 1.0000 - - - - - - - - - - 124.68
5.09(b) TMT for Substructure MT 181.003 1.0000 - - - - - - - - - - 181.00
5.09(c) TMT for Superstructure MT 95.807 1.0000 - - - - - - - - - - 95.81
5.10 H.P NP-4, 1200 mm Dia Lm 420.576 - - - - - - - - - - - 420.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,384.220 0.6810 0.9080 0.6810 - - - 942.654 1,256.872 942.654 - - - - -
6.05(a) PCC M15 for foundation Cum 294.025 0.3352 0.2301 0.6661 0.5441 0.2700 98.557 67.655 - 195.850 159.979 - - - - 79.387 -
6.05(b) RCC M30 for foundation Cum 1,843.875 0.2850 0.1958 0.6442 0.5261 0.3800 525.504 361.031 - 1,187.824 970.063 - - - - 700.673 -
6.06a(i) RCC M30 Upto 5m height Cum 2,878.840 0.2850 0.1958 0.6442 0.5261 0.3800 820.469 563.677 - 1,854.549 1,514.558 - - - - 1,093.959 -
6.06a(ii) RCC M30 5m - 10m height Cum 801.703 0.2850 0.1958 0.6442 0.5261 0.3800 228.485 156.973 - 516.457 421.776 - - - - 304.647 -
6.07(a) RCC M30 Super structure Cum 4,148.012 0.2850 0.1958 0.6442 0.5261 0.3800 1,182.183 812.181 - 2,672.149 2,182.269 - - - - 1,576.245 -
6.07(b) RCC M35 Super structure Cum - 0.4389 0.5450 0.6640 0.4000 - - - - - - - - - - -
6.08 M15 for Approach slab Cum 68.745 0.3352 0.2301 0.6661 0.5441 0.2700 23.043 15.818 - 45.791 37.404 - - - - 18.561 -
6.09 M30 for Approach slab Cum 222.744 0.2850 0.1958 0.6442 0.5261 0.3800 63.482 43.613 - 143.492 117.186 - - - - 84.643 -
6.10 Wearing course Sqm 1,341.360 0.0581 0.0290 0.0552 0.0797 0.0029 - - - 77.927 38.963 74.022 - 106.862 - 3.843 -
6.15(a) TMT for Foundation MT 556.704 1.0000 - - - - - - - - - - 556.70
6.15(b) TMT for Substructure MT 432.826 1.0000 - - - - - - - - - - 432.83
6.15© TMT for Superstructure MT 573.654 1.0000 - - - - - - - - - - 573.65
7.01 Footpath Sqm 2,371.738 0.0084 0.0058 0.0167 0.0136 0.3345 0.0068 19.875 13.643 - 39.495 32.262 - 793 - - 16.009
8.05© Lined surface Toe drains Lm 4,484.000 0.1103 0.0757 0.2191 0.1790 0.0888 494.499 339.452 - 982.655 802.676 - - - - 398.314 -
8.06(a) M-20 Median Kerb "A" Lm 9,428.115 0.0226 0.0241 0.0607 0.0198 213.075 227.218 - - 572.264 - - - - 187.054 -
8.06(b) M-20 Median Kerb "L" Lm 296.885 0.0385 0.0411 0.1034 0.0338 11.430 12.202 - - 30.698 - - - - 10.035 -
8.07 Water chutes PCC M15 Lm 546.364 0.0469 0.0322 0.0933 0.0762 0.0378 25.640 17.601 - 50.951 41.619 - - - - 20.653 -
8.08(b) filter material behind retaining wall Cum 692.820 0.6810 0.9080 0.6810 - - - 471.810 629.081 471.810 - - - - -
8.08© PCC M15 grade Cum 710.704 0.3352 0.2301 0.6661 0.5441 0.2700 238.228 163.533 - 473.400 386.694 - - - - 191.890 -
8.08(d) RCC M30 for foundation Cum 1,291.526 0.2850 0.1958 0.6442 0.5261 0.3800 368.085 252.881 - 832.001 679.472 - - - - 490.780 -
8.08(e) RCC M30 for Substructure Cum 908.760 0.2850 0.1958 0.6442 0.5261 0.3800 258.997 177.935 - 585.423 478.099 - - - - 345.329 -
8.08(f) TMT For foundation & substruc. Cum 250.738 1.0000 - - - - - - - - - - 250.74
8.10(a) Facia panals sloped surcharge Sqm 591.987 0.0878 0.1090 0.1328 0.0800 51.961 - - 64.527 78.616 - - - - 47.359 -
8.10(b) Facia panals Vertical surcharge Sqm 245.568 0.0878 0.1090 0.1328 0.0800 21.555 - - 26.767 32.611 - - - - 19.645 -
8.11 granular soil behind reinforced eart Cum 4,126.435 4,126.435 - - - - - - - - - - -
9.13 Chain link fencing Lm 1,225.500 0.0324 0.0452 0.0452 0.0182 39.756 - - 55.365 55.365 - - - - 22.335 -
9.15(a) W-Beam Crash Barrier Lm 11,307.000 0.0276 0.0380 0.0379 0.0162 311.770 - - 430.209 428.897 - - - - 183.626 -
9.17(a) NP2 600mm Dia Pipe Lm 430.664 - - - - - - - - - - - 430.7
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 8,734.000 - - - - - - - - - - 69,872
9.18(b) Dia 110mm (Main Carriageway) Rm 11,845.000 - - - - - - - - - - 11,845
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,474,306.02 7,901.41 8,618.54 28,242.94 69,174.01 47,398.67 68,060.90 141,913.94 5,354.46 339.74 8,077.07 2,215.41 430.66 420.58 81,717.00
Upto Previous Bill Quantity 2,400,887.53 7,201.137 8,337.335 28,242.94 59,341.92 41,771.10 59,900.76 141,120.593 4,139.855 299.231 7,074.816 2,176.12 327.98 420.576 74,893
Balance Quantities 73,418.484 700.276 281.208 - 9,832.091 5,627.563 8,160.139 793.346 1,214.604 40.504 1,002.251 39.293 42.000 - 6,824.000
in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT


0.058
Interim Payment certificate -18 For the Month of January 2011
Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Medak District
3.01 Granular Sub-base Cum 50,580.159 2.2300 - - - - - - 112,794 - - - -
3.02 Wet mix macadam Cum 63,399.664 0.7293 0.3536 0.3978 0.7293 - - 46,237.375 22,418.121 25,220.386 46,237.375 - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
6.07(b) RCC M35 Super structure Cum 1,631.538 0.4389 0.5450 0.6640 0.4000 716.035 - - 889.188 1,083.341 - - - - 652.615 -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 603.621 0.4452 0.6145 0.6126 0.3800 268.732 - - 370.895 369.778 - - - - 229.376 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -

- - - - - - - - -
Total Cumulative Quantity - 8,251.636 203.30 46,237.38 33,451.47 36,975.89 46,237.38 112,793.76 - - 6,695.145 - - - -
Upto Previous Bill Quantity - 8,251.636 203.30 44,117.20 32,423.51 35,819.43 44,117.20 101,155.47 - - 6,695.145 - - - -
Balance Quantities - - - 2,120.180 1,027.966 1,156.462 2,120.180 11,638.290 - - - - - - -
- - - - in No.s in No.s
Balance Quantity in This Month 73,418.5 700.276 281.208 42,757.425 1,214.604 40.504 1,002.251 39.293 42.000 - 6,824.0
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT


0.058
Interim Payment certificate -19 For the Month of February 2011
Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Ranga Reddy District
2.03 Embankment with Borrow Cum 1,820,751.245 1,820,751.25 - - - - - - - - - - -
2.04 Subgrade with approved material Cum 247,589.181 247,589.18 - - - - - - - - - - -
2.05 Shoulder with approved material Cum 23,478.554 23,478.55 - - - - - - - - - - -
2.06(a) Eambankment Reuse Cum 400,316.622 400,316.62 - - - - - - - - - - -
2.06(b) Subgrade Reuse Cum 40,949.043 40,949.04 - - - - - - - - - - -
2.06© Shoulder Reuse Cum 3,573.450 3,573.45 - - - - - - - - - - -
2.06(d) Median filling Reuse Cum 1,245.630 1,245.63 - - - - - - - - - - -
2.09 Filling of median / island with appr Cum 16,469.563 16,469.56 - - - - - - - - - - -
3.01 Granular Sub-base Cum 63,282.777 2.2300 - - - - - - 141,121 - - - -
3.02 Wet mix macadam Cum 35,426.596 0.7293 0.3536 0.3978 0.7293 - - 25,836.616 12,526.844 14,092.700 25,836.616 - - - - -
4.01 Prime Coat Sqm 409,118.855 0.0008 - - - - - - - - 306.839 - -
4.02(a) Tack coat over granular surface Sqm 83,523.050 0.0003 - - - - - - - - 22.969 - -
4.02(b) Tack coat over bitumen serface Sqm 262,647.650 0.0002 - - - - - - - - 59.096 - -
4.03 BM Cum 39.875 0.4366 0.4594 0.3906 0.9880 0.1103 0.0231 - - 17.408 18.320 15.574 39.397 - 4.398 - 0.922 -
4.04 DBM (Mytas mix) Cum 2,680.926 0.4366 0.4594 0.3906 0.9880 0.1103 0.0231 - - 1,170.413 1,231.742 1,047.110 2,648.761 - 295.670 - 61.974 -
4.04 DBM(Ramky mix) Cum 2,703.224 0.4508 0.4272 0.4272 0.9228 0.1086 0.0236 - - 1,218.505 1,154.709 1,154.709 2,494.427 - 293.462 - 63.796 -
4.04 DBM Cum 39,246.205 0.9708 0.4275 0.8338 0.1070 0.0229 - - - 38,099.509 16,778.616 32,722.936 - 4,199.289 - 899.185 -
4.06 BC Cum 11,329.085 0.8938 0.4469 0.8490 0.1226 0.0441 - - - 10,125.646 5,062.823 9,618.296 - 1,388.538 - 499.340 -
4.07 DLC Cum 325.812 0.5382 0.5723 0.6132 0.1703 175.352 - - 186.462 199.788 - - - - 55.486 -
4.08 PQC Cum 512.466 0.4364 0.4290 0.6360 0.4250 223.622 - - 219.848 325.928 - - - - 217.798 -
5.02 Sand filling in Foundation Cum 1,852.362 1.0000 1,852.362 - - - - - - - - - -
5.03 Back filling behind abutments Cum 209.752 209.752 - - - - - - - - - - -
5.04 Filter media Cum 197.612 0.6810 0.9080 0.6810 - - - 134.574 179.432 134.574 - - - - -
5.05 PCC M 15 for leveling course Cum 282.425 0.3352 0.2301 0.6661 0.5441 0.2700 94.669 64.986 - 188.123 153.667 - - - - 76.255 -
