Professional Documents
Culture Documents
QCP - Piping Press Test 11
QCP - Piping Press Test 11
LEGEND
QCP No.: Rev No.: 1
Main Contractor: CITIC Project No.: KMC-KKP-21-2145 W = Witness 1. Critical
Sub-Contractor: WHCC Enquiry: AS PER CONTRACT S = Surveillance ASME B31.3 Process Piping 2. Major X
DRA-0571-PV-DC-0600-Rev2-Piping and Valve Design
INTERVENTION
Scope: PIPING Order/Scope Reference: NA R = Review Specification: 3. Minor
Criteria (003)
Description: PRESSURE TESTING Sub-Contractor Order No: NA V = Verify Applicable SANS Standard ; ISO 9001:2018 4. Other
2268-25-WG-G2-138/143/238/243
Piping Line Number: 2268-100-WG-G2-136/174/141/193/236/274/241/293 P&ID DRW Number: KAM-PID-226801-01031/01032 A = Action WBS Area: 226081 FILTER HOUSE
2268-200-WG-G2-139/142/239/242
1. APPROVALS
2.1 Inspect the system to verify that openings are plugged and valves are closed. W V S S
If no leaks are detected, begin to increase pressure with the test pump up to
2.10 200 psi or 50 psi in excess of the static pressure when static pressure exceeds W V S S
150 psi.
Monitor the test gauge to determine that the system pressure is stable. If
2.11 pressure drops, check for leaks in the system, for open valves, or for leaks in W V S S
the test apparatus.
Once it is determined that the test pressure has stabilized, disconnect the
2.12 power to the test pump and notify the commissioning agent or authority having H W S S
jurisdiction that the 2-hour test period has begun.
LEGEND
QCP No.: Rev No.: 1
Main Contractor: CITIC Project No.: KMC-KKP-21-2145 W = Witness 1. Critical
Sub-Contractor: WHCC Enquiry: AS PER CONTRACT S = Surveillance ASME B31.3 Process Piping 2. Major X
DRA-0571-PV-DC-0600-Rev2-Piping and Valve Design
INTERVENTION
Scope: PIPING Order/Scope Reference: NA R = Review Specification: 3. Minor
Criteria (003)
Description: PRESSURE TESTING Sub-Contractor Order No: NA V = Verify Applicable SANS Standard ; ISO 9001:2018 4. Other
2268-25-WG-G2-138/143/238/243
Piping Line Number: 2268-100-WG-G2-136/174/141/193/236/274/241/293 P&ID DRW Number: KAM-PID-226801-01031/01032 A = Action WBS Area: 226081 FILTER HOUSE
2268-200-WG-G2-139/142/239/242
2.13 Record the time of day and test pressure at this time. W V S S
After the test, open the drain valve to drain the system, or, if the system is to
2.16 be commissioned immediately, relieve the test pressure and leave the water in W V S S
the system.
Disconnect the test pump and plug the outlet or test port through which the
2.17 W V S S
system was tested.
3. HANDOVER - DOCUMENTATION
Approvals
A point of inspection in the QCP that requires the presence of the inspection organization:-
H - where the next stage of the production/construction process cannot proceed beyond this point until an inspection has been performed by the inspection organization and the required conditions indicated as met/achieved.
W - where production can proceed beyond this point if the inspection organization has not attended, provided due notice of the activity has been given to the inspection organization in terms of the relevant contract.
S - where surveillance may be performed by the inspection organization.
R - where a review of the records developed by the supplier to ensure that the relevant activity has been performed satisfactory and that contractual requirements have been met.
V - where a verification by the inspection organization to ensure that the relevant activity has been performed satisfactory and that contractual requirements have been met.
A - where the organization needs to execute an operation prior to intervention and inspection.