National Highways of Infrastructure

Development Corporation Ltd


Consultancy Services for preparation of Detailed Project Report and
providing pre-construction activities Construction of 2-laning with hard
shoulder configuration of Chhumkhum to Tlabung from Design
Chainage Km 40.000 to Km 80.638 of NH-302 in the State of Mizoram
under ‘Bharatmala Pariyojana’ on EPC Mode

VOLUME – III: MATERIALS REPORT

Detailed Project Report


JULY - 2020

CM ENGINEERING & SOLUTION


Engineering, Planning and Project Management
House No. –1473A, Maruti Vihar, Gurgaon, Haryana – 122002, Tel – 0124 –4255138/9811406386
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Table of Contents
CHAPTER 1 SOIL, MATERIAL AND GEO-TECHNICAL INVESTIGATION -------------------------------------------------------- 2
1.1. MATERIALS REPORT: ---------------------------------------------------------------------------------------------------------- 2
1.1.1. Soil Classification -------------------------------------------------------------------------------------------------------- 3
1.1.2. Investigation on Sub Grade ------------------------------------------------------------------------------------------- 5
1.1.3. Quarry Material-------------------------------------------------------------------------------------------------------- 11
1.1.4. Investigation of Water Tables-------------------------------------------------------------------------------------- 15
1.2. GEOLOGY AND SOIL---------------------------------------------------------------------------------------------------------- 15
1.2.1. Seismicity ---------------------------------------------------------------------------------------------------------------- 17
1.3. METHODS OF INVESTIGATION -------------------------------------------------------------------------------------------- 17
1.3.1. General ------------------------------------------------------------------------------------------------------------------- 17
1.3.2. Drilling -------------------------------------------------------------------------------------------------------------------- 18
1.3.3. Standard Penetration Test ------------------------------------------------------------------------------------------ 18
1.3.4. Sampling ----------------------------------------------------------------------------------------------------------------- 18
1.3.5. Water Table Observation-------------------------------------------------------------------------------------------- 19
1.3.6. Laboratory Investigation -------------------------------------------------------------------------------------------- 19
1.4. RESULTS OF INVESTIGATION ---------------------------------------------------------------------------------------------- 19
1.4.1. General ------------------------------------------------------------------------------------------------------------------- 19
Annexure – Bore log Sheet

1
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Chapter 1 SOIL, MATERIAL AND GEO-TECHNICAL


INVESTIGATION
1.1. MATERIALS REPORT:
Introduction
This chapter covers the details of test and investigation carried out for evaluating the
characteristics of the sub-grade along the project corridor to establish the basis for the
design of various elements of the road including pavement and sub grade,
embankment and structures.
The main task carried out for soil and material investigation includes:
 Collection and Review of available soil data from various division of
Mizoram
 Soil classification along the proposed road
 Investigation of sub grade soil
 Investigation of construction material including identification and inspection
of potential source of construction material and extraction sites; testing and
evaluating of construction material for suitability for project road
construction.
 Geo-technical investigation for bridges and other structures.
 Pit test for foundation of structures
Investigations
The detailed investigations include both field and laboratory testing. Field work
covered field density test, sub-grade soil sampling by excavating test pits,
identification of rock sources and soil borrow sources/ quarries within reasonable
short haulage distances of the project road. Test pits were also excavated wherever
necessary to obtain samples for testing.
Appropriate laboratory tests were carried out on the representative samples of the
soil and material obtained during field investigations to determine relevant
engineering properties.
Standard Test Procedures
The following standard test procedures were followed for field testing, soil sampling
and laboratory testing:

S. No Type of Test Method


1 Field density using Sand Replacement method IS:2720 Part 28

2 Water Content IS: 2720 Part 2

3 Atterberg limits IS: 2720 Part 5

4 Sieve Analysis

(a) Natural Soil IS: 2720 Part 4

(b) Rock aggregate IS: 2386 Part 1

2
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

5 Heavy Compaction Test IS: 2720 Part 8

6 CBR IS: 2720 Part 16

7 Soundness by Sodium Sulphate (Na2So4) IS: 2386 Part 5

8 Aggregate Impact Value IS: 2386 Part 4

9 Specific Gravity and Water Absorption of Coarse IS: 2386 Part 3


Aggregate

Notations
CBR : California Bearing Ratio
LL : Liquid Limit
PL : Plastic Limit
PI : Plasticity Index
NP : Non – Plastic
MDD : Maximum Dry Density
OMC : Optimum Moisture Content
FMC : Field Moisture Content
FDD : Field Dry Density
DCP : Dynamic Cone Penetration

1.1.1. Soil Classification


In case of hill road, the soil classification of the hill face (hill/ valley side) plays an
important part.
Soil classifications consist of the following:
 Ordinary Soil
 Soft Rock
 Hard Rock
The classification is mostly done visually. The classification is tabulated as follows:
Chainage Classification of Soil in %
Sr.
Ordinary Ordinary Hard Soil Classification Remarks
No. To From
soil rock rock
1 0.0 1.0 52.0 45.0 3.0 Soil Mixed Boulder NH-54A
2 1.0 2.0 54.0 42.0 4.0 Soil Mixed Boulder NH-54A
3 2.0 3.0 50.0 45.0 5.0 Soil Mixed Boulder NH-54A
4 3.0 4.0 52.0 43.0 5.0 Soil Mixed Boulder NH-54A
5 4.0 5.0 30.0 50.0 20.0 Soil Mixed Boulder NH-54A
6 5.0 6.0 60.5 38.0 1.5 Soil Mixed Boulder NH-54A
7 6.0 7.0 43.0 45.0 12.0 Soil Mixed Boulder NH-302
8 7.0 8.0 33.0 47.0 20.0 Soil Mixed Boulder NH-302
9 8.0 9.0 40.0 45.0 15.0 Soil Mixed Boulder NH-302
10 9.0 10.0 39.0 46.0 15.0 Soil Mixed Boulder NH-302

3
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Chainage Classification of Soil in %


Sr.
Ordinary Ordinary Hard Soil Classification Remarks
No. To From
soil rock rock
11 10.0 11.0 55.8 42.5 1.7 Soil Mixed Boulder NH-302
12 11.0 12.0 55.6 42.2 2.2 Soil Mixed Boulder NH-302
13 12.0 13.0 52.0 45.5 2.5 Soil Mixed Boulder NH-302
14 13.0 14.0 51.0 45.5 3.5 Soil Mixed Boulder NH-302
15 14.0 15.0 55.9 42.0 2.1 Soil Mixed Boulder NH-302
16 15.0 16.0 54.1 44.0 1.9 Soil Mixed Boulder NH-302
17 16.0 17.0 54.4 43.5 2.1 Soil Mixed Boulder NH-302
18 17.0 18.0 52.0 44.0 4.0 Soil Mixed Boulder NH-302
19 18.0 19.0 53.0 43.0 4.0 Soil Mixed Boulder NH-302
20 19.0 20.0 58.0 39.5 2.5 Soil Mixed Boulder NH-302
21 20.0 21.0 60.9 37.0 2.1 Soil Mixed Boulder NH-302
22 21.0 22.0 57.3 40.0 2.7 Soil Mixed Boulder NH-302
23 22.0 23.0 68.0 30.0 2.0 Soil Mixed Boulder NH-302
24 23.0 24.0 62.0 35.0 3.0 Soil Mixed Boulder NH-302
25 24.0 25.0 60.2 37.0 2.8 Soil Mixed Boulder NH-302
26 25.0 26.0 58.5 40.0 1.5 Soil Mixed Boulder NH-302
27 26.0 27.0 55.9 42.0 2.1 Soil Mixed Boulder NH-302
28 27.0 28.0 57.0 40.0 3.0 Soil Mixed Boulder NH-302
29 28.0 29.0 62.5 35.0 2.5 Soil Mixed Boulder NH-302
30 29.0 30.0 58.1 40.0 1.9 Soil Mixed Boulder NH-302
31 30.0 31.0 62.5 35.0 2.5 Soil Mixed Boulder NH-302
32 31.0 32.0 61.0 37.0 2.0 Soil Mixed Boulder NH-302
33 32.0 33.0 62.5 36.0 1.5 Soil Mixed Boulder NH-302
34 33.0 34.0 59.8 38.0 2.2 Soil Mixed Boulder NH-302
35 34.0 35.0 64.5 34.0 1.5 Soil Mixed Boulder NH-302
36 35.0 36.0 65.2 33.0 1.8 Soil Mixed Boulder NH-302
37 36.0 37.0 61.0 35.0 4.0 Soil Mixed Boulder NH-302
38 37.0 38.0 62.2 36.0 1.8 Soil Mixed Boulder NH-302
39 38.0 39.0 60.9 37.0 2.1 Soil Mixed Boulder NH-302
40 39.0 40.0 59.6 38.0 2.4 Soil Mixed Boulder NH-302
41 40.0 41.0 52.0 40.0 8.0 Soil Mixed Boulder NH-302
42 41.0 42.0 56.9 41.0 2.1 Soil Mixed Boulder NH-302
43 42.0 43.0 48.0 44.0 8.0 Soil Mixed Boulder NH-302
44 43.0 44.0 52.0 45.0 3.0 Soil Mixed Boulder NH-302
45 44.0 45.0 54.0 44.0 2.0 Soil Mixed Boulder NH-302
46 45.0 46.0 55.0 44.0 1.0 Soil Mixed Boulder NH-302
47 46.0 47.0 63.0 32.0 5.0 Soil Mixed Boulder NH-302
48 47.0 48.0 56.0 40.0 4.0 Soil Mixed Boulder NH-302
49 48.0 49.0 54.0 41.0 5.0 Soil Mixed Boulder NH-302
50 49.0 50.0 52.0 44.0 4.0 Soil Mixed Boulder NH-302
51 50.0 51.0 52.0 45.0 3.0 Soil Mixed Boulder NH-302
52 51.0 52.0 51.0 44.0 5.0 Soil Mixed Boulder NH-302

4
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Chainage Classification of Soil in %


Sr.
Ordinary Ordinary Hard Soil Classification Remarks
No. To From
soil rock rock
53 52.0 53.0 53.0 44.0 3.0 Soil Mixed Boulder NH-302
54 53.0 54.0 52.0 44.0 4.0 Soil Mixed Boulder NH-302
55 54.0 55.0 52.0 45.0 3.0 Soil Mixed Boulder NH-302
56 55.0 56.0 52.0 44.0 4.0 Soil Mixed Boulder NH-302
57 56.0 57.0 52.0 45.0 3.0 Soil Mixed Boulder NH-302
58 57.0 58.0 50.0 42.0 8.0 Soil Mixed Boulder NH-302
59 58.0 59.0 51.0 44.0 5.0 Soil Mixed Boulder NH-302
60 59.0 60.0 51.0 43.0 6.0 Soil Mixed Boulder NH-302
61 60.0 61.0 52.0 43.0 5.0 Soil Mixed Boulder NH-302
62 61.0 62.0 51.0 42.0 7.0 Soil Mixed Boulder NH-302
63 62.0 63.0 51.0 43.0 6.0 Soil Mixed Boulder NH-302
64 63.0 64.0 53.0 44.0 3.0 Soil Mixed Boulder NH-302
65 64.0 65.0 53.0 45.0 2.0 Soil Mixed Boulder NH-302
66 65.0 66.0 52.0 44.0 4.0 Soil Mixed Boulder NH-302
67 66.0 67.0 50.0 42.0 8.0 Soil Mixed Boulder NH-302
68 67.0 68.0 52.0 43.0 5.0 Soil Mixed Boulder NH-302
69 68.0 69.0 51.0 44.0 5.0 Soil Mixed Boulder NH-302
70 69.0 70.0 51.0 43.0 6.0 Soil Mixed Boulder NH-302
71 70.0 71.0 51.0 43.0 6.0 Soil Mixed Boulder NH-302
72 71.0 72.0 51.0 43.0 6.0 Soil Mixed Boulder NH-302
73 72.0 73.0 50.0 43.0 7.0 Soil Mixed Boulder NH-302
74 73.0 74.0 52.0 43.0 5.0 Soil Mixed Boulder NH-302
75 74.0 75.0 52.0 45.0 3.0 Soil Mixed Boulder NH-302

