Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Challenging the Need for Insulation

Corrosion under insulation is an


endemic issue across the
process and chemical industries
and for which much time and
effort is expended.

The following article presents the


typical areas within a process
plant where insulation will have
been specified during the design
stages. The article then goes on
to describe the steps and
considerations when challenging
this requirement as an operation
matures.

Introduction
As an operating asset matures, the potential for corrosion under insulation (CUI)
increases. Without proper care and attention during installation and furthermore
when in service, moisture will penetrate and accumulate within the insulating
material. Dependent on the environment, this may lead to the accelerated external
corrosion of carbon steels and pitting of corrosion resistant alloys used in process
equipment and / or piping systems.

The option to remove insulation altogether and eliminate the CUI threat requires
continual assessment as part of an asset’s documented integrity management
system, [Ref. 1]. The original design conditions which led to the requirement for
insulating material in the first instance will often change. This is particularly relevant
in upstream and midstream operations where throughput and composition change
throughout the asset lifecycle.

This article provides some basic guidelines for the systematic review of the original
design intent against current operating conditions and parameters. This may done on
a rolling basis or as a single engineering re-evaluation of an asset’s insulation
philosophy.

In both cases, the assessment is ideally undertaken ahead of a CUI inspection


programme, such that when the insulation is removed for inspection purposes, the
case not to reinstate after completion of the inspection has already been made.

Issued May 2021 https://forum.xpertopinions.com

Reasons to Insulate large pressure drops across valves. As


operating conditions change compared
Understanding why the insulation was to the original design intent and flow
originally installed is clearly an rates for instance drop, there is an
important first step and this will often be opportunity to reconsider the
identified within original design requirement for acoustic insulation.
documents, such as a process basis of
design or more specifically an insulation Assessment against noise action levels
and winterisation philosophy or similar. is often difficult as many sources may
contribute to the overall noise levels,
P&IDs and Piping Line Lists should also such as alarm and tannoy volumes. A
be referenced as these will provide the specialist survey is often necessary to
definitive requirement for the insulation. assess whether acoustic insulation is
Typically this will be for one or more of required or may in fact be removed.
the following reasons, all of which have
the potential to create a CUI threat if the Before commissioning such a survey,
insulation is poorly installed: an initial review can identify likely
candidate lines that may no longer need
(a) Acoustic insulation acoustic insulation. For instance:
(b) Passive fire protection
(c) Heat conservation • Pipework where there has been a
(d) Low temperature conservation significant reduction in operating
(e) Anti-condensation velocities when compared to the
(f) Personal protection original design conditions.
(g) Winterisation
• Changes in walkway routings and
Each of the above requirements are thoroughfares such that certain lines
further explored within this article, are no longer sufficiently close to
including the reasons why the insulation walkways to require protection.
may be challenged out.

(b) Passive Fire Protection


(a) Acoustic Insulation
The purpose of passive fire protection
Acoustic insulation is often required on (PFP) insulation is to mitigate the
piping systems and process equipment impact of fire on piping systems,
as a means to reduce noise during process equipment and structural steel.
normal operations. As a guide this is The intent of the PFP might be to limit
typically 80-85dB on walkways and the relief rate for a fire case on a
thoroughfares, and above which hearing process vessel, provide more time to
protection will be consistently required, blowdown a hydrocarbon inventory
[Ref. 2]. and / or to limit the potential for a loss of
containment and subsequent
The main causes of excessive noise escalation.
include rotating equipment, high
velocities in pipework or flow-lines, and

Issued May 2021 https://forum.xpertopinions.com

PFP is sometimes applied as a sprayed conservation insulation was originally


intumescent coating and therefore specified to minimise the demand on
forms part of the equipment or pipework heat exchangers and associated
corrosion protection. Such applications heating medium systems. Examples of
typically char and expand into a layer of where insulation removal may be
thermal insulation when exposed to considered include:
intense heat and do not contribute to
CUI. • Increasing water-cut in late life
offshore operations often lead to
PFP can also be applied as a system of increased process temperatures and
flexible and removable mats which are therefore a reduced need for
wrapped and secured around piping stabilisation heat. Furthermore,
components, including valves, actuators heating medium systems can often
and instrument connections. Such accommodate the extra heating
systems if fitted poorly can on the other required to make up for the removal of
hand contribute to CUI. insulation.

