TBE for Control Valves

A1 2021/01/03 Issue For Approval A.Faraj P.Asadbeigi B.Salahi A.Kia


A0 2020/12/02 Issue For Comment A.Faraj P.Asadbeigi B.Salahi A.Kia

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED AUTHORISED


Page A0 A1 A2 A3 A4 A5 A6 A7 Page A0 A1 A2 A3 A4 A5 A6 A7

1  41
2  42
3  43
4   44
5   45
6   46
7 47
8 48
9 49
10 50
11 51
12 52
13 53
14 54
15 55
16 56
17 57
18 58
19 59
20 60
21 61
22 62
23 63
24 64
25 65
26 66
27 67
28 68
29 69
30 70
31 71
32 72
33 73
34 Appendix
35 1
36 2
37 3
38 4
39 5
40 6
Document Revision
INTRODUCTION:
Iranian Gas Engineering & Development Company intends to construct gas compressor stations near the
city of ABPAKHSH as an EPC project. The purpose of the stations is to boost the gas on IGAT-VI
pipeline. This compressor station will have an approximate capacity of 107 MMSCMD.
This is an E.P.C project where a joint venture between Iran Gas & Water Development Company & Rahab
Consulting Engineers was declared the winner through a tender.

DEFINITIONS:
Project: ABPAKHSH Gas Compressor Stations on IGAT-VI EPC Projects
Contract: The contract between client and contractor for the execution of the PROJECT.
Client: Iranian Gas Engineering & Development Company (I.G.E.D.C.)
Consultant: Scetiran Consulting Engineers
Contractor: Joint Venture Comprising of: Iran Gas & Water Development Company & Rahab Consulting
Engineers, Companies which have aim of supplying E.P.C. services (Engineering,
Procurement, Construction, commissioning, etc.).
Vendor: The Company which has been selected to supply the equipment and materials (goods such as
compressors, Air Coolers, valves, skids, instruments, etc.) and produces technical
documentation mainly related to the production of the ordered supply.
Sub-vendor: The person, firm, or corporation which supplies Vendor with materials, machinery, tools,
equipment, articles, items, or other work services which are used by Vendor in connection
with this Purchase Order.

The word “shall” indicates a requirement.


The word “should” indicates a recommendation.
RED LINES
A1
REQUISITION No.: 1264-AB-DE-IN-MR-001
BIDDER 1 BIDDER 2 BIDDER 3

MEETS SPEC.

MEETS SPEC.

MEETS SPEC.
NAME: NAME: NAME:
Item

Description Purchaser's Requirement KG Equipments S.r.l./ Fidar Rasta group Tadbir fan
QUOTATION No. & Rev.: QUOTATION No. & Rev.: QUOTATION No. & Rev.:

1 GENERAL
1.1 Manufacturer KG Equipments S.r.l./Fidar Rasta Group TVF
1.2 Country Italy IRAN Spain
1.3 Total Quantity 1 ok 1 ok 1
1.4 Origin of Material Italy ok IRAN ok
1.5 Experience Please refer to our Reference List ok As per reference list ok Not specified Not ok
1.6 Delivery time 28 W ok 28 ~ 32 weeks ok Not specified Not ok
1.7 Spare parts for Commissioning & Start-Up (Option or mandatory) Required Confirmed ok As per the attached file ok Listed in Offer ok
1.8 Spare parts for 2 years Operation (Option or mandatory) Required Confirmed ok Yes ok Yes ok
1.9 Documentation Required Confirmed ok Will be submitted ok Attached ok
In accordance to Document No. 1264-
1.10 Packing and shipping AS per shipping and packing specification Confirmed ok As per attached procedure Not ok ok
AB-DE-ME-SP-011-B0
In accordance to Document No. 1264-
1.11 Painting AS per painting and coating specification Confirmed ok As per attached procedure Not ok ok
AB-DE-PI-SP-001
1.12 Certificate Yes Yes ok Yes ok Yes ok
1.13 Catalogues Yes Yes ok Yes ok Yes ok
1.14 Vendor's ITP Yes Yes ok Yes ok Yes ok
1.15 Documentation Yes Yes ok Yes ok Yes ok
1.16 Guarantee 18-24 months at least 18-24 ok 18-24 ok 18-24 ok
2 SCOPE OF WORK

2.1 Management, Engineering and Documentation As per Data Sheet Confirmed ok Confirmed ok Confirmed ok

2.2 Predicted time schedule for project As per Data Sheet Confirmed ok Confirmed ok Confirmed ok

2.3 Manufacturing and Assembling As per Data Sheet Confirmed ok Confirmed ok Confirmed ok

2.4 Calibration and Alignment As per Data Sheet Confirmed ok Confirmed ok Confirmed ok
2.5 Preparation for shipment As per Data Sheet Confirmed ok Confirmed ok Confirmed ok