5.06(a) PCC Grade M 20 Cum 655.462 0.3315 0.2277 0.6594 0.5384 0.2800 217.286 149.249 - 432.212 352.901 - - - - 183.529 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,261.468 0.2980 0.2046 0.6448 0.5265 0.3500 375.917 258.096 - 813.395 664.163 - - - - 441.514 -
5.08(a) RCC M 25 superstructure Cum 667.757 0.2980 0.2046 0.6448 0.5265 0.3500 198.992 136.623 - 430.570 351.574 - - - - 233.715 -
5.09(a) TMT for Foundation MT 129.951 1.0000 - - - - - - - - - - 129.95
5.09(b) TMT for Substructure MT 188.519 1.0000 - - - - - - - - - - 188.52
5.09(c) TMT for Superstructure MT 100.002 1.0000 - - - - - - - - - - 100.00
5.10 H.P NP-4, 1200 mm Dia Lm 420.576 - - - - - - - - - - - 420.576
6.02 Granular material Filling in Foundat Cum 3,022.839 1.5950 - 4,821.428 - - - - - - - - -
6.03 Back filling with granular material Cum 2,167.883 2,167.883 - - - - - - - - - - -
6.04 Filter media behind abutments Cum 1,384.220 0.6810 0.9080 0.6810 - - - 942.654 1,256.872 942.654 - - - - -
6.05(a) PCC M15 for foundation Cum 319.892 0.3352 0.2301 0.6661 0.5441 0.2700 107.228 73.607 - 213.080 174.053 - - - - 86.371 -
6.05(b) RCC M30 for foundation Cum 2,166.867 0.2850 0.1958 0.6442 0.5261 0.3800 617.557 424.273 - 1,395.896 1,139.989 - - - - 823.409 -
6.06a(i) RCC M30 Upto 5m height Cum 2,878.840 0.2850 0.1958 0.6442 0.5261 0.3800 820.469 563.677 - 1,854.549 1,514.558 - - - - 1,093.959 -
6.06a(ii) RCC M30 5m - 10m height Cum 863.684 0.2850 0.1958 0.6442 0.5261 0.3800 246.150 169.109 - 556.385 454.384 - - - - 328.200 -
6.07(a) RCC M30 Super structure Cum 4,148.012 0.2850 0.1958 0.6442 0.5261 0.3800 1,182.183 812.181 - 2,672.149 2,182.269 - - - - 1,576.245 -
6.07(b) RCC M35 Super structure Cum - 0.4389 0.5450 0.6640 0.4000 - - - - - - - - - - -
6.08 M15 for Approach slab Cum 96.465 0.3352 0.2301 0.6661 0.5441 0.2700 32.335 22.197 - 64.255 52.487 - - - - 26.046 -
6.09 M30 for Approach slab Cum 302.616 0.2850 0.1958 0.6442 0.5261 0.3800 86.246 59.252 - 194.945 159.206 - - - - 114.994 -
6.10 Wearing course Sqm 1,726.160 0.0581 0.0290 0.0552 0.0797 0.0029 - - - 100.282 50.141 95.257 - 137.517 - 4.945 -
6.15(a) TMT for Foundation MT 614.676 1.0000 - - - - - - - - - - 614.68
6.15(b) TMT for Substructure MT 437.215 1.0000 - - - - - - - - - - 437.22
6.15© TMT for Superstructure MT 591.832 1.0000 - - - - - - - - - - 591.83
7.01 Footpath Sqm 7,981.588 0.0084 0.0058 0.0167 0.0136 0.3345 0.0068 66.886 45.914 - 132.913 108.570 - 2,670 - - 53.876
8.05© Lined surface Toe drains Lm 5,964.000 0.1103 0.0757 0.2191 0.1790 0.0888 657.715 451.492 - 1,306.992 1,067.609 - - - - 529.782 -
