Professional Documents
Culture Documents
Residential Calculation
Residential Calculation
Residential Calculation
FACULTY OF ENGINEERING
Signature: ______________
Signature………………………………
Signature………………………………..
V. ABSTRACT / SUMMERY
Civil engineering deals with planning, design and construction of
various structures like buildings, bridges, towers, etc.
Based on this I prepared my first project which is three floors of
residential building with complete drawings, calculations and
specifications.
This project is specially focusing on residentiall part. And based on the
area of 252sqm, it also consists of 4 offices and one secratory room,
meeting room and three toilets in the ground floor.
The other floors consists of offices, one comfrences room and three
toilets in each of other floors
This project book is consist of eight chapters;
The first chapter contains general introduction about the project and
general guidelines of the project design.
The second part of the book will associate with drawings of the project,
including the sections, elevations and other detailed figures like utility
supply details. This chapter may be the most important part of the
project. It deals with architectural engineering part. I used both
AutoCAD and ArchiCAD drawings to present acceptable drawings
The third part is the structural Calculation of the project which
contains the design of the structural members like columns, flat slabs,
Staircase beams, staircases and Mat Foundation based on limit state
serviceability method.
The fourth chapter is concrete design mix design. We will discuss how
to make tests of the concrete and which one is acceptable in our design
members.
The next chapter which is the fifth one will discuss about the
specifications of the material used in the construction. After this we will
look at the cost estimation of the building, which will be discussed in the
sixth chapter if Allah says.
And then the scheduling which is in chapter seven & and at the end the
contract and agreements of construction will be the last chapter of the
project which is chapter Eight.
The project is possible for execution in 99.9%, for the checked my
supervisor and his final comment was extremely valuable and highly
improved the projects safety.
ABBREVIATION LETTERS
No Abreviation Extension
The project title is School Building Project implement By: Awale Contraction Company
Eng. Yahye Ahmed as servicer
This Residential building is constructed in (Hargeisa) city of Somaliland district (Sheikh
Madar ) . Residential building Area:
This project is about construction of a residential and it is the first project I ever prepared,
but not the later. This Residential is only a Ground, First and second floor.
1.2 GENERAL
The basics needs of human existences are food, clothing‟s & shelter. From times
immemorial man has been making efforts in improving their standard of living. The
point of his efforts has been to provide an economic and efficient shelter. The
possession of shelter besides being a basic, used, gives a feeling of security,
responsibility and shown the social status of man.
Every human being has an inherent liking for a peaceful environment needed for his pleasant
living, this object is achieved by having a place of living situated at the safe and convenient
location, such a place for comfortable and pleasant living requires considered and kept in view.
• A Peaceful environment.
• Safety from all natural source & climate conditions.
• General facilities for community of his residential area.
The engineer has to keep in mind the municipal conditions, building bye laws, environment,
financial capacity, water supply, sewage arrangement, provision of future, aeration,
ventilation etc., in suggestion a particular type of plan to any client.
Civil engineering deals with planning, design and construction of various structures like
buildings, bridges, towers, etc.
Based on this I prepared my first project which is four floors of mall building with complete
drawings, calculations and specification
This project contains eight chapters, including drawings, structural designs, design mix and
specification of the project
The first chapter contains general introduction about the project and general guidelines of the
project design.
The second part of the book will associate with drawings of the project, including the section
elevations and other detailed figures like utility supply details. This chapter may be the most
important part of the project. It deals with architectural engineering part.
The third part is the structural designing of the project which contains the design of the
structural members like columns, slabs, beams, staircases and footings based on limit state
method.
The fourth chapter is concrete design mix design. We will discuss how to make tests of the
concrete and which one is acceptable in our design members.
The next chapter which is the fifth one will discuss about the specifications of the material
used in the construction. After this we will look at the cost estimation of the building, which
will be discussed in the sixth chapter if Allah says. And then the scheduling and at the end the
contract and agreements of construction which will be the last chapter of the project
1.1; - THE REFERENCE STANDARD (IS CODE)
This project is based on Indian Standard PLAIN AND REINFORCED CONCRETE CODE
OF PRACTICE (THE FOURTH REVISION) which is denoted by IS 456 2000. In this
standard it has been recommended that the minimum grade of concrete shall be not less than
M20 in reinforced concrete work (see clause 6.1.3 IS 456 2000). That is why I use M20 in all
of my calculations. IS 875 parts 1, 2 and 5 are also used in the load calculations. It may
contains also some other IS codes but no other codes other than IS codes are used in this
document.