1.1.2. Investigation on Sub Grade


The following laboratory tests were conducted on samples of soils below the road
level.
 Grain Size Analysis
 Liquid Limit
 Plastic Limit
 Maximum Dry Density
 CBR Test on 4 days soaked samples.
The results of the above field and laboratory investigations for various test
pits are reported in the following:

5
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Result of Laboratory Test of Soil


Existing Chainage
Sieve analysis:% by weight passing Atterberg Limits CBR
Road Max.Dry
OMC 2.50m
Name 100 63 22 6.30 4.75 2.00 600 300 75 Density 5.0mm
Liquid Plastic Plasticity % m
From To mm mm mm mm mm mm mic mic mic (g/cc) penetr
Limit Limit Index penetr
sieve sieve sieve sieve sieve sieve sieve sieve sieve ation
ation
NH54A 0+000 0+500 100 98.7 90.0 74.2 57.7 47.7 29.6 16.5 10.9 33.48 19.85 13.63 1.82 11.73 7.68 7.01
NH54A 0+500 1+000 100 98.8 87.5 71.8 63.0 35.1 20.7 11.2 8.2 32.62 19.27 13.35 1.83 10.60 8.41 7.22
NH54A 1+000 1+500 100 96.7 86.0 65.1 57.7 44.7 26.9 16.7 11.6 33.18 18.31 14.87 1.79 13.40 5.93 5.12
NH54A 1+500 2+000 100 96.3 88.0 71.1 58.0 40.9 27.4 15.8 10.3 32.30 20.26 12.04 1.73 12.98 6.18 6.53
NH54A 2+000 2+500 100 100.0 93.2 75.4 68.1 38.2 21.8 12.3 6.8 30.25 18.33 11.92 1.82 10.43 9.25 8.10
NH54A 2+500 3+000 100 96.4 89.0 80.0 64.8 39.9 26.0 13.7 5.5 31.16 18.78 12.38 1.82 13.00 10.55 10.26
NH54A 3+000 3+500 100 98.8 88.8 74.4 58.9 36.9 23.2 15.2 6.9 33.92 20.39 13.53 1.80 11.58 8.20 7.45
NH54A 3+500 4+000 100 98.3 85.3 69.5 50.1 27.6 19.0 11.7 10.7 32.15 19.33 12.82 1.89 10.80 6.40 6.10
NH54A 4+000 4+500 100 97.9 89.0 75.5 59.9 34.7 20.9 11.9 4.7 29.54 19.37 10.17 1.85 10.40 11.30 11.24
NH54A 4+500 5+000 100 99.2 88.4 78.3 58.3 37.8 18.2 10.7 5.1 31.28 18.79 12.49 1.88 10.00 10.99 11.10
NH54A 5+000 5+500 100 98.6 88.3 74.8 63.3 39.9 25.0 11.8 5.8 32.92 20.82 12.10 1.96 10.58 9.84 9.11
NH54A 5+500 6+000 100 97.9 87.9 74.9 64.0 40.8 28.1 16.7 10.4 32.10 20.89 11.21 1.75 13.16 6.60 6.35
NH54A 6+000 6+500 100 96.6 88.4 74.3 63.2 34.9 20.4 11.7 7.1 33.06 19.52 13.54 1.83 10.05 8.38 8.47
NH302 0+000 1+000 100 96.4 81.9 65.8 50.5 36.3 22.4 10.7 6.8 26.71 15.61 11.10 1.88 10.42 10.36 10.26
NH302 1+000 2+000 100 97.5 80.9 55.3 38.1 28.8 17.3 9.8 5.6 29.58 20.38 9.20 1.90 9.20 12.04 12.22
NH302 2+000 3+000 100 96.0 79.5 65.0 50.9 36.9 23.2 10.4 4.1 31.64 18.11 13.53 1.92 9.00 13.09 12.91
NH302 3+000 4+000 100 97.7 86.0 77.5 65.7 44.8 25.8 14.2 8.5 32.28 17.44 14.84 1.90 8.10 13.51 13.61
NH302 4+000 5+000 100 98.2 85.4 61.3 51.3 39.3 23.0 15.2 7.9 30.27 18.73 11.54 1.88 10.80 9.74 9.42
NH302 5+000 6+000 100 95.8 82.2 55.3 41.7 32.3 21.5 12.1 7.0 28.19 20.07 8.12 1.94 8.94 13.51 12.64
NH302 6+000 7+000 100 96.3 81.8 60.2 50.6 40.5 21.8 12.5 6.2 31.09 18.64 12.45 1.87 9.20 9.11 8.86
NH302 7+000 8+000 100 98.6 79.3 53.7 44.0 32.8 19.4 9.9 5.9 28.46 19.17 9.29 1.96 7.70 14.55 13.89
NH302 8+000 9+000 100 96.4 82.1 59.8 49.9 38.0 21.7 9.9 6.4 31.12 19.10 12.02 1.97 8.80 14.34 14.22
NH302 9+000 10+000 100 95.5 82.2 67.3 53.9 40.9 23.4 12.3 7.8 30.95 19.55 11.40 1.92 9.52 13.30 12.63
NH302 10+000 11+000 100 96.2 81.3 61.1 52.2 39.8 22.9 13.1 6.6 31.17 19.06 12.11 1.94 8.80 14.34 13.47
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Result of Laboratory Test of Soil


Existing Chainage
Sieve analysis:% by weight passing Atterberg Limits CBR
Road Max.Dry
OMC 2.50m
Name 100 63 22 6.30 4.75 2.00 600 300 75 Density 5.0mm
Liquid Plastic Plasticity % m
From To mm mm mm mm mm mm mic mic mic (g/cc) penetr
Limit Limit Index penetr
sieve sieve sieve sieve sieve sieve sieve sieve sieve ation
ation
NH302 11+000 12+000 100 99.0 83.1 59.3 46.4 36.4 22.8 12.3 8.5 28.48 19.13 9.35 1.84 9.10 9.53 9.00
NH302 12+000 13+000 100 96.6 79.5 62.0 50.3 34.5 22.4 11.4 7.3 30.84 19.66 11.18 1.89 10.80 12.46 11.66
NH302 13+000 14+000 100 98.5 80.1 63.8 51.4 32.2 22.2 14.3 8.9 31.08 18.59 12.49 1.93 8.40 13.72 12.22
NH302 14+000 15+000 100 96.0 80.2 66.8 50.2 36.3 24.0 12.5 7.1 30.90 19.12 11.78 1.93 10.40 11.41 11.38
NH302 15+000 16+000 100 99.2 81.0 60.9 47.6 38.5 23.3 12.2 8.3 29.94 20.53 9.41 1.88 9.10 11.20 11.24
NH302 16+000 17+000 100 97.4 78.3 57.4 47.1 37.0 21.6 12.1 8.2 30.54 20.10 10.44 1.91 8.00 12.04 11.24
NH302 17+000 18+000 100 97.3 77.0 62.1 44.6 30.8 23.3 12.4 7.4 29.32 19.50 9.82 1.92 9.86 13.30 13.89
NH302 18+000 19+000 100 98.2 79.3 64.7 49.2 30.4 17.9 9.9 5.3 28.83 17.18 11.65 1.95 9.05 15.18 14.17
NH302 19+000 20+000 100 97.0 80.2 62.8 50.2 34.1 22.7 12.6 8.1 30.74 18.22 12.52 1.88 9.10 11.20 11.24
NH302 20+000 21+000 100 97.1 78.3 62.4 51.0 34.8 23.7 14.0 7.9 31.90 18.10 13.80 1.92 10.40 12.88 12.22
NH302 21+000 22+000 100 97.1 81.1 64.3 51.3 36.2 25.2 13.1 6.3 31.72 18.42 13.30 1.93 8.80 11.83 12.08
NH302 22+000 23+000 100 96.6 80.9 65.7 50.0 35.3 22.1 12.4 8.2 31.94 18.85 13.09 1.91 8.40 12.04 11.94
NH302 23+000 24+000 100 97.5 78.8 62.4 46.7 34.0 23.2 13.4 8.1 29.67 19.05 10.62 1.93 9.55 12.67 12.36
NH302 24+000 25+000 100 100.0 84.6 65.9 49.3 35.4 22.9 14.2 7.6 31.15 17.05 14.10 1.95 8.40 11.41 11.94
NH302 25+000 26+000 100 98.0 81.9 65.2 49.7 35.5 21.8 13.8 7.7 31.12 18.76 12.36 1.91 9.20 10.57 9.98
NH302 26+000 27+000 100 97.2 81.5 66.2 49.0 33.6 18.9 10.0 6.0 30.32 17.57 12.75 1.90 8.41 10.58 10.54
NH302 27+000 28+000 100 94.2 77.9 62.8 47.3 32.7 21.3 13.9 6.9 28.90 19.76 9.14 1.87 9.46 10.36 10.26
NH302 28+000 29+000 100 98.1 83.3 68.1 53.3 37.2 23.3 13.3 7.2 31.74 18.17 13.57 1.85 10.25 9.95 10.26
NH302 29+000 30+000 100 95.8 88.9 69.4 46.0 29.5 19.2 11.2 6.6 29.67 20.48 9.19 1.90 10.00 11.62 11.10
NH302 30+000 31+000 100 100.0 88.8 68.8 45.7 29.2 17.8 10.7 5.2 28.68 20.59 8.09 1.90 10.30 11.41 11.24
NH302 31+000 32+000 100 96.4 81.9 65.8 50.5 36.3 22.4 10.7 6.8 26.71 15.61 11.10 1.88 10.42 10.36 10.26
NH302 32+000 33+000 100 96.4 82.2 68.2 50.6 37.4 23.7 10.6 6.6 32.27 20.40 11.87 1.95 8.25 14.14 13.47
NH302 33+000 34+000 100 89.2 75.4 54.3 37.6 27.8 20.8 11.4 7.0 26.38 15.74 10.64 1.76 12.00 7.63 8.10
NH302 34+000 35+000 100 90.0 85.5 66.7 47.3 30.6 24.6 15.0 4.7 26.69 17.56 9.13 1.79 13.10 8.68 8.67
NH302 35+000 36+000 100 89.0 80.9 60.5 39.1 24.4 21.7 13.7 9.8 30.95 18.41 12.55 1.87 10.65 11.21 11.38
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Result of Laboratory Test of Soil