8.06(a) M-20 Median Kerb "A" Lm 10,643.115 0.0226 0.0241 0.0607 0.0198 240.534 256.499 - - 646.012 - - - - 211.159 -
8.06(b) M-20 Median Kerb "L" Lm 296.885 0.0385 0.0411 0.1034 0.0338 11.430 12.202 - - 30.698 - - - - 10.035 -
8.07 Water chutes PCC M15 Lm 742.965 0.0469 0.0322 0.0933 0.0762 0.0378 34.866 23.934 - 69.284 56.595 - - - - 28.084 -
8.08(b) filter material behind retaining wall Cum 1,174.500 0.6810 0.9080 0.6810 - - - 799.835 1,066.446 799.835 - - - - -
8.08© PCC M15 grade Cum 710.704 0.3352 0.2301 0.6661 0.5441 0.2700 238.228 163.533 - 473.400 386.694 - - - - 191.890 -
8.08(d) RCC M30 for foundation Cum 1,305.312 0.2850 0.1958 0.6442 0.5261 0.3800 372.014 255.580 - 840.882 686.725 - - - - 496.019 -
8.08(e) RCC M30 for Substructure Cum 1,023.908 0.2850 0.1958 0.6442 0.5261 0.3800 291.814 200.481 - 659.602 538.678 - - - - 389.085 -
8.08(f) TMT For foundation & substruc. Cum 255.901 1.0000 - - - - - - - - - - 255.90
8.10(a) Facia panals sloped surcharge Sqm 1,512.183 0.0878 0.1090 0.1328 0.0800 132.731 - - 164.828 200.818 - - - - 120.975 -
8.10(b) Facia panals Vertical surcharge Sqm 903.240 0.0878 0.1090 0.1328 0.0800 79.281 - - 98.453 119.950 - - - - 72.259 -
8.11 granular soil behind reinforced eart Cum 13,119.974 13,119.974 - - - - - - - - - - -
9.13 Chain link fencing Lm 3,006.750 0.0324 0.0452 0.0452 0.0182 97.540 - - 135.838 135.838 - - - - 54.798 -
9.15(a) W-Beam Crash Barrier Lm 11,307.000 0.0276 0.0380 0.0379 0.0162 311.770 - - 430.209 428.897 - - - - 183.626 -
9.17(a) NP2 600mm Dia Pipe Lm 430.664 - - - - - - - - - - - 430.7
9.18(a) Dia 110mm ( a set of 8 pipes )SR Rm 9,734.000 - - - - - - - - - - 77,872
9.18(b) Dia 110mm (Main Carriageway) Rm 11,845.000 - - - - - - - - - - 11,845
SR Kerb M20 Inner Kerb "A" type Lm - 0.0201 0.0215 0.0541 0.0177 - - - - - - - - - - -
- - - - - - - - - - -
Total Cumulative Quantity 2,569,870.90 8,765.18 8,964.31 28,242.94 78,668.39 52,836.47 75,332.75 143,790.43 6,318.87 388.90 9,129.27 2,318.10 430.66 420.58 89,717.00
Upto Previous Bill Quantity 2,474,306.02 7,901.413 8,618.543 28,242.94 69,174.01 47,398.67 68,060.90 141,913.939 5,354.459 339.735 8,077.067 2,215.41 430.66 420.576 81,717
Balance Quantities 95,564.879 863.763 345.770 - 9,494.377 5,437.806 7,271.857 1,876.495 964.415 49.169 1,052.203 102.686 - - 8,000.000
in No.s in No.s
Name of Project : (Package -2) : Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, In the state of Andhra Pradesh, India in the stretches from Patancheru (Km.23+700) to Shamirpet (Km.61+700) Northern Arc Packag