With an appropriate degree of safety they should sustain all the loads and deformation
Of normal construction and use and have adequate durability and adequate resistance
To the effects of misuse and fire.
1.4; -METHODS OF DESIGN
The IS code has the following recommendation for the methods of designing:
Structure and structural elements shall normally be designed by limit state method. Account
should be taken of accepted theories, experiment and experience and the need to design for
durability. Calculations alone do not produce safe, serviceable and durable structures. Suitable
materials, quality control, adequate detailing and good supervision are equally important.
Where the limit state method cannot be conveniently adopted, working stress method (see
Annex B) may be used.
Limit state method is further improvement of ultimate load design. This method appeared to
be satisfactory and acceptable and was recommended by the codes of practice of many
countries. In the limit state method, a structure is designed to withstand all loads likely to act
on it in the duration of its life span and also to satisfy the serviceability requirements before
failure can occur. In other words the structure will not reach a limit state.
The structure in general shall be designed on the basis of the most critical limit state and shall
also be checked for other limit states.
The live loads on the buildings are considered to be uniformly distributed on the surface of
the structure, and they are also dynamic depending on the situation of the place. These are
also taken from IS 875 Revise
CHAPTER TWO
Architectural Drawings/Designs/
Plans
2.1 Introduction
An architectural drawing is a technical drawing of a building (or building project) that
falls within the definition of architecture. Architectural drawings are used by
architects and others for a number of purposes: to develop a design idea into a coherent
proposal, to communicate ideas and concepts, to convince clients of the merits of a design, to
enable a building contractor to construct it, as a record of the completed work, and to make a
record of a building that already exists.
This chapter will cover the architectural drawings and plans of the project. The
chapter contains all necessary plans and views of the building.
2.3 ELEVATIONS
The first five drawings are the elevation of the building (front, left, right and back sides
elevations and one of prospective view). The remaining parts of the chapter will cover the
plans of the building and sections.
CHAPTER THREE:
STRUCTURAL DESIGN
3.1 Introduction
Structural engineering deals with planning, design, and construction of structures, with one or
more than of the methods of designing. The concrete of the mixture of cement, sand, water
and aggregate in a certain proportion with steel bars by a known method is termed as
Reinforcement Cement Concrete. A reinforced concrete structures is one of the most useful
structures which are used in modern world. This is because of its durability and workability.
A SLAB is a plate element forming floors and roofs in buildings which normally carry unfirming
distributed loads. Slabs used in this project are two way slabs which contain three cases of the
different nine cases of the slabs. In the design the most critical one is designed. In this project,
one two way slab of case four with 6.x4.7 m is the critical one.
BEAMS: The beams in the project are considered to be simply supported beam. In the real
construction they are monolithic which are to be considered as continuous, but moment of the
