Hanoi University of Science and Technology School of Economics and Management
Hanoi University of Science and Technology School of Economics and Management
PROJECT REPORT
Project: “Build the center brokerage to support students and workers
easily and properly”
Students:
Name: ID:
Nguyễn Thị Hồng Gấm 20198011
Trần Thùy Linh 20198026
Trần Duy Khánh 20198020
Nguyễn Văn Chiến 20198008
Phạm Quốc Trung 20198048
Nowadays, information technology has become popular and very important. It has
been applied in many fields of life, and, of course, the benefits and effectiveness that
it has brought are not deniable. It is obvious that it helps us solve the optimization
problems such as minimizing manual and inefficient work stages, saving much time
and cost for manufacturing. In the current period that the world is entering the 4.0
revolution, the application of information technology in management and
administration is always a top priority for business and the projects based on
information technology (Internet of Things) are increasingly invested and developed.
Inspired by life, we have cherished and decided to launch a project to solve the
problem of finding accommodation for everyone and of course, it is based on IoT.
Accommodation and hostel are always an urgent need of everyone, especially
students, and finding it is always completely difficult. We had the intention of
building a center brokerage which runs both offline and online for accommodation
brokerage to help customers update with a large, diverse and accurate information
about accommodation. We hope that our project will provide new experience to
people in finding accommodation and bring maximum efficiency and convenience
when using it.
When our project is launched, it will be a potential project and attract the attention
of many customers due to its convenience, diversity and quick update.
1
B/ PROJECT CHAPTER:
1. Overview:
- Name of project: “Sweet home”
- Starting time: 5/8/2021
- Finishing time: 5/10/2021
- Budget: 10000$ (220,000,000 VND)
- Project manager: Nguyen Thi Hong Gam & Tran Duy Khanh
a, Approach to project:
- Determine specific requirements for the software and do survey about some
sample systems for orientation.
- Define the stakeholders clearly.
- Specify the work breakdown structure, scope statement, milestones to complete
the project within 2 weeks.
- Carry out the analysis, designing, development and software testing within a
month.
- Organize the meeting between the members of project team every week to
report project progress.
b, Reasons to establish project:
- The number of students increases rapidly every year and most of them come
from other provinces. So, the need to find accommodation is increasingly high and
becomes the important issue in the society.
- The demand for accommodation is constantly increasing while the ability of the
brokerage firms to meet is not enough.
- Many students are tricked into losing money into disreputable accommodations.
- Strong development of technology informatin and the explosion of Internet-
based technology.
c, Objective of project:
We will be the middle bridge between those who want to rent out and those who
want to rent.
- Help and support students to find accommodation with quality assurance and
reasonable price.
- Reduce the hard work of students and their families when looking for
accommodation.
- Save time and money for finding accommodation.
2. Business model:
- Combining online and offline.
2
- Firstly, providing internet-based environment for landlords to post the photos
and basic information about the accommodation to attract tenants. Students or
workers can access to our website to find accommodation which suits their interest
and finance.
- Secondly, we can set up (design and decorate) according to request. We have a
system of vacant accommodations rented by ourselves, we provide basic
information about it such as size, lighting level, location on the website. They can
find a suitable room, then we will design layout, installation and decorate following
their request which is stated on the contract.
3. Stakeholders:
- Definition: Project stakeholders are individuals, groups, or organizations who
may affect, be affected by, or perceive themselves to be affected by a decision,
activity, or outcome of a project.
- Internal:
1. Owner
2. Managers
3. Employees
- External:
1. Suppliers: landlords
3
2. Customers: students and their parents
3. Competitors: other brokerage centers
4. Regulators: local goverment
C/ STAKEHOLDER REGISTER:
4
Regulators Supporte Local External Supports Provide legal Reputation
r governme-nt documents
5
1. Project scope:
1.1. Production scope:
The final website had to respond to this requirement:
- Easy and comfortable to use
- Intuitive interface
- Works well with all required functions
- Coded by JSP language
- Used on multiple platforms: Google chrome, safari, firefox, internet explorer
1.2. Resource scope:
- The total expense of this project: 40 000 000 VNĐ:
+ The salary of staff
+ The renting cost of the office
+ The renting cost of the accommodations
+ The costs incurred:
+ The reserve cost: 8% of this project
- The number of members: 5 people
+ Layout and design the website: all of the members
+ Collect and analyze the data: all of the members
+ Contract with the IT designer: Gấm and Linh
+ Contract to rent and decorate the office: Khánh and Trung
+ Marketing: Chiến
1.3. Time range:
- The project implementation time: no longer than 2 months (around 60 days)
- Estimated time due to the small project, so if there is a change, not too large
at about 10 days
2. The planning tools:
- Microsoft Word 2016 (Public text editor)