Existing Chainage
Sieve analysis:% by weight passing Atterberg Limits CBR
Road Max.Dry
OMC 2.50m
Name 100 63 22 6.30 4.75 2.00 600 300 75 Density 5.0mm
Liquid Plastic Plasticity % m
From To mm mm mm mm mm mm mic mic mic (g/cc) penetr
Limit Limit Index penetr
sieve sieve sieve sieve sieve sieve sieve sieve sieve ation
ation
NH302 36+000 37+000 100 87.9 77.4 69.7 59.2 40.3 28.7 15.7 9.5 27.19 15.70 11.49 1.91 9.32 12.82 12.56
NH302 37+000 38+000 100 88.5 76.3 68.7 54.9 28.0 25.1 16.6 12.9 29.27 18.65 10.62 1.94 9.48 13.85 14.01
NH302 38+000 39+000 100 85.2 73.0 48.8 30.7 22.3 15.4 5.0 2.9 25.85 17.52 8.33 1.97 10.70 14.61 15.26
NH302 39+000 40+000 100 86.9 73.2 51.9 43.1 33.6 24.5 14.2 7.2 27.98 16.78 11.21 1.93 9.55 13.10 12.75
NH302 40+000 41+000 100 89.2 82.6 75.5 66.8 46.1 35.4 18.3 11.8 31.41 17.59 13.82 1.93 10.50 12.35 12.00
NH302 41+000 42+000 100 87.3 81.6 73.4 64.5 42.2 31.9 17.4 11.8 34.75 19.32 15.43 1.88 9.84 10.46 10.43
NH302 42+000 43+000 100 86.7 78.1 67.4 55.4 37.5 26.7 14.5 9.4 30.11 17.85 12.27 1.84 8.80 8.96 9.36
NH302 43+000 44+000 100 87.1 77.4 62.7 56.3 38.1 28.3 17.4 10.2 27.39 14.78 12.61 1.92 11.70 13.38 13.76
NH302 44+000 45+000 100 89.1 79.6 65.2 53.6 32.3 24.8 13.1 8.1 28.76 18.43 10.32 1.91 9.65 13.19 13.32
NH302 45+000 46+000 100 86.5 73.1 58.9 38.8 30.6 28.5 13.0 5.0 24.77 16.76 8.01 1.96 10.58 14.99 15.26
NH302 46+000 47+000 100 88.7 79.8 71.6 59.8 42.4 34.2 16.1 9.1 28.17 16.88 11.29 1.93 10.00 12.91 13.27
NH302 47+000 48+000 100 87.1 75.3 64.8 58.1 38.6 26.2 13.4 7.4 27.81 17.21 10.60 1.91 10.20 12.26 12.56
NH302 48+000 49+000 100 89.2 79.0 67.4 58.3 44.1 33.0 17.7 13.3 30.58 17.70 12.88 1.84 11.60 9.70 9.23
NH302 49+000 50+000 100 88.5 78.3 72.2 60.9 39.6 30.7 17.7 13.4 29.42 17.49 11.93 1.82 11.80 11.21 11.37
NH302 50+000 51+000 100 88.7 79.7 72.2 63.9 37.5 29.6 16.8 12.0 33.60 19.17 14.43 1.89 12.40 9.51 9.23
NH302 51+000 52+000 100 89.1 81.6 69.8 55.9 36.7 27.8 15.9 10.7 32.18 18.49 13.69 1.87 9.00 10.84 10.94
NH302 52+000 53+000 100 88.8 75.1 63.1 51.8 26.4 19.8 10.5 7.6 27.67 16.06 11.61 1.85 12.50 9.33 9.23
NH302 53+000 54+000 100 89.1 79.6 68.3 61.0 39.2 27.3 16.5 9.7 31.44 18.52 12.92 1.78 13.60 8.01 7.98
NH302 54+000 55+000 100 89.0 80.8 69.2 62.0 39.0 33.8 20.4 12.8 29.80 17.42 12.38 1.82 10.36 8.77 8.79
NH302 55+000 56+000 100 88.3 77.1 65.5 54.2 36.3 28.4 17.6 10.6 28.99 16.79 12.20 1.78 11.60 9.71 9.23
NH302 56+000 57+000 100 88.8 79.2 70.7 59.2 39.0 26.3 15.5 9.6 32.35 18.36 13.99 1.77 13.54 7.73 7.79
NH302 57+000 58+000 100 90.0 83.0 70.4 55.4 36.1 28.1 18.4 11.1 28.04 17.47 10.57 1.75 13.70 7.82 7.48
NH302 58+000 59+000 100 88.9 79.9 67.0 53.0 33.3 25.8 16.9 8.5 33.44 18.50 14.95 1.83 10.82 11.12 11.31
NH302 59+000 60+000 100 88.8 81.2 67.4 52.0 33.5 25.1 15.2 10.8 30.48 17.26 13.22 1.80 12.25 10.37 10.18
NH302 60+000 61+000 100 88.1 80.1 67.9 53.9 34.2 29.6 21.4 13.5 35.03 19.31 15.71 1.80 12.40 8.11 8.30
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Result of Laboratory Test of Soil


Existing Chainage
Sieve analysis:% by weight passing Atterberg Limits CBR
Road Max.Dry
OMC 2.50m
Name 100 63 22 6.30 4.75 2.00 600 300 75 Density 5.0mm
Liquid Plastic Plasticity % m
From To mm mm mm mm mm mm mic mic mic (g/cc) penetr
Limit Limit Index penetr
sieve sieve sieve sieve sieve sieve sieve sieve sieve ation
ation
NH302 61+000 62+000 100 89.2 82.3 75.1 62.1 41.1 35.3 22.6 15.0 28.57 16.35 12.21 1.80 13.80 8.39 8.61
NH302 62+000 63+000 100 89.2 83.5 77.3 61.6 40.1 30.1 15.1 8.7 27.77 17.68 10.10 1.74 13.00 7.91 7.67
NH302 63+000 64+000 100 90.0 79.9 68.2 54.4 29.2 23.3 15.4 9.3 28.19 16.68 11.51 1.82 11.70 10.08 10.12
NH302 64+000 65+000 100 86.8 80.1 72.0 58.3 36.0 28.9 16.0 9.3 26.66 17.45 9.21 1.94 10.40 12.16 12.38
NH302 65+000 66+000 100 89.1 82.3 69.7 53.9 36.1 29.3 14.8 10.3 26.87 18.42 8.45 1.93 9.32 13.94 14.20
NH302 66+000 67+000 100 89.3 79.6 65.3 42.2 28.9 19.0 10.7 4.4 25.83 18.34 7.49 1.96 9.40 14.52 14.64
NH302 67+000 68+000 100 87.7 78.9 65.9 53.2 34.4 27.3 13.1 6.1 28.48 16.30 12.18 1.94 10.52 13.76 13.57
NH302 68+000 69+000 100 89.1 84.1 73.2 66.2 46.2 36.5 20.4 12.6 30.38 17.57 12.82 1.79 14.40 8.11 8.30
NH302 69+000 70+000 100 88.1 78.8 65.9 53.9 40.6 33.1 18.0 10.6 27.86 16.43 11.42 1.88 8.50 12.26 12.31
NH302 70+000 71+000 100 88.8 79.5 67.3 57.0 35.9 27.8 13.1 7.9 31.91 18.35 13.55 1.86 10.10 10.94 10.94
NH302 71+000 72+000 100 90.0 83.0 67.8 60.5 35.4 20.1 8.9 5.2 33.84 19.33 14.51 1.90 10.98 8.20 8.10
NH302 72+000 73+000 100 90.0 83.9 67.8 61.3 34.4 24.2 13.7 7.6 29.11 18.42 10.68 1.87 10.58 9.42 8.86
NH302 73+000 74+000 100 86.9 79.6 66.9 56.9 31.4 22.7 13.0 7.9 30.11 17.37 12.74 1.88 11.65 11.03 11.38
NH302 74+000 75+000 100 90.0 82.1 68.4 59.5 38.9 31.4 19.4 13.1 27.85 16.54 11.30 1.95 11.50 8.87 8.92
NH302 75+000 76+000 100 84.5 74.1 67.7 56.2 38.6 26.2 13.5 8.4 34.73 19.26 15.47 1.77 10.75 8.39 8.42
NH302 76+000 77+000 100 88.9 78.8 64.6 56.7 31.6 23.0 11.6 5.6 28.52 15.70 12.83 1.88 11.80 10.56 10.31
NH302 77+000 78+000 100 88.8 83.0 74.6 65.5 40.4 29.8 16.7 10.4 31.10 18.34 12.75 1.78 13.00 9.05 9.05
NH302 78+000 79+000 100 90.0 82.2 66.0 55.7 38.0 28.4 15.2 8.6 27.46 16.80 10.66 1.83 11.80 10.08 10.18
NH302 79+000 80+000 100 87.9 81.6 66.4 55.3 38.1 27.5 14.6 7.7 28.19 15.85 12.34 1.78 13.50 8.11 8.17
NH302 80+000 81+000 100 89.0 80.1 68.8 58.5 40.3 28.7 15.2 8.3 27.55 16.42 11.13 1.81 12.80 9.23 9.30
NH302 81+000 82+000 100 88.1 79.1 67.4 57.6 36.7 31.3 18.5 11.5 29.23 19.20 10.04 1.86 12.00 8.29 8.42
NH302 82+000 83+000 100 87.7 78.7 66.3 59.7 35.1 23.6 12.2 6.6 31.87 17.52 14.35 1.86 10.55 11.49 11.62
NH302 83+000 84+000 100 86.8 77.5 70.0 59.0 38.4 27.5 15.3 8.3 33.98 19.29 14.69 1.85 12.50 11.12 11.56
NH302 84+000 85+000 100 89.1 79.2 71.9 61.3 38.9 28.5 15.0 7.7 28.28 15.90 12.38 1.82 13.00 9.89 9.23
NH302 85+000 86+000 100 90.0 81.0 64.8 54.1 34.0 24.2 13.0 6.8 27.17 15.56 11.61 1.85 10.40 9.98 9.93
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Result of Laboratory Test of Soil


Existing Chainage
Sieve analysis:% by weight passing Atterberg Limits CBR
Road Max.Dry
OMC 2.50m
Name 100 63 22 6.30 4.75 2.00 600 300 75 Density 5.0mm
Liquid Plastic Plasticity % m
From To mm mm mm mm mm mm mic mic mic (g/cc) penetr
Limit Limit Index penetr
sieve sieve sieve sieve sieve sieve sieve sieve sieve ation
ation
NH302 86+000 87+000 100 88.3 77.8 68.7 59.3 38.6 29.0 16.1 10.6 26.24 16.89 9.34 1.90 8.90 11.88 12.63
NH302 87+000 88+000 100 89.2 81.3 64.8 58.4 40.1 29.0 18.1 11.1 27.66 17.62 10.04 1.96 10.20 13.95 13.45
NH302 88+000 89+000 100 88.1 73.7 55.2 35.9 23.0 13.7 5.7 2.3 25.93 17.65 8.28 1.94 8.75 14.14 14.08
NH302 89+000 90+000 100 90.0 82.0 68.2 59.6 32.2 26.5 17.5 9.0 26.75 17.36 9.39 1.93 9.20 13.19 13.19
NH302 90+000 91+000 100 88.4 76.1 69.6 60.4 29.2 25.5 11.6 7.4 27.80 16.79 11.01 1.92 10.00 12.16 12.25
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

1.1.3. Quarry Material


The rock deposits are available along or the vicinity of the project road alignment.
Besides, cobbles, pebbles and sand deposits are available in the rivers or streams
crossing the main alignment. Aggregate for sub base, base, surface courses have been
collected from the identified rock quarries and rock metal from the crusher under
operation in the existing / potential quarries. The location, estimated quantity and
the approximate distance of each quarry from the nearest point on the Project
Corridor are compiled below.