simply supported beams is large than the moment of the continuous I use a simply supported
beam.
Given Data
L XO=4.7 m, LY =5 m
The allowable stresses and the design coefficient for a balanced section are:
F CK =20 MPA , F Y =415 MPA
j=0.80 , k=0.138
Live load W L =3 K N /m 2
Total load on the slab is:
KN
W t =W g +W L=3+3.75=6.75
M2
Design load
w c =1.5 ×6.75=10.125 N /M 2
(0.053−0.047)×(1.06−1.0)
α xn=0.047+
1.1−1.0
=0.051
α xp =¿0.035 for r=1.0
(0.040−0.035)×(1.06−1.0)
α xp =0.035+ =0.038
1.1−1.0
Effective depth:
mr 12146 Nm
d=
√ √kb f ck
=
0.138× 1 m×20
=66.3 let use d= 130 mm
Minimum Reinforcement
Asm= 0.12%bh, 0.12/100 x 1000 x 120 = 144mm2
live load =3 KN / m
Concrate grade f ck =20 MPa
Lo 4.94
bf= +bw +6 t = + 0.23+ 6 ( 0.15 )=1.95 m
6 6
b f =bw +12 t=0.23+12 ( 0.15 )=2.03 m
L 4.94
bf= = =1.64 m
3 3
Select the flange width as theleast of above ,
b f =1.64 m
A 1+ A 2 6.0025+6.0025
c /c = =2.45 C M 2
L 4.9
the
Let depth of the beam be takenas ,
all
L 4.94
h= = =0.24 mlet useh=0.45 m
20 18
h w =h−t=0.45−0.15=0.3 m
Effective Depth
m 120490 KN /M
d=0.5× 0.15+ = =0.13 m
0.45 ×bf ×t × fck 0.45× 1.64 ×0.15 × 20
h= 400-30-10=360
Design of reinforcement Area of reinforcement
The area of the tensile reinforcement is
1.15 M r 1.15 ×120490 N /m
Ast= f y ( d−0.5 t) = 2
415 N /mm (0.40 m−0.5× 0.15 m)
= 1027.3mm2
Ast(provide)¿1027.3/314¿3.27≈ 4
Use 4∅ 20
Ast provided ¿4×314¿1256¿ 1027.3
Provide 3 bars of ∅ 16 bars at top bars as hunger bars
Ast 3×314¿340mm
Percentage of steel ¿100×1256÷230×400¿1.32
∎ Design of shear ,
``
Given Data
L = 4.94
Wt=26.33
d=0.4
Thickness of the slab= 0.15 m
Effective flange bf = 1.64Fck= 20mpa, Fy=415mpa
Ast= 1256mm2asv=157mm2
h=0.45 ,bw=0.23 , hw= 0.3
w= 4.94x26.33= 130
Deflection loa d
C v W L3
Vf=
Ec I e
5
C v=
384
= 0.013
bf t 3 3
xu−t
I cr =
12
2
(
+b f t ( x u−0.5t ) +b w
3 )
1.64 × 0.153 3
I cr = +1.64 ×0.15 ( 0.192−0.5 x 0.15 ¿ ¿ ¿ )
12
+0.23 ¿ ¿
¿ 0.003963
w t l2 26.33(4.94 m) 2
M= = =80.3 kn
8 8
y c=¿The centroidal axis of the section¿ the bottom fibreis obtained by taking
hw t
bw hw (
+ )
2 2
y c =0.5 t +
bf t +bw hw
y c =0.5 × 0.15+
0.23× 0.30 ( 0.302 + 0.152 )
0.23 ×0.30+1.64 ×0.15
= 0.117
bf t 3 2
hw bw ×hw 3
I g=(
12
)+b f t
2 (
+t− yc +( )
12
)+¿
1.64 × 0153 2
0.30 0.23 × 0.303
I g= +1.64 × 0.15 (
+0.15−0.117 + ) + 0.23× 0.30 ¿ = 0.0132m
12 2 12
Then I cr =¿0.003936m
(C V W L3 )
Vf = E I
C E
(5.19¿¿ 3)
Vf =(0.0130)(130) 25491 X 10 6 x 0.003936 ¿ = 0.002355m
c cs l 2
v cs= h =it simply supported bea m
Rcs cs
0.65( p t− p c )
co =
√ pt
0.65( p t− p c ) 0.72(1.1−0.68)
co = = =0.29 ≈0.3
√ pt √ 1.1
h 0.36 m
Rcs = = =40000 mm
C o Ecs 0.30 ×0.0003
=0.000762 m+0.0025905m=0.0033525 m
Allowable Deflection
l 4.94
With-out wall= 250 = 250 =0.019m
p=wt ( l2 + l2 + l2 + l2 )
1 2 3 4
Assume wg=10kn
p=26.33 ( 5.22m + 5.22m + 2m2 + 4.92 m )+10 kn=237.8 kn
the multiply 3 Storey building
pd =3 ×237.8=713.4 kn
Design load
pd =α pa =1.5 ×713.4=1070.1
α =¿ Fsc/Fcc = 278/8 =34.4
The column size is fixed to fixed so we use this equation
l e =0.65 h=0.65 ×3 m=1.95 mb=0.23 m
l e 1.95 m
g= = =8.5<12 Short-column
b 0.23 m
sv ≤ 48 ∅ 6=48× 6=288 mm
I take sv =provide use ∅ 6 @Spacing of 230 mm
Xu = 0.479d L=4.94
Structural Design
w c l2 17.44 x 4.94 2
M c= = =53.2kn
8 8
Effective depth
mc 53200 N . m
d=
√ √
kb f ck
=
0.138× 0.4 m ×20 N /mm2
=0.25 = use d= 0.27
1
h=d +cover + =270 mm+20 mm+10=300 mm=0.3 m
2
L
V = w c( 2 - d)
4.94
V=17.44 KN ( 2 - 0.27) = 38.4kN
l1 l2 l3 l4
p=wt ( + + +
2 2 2 2 )
p=11.625 kn ( 5.22 m + 5.22m + 22m + 4.92m )=100.6 kN
Ps = load from the column + load from the ground beam
Ps= 713.4+100.6 = 814kn
Total load
p1 <¿pa