2.6 Protection, Marking and Packing As per Data Sheet Confirmed ok Confirmed ok Confirmed ok

Guarantee of the suitability of all used materials (chemical


2.7 As per Data Sheet Confirmed ok Confirmed ok Confirmed ok
composition, mechanical properties and origin of materials)

All Documents and Certificates for Iranian Government


2.8 As per Data Sheet Confirmed ok Confirmed ok Confirmed ok
Approval as Required
3 SCOPE OF SUPPLY
3.1 Design works, supply of materials and construction As per Data Sheet Confirmed ok Confirmed ok As per Data Sheet ok
4 INSPECTION AND TESTS
4.1 Inspection test procedures (Considering FAT procedure if applicable) As per Data Sheet and ITP Confirmed ok Confirmed ok As per Data Sheet and ITP ok
5 GUARANTEES
24 months after Delivery or 18 months 18 Month after Shipment or 24 Month
5.1 Requested Period 18 Month after Shipment or 24 Month after P.O Month after Shipment or 24 Month after ok ok ok
after commissioning. after P.O
6 EXCEPTION AND DEVIATION
6.1 Deviations List No deviation ok Yes(valve material) Not ok Yes(Valve charactristics) Not ok
7 DESIGN
7.1 Tag Number FCV-62001 FCV-62001 ok FCV-62001 ok FCV-62001 ok
7.2 Quantity 1 1 ok 1 ok 1 ok
7.3 Line Size (IN/OUT) 24" 24" ok 24 in ok 24" ok
7.4 Line Schedule (IN/OUT) 600# 600# ok 600# ok 600# ok
7.5 Manufacturer VTA KG Equipments S.r.l./ Fidar ok Rasta Group ok Vector Valves ok
7.6 Required Cv VTA 1280 ok 1170 ok 949 gpm/psi1/2 ok
7.7 Flow Condition Gas Gas ok Gas ok Gas ok
7.8 Body Type Globe valve Globe valve ok Globe ok Globe valve ok
7.9 Body Size 18" 16" ok 18 ins ok 18" ok
7.10 Valve Model GCS Bypass Control Valve GCS Bypass Control Valve ok 5414 ok GCS Bypass ok
7.11 ANSI Rating Class 600# 600# ok ASME 900 not ok 600# ok
7.12 Travel % VTA 27 ~ 75 ok 27 ~ 75 ok 72.2% ok
7.13 Predicted SPL dB(A) <85 <85 ok <75 ok 85 dB ok
7.14 Flange Face Finish RF RF ok RTJ not ok RF ok
7.15 Bonnet Type Standard Standard ok Standard ok Standard ok
7.16 Packing Type V TYPE(VTA) V TYPE ok V type ok V-Type ok
7.17 Trim Type Cage Guided/Anti-Noise Cage Guided/Anti-Noise ok Multi-stage Cage 3CC ok BSS ok
7.18 Trim Characteristic linear linear ok Linear ok Equal percentage Not ok
7.19 ANSI/FCI Leakage Class IV IV ok ANSI Class IV ok IV ok
7.20 Actuator Type Diaphragm & Spring Diaphragm & Spring ok Pneumatic Cylinder not ok Single actinc piston not ok
7.21 Actuator air requirements 7 Barg / Max: 9 Barg / Min: 4 Barg 7 Barg / Max: 9 Barg / Min: 4 Barg ok Min. 4 barg ok 4 barg ok
7.22 DP Shut-Off bar(g) VTA 95 bar ok 95 bar ok 95 barg ok
7.23 Spring Action (Fail Action) Open Open ok Air Fail Open ok Open ok
7.24 Limit stop & Handwheel N/R N/R ok None NO N/R ok
7.25 Positioner Type VTA Electro Pneumatic Smart ok Smart Electro-Pneumatic ok Pneumatic ok
7.26 Positioner IP degree & Ex class Ex ia IIB T4 / IP65 Ex ia IIB T4 / IP65 ok Eexi IIB T3, IP65 NO Ex ia IIB T4 / IP65 ok
7.27 Limit Switch Type VTA REED P2 type ok REED Type ok REED ok
7.28 Limit Switch IP degree & Ex class IP65 / Ex d IIB T4 IP65 / Ex d IIB T4 ok Exdb IIC T6, IP65 ok IP65 / Ex d IIB T4 ok
7.29 Limit Switch enclosure material VTA aluminium ok Aluminum ok Aluminum ok
7.30 Solenoid Valve type & material 3 way solenoid valve / SS316 3 way solenoid valve / SS316 ok 3/2 way ok 3 way solenoid valve / SS316 ok
7.31 Solenoid Valve IP degree & Ex class IP65 / Ex d IIB T4 IP65 / Ex d IIB T4 ok 316 SS NO IP65 / Ex d IIB T4 ok
7.32 Max Allowable Pressure 64.1 63.1 not ok 64.1 ok 64.1 ok
7.33 Min Requires Pressure 64.1 63.1 not ok 64.1 ok 64.1 ok
8 MATERIAL
8.1 Body & Bonnet Material A216 WCB A216 WCB ok CS ASTM A216 WCB ok A216 WCB ok
8.2 Plug/Ball/Disk Material SS316 13% cr No deviation ok SS316L + Stellite ok 316 SS + Stelite 6 ok
8.3 Seat Material SS316 13% cr A182 F6a (SS410-13%Cr) ok SS316L + Stellite ok 316 SS + Stelite 6 ok
8.4 Cage/Guide Material SS316 13% cr A182 F6a (SS410-13%Cr) ok SS316L ok 316 SS + Stelite 6 ok
8.5 Stem Material SS316 13% cr SS316 ok SS316L ok Not specified ok
8.6 Packing Material PTFE PTFE ok PTFE ok PTFE ok
OVERVIEW OF TECHNICAL EVALUATION RESULTS OK Not Ok Not Ok
REMARKS: LEGEND:
Yes : The bidder’s proposal in his quotation is acceptable without any deviation and clarification. Y = MEETS SPECIFICATION
AC-c : The bidder’s proposal in his quotation is acceptable after clarification, adjustment and/or correction. N = DOES NOT MEET SPECIFICATION
AC-d : The bidder’s proposal which is deviated from our specification is acceptable. NS = NOT SPECIFIED IN QUOTATION
No : The bidder’s proposal is not acceptable. NA = NOT APPLICABLE
INA : Information is not available in the bidder's quotation. VTS = VENDOR TO SPECIFY