Professional Documents
Culture Documents
Prof Kelkar Assignment
Prof Kelkar Assignment
Assignment
Interconnecting roads:
For the construction of the interconnecting roads following Are the activities & equipment which will get
involved as wearing course is asphalt 200 mm, hence the following deals with the equipment for the
asphalt roads
1. Cleaning of site:
Starting with the site clearance using various types of equipments. It uses bulldozers, scrapers and
various other equipments.
2. Excavation :
Excavating the marked area with the detailed depth & cutting all the area if area is rocky type then
blasting is done at the rock side.
3. Quaring :
The various types of rocks are quarrying include chalk, china clay, cinder, clay, coal, construction
aggregates granite, grit stone, gypsum, lime stone, marbles, ores, stand stone etc.
4. Aggregate production:
The construction material will get loaded to the dumper & than send to the crushing plants for the
aggregate production with different size of aggregates. These aggregates are then transported &
sent to side
5. Transportation:
Loading/unloading to site to the plant & vice-versa
7. Paving:
The equipment require for paving are hot mix plant, met mix plant, bituminous powder etc.
8. Lanes:
We use lane making machinery. The about selection of equipments depends on three factors:
a. Life time out past cost as per the unit work performed
b. It also depend upon the initial price
c. Lastly factory which categories the selection are the landed cost, fuel consumption of the
equipment, maintenance cost, reliability, reputation, dealership/service network, & all in
combined it is called as the decision matrix.
PROCESS OF
PROCESS OF CRUSHING
CRUSHING PLANT
PLANT
LOADING
LOADING OF AGGREATE ON
OF AGGREATE ON
DEMPER
DEMPER
TRANSPORTING
TRANSPORTING OF AGGREATS TO
OF AGGREATS TO
SITE
SITE
Assumption:
As per the L-section of road, 2km of each road requires cutting of avg. depth of 2m, hence for 6 km, the
avg. depth of cut will be about 6m
3m 3m
6 km
2m 4m 6m
6 km
Total area of road=6000m*6m*1/2=18000 m 2
Since the rock is only suitable for the WBM of the 100 mm
As the aggregate weight received is 129600 ton which is much higher than the required for WBM i.e.
4320 ton
Hence for crushing plant of capacity 60 tph require approximately 144 hrs to produce the asphalt
Since the time is very less i.e. not more than 15 days hence the work will be get completed within the
given time.