Structural design
B−a❑ 1.90 m−0.23 m
lm= = =0.84
2 2
ps 814 kN
Q= = =225.4 kn {m¿ 3
A ( 1.90 m )2
Mrb = m
B1 = 0.23 b2 = 1.90
K = 0.149 k2 = 0.025
m❑ ❑ 0.227
d=❑
√ 1.123
=
√
1.123
=0.45 use d=0.60 m
Peripheral shear
b 0=2 ( 0.23+0.60 ) +2 ( 0.45+0.60 ) =3.75 m
V =∝ Q ( B 2−( a❑ + d )2 ) =1.5 ×225.4 ( 1.90 2−( 0.23+0.60 )2 ) = 1021.06kn
(0.70−0.15)× 0.60
Hs = 0.70- 2 ×0.84
= 0.50
1
Ds = hs-cover- 2 ∅ = 500-50-10 = 440
v 1021.06
τ v= =
b0 d 3.75× 440
= 0.61
H0 = 0.15
1.902 x 0.232
Vf = 1.90*1.90*0.15+( 2
)*(0.50-0.15) = 0.57m3
Use ∅ 20
2237.3
N0,of bars = 314 = 7.12 use 8∅
solution
3
height of building is = 3 = 2 = 1.5
1.5
number of risers = 0.15 = 10
l 6 150
=
20 20
=0.3 then 300
=0.5
θ = tan−10.5= 24.70
1.5(0.3)25
Weight of the slab = cos 24.70 °
= 7KN/m
( 0.32 )( 0.9 )( 0.15)25
Weight of the steps = 2(0.32)
=2.687 KN/m
Total load wt
Wt= 7+2.687+2.3=11.99kn\m
Wc=αwt=1.5∗¿11.99=17.98kn\m
w cl 2 17.98× 5.22
M= 8
= 8
= 60.87KNm
M 60770
Mrb=mc=d= √ kb f ck
= √ 0.138× 1.8375× 20
= 99.24mm use d=150
design of reinforcement
1.15 M 1.15 ×109510
ast= jd x f y 0.8 ×0.22 m× 415 =1724.2
=
use =10∅ 12
ast(provided)= 10*113=1130
1837.5× 113
sv= 1130 =183.5 take 180
minimum reinforcement
=0.12% bh
0.12
= 100 ×1837.5 ×260 =573.3mm2
2 Beam
2.1 Main bars of the beam 7 ∅ 20
2.2 Hungers 2 ∅ 20
3 Column
3.1 Column bars 8 ∅ 18
3.2 Ties of the column ∅6 200 mm
4 Footing
4.1 Main bars of the
footing ∅ 18
10
X-direction 10 ∅ 18
Y-direction
5 Ground beam
5.1 Main bars of the 6 ∅ 16
ground beam
5.2 Hanger bars 2 ∅ 16
6 Stair case
6.1 Main bars of the stair 8 ∅ 12 100 mm
case
6.2 Distribution bars ∅ 12 220 mm
CHAPTER FIVE
GENERAL SPECIFICATIONS
The excavation will generally refer to open excavation of foundation (including basement if
necessary) .The Contractor shall visit and ascertain the nature of the ground to be excavated
and the work to be done and shall accept all responsibility for the cost of the work involved
either less or more money either had or easy.
Excavation shall include removal of all materials of whatever nature at all depths and
whether wet or dry necessary for the construction of foundation and sub-structure exactly in
accordance with the drawings or as directed by the reprehensive Engineer.
Should the Contractor excavate to a greater depth of width than shown on the drawing or as
directed by the representative engineer, he shall at his own expense fill the extra depth or width
with cement concrete in proportion as directed by the repetitive engineer but in no case with
concrete of mix leaner than 1:4:8 cement concrete.
Excavated Materials suitable and useful for backfilling, plinth filling or leveling of the plot or
other use shall be stacked in convenient places but not in such a way as to obstruct free
movement of men, animals and vehicles or encroach on the area required for constructional
purposes.
All space between foundation masonry or concrete and the sides of excavation shall be refilled to
the original surface with approved excavated materials, watered and rammed. The filling shall be
done after concrete or masonry is fully set and done in such a way as not to cause undue thrust
on any part of the structure.
All excavated material certified as surplus and not useful shall be removed by the Contractor
from the site in an approved manner to his own dump at his own cost.
5.2 Excavation:- Foundation trenches shall be dug out to the exact width of foundation
concrete and the sides shall be vertical. If the soil is not good and does not permit vertical sides,
the sides should be sloped back or protected with timber shoring.
