Ugc - 03 DPR - 12 Apr 21
Ugc - 03 DPR - 12 Apr 21
Ugc - 03 DPR - 12 Apr 21
Max. Temp
30.0 Weather Cloudy LOA 1-Jul-16 Original Project End Date 10-Jan-21 Progress Date 12-Apr-21
(0C) GENERAL
Min. Temp Rainfall Notice To CONSULTANT
23.0 18-Jul-16 Reporting Date 13-Apr-21
(0C) (mm) Proceed
Concourse Slab Rmt 252 252 252 100.00% TBM cutout (12 x 8) casted on 16-Oct-2020 in south shaft.
Side Walls (Concourse to Roof) Rmt 468 268 268 57.30%
End Walls (Concourse-Roof) Rmt 54 27 27 50.22%
Roof Slab Rmt 250 152 152 60.68%
Platform Slab Rmt 250 31 31 12.32%
UPE Wall
Inner Wall Rmt 400 203 203 50.78%
Outer Wall Rmt 400 74 74 18.54%
Column
Base to Concourse Nos 22 22 22 100.00%
Concourse to Roof Nos 22 14 15 68.18%
ROOMS AT CONCOURSE LEVEL
Block Work Cum 1,327 19 19 1.43% SP-4
Plenum Walls Rmt 31 38
1.07 ENTRY-EXIT SLAB & WALLS
Entry-Exit-6 Concourse Rmt 50 28 28 56.00%
Side Walls Rmt 53 17 17 31.89%
Entry-Exit-5 Concourse Rmt 55
Entry-Exit-4 Concourse Rmt 63
Entry-Exit-3 Concourse Rmt 70 70 70 99.37%
Side Walls - (EE 03) Rmt 70 8 11.04% 7.73 Rmt - 2.8 m Height
E.E-1,2,3 Common Passage Concourse Rmt 103
SideWalls Rmt 136 EE-06 (17.58*1.65m(H) 1st Lift casted-20/2/21)
Excavation EE-3 Cum 7,800
EE-06 Roof slab Rmt 70 17 24.00%
1.08 ANCILLARY-BUILDING
Base Slab Rmt 9 9
2.0 Mahalakshmi Station
2.01 Barricade Erection Rmt 900.00 900 900 100.00%
2.02 Tree Cutting Nos 33.00 33 33 100.00%
100% scope has been achieved,WIP is a varition.
2.03 Tree Transplantation Nos 122.00 121 121 99.18%
Land Hand over Area
2.04 Sqm 15,844.51 15,923 15,923 100.50% Including Temorary & Permanent Land
(Area as per Revised Appendix-2A as on 19th July 2017)