MATERIAL CONSUMPTION STATEMENT


0.058
Interim Payment certificate -19 For the Month of February 2011
Factor Material Consumption
This Bill Gravel RCC Pipe RCC Pipe
BOQ No. Description Unit Robo Sand Robo Sand 40mm 20mm 10mm Dust Bitumen Emulsion Cement Steel HDPE 110
Quantity Sand 40mm 20mm 10mm Dust GSB Bitumen Emulsion Cement Steel /Morrum GSB (MT) 600 mm 1200 mm
Sand (Cu.m) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT) Dia
(Cu.m) (m) (m)
Consumed from Medak District
3.01 Granular Sub-base Cum 59,324.717 2.2300 - - - - - - 132,294 - - - -
3.02 Wet mix macadam Cum 72,206.967 0.7293 0.3536 0.3978 0.7293 - - 52,660.541 25,532.384 28,723.931 52,660.541 - - - - -
5.05 PCC M 15 for leveling course Cum 504.370 0.4806 0.6693 0.6693 0.2700 242.400 - - 337.575 337.575 - - - - 136.180 -
5.06(a) PCC Grade M 20 Cum 324.994 0.4754 0.6560 0.6540 0.2800 154.502 - - 213.196 212.546 - - - - 90.998 -
5.07(a) RCC M 25 foundations & Substructu Cum 1,903.820 0.4524 0.6244 0.6225 0.3500 861.288 - - 1,188.650 1,185.033 - - - - 666.337 -
5.08(a) RCC M 25 superstructure Cum 409.716 0.4524 0.6244 0.6225 0.3500 185.356 - - 255.806 255.028 - - - - 143.401 -
6.05(a) PCC M15 for foundation Cum 758.734 0.4806 0.6631 0.6611 0.2700 364.648 - - 503.117 501.599 - - - - 204.858 -
6.05(b) RCC M30 for foundation Cum 5,421.469 0.4452 0.6145 0.6126 0.3800 2,413.638 - - 3,331.222 3,321.192 - - - - 2,060.158 -
6.06a(i) RCC M30 Upto 5m height Cum 2,747.082 0.4452 0.6145 0.6126 0.3800 1,223.001 - - 1,687.945 1,682.862 - - - - 1,043.891 -
6.06a(ii) RCC M30 5m - 10m height Cum 829.446 0.4452 0.6145 0.6126 0.3800 369.269 - - 509.653 508.119 - - - - 315.189 -
6.07(a) RCC M30 Super structure Cum 951.462 0.4452 0.6145 0.6126 0.3800 423.591 - - 584.626 582.866 - - - - 361.556 -
6.07(b) RCC M35 Super structure Cum 1,828.684 0.4389 0.5450 0.6640 0.4000 802.557 - - 996.633 1,214.246 - - - - 731.474 -
8.05© Lined surface Toe drains Lm 855.000 0.1581 0.2182 0.2175 0.0888 135.190 - - 186.527 185.964 - - - - 75.950 -
8.06(a) M-20 Median Kerb "A" Lm 7,346.000 0.0226 0.0245 0.0672 0.0198 166.020 179.977 - - 493.604 - - - - 145.745 -
8.08© PCC M15 grade Cum 378.308 0.4806 0.6631 0.6611 0.2700 181.815 - - 250.856 250.099 - - - - 102.143 -
8.08(d) RCC M30 for foundation Cum 1,178.445 0.4452 0.6145 0.6126 0.3800 524.644 - - 724.096 721.915 - - - - 447.809 -
8.08(e) RCC M30 for Substructure Cum 603.621 0.4452 0.6145 0.6126 0.3800 268.732 - - 370.895 369.778 - - - - 229.376 -
SR Kerb M20 Inner Kerb "A" type Lm 1,070.000 0.0201 0.0218 0.0598 0.0177 21.507 23.326 - - 63.986 - - - - 18.939 -

- - - - - - - - -
Total Cumulative Quantity - 8,338.158 203.30 52,660.54 36,673.18 40,610.34 52,660.54 132,294.12 - - 6,774.004 - - - -
Upto Previous Bill Quantity - 8,251.636 203.30 46,237.38 33,451.47 36,975.89 46,237.38 112,793.76 - - 6,695.145 - - - -
Balance Quantities - 86.522 - 6,423.166 3,221.707 3,634.450 6,423.166 19,500.364 - - 78.859 - - - -
- - 78.9 - in No.s in No.s
Balance Quantity in This Month 95,564.9 950.285 345.770 63,629.158 964.415 49.169 1,131.062 102.686 - - 8,000.0
HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Abstract of ROYALTY TO BE RECOVERED (DISTRICT WISE)

Consumed From Ranga Reddy District

S.No. Description Unit Rate IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 IPC-11 IPC-12 IPC-13

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 53,275.000 - - - 19,769.000 - - - -

2 Royalty on Sand Material Used Cum 36.00 - - - - - - - - -

3 Royalty on Stone Material Used MT 30.00 - - - - - - - - -

As per Lr.No.104/Vg/2008 dated 22.08.2009

1 Royalty on Earthwork/Morram material Cum 22.00 80,450.510 127,086.910 172,732.928 218,765.588 442,396.340 231,814.030 235,333.836 92,390.905 152,924.218 118,874.313 103,549.060 33,126.303 25,046.108

2 Royalty on Sand Material Used Cum 40.00 - - - - - - - - - - -

3 Royalty on Stone Material Used MT 33.00 - - - - 31,287.535 95,173.051 20,907.697 44,476.605 17,696.372 21,599.212 14,913.354 17,327.101

Total Amounts IPC Wise 2,835,411.22 2,795,912.02 3,800,124.42 4,812,842.94 10,128,099.48 6,132,397.32 8,318,055.07 2,722,553.90 4,832,060.76 3,199,215.16 2,990,853.32 1,220,919.35 1,122,808.71

Consumed From Medak District

S.No. Description Unit Rate IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 IPC-11 IPC-12 IPC-13