Sr. Quarry Location Remarks


No. Location
1 Tuipui River 7.0 Km from Darzokai at Sand & River Bed
359.00 Kmp on NH54 Material
2 Tuichawng 72.80 Km of NH-302 Sand & River Bed
River Material
3 Maudarh 374.00 Kmp of NH 54 Stone Boulder and
quarry quarry material
4 Chawilung 32.0 Km from Chhumkhum Stone Boulder and
(Khojoisuri) quarry material
The availability of the stone in rock quarries & sand quarry are indicated in the map.

The following tests have been conducted on rock aggregate from the quarry:
 Specific gravity
 Water Absorption
 Impact Value
 Los Angeles Abrasion Value
The results of the above field and laboratory investigations for various test pits are
reported in the following:

11
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Sl. Quarry Impact Loss Angeles Specific Water


No. Value (%) Abrasion Value gravity Absorption
(%)
1 Chawilung 21.74 36.25 2.62 1.965
2 Chawilung 23.93 37.10 2.60 2.091
3 Chawilung 24.26 38.72 2.49 2.140
4 Maudarh 23.23 37.85 2.50 2.037
5 Maudarh 20.83 36.07 2.51 1.933
6 Maudarh 21.78 36.67 2.57 1.868

Fine Aggregates: Fine Aggregate for Structural work have been collected from Tuichawng
Rivers and Tuipui River
The gradation tests have been conducted on fine aggregate from Tuichawng River Gradation
test results are as follows:
Sample No. 1

SIEVE ANALYSIS FOR C.Agg./F.Agg./GSB/WMM

Source :- Tuichawng River

Material :- Sand

Weight of Dry Material:- 1000 gms.

Spec. % of
Sieve Weight Cumulative
% of % of Passing as
Size Retained %
Retained Passing per MOST
(mm) (g) of Retained
(Zone - III)

10.00 nil nil nil 100 100

4.75 35 3.50 3.50 96.50 90 - 100

2.36 104 10.40 13.90 86.10 85 - 100

1.18 102 10.20 24.10 75.90 75 - 100

600 micron 115 11.50 35.60 64.40 60 - 79

300 micron 345 34.50 70.10 29.90 12 - 40

150 micron 216 21.60 91.70 8.30 0 - 10

FM = 2.40

12
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Sample No.2

SIEVE ANALYSIS FOR C.Agg./F.Agg./GSB/WBM


Source :- Tuichawng River
Material :- Sand
Weight of Dry Material:- 1000 gms.
Spec. % of
Sieve Weight Cumulative
% of % of Passing as
Size Retained %
Retained Passing per MOST
(mm) (g) of Retained
(Zone - II)
10.00 nil nil nil 100 100
4.75 51 5.10 5.10 94.90 90 - 100

2.36 107 10.70 15.80 84.20 75 - 100


1.18 114 11.40 27.20 72.80 55 - 90
600 micron 165 16.50 43.70 56.30 35 - 59

300 micron 282 28.20 71.90 28.10 8 - 30


150 micron 193 19.30 91.20 8.80 0 - 10

FM = 2.55
Sample No.3

SIEVE ANALYSIS FOR C.Agg./F.Agg./GSB/WMM


Source :- Tuichawng River
Material :- Sand
Weight of Dry Material:- 1000 gms.
Spec. % of
Sieve Weight Cumulative
% of % of Passing as
Size Retained %
Retained Passing per MOST
(mm) (g) of Retained
(Zone - III)
10.00 nil nil nil 100 100

4.75 25 2.50 2.50 97.50 90 - 100

2.36 92 9.20 11.70 88.30 85 - 100

1.18 120 12.00 23.70 76.30 75 - 100

600 micron 138 13.80 37.50 62.50 60 - 79

300 micron 352 35.20 72.70 27.30 12 - 40


150 micron 229 22.90 95.60 4.40 0 - 10

FM = 2.44

13
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

The gradation tests have been conducted on fine aggregate from Tuipui River Gradation test
results are as follows:
Sample No. 1

Source :- Tuipui River


Material :- Sand
Weight of Dry Material:- 1000 gms.
Spec. % of
Sieve Cumulative
Weight % of % of Passing as per
Size %
(mm)
Retained (g) Retained
of Retained
Passing MOST
(Zone - III)
10.00 nil nil nil 100 100

4.75 22 2.20 2.20 97.80 90 - 100


2.36 259 25.90 28.10 78.90 75 - 100
1.18 135 13.50 41.60 58.40 55 - 90
600 micron 187 18.70 60.30 39.70 35 - 59
300 micron 102 10.20 70.50 29.50 08 - 30
150 micron 75 7.50 78.00 8.70 0 - 10
FM = 2.81
Sample No.2

Source :- Tuipui River


Material :- Sand
Weight of Dry Material:- 1000 gms.
Spec. % of
Sieve Weight Cumulative
% of % of Passing as per
Size Retained %
Retained Passing MOST
(mm) (g) of Retained
(Zone - III)
10.00 nil nil nil 100 100

4.75 4 0.40 0.40 99.60 90 - 100


2.36 145 14.50 14.90 85.10 85- 100
1.18 100 10.00 24.90 75.10 75-100
600 micron 135 13.50 38.40 61.60 60 - 79
300 micron 245 24.50 62.90 37.10 12 - 40
150 micron 289 28.90 91.80 8.20 0- 10
FM = 2.33

14
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Sample No.3

Source :- Tuipui River


Material :- Sand
Weight of Dry Material:- 1000 gms.
Spec. % of
Sieve Weight Cumulative
% of % of Passing as per
Size Retained %
Retained Passing MOST
(mm) (g) of Retained
(Zone - III)
10.00 nil nil nil 100 100

4.75 21 2.10 2.10 97.90 90 - 100


2.36 79 7.90 10.00 90.00 85- 100
1.18 109 10.90 20.90 79.10 75-100
600 micron 134 13.40 34.30 65.70 60 - 79
300 micron 305 30.50 64.80 35.20 12 - 40
150 micron 268 26.80 91.60 8.40 0- 10
FM = 2.24

1.1.4. Investigation of Water Tables


The water table depth along the road corridor has been measured at suitable
locations. The water table depth is dependent upon the season and the precipitation.
There is no location where the water is directly affecting the road bank.
1.2. GEOLOGY AND SOIL
The North-East India is located on the north-east edge of the Himalayan orogenic
belt resulted from Indo-Eurasian continental plate collision that took place during
Cenozoic era, and represents one of the youngest and the highest mountain range in
the world. The Himalayan orogenic belt has a unique agglomeration with a
diversified geological setup. The various topographic features include the Himalayan
mountain belt in the north, the Indo-Myanmar Range in the east, Shillong Massif
Plateu in the west, and the expansive Brahmaputra forming the Assam plains in
between.
Mizoram state is predominately composed of mountainous terrain of tertiary rocks.
The mountain ridges strike north to south direction in parallel series. The mountain
ranges are separated from one another by narrow deep river valleys. The elevation
ranges from 40 meters to 2,157 meters, the highest point at Phawngpui. There are
only a few and small patches of flat lands, which are mostly intermontane basins.
Figure 2.1 shows the geological map of the Mizoram state. According to this map, the
geology along NH302 consists of Bokabil formation and Bhuban formation of Surma
groups.
The soils in the project area are primarily silty sands with gravel and rock fragments.
The area exposes predominantly low grade metamorphite rocks comprising
sandstone with concretions, shale, siltstone and conglomerate Based on the field
observations and microscopic study, rock of this area can be classified into the

15
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

following (i) shale (ii) siltstone (iii) sandstone. The rocks are highly jointed with
diversity in their orientations.

Figure 2.1 Geological Map of Mizoram


Source: Geological Survey in India

16
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Formation Lithoiogy
Bokabil Mainly argillaceous rocks represented by shale/siltstone and thinly
bedded sandstone alternations with subordinate buff colored, fine to
medium grained soft, friable sandstone
Upper Mainly arenaceous rocks which includes mainly thickly bedded, grey,
Bhuban khaki, buff colored fine to medium grained, at places friable, kaolinised
sandstone with very fine grained sandstone, siltstone, shale (grey, olive
green) interbands, with shell limestone as lensoidal bodies, conglomeratic
at places, grey, very fine grained to fine grained, hard compact, calcareous
sandstones
Middle Mainly argillaceous rocks which include grey, khaki shale, silty shale and
Bhuban siltstone/ shale interlaminations with grey, buff colored hard, compact,
micaceous, fine to medium grained, thinly to moderately bedded
sandstone with a few thick, grey, hard, very fine grained, micaceous
sandstone bands
Lower Mainly arenaceous rocks which includes fine to very fine grained,
Bhuban compact, blue, ash, green colored, massive to well bedded sandstone
exhibiting turbidite features and well laminated siltstone, olive green silty
shale/shale interlaminations
Source: Geological Survey in India
Soil texture, in general, varies from sandy loams, clayey loams to clay. Although the
soils are mature, profuse rainy spells in the region coupled with the high gradients
have accelerated the problem of leaching of the loose soils. These soils are highly
porous with low water holding capacity and this is the main cause of the low water
table in Mizoram. The soils of Mizoram are deficient in potassium, phosphorous,
nitrogen and humus. The traditional jhum cultivation has adversely affected the
productivity. Although superficial greenery is observed owing to the profuse
rainfall, the tract is actually in the process of fast degradation. The pH of these soils is
acidic to neutral due to excessive leaching. The soil structure of the project area is
summarized below.
Table 2.1 Soil Structures in Project Area

Nitrogen Phosphorus Potash


District Soil pH
(Kg/ha) (Kg/ha) (Kg/ha)

Lunglei 5.38 251 10 147


Source: Soil Information System

1.2.1. Seismicity
The site area falls under the Seismic zone V (as per IS: 1893; Part -1: 2002). This area is
high damage risk zone.
1.3. METHODS OF INVESTIGATION

1.3.1. General
This section will present details about the investigations that had been carried out at
site and at the laboratory.

