HENS Part-2

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

Heat Exchanger Network

Synthesis (HENS)

PROF. RASHMITA PATEL


PINCH DESIGN METHOD (PDM)
FOR HEN SYNTHESIS
 Varying ΔTmin , as shown in
Figure, changed the relative
position of the process composite
curves.
 As ΔTmin is changed from a small
to a large value, the capital cost
decreases but the energy cost
increases.
 When the two costs are combined
to obtain a total cost, the optimum
point in the capital-energy trade-
off is identified, corresponding
with an optimum value of Δ Tmin

Fig. The correct setting for ΔTmin is


fixed economic trade-offs.
Continue…

 The tradeoff between energy and capital cost suggests a good


initialization would be to assume that no individual exchanger
should have a temperature difference smaller than ΔTmin .
 To comply with this, the process should be divided at the pinch.
this is most clearly done by representing the stream data in the
grid diagram.
 Figure in next slide shows the stream data from Table in grid form
with the pinch marked.
 Above the pinch, steam can be used (up to QHmin ), and below the
pinch cooling water can be used (up to QCmin ) as utilility.

 But what strategy should be adopted for the design? A number of


simple criteria can be developed to help.
HOT PINCH TEMPERATURE: 150oc
COLD PINCH TEMPERATURE: 140oc
THE PINCH DESIGN METHOD


Criteria for PINCH DESIGN METHOD

1. Start at the pinch.:


 The pinch is the most constrained region of the problem.
At the pinch, ΔTmin exists between all hot and cold
streams. As a result, the number of feasible matches in this
region is severely restricted. Quite often there are essential
matches to be made.
2. Stream population criteria

For Above Pinch Region:

For Below Pinch Region:


3. The CP inequality for individual matches.
Above Pinch

 On the other hand, Figure b


shows a match involving the
same hot stream but with a
cold stream that has a larger
CP.
 The relative slopes of the
temperature–enthalpy
profiles now cause the
temperature differences to
become larger moving away
from the pinch, which is
feasible.
 Thus, starting with ΔTmin at
the pinch, for temperature
differences to increase
moving away from the pinch.
Below Pinch

 If the same cold stream is


matched with a hot stream
with a larger CP (i.e. a less
steep slope), as shown in
Figure b, then temperature
differences become larger,
which is feasible.
 Thus, starting with ΔTmin
at the pinch, for
temperature differences to
increase moving away from
the pinch
CP Table for Above Pinch
CP Table for Below Pinch
 The “tick-off” heuristic:
 Once the matches around the pinch have been chosen to satisfy
the criteria for minimum energy, the design should be continued
in such a manner as to keep capital costs to a minimum.
 One important criterion in the capital cost is the number of units
(there are others, of course, which shall be addressed later).
 Keeping the number of units to a minimum can be achieved
using the tick-off heuristic.
 To tick off a stream, individual units are made as large as
possible, that is, the smaller of the two heat duties on the streams
being matched.
HOT PINCH TEMPERATURE: 150oc
COLD PINCH TEMPERATURE: 140oc
THE PINCH DESIGN METHOD


Above Pinch

250oC 150oC
2 √ 15 MW

200oC √
4 150oC 12.5MW

Feasible

180oC
√ 1 140oC 8MW

8MW
230oC H 3 27MW
140oC
7.5 12.5 7
MW MW MW
250oC √ 150oC
15 MW
2 0.5
MW
200oC
4 C 150oC 12.5MW

Infeasible

140oC 8MW
180oC H 1
8
230oC MW 3
140oC 27MW
12 15
MW MW
BELOW PINCH

16.5 MW
17.5MW

24MW
The completed design for the given data
• No. of Heat Exchanger used above pinch region
(including cold utility): 04

• No. of Heat Exchanger used below pinch region


(including cold utility): 03

• Therefore,
Total no. of Heat Exchanger used are: 07

• Minimum no. of HE required theoretically=


• =(Sabove Pinch-1)+(Sbelow pinch -1)
= (5-1)+(4-1)
=7
PINCH DESIGN METHOD STEPS
Above Pinch

400oC √ 120oC
1 84 MW

210oC √ 45MW
2 120oC

160oC
√ 3 100oC 24MW

24MW
300oC H 4 120MW
100oC
15MW 60MW 45MW
Stream splitting algorithms
GRID DIAGRAM & CP TABLE
ABOVE PINCH

CP √
CP 0.040
CP
0.045 0.005
720oC √ 520oC 8 MW
9.0
1 1 MW
MW

0.043 17.2
500oC17.2
0.043
900oC H 3 MW MW
0.020
0.020 9.2 MW 8MW
550oC 4 500oC
1 MW 1 MW

1MW
Below Pinch

CP
520oC 320oC
0.045 1 9 MW
0.040 220oC
520oC 2
12 MW

0.043 500oC √ 3 300oC 8.6 MW

0.020 8.6MW 6 MW
500oC 4 200oC

6MW √
8 MW
1 MW 9 MW

12 MW

8.6
17.2 MW
MW
6 MW

1 MW
 Example : The stream data for a process are given in Table below:
Steam is available condensing between 180 and 179◦C and cooling water
between 20 and 30◦C. All film transfer coefficients are 200 W·m−2·K−1.
For Tmin = 10◦C, the minimum hot and cold utility duties are 7 MW and
4 MW respectively, corresponding with a pinch at 90◦C on the hot
streams and 80◦C on the cold streams.
 a. Develop a maximum energy recovery design above the pinch that
comes close to the area target in the minimum number of units.
 b. Develop a maximum energy recovery design below the pinch that
comes as close as possible to the minimum number of units.
Above Pinch

150oC √ 90oC
1 12 MW

170oC √
2 90oC 8 MW

120oC
√ 3 80oC 12 MW

12 MW
110oC H 4 15 MW
80oC
7 MW 8 MW

You might also like