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 - - - - - - - - -

2 Royalty on Sand Material Used Cum 36.00 - - - - - - - - -

3 Royalty on Stone Material Used MT 30.00 84.906 - - - - - - - -

As per Lr.No.104/Vg/2008 dated 22.08.2009

1 Royalty on Earthwork/Morram material Cum 22.00 - - - - - - - - - - -

2 Royalty on Sand Material Used Cum 40.00 - - - - - - - - - - - -

3 Royalty on Stone Material Used MT 33.00 726.373 1,716.444 1,595.302 1,571.957 1,414.960 892.191 3,926.397 10,171.084 46,485.862 41,100.801 17,247.075 11,655.244

Total Amounts IPC Wise 2,547.18 23,970.32 56,642.66 52,644.97 51,874.57 46,693.67 29,442.31 129,571.09 335,645.78 1,534,033.44 1,356,326.43 569,153.48 384,623.05

Consumed From Nizmabad District

S.No. Description Unit Rate IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 IPC-11 IPC-12 IPC-13

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 - - - - - - - - -

2 Royalty on Sand Material Used Cum 36.00 377.422 - - - - - - - -

3 Royalty on Stone Material Used MT 30.00 - - - - - - - - -

As per Lr.No.104/Vg/2008 dated 22.08.2009

1 Royalty on Earthwork/Morram material Cum 22.00 - - - - - - - -

2 Royalty on Sand Material Used Cum 40.00 263.552 622.566 723.875 570.087 1,345.302 2,592.220 (719.539) 1,937.966 2,043.07 724.61 607.45 778.97

3 Royalty on Stone Material Used MT 33.00 - - - - - - - -


HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Total Amounts IPC Wise 13,587.20 10,542.09 24,902.66 28,955.02 22,803.49 53,812.08 103,688.79 (28,781.55) 77,518.63 81,722.95 28,984.52 24,297.80 31,158.80
HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Abstact of ROYALTY RECOVERED FROM IPC's

S.No. Description Unit Rate IPC-1 IPC-2 IPC-3 IPC-4 IPC-5 IPC-6 IPC-7 IPC-8 IPC-9 IPC-10 IPC-11 IPC-12 IPC-13

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 53,275.000 - - - 19,769.000 - - - - -

2 Royalty on Sand Material Used Cum 36.00 377.421 - - - - - - - - -

3 Royalty on Stone Material Used MT 30.00 84.905 - - - - - - - - -

As per Lr.No.104/Vg/2008 dated 22.08.2009

1 Royalty on Earthwork/Morram material Cum 22.00 80,450.510 127,086.910 172,732.928 218,765.588 442,396.340 231,814.030 235,333.836 92,390.905 152,924.218 118,874.313 103,549.060 33,126.303 25,046.108

2 Royalty on Sand Material Used Cum 40.00 - 263.565 622.566 723.875 570.084 1,345.302 2,592.220 (719.539) 1,937.961 2,043.074 724.613 607.445 778.970

3 Royalty on Stone Material Used MT 33.00 - 726.373 1,716.444 1,595.302 1,571.957 32,702.495 96,065.242 24,834.093 54,647.689 64,182.234 62,700.013 32,160.429 28,982.375

Total Amounts IPC Wise 2,851,545.53 2,830,424.93 3,881,669.71 4,894,442.90 10,202,777.42 6,232,903.08 8,451,186.18 2,823,343.42 5,245,224.97 4,814,971.57 4,376,164.27 1,814,370.62 1,538,591.55
HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Abstract of ROYALTY TO BE RECOVERED (DISTRICT WISE)

Consumed From Ranga Reddy District

S.No. Description Unit Rate IPC-14 IPC-15 IPC-16 IPC-17 IPC-18 IPC-19 IPC-20 Total Quantity Amount

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 73,044.000 1,460,880

2 Royalty on Sand Material Used Cum 36.00 - -

3 Royalty on Stone Material Used MT 30.00 - -

- 1,460,880

As per Lr.No.104/Vg/2008 dated 22.08.2009 -

1 Royalty on Earthwork/Morram material Cum 22.00 15,963.013 79,893.855 122,984.798 74,510.819 73,418.484 95,564.879 2,496,826.897 54,930,192