The specification of PFP is normally • Originally over-specified process


established as part of a formal safety heaters and exchangers such that
assessment for a major accident hazard there is considerable overcapacity in
site. Removal can be considered but process heat which can therefore
only after careful assessment of the accommodate relatively minor losses
hazards which the PFP was originally following the removal of pipe
intended to mitigate. Considerations insulation.
include:
• Reducing superheat for offshore gas
• Changes in operating conditions and turbines, as fuel gas becomes
parameters, such as reduced increasingly lean in late life assets.
hydrocarbon inventories, operating Depending on the operating
pressures and composition. conditions, this can mean the dew
point moves such that the required
• Retirement or decommissioning of superheat is closer to atmospheric
adjacent processing facilities which temperatures, therefore removing the
reduce or eliminate an escalation need for heat conservation.
path.

(c) Heat Conservation


Pipework with heat conservation
insulation can be reviewed to determine
the effect of insulation removal,
particularly if there has been a change
in operating conditions. The option to
provide additional process heat to
compensate for heat loss can also be
considered, particularly where heat Image courtesy of Thermal Supports

Issued May 2021 https://forum.xpertopinions.com

If unable to justify the full removal of (e) Anti-Condensation


insulation for heat conservation
purposes, the limited use of wire mesh Application of insulation is often
cages may provide a useful alternative, required to inhibit the condensation of
particularly for pipework operating in moisture on the surface of the pipework
excess of 70°C, (see Personal from the atmosphere. In such cases, the
Protection). Such cages might be insulation is designed to be maintained
installed around piping components above the water dew point temperature
which are otherwise difficult to insulate which in turn prevents condensation.
and fully seal against water ingress,
such as valves. The insulation will prevent moisture
from subsequently falling onto electrical
equipment, walkways, or normally
( d ) L o w Te m p e r a t u r e occupied areas where it could form a
Conservation nuisance or a hazard.

Low temperature or cryogenic The main purpose of an insulation


applications are often found in review would be to ensure that
refrigeration systems and furthermore insulation is only installed where
gas systems where pressure has been dripping condensation or ice build-up
reduced through a turbo-expander or a might form an operational or personnel
Joule-Thompson (JT) valve. hazard.

In such cases, the insulation is typically


intended to provide low temperature
conservation as part of the process
design. The insulation will also prevent
the build-up of ice on exposed sections
of pipework and process equipment,
potentially resulting in structural
damage and furthermore creating an
operational hazard by impeding access
to small bore pipe-work and instrument
fittings.

Clearly, the removal of insulation in


such circumstances does not provide a
benefit. Furthermore, the CUI threat is
also much decreased at low
temperatures, though this would be on
the basis that the plant is not subject to
intermittent or cyclic operation.

Issued May 2021 https://forum.xpertopinions.com

Considerations when assessing the and also provide heat or cold


removal of anti-condensation insulation conservation. Care should therefore
include: be exercised to ensure that such
additional functionality is not impaired
• Small quantities of water falling onto a as a consequence of removing the
walkway already exposed to the insulation.
weather may probably not constitute
an additional nuisance or operational • Where justified, personnel protection
hazard. should be provided by wire mesh
cages as opposed to insulation to
• Changes to walkway routings might eliminate the CUI threat. It may be
mean that anti–condensation possible to replace limited amounts of
insulation is no longer required in insulation with mesh cages around
certain areas. certain piping components such as
valves which are difficult to insulate
effectively and without impairing the
(f) Personal Protection heat conservation requirements of the
process.
Personnel protection is used on lines
that have operating temperatures either • Where insulation has been removed
below -10°C or above 70°C, [Ref. 3]. from either hot or cold lines which are
The purpose is to protect personnel located away from normal working
from heat or frost burns. Application areas, it would be appropriate to
should be restricted to areas which are provide labelling to warn personnel of
typically less than 2.1m vertically and the possible hazard.
0.8m horizontally from any walkway,
thoroughfare, ladder or normal working
area, [Ref. 3].

As previously noted, high temperature


pipework is often associated with
heating medium systems and gas
compressor discharges whereas cold
temperature pipework might be found in
refrigeration systems and cryogenic
applications.

Protection is not necessarily required


outside such areas on the basis that
appropriate permit controls may be put
in place to prevent contact with
pipework and process equipment.