17
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

Depth
Sl.No. Easting Northing level Code Remarks
in m
PHAIRUANG RIVER
1 463304.453 2524191.456 105.325 BH-1 23.0 Abutment
2 463256.555 2524195.906 94.273 BH-2 28.0 Pier
3 463156.765 2524165.536 104.258 BH-3 28.0 Abutment
CHHAWCHHI RIVER
1 462265.760 2524020.462 90.291 BH-1 23.0 Abutment
2 462280.562 2523989.059 91.432 BH-2 22.5 Abutment
TUICHAWNG RIVER
1 451455.370 2534308.655 70.291 BH-1 22.0 Abutment
2 451350.513 2534257.882 81.133 BH-2 23.3 Abutment
3 451389.226 2534266.12 62.172 BH-3 23.0 Pier
THAWRIKAU RIVER
1 450263.478 2533258.592 78.695 BH-1 22.0 Abutment

1.3.2. Drilling
Since the site itself is a rocky terrain, drilling was undertaken from the very
beginning of the hole. Drilling was done by rotary core drilling method deploying
‘Geo’ core drilling rig. Core drilling is a process in which a sampler, consisting of a
tube (core barrel) with a cutting bit at its end, cuts annular hole in a rock mass
thereby creating a cylinder or core of rocks which is recovered in the core barrel.
Both TC and diamond bits were used during the drilling operation. All the boreholes
were systematically logged and drilling data were noted. Borehole logs are presented
in the annexure – I.

1.3.3. Standard Penetration Test


Standard penetration tests (SPT) were conducted in all exploratory bore holes at
regular intervals as per as the provision laid down in IS: 2131 - 1981. The split spoon
sampler used for such tests was of standard design and dimensions as stipulated in
IS: 9640-1980. The split spoon sampler in the entire test had been adapted to lower
end of drill rods taken up-to specific depth of test. The split spoon sampler was
advanced by driving with a drop hammer, weighing 63.5 kg. Falling freely through a
height of 75 cm. A record of number of blows required for penetration of 30 cm after
penetration of first 15 cm as seating drive at the specific depth of test in each bore
hole was recorded as 'N' values for corresponding test depths in the respective bore
holes.
The disturbed soil samples, collected from the split spoon sampler after completion
of each test had been subsequently used for visual identification and classification of
the subsurface deposits and for preparation of the bore hole logs and also for
carrying out laboratory tests.

1.3.4. Sampling
Due to rocky nature of site, drilling was introduced from the very beginning; no 4”
undisturbed soil sample (UDS) could be obtained. Mainly core samples were
collected during drilling work. Those samples have been relied upon for

18
Construction of 2-laning with hard shoulder
Detailed Project
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Report

understanding the properties of the sub-soil profile. Core samples were used both for
visual identification and laboratory test. Wash samples were also collected from
boreholes, which have been mainly used for visual identification.

1.3.5. Water Table Observation


Water levels in the boreholes were observed during and after completion of drilling
operation. The final water levels were recorded in the field and are shown in the
individual logs.

1.3.6. Laboratory Investigation


Since the site is a rocky terrain, mainly rock cores have been recovered from
boreholes. Various laboratory tests on rock cores have been conducted. Following
parameters has been tested in the laboratory.

(a) Unit weight.

(b) Specific gravity.

(c) Water absorption.

(d) Void ratio.

(e) Porosity.

(f) Point load.

(g) Uni-axial compressive strength.

(h) Modulus of elasticity.


1.4. RESULTS OF INVESTIGATION

1.4.1. General
This Section contains discussion on results of sub-soil exploration. The objective of
the investigation was overall assessment of sub-soil conditions and evaluation of
foundation parameters at specified borehole locations. For evaluation of foundation
parameters, sub-soil profile was established first. Analyses of various sub-soil data
lead to selection and evaluation of foundation design parameters
(i) The sub soils in general are of good quality. The subsoil is a Hard yellowish
brown silty clay with kankars followed by Medium dense brownish grey silty
sand then completely weathered dark gray brownish slate then Highly
weathered dark grey slate up to depth of bore termination.
(ii) Considering the subsoil condition, it is proposed to go for pile foundation
(iii) Chemical test were carried out on a few soil samples so as to detect the pH
value, Sulphate, Chloride etc. It is seen that all the values are well within
limits. So no precaution will be required for foundation concrete. Either
Ordinary Portland cement or Portland Slag cement or Portlant Pozzolana
cement can be used for the purpose.
.

19
Sheet No.: A-1

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-1
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +105.325m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of 9-May-10
Equipment Commencement :
Water Level (Static) : 4.75m bgl. Date of Completion : 11-May-10

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
& Depth/Run (m) Length Description
Depth
(m) From To (m)
09/05/10 Chiselling started from 0.00m depth Brownish gray sandy clayey silt with traces

Completely weathered grey sand


0.00 0.00 0.07 0.07 60 - - >100 P
stone and slate.
(7cm)
0.00 0.00 0.30 - - - - - Chisel

0.30 0.30 0.32 0.02 57 - - >100 P


(2cm)
0.30 0.30 0.60 - - - - - Chisel

0.60 0.60 0.64 0.04 52 - - >100 P


(4cm)
0.60 0.60 0.90 - - - - - Chisel

0.90 0.90 1.07 0.17 48 62 - >100 P


(2cm)
1.00m
0.90 0.90 1.20 - - - - - Chisel
Completely weathered yellowish
1.20 1.20 1.38 0.18 46 55 - >100 P
brown fractured slate.
(3cm)
1.20 1.20 1.50 - - - - - Chisel

1.50 1.50 1.53 0.03 60 - - >100 P


(3cm)
1.50 1.50 1.80 - - - - - Chisel

1.80 1.80 1.86 0.06 56 - - >100 P


(6cm)
1.80 1.80 2.10 - - - - - Chisel

2.10 2.10 2.21 0.11 54 - - >100 P


(11cm)
2.10 2.10 2.40 - - - - - Chisel

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
1.00m Sheet No.: A-2
Completely weathered yellowish
BORE / DRILL LOG brown fractured slate.
Project : Geotechnical Investigation for various Bore Hole No. : BH-1
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +105.325m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of 9-May-10
Equipment Commencement :
Water Level (Static) : 4.75m bgl. Date of Completion : 11-May-10

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
& Depth/Run (m) Length Description
Depth
(m) From To (m)
2.40 2.40 2.42 0.02 50 - - >100 P Brownish gray sandy clayey silt with traces
(2cm)
Completely weathered grey sand
2.40 2.40 2.70 - - - - - Chisel
stone and slate.

2.70 2.70 2.85 0.15 42 - - >100 P


(15cm)
2.70 2.70 3.00 - - - - - Chisel

3.00 3.00 3.09 0.09 56 - >100 P Blackish grey gravels


Completely / boulder with
weathered boulder
yellowish
(9cm) brown fractured slate.
Drilling started from 3.00m depth
3.00 3.00 4.00 1.00 0.17 17 C/NIL

4.00 4.00 5.00 1.00 0.20 20 C/NIL


10/05/10
5.00 5.00 6.00 1.00 0.15 15 C/NIL

6.00 6.00 7.00 1.00 0.19 19 C/NIL


7.00m
7.00 7.00 8.00 1.00 0.18 18 C/NIL Completely weathered greyish brown
fractured slate.
8.00 8.00 9.00 1.00 0.23 23 C/NIL

9.00 9.00 10.00 1.00 0.20 20 C/NIL


10.00
10.00 10.00 11.00 1.00 0.28 28 C/NIL
Highly weathered grey fractured slate.

11.00 11.00 12.00 1.00 0.26 26 C/NIL

12.00 12.00 13.00 1.00 0.28 28 C/NIL

13.00 13.00 14.00 1.00 0.27 27 C/NIL

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-3

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. 7.00m : BH-1
bridge sites in Mizoram
Completely weathered greyish brown
Location : PHAIRUANG RIVER Ground Elevation : fractured
+105.325mslate.

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of 10.00 9-May-10
Equipment Commencement :
Water Level (Static) : 4.75m bgl. Date of Completion
Highly weathered grey: fractured
11-May-10slate.

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
& Depth/Run (m) Length Description
Depth
(m) From To (m)
11/05/10 Brownish gray sandy clayey silt with traces
14.00 14.00 15.00 1.00 0.24 24 C/NIL
Completely weathered grey sand
stone and slate.
15.00 15.00 16.00 1.00 0.28 28 C/NIL

16.00 16.00 17.00 1.00 0.32 32 C/NIL

17.00 17.00 18.00 1.00 0.45 45 C/NIL


18.00
18.00 18.00 19.00 1.00 0.53 53 C/NIL
Moderately weathered grey fractured

19.00 19.00 20.00 1.00 0.57 57 C/NIL

20.00 20.00 21.00 1.00 0.53 53 C/NIL

21.00 21.00 22.00 1.00 0.59 59 C/NIL

22.00 22.00 23.00 1.00 0.63 63 C/NIL

23.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-4

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-2
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +94.273m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 12-May-10
Equipment Commencement :
Water Level (Static) : 6.20m bgl. Date of Completion : 14-May-10

Sample and in-situ

Recovery (%)
Blows / Core
Date
Test

R.Q.D. (%)
Recovered

N' Value /
& Depth/Run (m) Length * No. of Description
Depth (m)

Type /
(m) From To
12/05/10 (m) Brownish gray sandy clayey silt with traces

1.50 1.50 1.95 0.45 2 3 2 5 P Loose yellowish brown / greyish

3.00 3.00 3.45 0.45 3 4 3 7 P

4.00 4.00 4.05 0.05 32 - - >100 P


(5 cm)
Chiselling started from 4.00m depth 4.00m

4.00 4.00 4.13 0.13 51 - - >100 P Completely weathered greyish yellow


(13cm) sand stone mixed with pebbles and
4.00 4.00 4.30 - - - - - Chisel

4.30 4.30 4.45 0.15 41 - - >100 P


(15cm)
4.30 4.30 4.60 - - - - - Chisel

4.60 4.60 4.74 0.14 52 - - >100 P


(14cm)
4.60 4.60 4.90 - - - - - Chisel

4.90 4.90 4.99 0.09 56 - - >100 P


(9cm)
4.90 4.90 5.20 - - - - - Chisel

5.20 5.20 5.31 0.11 51 - - >100 P


(11cm)
5.20 5.20 5.50 - - - - - Chisel

5.50 5.50 5.60 0.10 55 - - >100 P


(10cm)
5.50 5.50 5.80 - - - - - Chisel

*Each value in this column for SPT indicates no.of blows for each 15cm penetration
Blackish unless/ boulder
grey gravels otherwise
withstated
boulder
U-Undisturbed Sample C-Core Sample D-Disturbed Sample Completely
P-Standardweathered greyish
Penetration Test yellow
sand stone mixed with pebbles and
Sheet No.: A-5

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-2
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +94.273m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 12-May-10
Equipment Commencement :
Water Level (Static) : 6.20m bgl. Date of Completion : 14-May-10

Sample and in-situ

Recovery (%)
Blows / Core
Date
Test

R.Q.D. (%)
Recovered

N' Value /
& Depth/Run (m) Length * No. of Description
Depth (m)

Type /
(m) From To
5.80 5.80 5.84 0.04 (m)
60 - - >100 P Brownish gray sandy clayey silt with traces
(4cm)
5.80 5.80 6.10 - - - - - Chisel Loose yellowish brown / greyish
13/05/10
6.10 6.10 6.19 0.09 54 - - >100 P
(9cm)
6.10 6.10 6.40 - - - - - Chisel
Blackish grey gravels / boulder with boulder
6.40 6.40 6.49 0.09 53 - - >100 P Completely weathered
4.00m greyish yellow
(9cm) sand stone mixed with pebbles and
6.40 6.40 6.70 - - - - - Chisel

6.70 6.70 6.90 0.20 32 63 - >100 P


(5cm)
6.70 6.70 7.00 - - - - - Chisel

7.00 7.00 7.05 0.05 56 - - >100 P


(5cm)
Drilling started from 7.00m depth
7.00 7.00 8.00 1.00 0.17 17 C/NIL

8.00 8.00 9.00 1.00 0.20 20 C/NIL

9.00 9.00 10.00 1.00 0.22 22 C/NIL


10.00m
10.00 10.00 11.00 1.00 0.26 26 C/NIL Completely weathered grey sand

11.00 11.00 12.00 1.00 0.28 28 C/NIL

12.00 12.00 13.00 1.00 0.17 17 C/NIL

13.00 13.00 14.00 1.00 0.18 18 C/NIL


15.00m
14.00 14.00 15.00 1.00 0.24 24 C/NIL

Highly weathered grey sand stone.