2 Royalty on Sand Material Used Cum 40.00 - - - - - - - -

3 Royalty on Stone Material Used MT 33.00 8,942.243 29,815.458 18,976.861 9,261.827 24,413.139 24,080.535 378,870.990 12,502,743

67,432,934

Total Amounts IPC Wise 646,280.31 2,741,574.92 3,331,901.97 1,944,878.31 2,420,840.24 2,897,084.99 68,893,814

Consumed From Medak District

S.No. Description Unit Rate IPC-14 IPC-15 IPC-16 IPC-17 IPC-18 IPC-19 IPC-20 Total Quantity Amount

As per G.O.No.217 dated 29.09.2004 -

1 Royalty on Earthwork/Morram material Cum 20.00 - -

2 Royalty on Sand Material Used Cum 36.00 - -

3 Royalty on Stone Material Used MT 30.00 84.906 2,547

- 2,547

As per Lr.No.104/Vg/2008 dated 22.08.2009 -

1 Royalty on Earthwork/Morram material Cum 22.00 - - - - - - - -

2 Royalty on Sand Material Used Cum 40.00 - - - - - - - -

3 Royalty on Stone Material Used MT 33.00 10,270.441 19,171.473 56,872.761 41,270.193 18,344.286 39,548.623 323,981.467 10,691,388

10,691,388
Total Amounts IPC Wise 338,924.55 632,658.61 1,876,801.11 1,361,916.37 605,361.44 1,305,104.56 10,693,936

Consumed From Nizmabad District

S.No. Description Unit Rate IPC-14 IPC-15 IPC-16 IPC-17 IPC-18 IPC-19 IPC-20 Total Quantity Amount

As per G.O.No.217 dated 29.09.2004 -

1 Royalty on Earthwork/Morram material Cum 20.00 - -

2 Royalty on Sand Material Used Cum 36.00 377.422 13,587

3 Royalty on Stone Material Used MT 30.00 - -

- 13,587

As per Lr.No.104/Vg/2008 dated 22.08.2009 -

1 Royalty on Earthwork/Morram material Cum 22.00 - -

2 Royalty on Sand Material Used Cum 40.00 803.77 742.62 1,321.16 717.68 700.28 950.28 16,725.909 669,036

3 Royalty on Stone Material Used MT 33.00 - -


HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

669,036
Total Amounts IPC Wise 32,150.60 29,704.64 52,846.20 28,707.20 28,011.04 38,011.40 682,624
HYDERABAD GROWTH CORRIDOR LIMITED
Construction of Eight - lane Access Controlled Expresway as Outer Ring Road to Hyderabad City, Package-2 from Mallampet (Km.35+000) to Dindigal (Km.46+000)

Abstact of ROYALTY RECOVERED FROM IPC's

S.No. Description Unit Rate IPC-14 IPC-15 IPC-16 IPC-17 IPC-18 IPC-19 IPC-20 Total Quantity Amount

As per G.O.No.217 dated 29.09.2004

1 Royalty on Earthwork/Morram material Cum 20.00 73,044.000 1,460,880

2 Royalty on Sand Material Used Cum 36.00 377.421 13,587

3 Royalty on Stone Material Used MT 30.00 84.905 2,547

- 1,477,014

As per Lr.No.104/Vg/2008 dated 22.08.2009 -

1 Royalty on Earthwork/Morram material Cum 22.00 15,963.013 79,893.855 122,984.798 74,510.819 73,418.484 95,564.879 2,496,826.897 54,930,192

2 Royalty on Sand Material Used Cum 40.00 803.766 742.616 1,321.156 717.679 700.276 950.285 16,725.914 669,037

3 Royalty on Stone Material Used MT 33.00 19,212.656 48,986.927 75,849.616 50,531.991 42,757.425 63,629.157 702,852.418 23,194,130

78,793,358

Total Amounts IPC Wise 1,017,354.57 3,403,938.04 5,261,549.12 3,335,500.88 3,054,212.71 4,240,200.92 80,270,372
-