5.3 Finish of trench: -the bottom of foundation trenches shall be perfectly leveled both
longitudinally and transversely and the sides of the trench shall be dressed perfectly vertical from
the bottom up to the least thickness of loose concrete so that concrete may be laid to the exact
width as per design.
5.4Water
Mixing water should be clean and free from oil, acid, iron or rust (which may cause staining),
and
Injurious amounts of vegetable matter, alkalis, or other salts. Almost any natural water that is
drinkable and has no pronounced taste or odor is satisfactory. Warm water may tend to cause
false set or shorten the working time of the mix. Chilled water or use of ice may retard the set or
make mixing more difficult.
5.5 Water in Foundation: -Water, if any accumulates in the trench, should be bailed or
pumped out without any extra payment and necessary precautions shall be taken to prevent
surface water to enter into the trench.
Materials – Aggregate shall be o invert materials and should be clean, dense, hard, sound,
durable, non – absorbent and capable of developing good bond with mortar.
Coarse aggregate shall be of hard broken stone of granite or similar stone, free from dust, dirt
and other foreign matters. The stone ballast shall be 20mm size and down and all should be
retained in a 5mm square mesh and well graded such that the voids do not exceed 42 percent.
Fine aggregate shall be of coarse sand consisting of hard, sharp and angular grains and shall pass
through screen of 5mm square mesh.
Cement shall be fresh Portland cement of standard I.S.I. Specifications, and shall have the
required tensile and compressive stresses and finesses.
Water shall be clean and free from alkaline and acid matters and suitable for drinking purpose,
Fine aggregate shall be of coarse sand consisting of hard, sharp and angular grains and shall pass
through screen of 5mm square mesh. Sand shall not be used. (Fine aggregate may also be of
crushed stone if specified).
Cement shall be fresh Portland cement of standard I.S.I. specifications, and shall have the
required tensile and compressive stresses and fineness.
Water shall be clean and free from alkaline and acid matters and suitable for drinking purposes.
5.8 Proportion: The proportion of concrete shall be 1:1.5:3 as cement: sand: stone: ballast by
volume unless otherwise specified. Minimum compressive strength of concrete of 1:2:4
proportions shall be 140 Kg per sq cm (200-lbs/sq in) on 7days.Stone aggregate and sand shall
be measured by volume with boxes. Cement need not be measured by box, one bag of cement
(50Kg) should be considered as 1/30cu m. Size of measured box may be 30cmx38cm. All
material shall be dry.
5.9 Random rubble stone masonry:-
The stone shall be hard, sound and durable of approved quarry. Stone shall be hammer dressed to
secure close joint so that the stones when laid will come into close proximity.
Stones shall be fairly equal in size and every stone shall be fitted to the adjacent stones. No stone
shall be less than 15 cm in size. Stone with round surface shall not be used.
Face stone shall be comparatively larger and uniform in size and color to give a good appearance
and breadth of face stones shall be greater than the height. Face stone should tail into wall to a
sufficient depth to bond well. Stones shall be laid with broader face downward to give good
bedding. Face joints shall be broken and face of wall shall be truly in plumb. Corner stone of
quoins should be a good stone and dressed to correct angle and laid as headers and stretchers.
Mortar shall be 1: 3. Mortar shall be first dry mixed to have the required proportion and then
mixed with water by adding water slowly and gradually and mixed thoroughly to get a uniform
mortar of workable consistency.
All the stones shall be thoroughly wetted before laying. Every course of stone shall be hammer
dressed and laid truly horizontal and every vertical joint shall be truly vertical. Faces shall be
accurately squared and each face joint shall be dressed at right angles. The face stones shall be -
laid in alternate headers and stretchers fashion. The masonry shall be carried up regularly and
true to plumb. The thickness of joints shall not exceed 12mm
The joints of the brickwork shall be raked out to a depth of 18 mm and the surface of the wall
shall be washed and kept wet for two days before plastering.
The materials of mortar, cement, and sand or lime should be standard specifications, the
materials or mortar shall be first dry mixed, by measuring with boxes to have the required
proportion, and then water added slowly and gradually and mixed thoroughly.
The thickness of plastering should be 12mm applied in two coats. To ensure uniform thickness of
plaster, patches of 15cm x15cm strips 1m apart shall be applied. First mortar shall be dashed and
pressed over the surface and then brought to a true smooth and uniform surface by means of float
and trowel.
External plastering shall be started from top worked down towards floor.
Internal plastering shall be started wherever the building frame is ready and centering of the roof
slabs have been removed, Ceiling plastering shall be completed before starting of wall plaster.