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-6

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-2
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +94.273m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of 10.00m : 12-May-10
Equipment Commencement :
Completely weathered grey sand
Water Level (Static) : 6.20m bgl. Date of Completion : 14-May-10

Sample and in-situ

Recovery (%)
Blows / Core
Date
Test

R.Q.D. (%)
Recovered

N' Value /
& Depth/Run (m) Length * No. of Description
Depth (m)

Type /
(m) From To 15.00m

14/05/10 (m) Brownish gray sandy clayey silt with traces


15.00 15.00 16.00 1.00 0.26 26 C/NIL Highly weathered grey sand stone.
Loose yellowish brown / greyish

16.00 16.00 17.00 1.00 0.30 30 C/NIL

17.00 17.00 18.00 1.00 0.32 32 C/NIL

18.00 18.00 19.00 1.00 0.34 34 20 4.00m

19.00 19.00 20.00 1.00 0.29 29 12

20.00 20.00 21.00 1.00 0.32 32 22

Highly weathered grey sand stone.


21.00 21.00 22.00 1.00 0.35 35 C/NIL

22.00 22.00 23.00 1.00 0.43 43 C/NIL


23.00m
23.00 23.00 24.00 1.00 0.55 55 26

24.00 24.00 25.00 1.00 0.60 60 37 Moderately weathered grey sand


stone.
25.00 25.00 26.00 1.00 0.63 63 C/NIL

26.00 26.00 27.00 1.00 0.57 57 C/NIL

27.00 27.00 28.00 1.00 0.64 64 C/NIL

28.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-7

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-3
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +104.258m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 15-May-10
Equipment Commencement :
Water Level (Static) : 4.60m bgl. Date of Completion : 18-May-10

Sample and in-situ

* No. of Blows

Recovered (m)

Recovery (%)
Date Test

R.Q.D. (%)
& Length

N' Value /
Depth/Run (m) Description
Depth (m)

Type /
(m) / Core
From To
15/05/10 Brownish gray sandy clayey silt with traces

1.50 1.50 1.95 0.45 5 12 17 29 P Medium dense yellowish brown

3.00 3.00 3.21 0.21 32 48 - >100 P


(6 cm)
Chiselling started from 3.00m depth 3.00m

Completely weathered yellowish


3.00 3.00 3.02 0.02 52 - - >100 P
brown / greyish sand stone.
(2cm)
3.00 3.00 3.30 - - - - - Chisel

3.30 3.30 3.40 0.10 52 - - >100 P


(10cm)
3.30 3.30 3.60 - - - - - Chisel

3.60 3.60 3.75 0.15 39 - - >100 P


(15cm)
3.60 3.60 3.90 - - - - - Chisel

3.90 3.90 4.03 0.13 51 - - >100 P


(13cm)
3.90 3.90 4.20 - - - - - Chisel

4.20 4.20 4.29 0.09 55 - - >100 P


(9cm)
4.20 4.20 4.50 - - - - - Chisel

4.50 4.50 4.55 0.05 56 - - >100 P


(5cm)
4.50 4.50 4.80 - - - - - Chisel

4.80 4.80 4.87 0.07 57 - - >100 P


(7cm)
4.80 4.80 5.10 - - - - - Chisel

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Blackish grey gravels / boulder with

Completely weathered yellowish brown


Sheet No.: A-8

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Hole No. : BH-3
bridge sites in Mizoram
Location : PHAIRUANG RIVER Ground Elevation : +104.258m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 15-May-10
Equipment Commencement :
Water Level (Static) : 4.60m bgl. Date of Completion : 18-May-10

Sample and in-situ

* No. of Blows

Recovered (m)

Recovery (%)
Date Test

R.Q.D. (%)
& Length

N' Value /
Depth/Run (m) Description
Depth (m)

Type /
(m) / Core
From To
Brownish gray sandy clayey silt with traces
5.10 5.10 5.13 0.03 55 - - >100 P
(3cm) Medium dense yellowish brown
5.10 5.10 5.40 - - - - - Chisel

5.40 5.40 5.54 0.14 58 - - >100 P 3.00m


(14cm)
Drilling started from 5.40m depth Completely
Blackish grey weathered yellowish
gravels / boulder with
brown / greyish sand stone.
5.40 5.40 6.00 0.60 0.05 8 C/NIL Completely weathered yellowish brown
16/05/10 / greyish sand stone.
6.00 6.00 7.00 1.00 0.17 17 C/NIL

7.00 7.00 8.00 1.00 0.16 16 C/NIL

8.00 8.00 9.00 1.00 0.19 19 C/NIL

9.00 9.00 10.00 1.00 0.22 22 C/NIL


10.00m
10.00 10.00 11.00 1.00 0.25 25 C/NIL
Highly weathered grey sand stone.
11.00 11.00 12.00 1.00 0.27 27 C/NIL
17/05/10
12.00 12.00 13.00 1.00 0.25 25 C/NIL

13.00 13.00 14.00 1.00 0.28 28 C/NIL

14.00 14.00 15.00 1.00 0.36 36 C/NIL

15.00 15.00 16.00 1.00 0.30 30 C/NIL

16.00 16.00 17.00 1.00 0.32 32 C/NIL

17.00 17.00 18.00 1.00 0.38 38 C/NIL

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-9

BORE / DRILL LOG 10.00m


Project : Geotechnical Investigation for various Bore Hole No. : BH-3
bridge sites in Mizoram Highly weathered grey sand stone.
Location : PHAIRUANG RIVER Ground Elevation : +104.258m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 15-May-10
Equipment Commencement :
Water Level (Static) : 4.60m bgl. Date of Completion : 18-May-10

Sample and in-situ

* No. of Blows

Recovered (m)

Recovery (%)
Date Test

R.Q.D. (%)
& Length

N' Value /
Depth/Run (m) Description
Depth (m)

Type /
(m) / Core
From To
18.00 18.00 19.00 1.00 0.35 35 C/NIL Brownish gray sandy clayey silt with traces

Medium dense yellowish brown


19.00 19.00 20.00 1.00 0.37 37 C/NIL
18/05/10
20.00 20.00 21.00 1.00 0.40 40 C/NIL
3.00m
21.00 21.00 22.00 1.00 0.45 45 C/NIL
Completely weathered
22.00m yellowish
brown / greyish sand stone.
22.00 22.00 23.00 1.00 0.56 56 23
Moderately weathered grey sand stone.

23.00 23.00 24.00 1.00 0.63 63 12

24.00 24.00 25.00 1.00 0.70 70 37

25.00 25.00 26.00 1.00 0.68 68 C/NIL

26.00 26.00 27.00 1.00 0.71 71 C/NIL

27.00 27.00 28.00 1.00 0.70 70 C/NIL

28.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-1

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
bridge sites in Mizoram
Location : CHHAWCHHI RIVER Ground Elevation : +90.291m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 19-May-10
Equipment Commencement :
Water Level : 3.70m bgl. Date of Completion : 21-May-10
(Static)

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
&
Depth/Run (m) Length Description
Depth
(m)
From To (m)
19/05/10

Hard yellowish brown silty clay.


1.50 1.50 1.95 0.45 9 17 21 38 P

3.00 3.00 3.22 0.22 35 48 - >100 P


(7 cm)
Chiselling started from 3.00m depth 3.00m

3.18 Completely weathered yellowish


3.00 3.00 0.18 43 58 - >100 P
brown fractured slate.
(4cm)
3.00 3.00 3.30 - - - - - Chisel

3.30 3.30 3.48 0.18 32 68 - >100 P


(3cm)
3.30 3.30 3.60 - - - - - Chisel

3.60 3.60 3.63 0.03 55 - - >100 P


(3cm)
3.60 3.60 3.90 - - - - - Chisel

3.90 3.90 4.06 0.16 36 64 - >100 P


(1cm)
3.90 3.90 4.20 - - - - - Chisel

4.20 4.20 4.32 0.12 53 - - >100 P


(12cm)
4.20 4.20 4.50 - - - - - Chisel

4.50 4.50 4.53 0.03 56 - - >100 P


(3cm)
4.50 4.50 4.80 - - - - - Chisel

4.80 4.80 4.82 0.02 58 - - >100 P


(2cm)
4.80 4.80 5.10 - - - - - Chisel

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-2

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
bridge sites in Mizoram
Location : CHHAWCHHI RIVER Ground Elevation : +90.291m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 19-May-10
Equipment Commencement :
Water Level : 3.70m bgl. Date of Completion : 21-May-10
(Static)

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
&
Depth/Run (m) Length Description
Depth
(m)
From To (m)

5.10 5.10 5.25 0.15 42 - - >100 P


Hard yellowish brown silty clay.
(15cm)
5.10 5.10 5.40 - - - - - Chisel

5.40 5.40 5.51 0.11 55 - - >100 P


(11cm) 3.00m
Drilling started from 5.40m depth Blackish grey gravels / boulder with boulder

Completely weathered greyish brown


5.40 5.40 6.00 0.60 0.07 12 C/NIL fractured slate.
20/05/10
6.00 6.00 7.00 1.00 0.16 16 C/NIL

7.00 7.00 8.00 1.00 0.19 19 C/NIL

8.00 8.00 9.00 1.00 0.23 23 C/NIL

9.00 9.00 10.00 1.00 0.20 20 C/NIL


10.00
10.00 10.00 11.00 1.00 0.25 25 C/NIL Highly weathered greyish brown fractured
slate.
11.00 11.00 12.00 1.00 0.18 18 C/NIL

12.00 12.00 13.00 1.00 0.27 27 C/NIL


21/05/10
13.00 13.00 14.00 1.00 0.30 30 C/NIL

14.00 14.00 15.00 1.00 0.28 28 C/NIL

15.00 15.00 16.00 1.00 0.36 36 C/NIL

16.00 16.00 17.00 1.00 0.48 48 C/NIL


17.00m
17.00 17.00 18.00 1.00 0.54 54 C/NIL Moderately weathered greyish brown

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
10.00 Sheet No.: A-3

BORE / DRILL LOG Highly weathered greyish brown fractured


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey silt with slate.
: BH-1 traces
bridge sites in Mizoram
Location : CHHAWCHHI RIVER Ground Elevation : +90.291m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 19-May-10
Equipment Commencement :
Water Level : 3.70m bgl. Date of Completion : 21-May-10
(Static)

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
& 17.00m
Depth/Run (m) Length Description
Depth Moderately weathered greyish brown
(m)
From To (m)
18.00 18.00 19.00 1.00 0.52 52 C/NIL

Hard yellowish brown silty clay.


