San Pablo, Joseph Sil (14-0015-b)

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

MPW FORM 77-004-1

CERTIFICATE OF COMPLETION

THE BUILDING OFFICIAL


AREA CODE NO. 03027

THIS IS TO CERTIFY THAT THE CONSTRUCTION OF THE BUILDING COVERED BY THE


BUILDING PERMIT NO. 14-0015-B ISSUED ON JANUARY 15, 2014 HAS BEEN COMPLETED IN
ACCORDANCE WITH THE APPROVED PLANS AND SPECIFICATIONS ON FILE WITH THE
OFFICE OF THE BUILDING OFFICIAL AND THE “NATIONAL BUILDING CODE” (PD 1096).

THAT THE SAID BUILDING AND/OR STRUCTURE IS READY FOR FINAL INSPECTION FOR
THE ISSUANCE OF THE “CERTIFICATE OF OCCUPANCY”.

NAME OF OWNER: SAN PABLO JOSEPH SIL T.


(Last Name) (First Name) (Middle Name)
ADDRESS OF OWNER :BUENAVISTA, STA. MARIA, BULACAN
LOCATION OF CONSTRUCTION : SAN VICENTE, STA. MARIA, BULACAN
USE OR TYPE OF OCCUPANCY : GASOLINE STATION
DATE OF CONSTRUCTION
PROPOSED: JANUARY 2014 ACTUAL:
DATE OF COMPLETION
EXPECTED: JUNE 2014 ACTUAL:
NO. OF STORIES: ONE ACTUAL HEIGHT: 7.50M
ESTIMATED COST P: 1,003,752.80 ACTUAL COST P: 1,124,265.00
(For Statistical Purposes Only)

A.) MATERIALS (TOTAL COST) P: 786,985.00

1. CEMENT (bags): 225


2. LUMBER (board foot):580
3. REINFORCING BARS (kg.): 1760
4. NO. OF G.I. SHEETS: 45
5. PRE-FAB STRUCTURAL STEEL (kg.):1800

B.) DIRECT LABOR (TOTAL COST) P: 337,279.00


This includes compensation whether by salary or contract for project architect/engineer down to laborers.

C.) RENTAL OF EQUIPMENT (IF ANY): 60,000.00

D.) OTHER COSTS P: 50,000.00


This includes professional fees, permits and other fees.

IF CONSTRUCTION IS UNDERTAKEN BY CONTRACT

JOSEPH SIL T. SAN PABLO


ARCHITECT/CIVIL ENGINEER CONTRACTOR
PRC: PRC REG. NO. _________CLASS___
PTR: TIN ______________CTC __________
DATE ISSUED: ADDRESS _______________________

CONFORME:

________________________
OWNER/APPLICANT

You might also like