All corners and edges shall be rounded. The plastered surface shall be kept wet for 10 days.
The surface should be protected from rain, sun, frost, etc
5.1.7 Proportion :
Fresh white lime slacked at site of work should be mixed with sufficient water to make a thin
cream. The approximate quantity of water required in making the cream is 5 litter of water to 1
kg of lime. It shall the be screened through a coarse cloth an gum in the proportion of 100 grams
of gum to 16 litre of wash shall be added. The surface should be dry and thoroughly cleaned
from dust and dirt. The wash shall be applied with a jute brush, vertically and horizontally
alternately and the wash kept stirred in the container while using.
One coat shall be applied.
Colour wash shall be prepared with fresh slaked white lime mixed with water to make thin cream
adding the colours pigment to the required quantity to give the required tint. Gum in the
proportion of 100gm of gum to 16litres of wash shall be added, the colour wash should be
applied one coats. The method of application should be same as for white washing.
5.2.0 Distempering:
The distemper shall be of best quality and the colour should be as specified. The distemper
should be mixed and prepared and water added, as laid down in the instructions of the
manufacturer.
First a paste is made by adding little hot water to the distemper powder and stirred thoroughly,
and the paste is allowed to stand for a few minutes, the paste is then thoroughly, and the paste is
allowed to stand for a few minutes, the paste is then thinned with water to have a thin cream to
the consistency of oil paint and stirred thoroughly all the time while applying. If the surface is
rough, it should be smoothened with sand paper.
The surface must be perfectly dry before distempering is commenced, In new cement plaster the
surface shall be washed over with a solution of zinc sulphate, one kg zinc sulphate in 10litres of
water and then allowed to dry. In old surface, the surface shall be repaired with plaster of Paris
where required and then whole surface sand papered and washed and allowed to dry. One coat
should be applied. The distemper shall be kept well stirred in containers and shall be applied
with broad brushes first horizontally and immediately crossed vertically. Brushing should not be
continued too long to avoid brush marks.
5.2.1 Plain Cement Concrete (PCC )
Materials Specifications
Aggregate: shall be of invert materials and should be clean, dense, hard, sound, durable, non-
absorbent and capable of developing good bond with mortar.
Coarse aggregate: shall be of hard broken stone of granite or similar stone, free from dust,
dirt and other foreign matters. The stone ballast shall be of 20mm size and smaller. All the coarse
material should be retained in a 5mm square mesh and should be well graded such that the voids
do not exceed 42%.
Fine aggregate: shall be of coarse sand consisting of hard, sharp and angular grains and shall
pass through a screen of 5mm square mesh. Sand shall be of standard specifications, clean and
free from dust, dirt and organic matter. Sea sand shall not be used.
Cement shall be fresh Portland cement of standard ISI specifications and
shall have the required tensile and compressive stresses and fineness.
Water shall be clean and free from alkaline and acid matters and suitable for drinking purposes.
1:1.5:3 (cement: sand: stone ballast) by volume when specified. Minimum compressive strength
of concrete of 1:2:4 proportions shall be 140 kg/cm2 in 7 days.
Hand mixing:
Mixing shall be done on masonry platform or sheet iron tray.
Machine mixing:
Stone ballast, sand and cement shall be put into cement concrete mixer to have the required
proportions.
Slump:
Regular slump test should be carried out to control the addition of water and to maintain the
required consistency. A slump of 7.5cm to 10cm may be allowed for building work.
5.2.3 Formwork:
Formwork centering and shuttering shall be provided as required as per the standard
specification before lying concrete to confine to support or to keep the concrete in position. The
inner surface of shuttering shall be oiled to prevent concrete sticking to it.
5.2.4 Laying Technique:
Concrete shall be laid gently (not thrown) in layers not exceeding 15cm and compacted by
pinning with rods and tamping with wooden tampers or with mechanical vibrating machine until
a dense concrete is obtained.
5.2.5 Curing Method:
After about two hours of lying of concrete, when the concrete has begun to harden, it shall be
kept damp by covering with wet gunny bags or wet sand for 24 hours.
5.2.6 RCC Specification:
Shuttering shall be done using seasoned wooden boards of thickness not less than 30mm.
Surface contact with concrete shall be free from adhering grout, nails, splits and other
defects.
All the joints are perfectly closed and lined up.
The shuttering and framing is sufficiently braced.
Nowadays timber shuttering is replaced by steel plates.
All the props of approved sizes are supported on double wedges and when taken out,
these wedges are eased and not knocked out.
