Tugas Process Engineering Summer School (PESS) 2021 - Heat Exchanger Optimization: Bapak Zulfan Adi Putra (ZAP) Nama Wahyu Rinaldi Nomer 238
Tugas Process Engineering Summer School (PESS) 2021 - Heat Exchanger Optimization: Bapak Zulfan Adi Putra (ZAP) Nama Wahyu Rinaldi Nomer 238
Tugas
Data
Supplay
Ts 170 °C Tt 80 °C
Fs 500 kg/hr
Cps 1 kJ/kg °C
Objective Function :
Cost : (aA^0,84)R+Fw*C*Op
Where :
A = Q/ (U*LMTD) Fw = Q / (Cpw*{Tw,t-Tw,s})
LMTD = (dT1 - dT2) / (In{dT1/dT2})
dT1 = Tt - Tw,s
dT2 = Ts - Tw,t
Assume :
a R C Q Op U
1000000 0.1 0.01 45000 8000 3600
dollars/kg kJ/hr op. hours (kJ/hr)/m2 °C
Kesimpulan
Sehingga, untuk mendapatkan cost paling
Plotting Tw,t against Cost Fw
120000 Tw,t
100000
90000
80000
70000
60000
80000
70000
60000
50000
40000
30000
20000
10000
0
20 40 60 80 100 120 140 160 180
Cost
hanger Optimization : Bapak Zulfan Adi Putra (ZAP)
Supplay Target
170 °C 80 °C
Ts Tt
dT2 = Ts - Tw,t
2
J/hr)/m °C Target
Tw,t
Fw Cost
1071.4286 $104,924.72 Maximal Cost
714.2857 $76,705.03
535.7143 $62,789.64
428.5714 $54,608.85
357.1429 $49,307.50
306.1224 $45,663.32
267.8571 $43,066.66
238.0952 $41,180.37
214.2857 $39,803.85
194.8052 $38,811.31
178.5714 $38,120.99
164.8352 $37,678.73
153.0612 $37,448.66
142.8571 $37,407.86 Minamal Cost
133.9286 $37,543.28
126.0504 $37,850.04
119.0476 $38,553.45
112.7820 $38,996.69
107.1429 $39,867.58
102.0408 $40,976.32
97.4026 $42,373.68
93.1677 $44,138.84
89.2857 $46,399.78
85.7143 $49,377.31
82.4176 $53,494.74
79.3651 $59,719.61