19.00 19.00 20.00 1.00 0.63 63 C/NIL

20.00 20.00 21.00 1.00 0.46 46 C/NIL

21.00 21.00 22.00 1.00 0.51 51 C/NIL 3.00m

22.00 22.00 23.00 1.00 0.58 58 C/NIL

23.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-4

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-2
silt with traces
bridge sites in Mizoram
Location : CHHAWCHHI RIVER Ground Elevation : +91.432m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 3-Jun-10
Equipment Commencement :
Water Level (Static) : 4.00m bgl. Date of Completion : 4-Jun-10

Recovery (%)
Blows / Core
Date Sample and in-situ Test

R.Q.D. (%)
Recovered

N' Value /
* No. of

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m) From To (m)
03/06/10

1.50 1.50 1.95 0.45 2 3 3 6 P Medium stiff to stiff yellowish grey


silty clay with kankar.
3.00 3.00 3.45 0.45 5 7 8 15 P

4.50 4.50 4.75 0.25


28 48 - >100 P
(10 cm)
Chiselling started from 4.50m depth
4.50m
4.50 4.50 4.68 0.18 38 70 - >100 P
Completely weathered yellowish
(3cm)
4.50 4.50 4.80 - - - - - Chisel
grey fractured slate.

4.80 4.80 4.90 0.10 57 - - >100 P


(10cm)
4.80 4.80 5.10 - - - - - Chisel

5.10 5.10 5.16 0.06 59 - - >100 P


(6cm)
5.10 5.10 5.40 - - - - - Chisel

5.40 5.40 5.44 0.04 55 - - >100 P


(4cm)
5.40 5.40 5.70 - - - - - Chisel

5.70 5.70 5.83 0.13 58 - - >100 P


(13cm)
5.70 5.70 6.00 - - - - - Chisel

6.00 6.00 6.19 0.19 31 59 - >100 P


(4cm)
6.00 6.00 6.30 - - - - - Chisel

6.30 6.30 6.33 0.03 60 - - >100 P


(3cm)
6.30 6.30 6.60 - - - - - Chisel

Blackish grey gravels / boulder with boulder


*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
Completely weathered yellowish grey
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
fractured slate.
Sheet No.: A-5

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-2
silt with traces
bridge sites in Mizoram
Location : CHHAWCHHI RIVER Ground Elevation : +91.432m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 3-Jun-10
Equipment Commencement :
Water Level (Static) : 4.00m bgl. Date of Completion : 4-Jun-10

Recovery (%)
Blows / Core
Date Sample and in-situ Test

R.Q.D. (%)
Recovered

N' Value /
* No. of

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m) From To (m)
6.60 6.60 6.66 0.06 55 - - >100 P
(6cm)
04/06/10
Medium stiffgravels
to stiff yellowish grey
Drilling started from 6.60m depth Blackish grey / boulder with boulder
silty clay with kankar.
7.50 7.50 8.50 1.00 0.14 14 C/NIL Completely weathered yellowish grey
fractured slate.
8.50 8.50 9.50 1.00 0.15 15 C/NIL

9.50 9.50 10.50 1.00 0.17 17 C/NIL 4.50m

10.50 10.50 11.50 1.00 0.12 12 C/NIL

11.50 11.50 12.50 1.00 0.15 15 C/NIL

12.50 12.50 13.50 1.00 0.19 19 C/NIL

13.50 13.50 14.50 1.00 0.14 14 C/NIL

14.50 14.50 15.50 1.00 0.20 20 C/NIL

15.50 15.50 16.50 1.00 0.16 16 C/NIL

16.50 16.50 17.50 1.00 0.20 20 C/NIL

17.50 17.50 18.50 1.00 0.24 24 C/NIL


18.50m
18.50 18.50 19.50 1.00 0.27 27 C/NIL
Highly weathered yellowish grey
fractured slate.
19.50 19.50 20.50 1.00 0.31 31 C/NIL

20.50 20.50 21.50 1.00 0.36 36 C/NIL

21.50 21.50 22.50 1.00 0.42 42 C/NIL

22.50m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-1

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
bridge sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +70.291m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 5-May-10
Equipment Commencement :
Water Level (Static) : 7.00m bgl. Date of Completion : 6-May-10

Core Recovered
* No. of Blows /
Sample and in-situ Test

Recovery (%)
Date

R.Q.D. (%)
N' Value /

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m)
From To (m)
05/05/10

1.50 1.50 1.95 0.45 6 10 12 22 P Very stiff yellowish brown silty clay.

3.00 3.00 3.22 0.22 24 49 - >100 P


(7 cm)
Chiselling started from 3.00m depth
3.00m
3.00 3.00 3.12 0.12 55 - - >100 P Completely weathered yellowish
(12cm) brown fractured slate.
3.00 3.00 3.30 - - - - - Chisel

3.30 3.30 3.38 0.08 56 - - >100 P


(8cm)
3.30 3.30 3.60 - - - - - Chisel

3.60 3.60 3.80 0.20 50 66 - >100 P


(5cm)
3.60 3.60 3.90 - - - - - Chisel

3.90 3.90 4.05 0.15 45 - - >100 P


(15cm)
3.90 3.90 4.20 - - - - - Chisel

4.20 4.20 4.26 0.06 55 - - >100 P


(6cm)
4.20 4.20 4.50 - - - - - Chisel

4.50 4.50 4.64 0.14 53 - - >100 P


(14cm)
4.50 4.50 4.80 - - - - - Chisel

4.80 4.80 4.87 0.07 53 - - >100 P


(7cm)
4.80 4.80 5.10 - - - - - Chisel

5.10 5.10 5.19 0.09 50 - - >100 P

5.00m
Blackish grey gravels / boulder with boulder

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-2

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
bridge sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +70.291m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 5-May-10
Equipment Commencement :
Water Level (Static) : 7.00m bgl. Date of Completion : 6-May-10

Core Recovered
* No. of Blows /
Sample and in-situ Test

Recovery (%)
Date

R.Q.D. (%)
N' Value /

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m)
From To (m)
(9cm)
Drilling started from 5.00m depth
5.00mbrown silty clay.
Very stiff yellowish
5.00 5.00 6.00 1.00 0.12 12 C/NIL
Blackish grey gravels / boulder with boulder
6.00 6.00 7.00 1.00 0.14 14 C/NIL
06/05/10
7.00 7.00 8.00 1.00 0.18 18 C/NIL 3.00m
Completely weathered yellowish
8.00 8.00 9.00 1.00 0.15 15 C/NIL brown fractured slate.

9.00 9.00 10.00 1.00 0.14 14 C/NIL

10.00 10.00 11.00 1.00 0.19 19 C/NIL

11.00 11.00 12.00 1.00 0.16 16 C/NIL

12.00 12.00 13.00 1.00 0.21 21 C/NIL

13.00 13.00 14.00 1.00 0.15 15 C/NIL Completely weathered grey


fractured slate.
14.00 14.00 15.00 1.00 0.23 23 C/NIL

15.00 15.00 16.00 1.00 0.20 20 C/NIL

16.00 16.00 17.00 1.00 0.22 22 C/NIL

17.00 17.00 18.00 1.00 0.26 26 C/NIL


17.00
18.00 18.00 19.00 1.00 0.34 34 15 Highly weathered grey fractured
slate.
19.00 19.00 20.00 1.00 0.50 50 40

20.00 20.00 21.00 1.00 0.51 51 C/NIL

21.00 21.00 22.00 1.00 0.56 56 C/NIL

22.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-3

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-2
silt with traces
bridge sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +81.133m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 30-Apr-10
Equipment Commencement :
Water Level (Static) : - Date of Completion : 1-May-10

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
&
Depth/Run (m) Length Description
Depth
(m) From To (m)
30/04/10

1.50 1.50 1.95 0.45 15 19 26 45 P Dense yellowish grey silty sand.

3.00 3.00 3.22 0.22 12 48 - >100 P


(7 cm)
Chiselling started from 3.30m depth 3.30m

3.30 3.30 3.41 0.11 51 - - >100 P


(11cm)
Completely weathered yellowish
3.60
brown fractured slate.
3.30 3.30 - - - - - Chisel

3.60 3.60 3.71 0.11 54 - - >100 P


(11cm)
3.60 3.60 3.90 - - - - - Chisel

3.90 3.90 3.96 0.06 51 - - >100 P


(7cm)
3.90 3.90 4.20 - - - - - Chisel

4.20 4.20 4.29 0.09 50 - - >100 P


(9cm)
4.20 4.20 4.50 - - - - - Chisel

4.50 4.50 4.64 0.14 58 - - >100 P


(14cm)
4.50 4.50 4.80 - - - - - Chisel

4.80 4.80 4.82 0.02 58 - - >100 P


(2cm)
4.80 4.80 5.10 - - - - - Chisel

5.10 5.10 5.27 0.17 40 54 - >100 P


(2cm)
5.10 5.10 5.40 - - - - - Chisel

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test

Blackish grey gravels / boulder with boulder


7.00m
Sheet No.: A-4

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-2
silt with traces
bridge sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +81.133m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 30-Apr-10
Equipment Commencement :
Water Level (Static) : - Date of Completion : 1-May-10

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
&
Depth/Run (m) Length Description
Depth
(m) From To (m)

5.40 5.40 5.49 0.09 54 - - >100 P


(9cm) Dense yellowish grey silty sand.
5.40 5.40 5.70 - - - - - Chisel

5.70 5.70 5.89 0.19 32 67 - >100 P


3.30m
01/05/10 Drilling started from 5.70m depth Blackish grey gravels / boulder with boulder
7.00m
5.70 5.70 6.30 0.60 0.10 17 C/NIL Completely weathered grey
fractured slate.
6.30 6.30 7.30 1.00 0.19 19 C/NIL

7.30 7.30 8.30 1.00 0.26 26 C/NIL

8.30 8.30 9.30 1.00 0.13 13 C/NIL

9.30 9.30 10.30 1.00 0.18 18 C/NIL

10.30 10.30 11.30 1.00 0.21 21 11

11.30 11.30 12.30 1.00 0.18 18 C/NIL

12.30 12.30 13.30 1.00 0.20 20 C/NIL

13.30 13.30 14.30 1.00 0.23 23 C/NIL

14.30 14.30 15.30 1.00 0.15 15 C/NIL


15.30
15.30 15.30 16.30 1.00 0.30 30 C/NIL Highly weathered grey fractured
slate.
16.30 16.30 17.30 1.00 0.46 46 C/NIL
17.30
17.30 17.30 18.30 1.00 0.52 52 C/NIL

Moderately
weathered grey
fractured slate.
*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-5

BORE / DRILL LOG


Project : Geotechnical Investigation for various Bore Holegray
Brownish No. sandy clayey
: BH-2
silt with traces
bridge sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +81.133m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 30-Apr-10
Equipment Commencement :
Water Level (Static) : - 15.30 : 1-May-10
Date of Completion
Highly weathered grey fractured
slate.