The entire framework is removed after 21 days of curing without any shocks or
vibrations.
All reinforcement bars conform IS specifications and are free from rust, grease oil etc.
The steel grills are perfectly as per detailed specifications.
The covers to concrete are perfectly maintained as per code.
Bars of diameter beyond 25mm diameter are bent when red hot.
The materials proportion should be as per the specifications of the concrete.
For cement concrete of ratio 1:1:2(1 cement: 1 sand/coarse sand:2 graded stone
aggregate) require 11no bags of 50kg.
For cement concrete of ratio 1:1.5:3 require 7.8no bags of 50kg.
For cement concrete of ratio 1:2:4 require 6 no bags of 50kg.
For cement concrete of ratio 1:3:6 require 4.25no bags of 50kg.
For cement concrete of ratio 1:4:8 require 3.2 no bags of 50kg.
For cement concrete of ratio 1:5:10 require 2.50 no bags of 50kg.
For cement concrete of ratio 1:6:12 require 2.25 no bags of 50kg.
5.2.7 AGGREGATES:
The fine aggregate-sand shall be hard, strong, dense durable, clean with uncoated grains. The
sand shall not contain any harmful material such as iron pyrites, coal, mica, silt clay, alkaline,
sea shells, organic impurities, loam etc. or in case reinforced concrete work, any material which
might attack the reinforcement or which might be detrimental to concrete
Coarse aggregate shall consist of hard, dense, durable, uncoated crushed rock. Gravel aggregate
shall be allowed to be used only if specially specified in the schedule of quantities. Otherwise, it
shall be taken that only crushed rock from an approved quarry as coarse aggregates the
aggregates shall not be from soft, thin or long laminated pieces.
Generally on reinforced concrete work, nominal maximum size of 20 mm is considered suitable.
3- R.C.C. of the super structure such as lintel (0.1x0.2m) column (0.3x0.5m) beam (0.2xo.2m),
Slab thickness (0.1m) and stair case are building R.C.C. and mixing concrete: 1:1.5:3
5.2.9 Formworks
The method and system of formwork shall be approved by the Engineer before construction
commences. Formwork shall be substantially and rigidly constructed of timber or steel or pre-
cast concrete or other approved material.
All timber for formwork shall be good, sound, clear sawn, well-seasoned timber, free from warps
and loose knots and of scantlings sufficiently strong for their purposes to the approval of the
Engineer
All formwork shall be removed without undue vibration or shock and without damage to the
concrete.
No formwork shall be removed without the prior consent of the Engineer and the minimum
periods that shall elapse between the placing of the concrete and subject to the concrete cube
strengths complying with the specification, the striking of the formwork and props will be as
follows:
Removal of formwork:
Beam sides, walls and columns 4 days
Slab soffits (props left under) 5 days
Beam soffits (props left under) 8 days
Removal of props:
Slabs 11 days
Beams 14 days
The above times may be reduced in certain circumstances, at the discretion of the
Engineer, provided an approved method is adopted at the Contractor’s expense to
ensure that the required concrete strength is attained before the forms are stripped.
5.3.0 Decoration:
Stucco and enamel paint for internal walls with lime wash and emulsion paint for ceiling and
external walls with three coats of walls and ceiling. White wash shall be prepared from lime, the
lime shall be dissolved in a tub with sufficient quantity of water (about 4/5 liters/Kg. of lime) and
the whole thoroughly mixed and stirred until it attains the consistency of the cream.
The surface shall be prepared by removing all mortar dropping and foreign matter and
thoroughly cleaned with hair or fiber brush or other means as may be ordered by the client
Engineer to produce an approved clean and an even surface.
All internal doors (1.2mX2.1m) of the mahogany wooden door with fixing frames of good
quality, small doors (0.8x2.1m).
All windows and hand rail of stair case are Aluminum and glass, aluminum framed windows
with mosquito net and steel.
main windows must be Aluminum glass with (1.2mx1.5m) dimensions. While toiletes window
(0.8mx0.8m)
The timber shall be of the best quality, well-seasoned and free from sap, knots, warps, cracks,
and other defects. All wood work shall be planed, and neatly and truly finished to the exact
dimensions, all joints shall be neat and strong, truly and accurately fitted, and glued before fitted
together.
Shuttering shall be either of hard wooden planking 30mm thick. The shuttering shall be
supported on battens, beams, props and wedges and properly cross braced together so as to make
the form work sufficiently rigid strong and stable to support the wet concrete work and should
not yield on working and laying concrete. Beams for centering shall be carried and supported on
the walls with double wedges underneath and supported at intervals with props.
