Aug. 16 2021 Grand Forks Public Schools Referendum Presentation
Aug. 16 2021 Grand Forks Public Schools Referendum Presentation
Aug. 16 2021 Grand Forks Public Schools Referendum Presentation
Schools
10 mill Referendum
District Statistics
99 Projects @ $52M
● Replace skylight over commons
● Repair exterior of pool addition, provide vapor barrier
● Remove/redesign skylights over gymnasium addition
● Repair exterior granite steps on 1st, 4th, and City Hall
facades
● Provide exterior secure entryway
● Repair main elevator
● Replace interior carpet throughout academic building
● Replace existing fire alarm system, add notification
system
Red River High School
56 projects @ $32.5M
● Replace 1993 and 1967 AHUs in large gym, autos, wood shop, and pool
areas
● Provide secure entryway and update counselors offices and commons
● Replace fire alarm system (add notification system)
● Replace hallway carpets w/solid surface
● Replace curb and gutter on Knudsvig Drive
● Repair Cushman field, track, and grandstand
South Middle School
52 Projects at $21.4M
● Repair EFIS over gym, penthouses, and
cafetorium
● Provide secure entryway
● Replace classroom carpets
● Provide upgrades to drop-off and pick-up
lanes
● Renovate pod hallways to become learning
spaces; 6, 7, and 8 grade wings
Elroy Schroeder Middle School
58 Projects @ $20.7M
● Provide secure entryway, counselor/office areas, and Career and
Technical Education (CTE) space
● Replace HVAC
● Remodel restrooms to provide ADA access
● Replace electrical systems
● Replace roof
● Renovate locker rooms
● Provide appropriate Special Ed Spaces
Valley Middle School