* No. of Blows

Recovered (m)

Recovery (%)
Date Sample and in-situ Test

R.Q.D. (%)
N' Value /

Type /
/ Core
&
Depth/Run (m) Length Description
Depth 17.30
(m) From To (m)
18.30 18.30 19.30 1.00 0.55 55 10

Dense yellowish grey silty sand.


19.30 19.30 20.30 1.00 0.53 53 C/NIL Moderately weathered grey
fractured slate.
20.30 20.30 21.30 1.00 0.50 50 C/NIL
3.30m
21.30 21.30 22.30 1.00 0.56 56 C/NIL

22.30 22.30 23.30 1.00 0.62 62 C/NIL

23.30m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-6

BORE / DRILL LOG


Project : Geotechnical Investigation for various bridge Bore Hole No. : BH-3
sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +62.172m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 2-May-10
Equipment Commencement :
Water Level (Static) : 5.50m bgl. Date of Completion : 4-May-10

Recovery (%)
Blows / Core
Date Sample and in-situ Test

R.Q.D. (%)
Recovered

N' Value /
* No. of

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m) To
From (m)
02/05/10 Brownish gray sandy clayey silt with traces

1.50 1.50 1.95 0.45 7 10 12 22 P Very stiff yellowish brown silty clay.

3.00 3.00 3.20 0.20 42 57 - >100 P


(5 cm)
Chiselling started from 3.00m depth 3.00m

3.00 3.00 3.03 0.03 53 - - >100 P


Completely weathered yellowish
brown /brownish grey fractured
(3cm)
3.00 3.00 3.30 - - - - - Chisel

3.30 3.30 3.44 0.14 54 - - >100 P


(14cm)
3.30 3.30 3.60 - - - - - Chisel

3.60 3.60 3.67 0.07 51 - - >100 P


(7cm)
3.60 3.60 3.90 - - - - - Chisel

3.90 3.90 4.09 0.19 47 59 - >100 P


(4cm)
3.90 3.90 4.20 - - - - - Chisel

4.20 4.20 4.32 0.12 56 - - >100 P


(12cm)
4.20 4.20 4.50 - - - - - Chisel

4.50 4.50 4.55 0.05 58 - - >100 P


(5cm)
4.50 4.50 4.80 - - - - - Chisel

4.80 4.80 4.97 0.17 47 67 - >100 P


(2cm)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test

Completely weathered
Blackish grey gravels yellowish
/ boulder with boulder
Sheet No.: A-7

BORE / DRILL LOG


Project : Geotechnical Investigation for various bridge Bore Hole No. : BH-3
sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +62.172m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 2-May-10
Equipment Commencement :
Water Level (Static) : 5.50m bgl. Date of Completion : 4-May-10

Recovery (%)
Blows / Core
Date Sample and in-situ Test

R.Q.D. (%)
Recovered

N' Value /
* No. of

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m) To
From (m)
4.80 4.80 5.10 - - - - - Chisel Brownish gray sandy clayey silt with traces

Very stiff yellowish brown silty clay.


5.10 5.10 5.17 0.07 58 - - >100 P
(7cm)
5.10 5.10 5.40 - - - - - Chisel

3.00m
5.40 5.40 5.51 0.11 58 - - >100 P
(11cm) Completely weathered yellowish
Completely
Blackish grey
brown weathered
gravels
/brownish / boulder yellowish
grey with boulder
fractured
5.40 5.40 5.70 - - - - - Chisel brown /brownish grey fractured slate.

5.70 5.70 5.83 0.13 50 - - >100 P


(13cm)
5.70 5.70 6.00 - - - - - Chisel

6.00 6.00 6.02 0.02 58 - - >100 P 6.00m


(2cm)
Drilling started from 6.00m depth

6.00 6.00 7.00 1.00 0.20 20 C/NIL Completely weathered grey


03/05/10 fractured slate.
7.00 7.00 8.00 1.00 0.17 17 C/NIL

8.00 8.00 9.00 1.00 0.14 14 C/NIL

9.00 9.00 10.00 1.00 0.19 19 C/NIL

10.00 10.00 11.00 1.00 0.11 11 C/NIL

11.00 11.00 12.00 1.00 0.21 21 C/NIL

12.00 12.00 13.00 1.00 0.22 22 C/NIL

13.00 13.00 14.00 1.00 0.18 18 C/NIL

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
16.00m

Highly weathered grey fractured


6.00m

Sheet No.: A-8

BORE / DRILL LOG


Completely weathered grey
Project : Geotechnical Investigation for various bridge Bore Hole No. : BH-3
fractured slate.
sites in Mizoram
Location : TUICHAWNG RIVER Ground Elevation : +62.172m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 2-May-10
Equipment Commencement :
Water Level (Static) : 5.50m bgl. Date of Completion : 4-May-10

Recovery (%)
Blows / Core
Date Sample and in-situ Test

R.Q.D. (%)
Recovered

N' Value /
* No. of

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m) To
From (m)
04/05/10 Brownish gray sandy clayey silt with traces
14.00 14.00 15.00 1.00 0.24 24 C/NIL
Very stiff yellowish brown silty clay.

15.00 15.00 16.00 1.00 0.23 23 C/NIL


16.00m
16.00 16.00 17.00 1.00 0.26 26 C/NIL 3.00m
Highly weathered grey fractured
slate.
Completely weathered yellowish
17.00 17.00 18.00 1.00 0.28 28 C/NIL
brown /brownish grey fractured
18.00 18.00 19.00 1.00 0.31 31 12

19.00 19.00 20.00 1.00 0.45 45 20

20.00 20.00 21.00 1.00 0.48 48 C/NIL 21.00m

21.00 21.00 22.00 1.00 0.52 52 C/NIL Moderately weathered grey


fractured slate.
22.00 22.00 23.00 1.00 0.57 57 C/NIL

23.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-1

BORE / DRILL LOG


Project : Geotechnical Investigation for various bridge Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
sites in Mizoram
Location : THAWRIKAU RIVER Ground Elevation : +78.695m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 7-May-10
Equipment Commencement :
Water Level (Static) : 3.10m bgl. Date of Completion : 8-May-10

Core Recovered
* No. of Blows /
Sample and in-situ Test

Recovery (%)
Date

R.Q.D. (%)
N' Value /

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m)
From To (m)
07/05/10 Chiselling started from 0.00m depth

Completely weathered yellowish


0.00 0.00 0.04 0.04 52 - - >100 P brown fractured slate.
(4cm)
0.00 0.00 0.30 - - - - - Chisel

0.30 0.30 0.43 0.13 53 - - >100 P


(13cm)
0.30 0.30 0.60 - - - - - Chisel

0.60 0.60 0.79 0.19 42 51 - >100 P


(4cm)
0.60 0.60 0.90 - - - - - Chisel

0.90 0.90 1.08 0.18 35 70 - >100 P


(3cm)
0.90 0.90 1.20 - - - - - Chisel

1.20 1.20 1.36 0.16 41 67 - >100 P


(1cm)
1.20 1.20 1.50 - - - - - Chisel

1.50 1.50 1.68 0.18 44 51 - >100 P


(3cm)
1.50 1.50 1.80 - - - - - Chisel

1.80 1.80 1.91 0.11 59 - - >100 P


(11cm)
1.80 1.80 2.10 - - - - - Chisel

2.10 2.10 2.16 0.06 58 - - >100 P


(6cm)
Drilling started from 2.10m depth

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test
Sheet No.: A-2

BORE / DRILL LOG


Project : Geotechnical Investigation for various bridge Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
sites in Mizoram
Location : THAWRIKAU RIVER Ground Elevation : +78.695m

Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm


Drilling Boring/Drilling
Boring / Drilling : Winch / GO Date of : 7-May-10
Equipment Commencement :
Water Level (Static) : 3.10m bgl. Date of Completion : 8-May-10

Core Recovered
* No. of Blows /
Sample and in-situ Test

Recovery (%)
Date

R.Q.D. (%)
N' Value /

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m)
From To (m)
2.10 2.10 3.00 0.90 0.18 20 C/NIL

Completely weathered yellowish


3.00 3.00 4.00 1.00 0.17 17 C/NIL brown fractured slate.

4.00 4.00 5.00 1.00 0.19 19 C/NIL

5.00 5.00 6.00 1.00 0.16 16 C/NIL

Blackish grey gravels / boulder with boulder


Completely weathered grey fractured
6.00 6.00 7.00 1.00 0.20 20 C/NIL slate.

7.00 7.00 8.00 1.00 0.22 22 C/NIL

8.00 8.00 9.00 1.00 0.20 20 C/NIL

9.00 9.00 10.00 1.00 0.27 27 C/NIL

10.00 10.00 11.00 1.00 0.21 21 C/NIL

11.00 11.00 12.00 1.00 0.26 26 C/NIL


08/05/10
12.00 12.00 13.00 1.00 0.19 19 C/NIL
13.00m

13.00 13.00 14.00 1.00 0.25 25 C/NIL


Highly weathered grey fractured

14.00 14.00 15.00 1.00 0.28 28 C/NIL

15.00 15.00 16.00 1.00 0.24 24 C/NIL

16.00 16.00 17.00 1.00 0.35 35 C/NIL

17.00 17.00 18.00 1.00 0.32 32 10

19.00m
*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard ModeratelyPenetration Test
weathered grey
Sheet No.: A-3

BORE / DRILL LOG


Project : Geotechnical Investigation for various bridge Bore Holegray
Brownish No. sandy clayey
: BH-1
silt with traces
sites in Mizoram
Location : THAWRIKAU RIVER Ground Elevation : +78.695m
13.00m
Method of Boring / : Shell / RMC Dia. of : 75mm / 150mm
Drilling Boring/Drilling
Highly weathered grey fractured
Boring / Drilling : Winch / GO Date of : 7-May-10
Equipment Commencement :
Water Level (Static) : 3.10m bgl. Date of Completion : 8-May-10

Core Recovered
* No. of Blows /
Sample and in-situ Test

Recovery (%)
Date

R.Q.D. (%)
N' Value /

Type /
&

(m)
Depth/Run (m) Length Description
Depth
(m)
From To (m)
18.00 18.00 19.00 1.00 0.40 40 C/NIL
19.00m
Completely weathered yellowish
19.00 19.00 20.00 1.00 0.58 58 C/NIL brown fractured slate.
Moderately weathered grey

20.00 20.00 21.00 1.00 0.63 63 C/NIL

21.00 21.00 22.00 1.00 0.67 67 C/NIL

22.00m (Termination Depth)

*Each value in this column for SPT indicates no.of blows for each 15cm penetration unless otherwise stated
U-Undisturbed Sample C-Core Sample D-Disturbed Sample P-Standard Penetration Test