FRL Lagos State Multi-Agency Complex Building

Weekly Progress Report

FRL
Date: 06/08/2021 Job No:

Week 31 Report No: 1

WEEKLY PROGRESS REPORT Location: ALAUSA, IKEJA LAGOS STATE

Project Title: LAGOS STATE MULTI AGENCY OFFICE COMPLEX ALAUSA

Contractor: MC&T

Sub-Contractor:

Project Duration: Commencement Date: Completion Date:

Overall Project Status to Date:

Work Weeks Completed to Date: Work Weeks Left to completion:

On Track Off Track Delayed


LEGEND:

DISTRIBUTION LIST

Contacts Name Phone No Email

The Special Adviser


Perm Secretary
Dir. Architectural Services
Dir. Mechanical Services
Dir. Electrical Services
MD Metrol Fittings & Acc.
MD MC&T
MD Palmyra

SUMMARY OF WEEKLY WORK PROGRESS WEEK __31

ITEMS PROJECT ACTIVITIES AVERAGE TOTAL % PROGRESS

1 Mobilization 90%
2 Demolition & Alteration 30%

3 Wet Works 10%

4 Dry Works 0%

5 External Works 0%

6 Commissioning & Handover 0%

Issues/Delays/Disruptions
1 Resolution of HVAC system
2 Production, coordination and approval of construction drawings
3 Submission of construction methodologyy, work plan, HSE and Quality plan
4 Delay in sample room set-up

1
FRL Lagos State Multi-Agency Complex Building
Weekly Progress Report

WORK DESCRIPTION & PROGRESS REPORT

WORK PROGRESS

ITEM DESCRIPTION OF ITEM Start Date Due Date % Achieved Status Remarks

A ______________ PROJECT

A1 MOBILIZATION -
Kick-off Meeting 100% Completed

Safety Induction
Set up site office, store, deploy equipments
100% Completed
machines etc
A2 DEMOLITION & ALTERATION (Ground - Pent floor)
Remove existing marked out areas - floor
tiles, walls, windows, door frames, slab 90% Ongoing
coring, curtain walls etc
Set out revised plan 95% Ongoing

A3 WET FINISHES
All blockwall and lintels 85% Ongoing

Install door/window subframes 90%

1st/2nd fix MEP and VRF AC pipworks 0%

Internal plastering 1%
Wall tiling
Floor tiling/toilet floor felting

Floor surface & expansion joint


treatment/felting - (Parking & Terrace areas)

External Plastering
A4 DRY FINISHES
Install Windows
Suspended Modular ceiling grids
Aluminium/Metal works
Doors
1st coat internal painting
MEP/AC fittings & accessories
Suspended Modular ceiling tiles
Panel glass Partitioning
Final coats internal painting, signages &
Furnitures
Lift works
A5 EXTERNAL WORKS
External Painting

Emergency Stair Exit

A6 COMMISSIONING/HANDOVER

External Painting

Cleaning, Testing etc

2
FRL Lagos State Multi-Agency Complex Building
Weekly Progress Report

WORK PROGRESS PICTURES

PIC 1. SHOWING BLOCKWALL IN PROGRESS PIC 2. SHOWING IN ALTERATIONS

PIC 3. SHOWING LINTEL INSTALLATION PIC 4. SHOWING BLOCKWALL IN PROGRESS

PIC 5. SHOWING TILE REMOVAL PIC 6. SHOWING WALL SETTING OUT

3
FRL Lagos State Multi-Agency Complex Building
Weekly Progress Report

PIC 7. SHOWING SAMPLE BASIN, SINK & FLOOR TILES PIC 8. SHOWING SAMPLE FLOOR & WALL TILES

PIC 9. SHOWING SAMPLE MEP FITTINGS PIC 10. SHOWING SAMPLE URINAL & WC

PIC 11. SHOWING SAMPLE OFFICE DOORS PIC 12. SHOWING SAMPLE OFFICE DOORS