Professional Documents
Culture Documents
Placing Finish Concrete
Placing Finish Concrete
Concrete
Basic Requirements for
Placing Concrete (1)
● Preserve concrete quality
● Water-cement ratio
● Slump
● Air-content
● Homogeneity
● Avoid separation of
aggregate and mortar
Placing and
Finishing Concrete
Basic Requirements for
Placing Concrete (2)
Placing and
Finishing Concrete
Preparation Before Placing
Includes:
● Moistening the subgrade
Placing and
Finishing Concrete
Preparation Before Placing
Includes:
● Compacting the subgrade
Placing and
Finishing Concrete
Depositing Concrete
● DO NOT —
(a) disturb saturated subgrades so
bearing capacity is maintained
(b) deposit on frozen subgrade
● Do not —
(a) dump in separate piles & then
level and work together
(b) deposit in large piles & then
move horizontally into position
These practices result in segregation
(mortar flows ahead of coarser material)
Placing and
Finishing Concrete
Depositing Concrete
Effective use of
wheelbarrows
Shallow
hopper
Rock Mortar
Placing and
Finishing Concrete
Placement with Conveyor
Belt
Placing and
Finishing Concrete
Depositing Concrete
Pavement Slab
● Concrete deposited in
front of slip form paver
by dump trucks
● Concrete spread evenly
across the subgrade by
the paver before
consolidation and
finishing
Placing and
Finishing Concrete
Depositing Concrete
Curb/Curb and Gutter
● Concrete deposited
into hopper of slip
form curb and gutter
machine which then
extrudes the concrete
into the desired
shape
Placing and
Finishing Concrete
Depositing Concrete
Walls
● Deposit in horizontal layers of
uniform thickness
● Reinforced — 150 mm to 500 mm
● Mass — 375 mm to 500 mm
Placing and
Finishing Concrete
Horizontal Construction Joints
Placing and
Finishing Concrete
Underwater Placement
Methods
● Tremie
● Pump
● Bottom dump buckets
● Grouted preplaced
aggregate (specialized)
● Toggle bags
● Bagwork
● Diving bell
Placing and
Finishing Concrete
Placing Concrete
Under Water
Basic Recommendations
● Water velocity ≤ 3 m (10 ft) / min.
● Water temperature ≥ 5°C
(if below — test for strength gain)
● w/c ≤ 0.45
● Cementing materials content ≥
390 kg/m3 (600 lb/yd3)
● Slump range 150 to 225 mm (6 to
10 in.)
Placing and
Finishing Concrete
Placing Concrete
Underwater
● Used: Tremie
● Internal Vibration
● External Vibration
Placing and
Finishing Concrete
Internal Vibration
Vibrator
R
1½ R
INCORRECT
Haphazard random penetration of the
vibrator at all angles and spacings
without sufficient depth will not assure
intimate combination of the two layers
Placing and
Finishing Concrete
Placing Concrete in a
Sloping Lift
CORRECT
Start placing at bottom of slope so
that compaction is increased by
weight of newly added concrete.
Vibration consolidates the concrete.
INCORRECT
When placing is begun at top of slope
the upper concrete tends to pull apart
especially when vibrated below as
this starts flow and removes from
Placing and concrete above.
Finishing Concrete
External Vibration
● Form vibrators
● Vibrating tables
● Surface vibrators
● Vibratory screeds
● Plate vibrators
● Vibratory roller screeds
● Vibratory hand floats or
trowels
Placing and
Finishing Concrete
Consolidating Concrete
Inadequate consolidation
can result in:
● Honeycomb
● Excessive amount of entrapped
air voids (bugholes)
● Sand streaks
● Cold joints
● Placement lines
● Subsidence cracking
Placing and
Finishing Concrete
Nuclear Gauges to Determine
Subbase Compaction
Placing and
Finishing Concrete
Screeding (Strikeoff)
The process of cutting off excess
concrete to bring the top surface of a
slab to proper grade
Placing and
Finishing Concrete
Vibratory
Screeds
Placing and
Finishing Concrete
Bullfloating
Placing and
Finishing Concrete
Darbying
Placing and
Finishing Concrete
Edging
Edging densifies and compacts concrete
next to forms where floating is less effective
Placing and
Finishing Concrete
Floating (Power or Hand)
● To embed aggregate
particles just beneath the
surface
● To remove slight
imperfections, humps, and
voids
● To compact the mortar at
the surface in preparation
for additional finishing
operations.