(Station Box + EE -01+02+03+04+05+06) & (115 Nos.) of Ancillary
2.05 Piles (Ancillary & Utility Gallery) Nos 362.00 215 215 59.39%
Building secant pile is complete
2.06 Excavation (Station Box & associted Entry Exits) Cum 1,66,229.00 1,65,989 1,65,989 99.86%
2.07 Excavation (Ancillary Building + utility Gallery) Cum 7,179.00 4,012 4,042 56.30%
2.08 Deck (Installations of Deck Panels)
Max. Temp
30.0 Weather Cloudy LOA 1-Jul-16 Original Project End Date 10-Jan-21 Progress Date 12-Apr-21
(0C) GENERAL
Min. Temp Rainfall Notice To CONSULTANT
23.0 18-Jul-16 Reporting Date 13-Apr-21
(0C) (mm) Proceed
4.09 Deck slab-Cross Deck SQM 1,029 724 724 70.39% Main Deck completed along with traffic diversion.
4.10 RCC Strut Level-1 Nos. 25 24 24 96.00%
4.11 Steel Strut Level-2 Nos. 41 34 34 82.93%
4.12 Steel Strut Level-3 Nos. 41 26 26 63.41%
4.13 Steel Strut Level-4 Nos. 45 23 23 51.11%
4.14 Steel Waler Level-2 Rmt 334 334 334 100.00%
4.15 Steel Waler Level-3 Rmt 334 266 266 79.49%
4.16 Steel Waler Level-4 Rmt 334 240 240 71.92%
4.19 RCC Waler Level-2 Rmt 186 107 107 57.69%
4.20 RCC Waler Level-3 Rmt 186 87 87 46.77%
4.21 RCC Waler Level-4 Rmt 186 90 90 48.55%
4.22 Runner Level-2 Rmt 25 21 21 84.00%
4.23 Runner Level-3 Rmt 25 15 15 60.00%
4.24 Runner Level-4 Rmt 25 12 12 48.00%
4.25 Steel Waler Level-2 (Ancillary Building & EE) Rmt 172 172 172 100.00%
4.26 Steel Waler Level-3 (Ancillary Building & EE) Rmt 172 112 112 65.12%
4.27 Steel Waler Level-4 (Ancillary Building & EE) Rmt 172 70 70 40.70%
4.28 Rock Bolt Nos. 700 352 352 50.29%
5.00 STATION BOX - SLABS & WALLS
Base Slab Rmt 250 95 115 45.84%
Side Walls (B-C) Rmt 250 53 68 27.38%
1st Lift Rmt 56 56 West-28.75 Rmt, East-18.75 Rmt
UPE Wall Rmt 1,020 50 70 6.86%
COLUMN
Base to Concourse No's 22 3 4 18.18%
5.01 ENTRY-EXIT SLABS & WALLS
EE-2 Base / Extended Concourse Rmt 17 17 17 100.00%
EE-2 Walls Rmt 42 (9 Rmt-1.5m Height casting completed)
5.0 Worli Station
7.0 TBM;TANSA-1
Initial Drive for TANSA 1 - 23 Aug-18; Breakthrough at SWO on 28-Jan-
7.01 Tunneling up line (SSM-SWO) Rings 1,382 1,382.00 1,382 100.00%
20
7.02 Tunneling down line (SSM-SMC) Rings 1,311 439.00 4 471 35.93% 4
8.0 TBM;TANSA-2
8.03 Tunneling up line (SSM-SMC) Rings 1,303 373.00 408 31.31% Start Date - 08-11-2020
Max. Temp
30.0 Weather Cloudy LOA 1-Jul-16 Original Project End Date 10-Jan-21 Progress Date 12-Apr-21
(0C) GENERAL
Min. Temp Rainfall Notice To CONSULTANT
23.0 18-Jul-16 Reporting Date 13-Apr-21
(0C) (mm) Proceed
9.02 Excavation Cum 2,564 2,564 2,564 100.00% Start Date -12-07-2019; End Date - 01-06-2020
9.03 Base Slab SQM 108 108 108 100.00% Start Date -22-06-2020; End Date - 22-06-2020
9.04 Pipe Umbrella Cycle 1 & 2 Nos 90 90 90 100.00% Start Date -25-07-2020; End Date - 15-09-2020
9.05 Pipe Umbrella Cycle-3 Nos 45 45 45 100.00% Start Date - 15 Feb-21
10.05
10.0 Access Tunnel (Cross Over)
10.01 Excavation - Heading Rmt 27 20.34 20.34 75.70% Start Date - 05-10-2020
10.02 Excavation - Benching Rmt 27 9.94 14.7 54.92%
11.0 Cross Passge - SAA to SWO
CP 1
Excavation - Heading Rmt 9 2.00 6 66.67%
CP 2
Excavation - Heading Rmt 9 5.00 7 77.78%
CP 3
Excavation - Heading Rmt 9 7.00 7 77.78%
CP 4
Excavation - Heading Rmt 8 8.00 8 100.00% Start Date - 03-01-2021, End Date - 17 -02 -2021
CP 5
Excavation - Heading Rmt 9 3.00 7 77.78%
Staff MAJOR PLANT & EQUIPMENTS Other Equipment Manpower Project Bottlenecks
Sr No Key Staff Deployment Nos. Major Equipment SMC SML SSM SAC SWO Total TBM 02 Nos. SMC 249 All stations
SMC
3 Stations Managers 4 Hydra 1 1 1 1 1 5 SAC 194
• Delay in design finalisation of EE 1, 2 & 3.
SML
Crane (Tower Crane, Mobile
4 Enginnering Manager & Design 1 3 2 6 2 1 14 SWO 262 MHADA Building west side Grid no (19-23).
Crane)
Congested workspace due to unavailability of land
5 Civil Engineers (Execution) 40 DTH Machine 1 1 CY 66 outside station box for utility diversion.
SSM
Due to awaiting traffic diversion permission
6 SHE Manager & Team 25 Dumper 2 2 1 1 1 7 RG 51 CJV is unable to clear the area free from
utilities obstruction to facilitate the
construction of EE 5 & 6.
SAC:
7 QA & QC Team 30 ROC Machine 1 2 1 2 6 Sewri Loss of time due to manual excavation in
between the cluster of multiple utilities.
SWO
8 Tunnel Team 60 Shotcrete machine 1 1 2 NATM 157 Non-Availability of land and access to Ancillary
Building.
Total 1526
# Note
1 Due to Covid-19 and social distancing norms DSJV is finding it difficult to achieve desired progress for Station, Tunnel and NATM works.