Some additional considerations include:


Image courtesy of Thermal Supports
• Insulation installed for personnel
protection may often be dual purpose

Issued May 2021 https://forum.xpertopinions.com

• Blowdown lines require careful The requirement for insulation can often
consideration as these only be avoided with appropriate mitigating
experience low temperatures during measures in place, such as the
transient conditions. Blowdown pipe- following:
work also tends to be found in
inaccessible locations. • Pipework and equipment is drained
down when not in use, inclusive of
any dead-legs;
(g) Winterisation • A minimum flow rate is maintained in
lines with the potential to freeze, such
Winterisation insulation is applied to
as a firewater ring main;
prevent freezing or crystallisation of
fluids in pipework caused by low
• The use of circulating solutions such
ambient temperatures. Equipment
as 30% TEG plus water as a cooling
holding static fluids for periods of time
medium in a closed system.
without being adequately drained may
also require winterisation.
When considering winterisation
insulation criteria, the lowest ambient
Equipment and pipework is often
temperature is usually described as the
insulated, with or without heat tracing,
lowest daily temperature after rejection
when the following conditions occur at
of the lowest 1% of daily temperatures
the lowest ambient temperature:
in the year. For the UKCS, this is
generally taken to be -7°C.
• Flow rates are such that fluids may fall
Winterisation should only be applied to
below the pour point or freezing point.
external lines where the temperature
can realistically fall towards such
• Undesirable phase separation,
temperatures.
deposition of crystals or hydrate
formation may occur.
The winterisation of seawater lines
requires additional consideration. At
• Fluid viscosity is so high that it is not
typical salinity, stagnant seawater starts
possible, with the available pressure,
to freeze at -2°C. The water will freeze
to establish an adequate flow rate.
from the inner surface of the pipe
towards the centre, leaving the inner
• Moisture which may be introduced
core with increasing salinity and a
during a transient condition is below
correspondingly lower freezing
freezing point. Areas where such
temperature. By -7°C, the seawater will
moisture may collect may cause a
still be less than 85% frozen by weight.
blockage, such as flare lines, small
bore instrument lines and PSV pilot
Judgement is therefore required when
lines.
assessing seawater lines. Insulation on
dead-legs, small bore lines (say less
• Rapid cooling of surfaces by snow, ice
than 4 inch NB), instrument tubing and
or hail could cause condensation
impulse lines in exposed areas may
leading to a partial vacuum or
need to be maintained, whereas a case
undesirable reverse flow.

Issued May 2021 https://forum.xpertopinions.com

for the removal of insulation from larger In Summary


bore pipework in sheltered areas or
within a module can be made. The article provides a number of
considerations for the systematic
The criticality of the service should also challenge of insulation on process
be considered, such as the requirement equipment and piping systems. The
for instantaneous flow from say a objective is to justify the ongoing
firewater ring-main versus the gradual requirement for insulation and reduce
start-up of a seawater cooling system. the use of insulation to the extent
possible along without the ongoing
Winterisation insulation is an area effort required to manage the CUI
where significant removal is possible. threat. Process conditions continually
Each winterised line should be evolve as an asset matures across its
considered individually and carefully design life. This may be because of
and balanced against the corrosion changing feedstock, throughput or
threat which very often outweighs the composition.
potential for freezing.
Finally, the figures quoted within this
article are based on current industry
Insulation Review Process standards and it is always important to
refer back and cross-check against any
A systematic and prioritised approach to company standards which may
challenge and justify insulation supersede industry standards.
requirements needs to be adopted. This
can either be applied as a single and
periodic study which considers all the Further Reading and
insulation requirements across a facility References
or on a rolling basis as each corrosion
circuit is considered ahead of a planned 1. Energy Institute: Guidelines for the
CUI inspection. Attachment 1 provides a Design, Installation and Management
simple flowchart which summarises this of Thermal Insulation Systems
process.
2. H e a l t h a n d S a f e t y E x e c u t i v e :
Appropriate multi-discipline input using Controlling Noise at Work
a management of change procedure Regulations 2005
should be adopted in the challenge
process, as it is often the case that the 3. Norsok Standard R-004: Piping and
insulation has been installed for more Equipment Insulation
than one reason. For instance, heat
conservation and personal protection
combined.

Issued May 2021 https://forum.xpertopinions.com

Attachment 1: Insulation Review Process

Issued May 2021 https://forum.xpertopinions.com



Ar cle peer reviewed by Yunnan Gao. With over 24 years experience in
materials, metallurgy, corrosion and asset integrity, Yunnan holds a PhD in
materials science, is a chartered engineer and chartered scien st, a fellow of the
IMMM and ICorr as well as a NACE cer ed corrosion specialist.

Issued May 2021 https://forum.xpertopinions.com


ti
ti
fi
ti

You might also like