Placing and
Finishing Concrete
Troweling
● Creates smooth,
hard,dense surface
● Exterior concrete should
not be troweled because:
● it can lead to a loss of
entrained air caused by
overworking the surface
● troweled surfaces can
be slippery when wet.
Placing and
Finishing Concrete
Brooming
Placing and
Finishing Concrete
Tining
Placing and
Finishing Concrete
Curing and Protection
Placing and
Finishing Concrete
Bonding New to Previously
Hardened Concrete
● Cement-sand
grout
● Latex
● Epoxy
Placing and
Finishing Concrete
Isolation Joints
Placing and
Finishing Concrete
Contraction Joints
Placing and
Finishing Concrete
Spacing of Contraction
Joints in Meters
Slab Maximum-size Maximum-size
thickness, aggregate less aggregate
mm than 19 mm 19 mm and larger
100 2.4 3.0
125 3.0 3.75
150 3.75 4.5
175 4.25 5.25
200 5.0 6.0
225 5.5 6.75
250 6.0 7.5
Placing and
Finishing Concrete Metric
Spacing of Contraction
Joints in Feet
Maximum-size Maximum-size
Slab aggregate aggregate
thickness, in. less than ¾ in. ¾ in. and larger
4 8 10
5 10 13
6 12 15
7 14 18
8 16 20
9 18 23
10 20 25
Placing and
Finishing Concrete Inch-Pound
Making Contraction Joints
Grooving tool
on bull-float
Placing and
Finishing Concrete
Dry-cut sawing concrete
Construction
Joints
Placing and
Finishing Concrete
Joint Layout for Slabs
Basic Factors to Remember
● Panels created by contraction joints
should be approximately square
● Panel aspect ratio max. 1½ to 1
● Contraction (control) joints should
only terminate at a free edge or at
an isolation joint
● When joint spacing exceeds 4.5 m
(15 ft), load transfer by aggregate
interlock decreases significantly
Placing and
Finishing Concrete
Typical Joint Layout
Placing and
Finishing Concrete
Finishing Operations
Single Course Floors
● Consolidation
● Strike-off
● Edging
● Darbying or Bull Floating
Lapse of Time
● Edging
● Grooving (if desired)
● Floating (power or hand)
● Troweling (power or hand)
Lapse of Time
● Second Troweling (power or hand)
● Final Troweling (hand)
Placing and ● Curing
Finishing Concrete
Finishing Operations - Exterior Slabs
Sidewalks, Driveways etc.
● Consolidation
● Strike-off
● Depress aggregate with metal/wood strip
at joint location if hand tooled
● Darbying or Bull floating
Lapse of time
● Edging
● Jointing (optional if hand tooled)
● Floating
Lapse of time
● Texturing (brooming/swirl float finish)
Placing and ● Curing
Finishing Concrete
Patching
Placing and
Finishing Concrete
Curing Patches
Placing and
Finishing Concrete
Cleaning Concrete
Surfaces
● Cleaning methods:
● Water
● Chemical
● Mechanical
Placing and
Finishing Concrete
Finishing Formed
Surfaces
● Rough-form finishes
● Smooth off-the-form finish
● Sand-floated finish
● Grout cleandown
(sack-rubbed finish)
Placing and
Finishing Concrete
Special Surface Finishes
● Pattern and Textures
● Exposed Aggregate Concrete
● Colored Finishes
Placing and
Finishing Concrete
Placing and
Finishing Concrete
Working Safely with Concrete
Protect:
● Your Eyes
● Your Back
● Your Skin
Placing and
Finishing Concrete
Precautions
WARNING: Contact with wet (unhardened) concrete, mortar,
cement, or cement mixtures can cause SKIN IRRITATION, SEVERE
CHEMICAL BURNS (THIRD-DEGREE), or SERIOUS EYE
DAMAGE. Frequent exposure may be associated with irritant and/or
allergic contact dermatitis. Wear water-proof gloves, a long-sleeved
shirt, full-length trousers, and proper eye protection when working
with these materials. If you have to stand in wet concrete, use
waterproof boots that are high enough to keep concrete from flowing
into them. Wash wet concrete, mortar, cement, or cement mixtures
from your skin immediately. Flush eyes with clean water immediately
after contact. In-direct contact through clothing can be as serious as
direct contact, so promptly rinse out wet concrete, mortar, cement,
or cement mixtures from clothing. Seek immediate medical attention
if you have persistent or severe discomfort.