Septic Tank
1 Excavation 3 2 3 CUM 18 20 $ 360.00
2 Construction Hallow Blocks 10 3 SQM 30 22 $ 660.00
3 Cover Slap 3 2 0.2 CUM 1.2 300 $ 360.00
Sub Total 2 $ 1,380.00