Props shall be consist of ballies or brick pillars in mud mortar.
The Shuttering shall be kept clear of wall bearing and made to rest on cross-beams or battens.
The shuttering shall have smooth and even surface and its joints shall be closed tight and shall
not permit leakage of cement mortar, if required the joints shall be lined with craft paper or other
approved material.
Centering and shuttering shall not be removed before 14 days in general (4 days for R.C.C.
columns, 10 days for roof slab and 14 days for beams).
All reinforcement shall be free from loose mill scale or rust, grease, paint or other substances
likely to reduce the bond between the steel and concrete.
Reinforcement shall be accurately bent to the shapes and dimensions as 10 cm to bend for hooks.
During concreting a competent steel fixer must be in attendance to adjust and correct the position
of any reinforcement which may be displaced. The vibrators are not to come into contact with
the reinforcement
The stone shall be hard, sharp-edged and shall not be less than 20cm in diameter.
Stones shall be laid with cement mortar embedded in between the stones with joints not
less than 5mm and not exceed 15mm.
Cement used for mortar shall be Ordinary Portland Cement.
Sand shall be fine and free from foreign matters.
The cement: sand ratio shall be 1:4.
The finished surface shall be leveled both longitudinally and transversely.
Form work shall be rigid construction true to shape and dimensions specified in the bill
of quantities. It shall be strong enough to withstand the forces caused by ramming and
vibrations of concrete.
Cement and sand shall be the same as those in the construction of the foundation wall.
The coarse aggregate (gravel) shall be crushed or broken the hard stone. It shall be clean
and free from foreign matter. The size of the coarse aggregate shall 20mm grade down
and shall be retained in a 5mm square mesh.
The reinforcement bars shall be twisted type and should be free from rust, dust, oil, paint,
or other coatings which may destroy or reduce the bond.
The cement: sand: aggregate ratio shall be 1:2:4.
The quantity of water to be used for each bag of cement shall not be more than 35 liters
(5 buckets).
The top reinforcement bars of the tie beam shall be two in number with diameter of
10mm. minimum and the bottom bars shall be two in number with diameter of 12mm.
The reinforcement bars of the lintel are the same as those in the tie beams.
The stirrups shall be 8mm diameter and their spacing shall be 20cm center to center and
shall not exceed 25cm c/c.
All reinforcement bars shall be bent at both ends to make good bond to the concrete. And
the hook shall not be less than 4(diameter).
CHAPTER EIGHT
Contract and contract Agreement
Ref: AHA 00333 Date: ----- /02/2018
CONSTRUCTION OF EDUCATIONAL BUILDING
Dear Sir/Madam
We would like to submit you, the Drawings, Technical specifications, Bill of quantities,
Work Program Schedule and all Technical conditions for the above-mentioned works.
If you offer the contract to us as consultant, we assure you to carry out, perform, and
maintain the whole of that works accordingly.
If you require any further information, kindly contact us.
Thanks in advance for selecting us to carry out the preliminary survey, prepare the
drawing, bill of quantities, cost estimation, and specifications regarding to the
construction of the above mentioned building.
Yours sincerely,
Eng: Mohamed Ahmed Awale
Construction of Institute project
Content
Ref: GOLLIS/200/2015 Date:
----/_____/2015
1. Company’s letter
2. Drawing
3. Structural analysis
7. Form of contract.
8. Technical specification.
CONSTRUCTION OF EDUCATIONA BUILDING
Form of Contract
Dear Sir/Madam
I undersigned, have examined the general conditions of the proposed construction Site,
and carried out Preliminary survey, Drawings, Bill of Quantities for the above-mentioned
works.
We are accepting to perform, complete, and maintain the whole of the said works in
Conformity with the above-mentioned documents for the following sums.
FIXED PRICE (inclusive of all taxes) of proposed construction of
($ + 2% of Government taxation = $264962.974+5299.26=( $270262.234)
I also undertake to complete and deliver the whole of the said works within the Period of
(18 months) after possession of the site & receive the first Installment of the Project Cost.
Yours sincerely,
Eng: Nour farah mohamoud
NAME OF CONTRACTOR: MAANSO CONSTRUCTION AND
CONTRACTING COMPANY
(Contractor) (Employer)
_______________________ __________________
Payment Procedure
Total Cost of the Whole Project is: $ …264962.974…….
1st Installment 50%-------------132481.487------------------------- USD
9. References
ReinforcedConcreteStructuresI (IndianCode).
ReinforcedConcreteStructuresII(Indian Code).