- Microsoft Excel 2016 (Computational and drafting tools)
- Microsoft Project 2016 (Construction tool for project management scheduling)
- Eclipse, Subtext (Software programming)
- SQL Server (Construction tools database)
- Star-UML (Design tool to build Usecase organization chart)
- References to other project
6
3. Work breakdown structure:
7
F/ PLAN SCHEDULE MANAGEMENT
8
(9) (10) 1/2 80
(11), (12), (13) (6), (7) 0 0
(14) - 1 0
(15), (16) (14) 1 150
(17) - 1/2 0
(18) (17) 3 250
(19), (20), (21), (22) (18) 1 300
(23) - 3 130
(24) (23) 1 700
(25), (26), (27), (28) - 2 350
(29), (30), (31) - 1 100
(32) (31) 1 320
3. Gantt chart:
9
G/ PROJECT COST MANAGEMENT
1. Estimate Material costs:
Project budgets presented as material costs such as :
Categories Number Cost Total
Data Base 1 30.000.000đ 15.000.000đ
Copyright registration 1 1.000.000đ 500.000đ
Total costs 15.500.000đ
10
time
Categories Number cost Total amount
5
Office 1 65$/month 3.500.000đ
Internet 5
1 22$/month 1.500.000đ
5
Utility bills 1 22$/month 1.500.000đ
6 Programmer 100.000đ
7 Tester 100.000đ
11
1.0 1 Survey 7.7 3.700.000đ
1.1 1 Customer meeting 2.1 1 1 500.000đ
1.2 2 Requirement 3.4 1 3 2.000.000đ
1.3 3 Requirement 1.0 1 3 500.000đ
control
1.4 4 Report 1.0 1 4 700.000đ
2.0 2 Analytical course 27 9.950.000đ
12
6.1 1 Test module 2.16 1 3 1.150.000đ
Total 65.680.000đ
costs
5. Costs incurred:
Number
Categories Number Cost Total
2 130$
Party cost 2 6.000.000đ
3 Setup cost 5 10$
1.000.000đ
4 Telephone
44$ 1.000.000đ
6. Total costs:
13
2 Facility costs 8.000.000đ
3 Salaries 108.000.000đ
4 Website 65.680.000d
5 Costs incurred 8.400.000đ
Total 205.580.000đ
costs
This is the total estimated cost for Sweet Homes project , this cost is under control
as the initial costs prediction
7. NPV:
Material costs 15,500,000
Investment cost Website 65,680,000
1
Sum 81,180,000
2 Useful life (N) 5
3 Salvage value (S) 10,000,000
4 Revenue (R) 160,000,000
Facility costs 8,000,000
Expenses Salaries 108,000,000
5
Costs incurred 8,400,000
Operating expenses (Sum) 124,400,000
6 Depreciation 14,236,000
7 Tax rate (i) 25%
8 Firm interest(MARR) 15%
9 Taxable income 21,364,000
10 Income tax 5341000
Income
Years Investment Cost Revenue Operating Expenses tax Cash flow
0 -81,180,000 -81,180,000
1 160,000,000 -124,400,000 -5341000 30259000
2 160,000,000 -124,400,000 -5341000 30259000
3 160,000,000 -124,400,000 -5341000 30259000
4 160,000,000 -124,400,000 -5341000 30259000
5 10,000,000 160,000,000 -124,400,000 -5341000 40259000
NPV 25224628
IRR 27%
14
H/ HUMAN RESOURCE MANAGEMENT PLAN
1. Positions in project management
Positions Quantity
Business analyst team Total: 5
Leader 1
Members 4
Design team Total: 5
Leader 1
Solution Designer 1
Interface Designer 1
Database designer 2
Programming team Total: 3
Leader 1
Programmer 2
Deployment team Total: 2
15
I/ COMMUNICATION PLAN:
16
- Feedback method: Ask the customer to finalize the final change.
- Estimated cost of response: Depending on the stage of change, additional costs
may be required from the customer.
- Estimated response time: Instant.
- Personnel to deal with: PM, system analyst.
2. Project ruptured time plan
- Characteristics: The work is not completed on schedule leading to delayed
handover of products to customers.
- Appearance Time / Frequency : At the beginning and end of the project
- Causes: Due to the subjectivity of the project team members, it takes time to
learn the business process of the customer supermarket, there is no specific
schedule.
- Hedging: PM needs to clearly identify the work to be done from the beginning,
creating a specific schedule for each member.
- Response method: Determine the number of days behind schedule, shorten the
time some work does not matter, if it is not possible in time, it must notify the
customer in advance with an apology and explanation.
- Estimated response time : Immediately after the PM holds a meeting to resolve
difficulties with members.
3. The members of the project team are not united, contradictory to each other
- Characteristics: Members do not really cooperate at work, slander each other
affecting the quality as well as project progress.
- Appearance time / Frequency : At any time, but most often during the project
execution phase.
- Causes: It is possible that because the team is newly formed, the members have
not had time to get to know each other.
- Hedging: PM needs to hold a meeting for the entire project team before starting
to work on the official project so that everyone understands each other better.
- Response method: When assigned to members, the PM must ensure fairness.
During the implementation period, the PM must pay close attention to the team,
promptly resolve small conflicts. · Estimated reaction time : Instant.
- Human Response Personnel : PM.
4. A member unexpectedly asked to withdraw from the project
- Characteristics : A team member suddenly started his intention to leave the
project despite the ongoing progress.
- Appearance Time / Frequency : At any time during the project implementation
period
17
- Causes: There can be many causes such as: That member has health problems
or family reasons, sometimes due to being attracted by another company.
- Hedging: Before starting the project, the PM needs to establish strict team
contracts with the project team, which stipulates that each member who wants to
quit must notify the PM at least 2 weeks in advance.
- Response method: In case of risks, the PM first needs to carefully determine the
large amount of work that employees leave behind. It's best to give other employees
that part of it. If there are not enough personnel, we need to recruit new people to
complete the job.
- Estimated reaction time : 1 to 2 weeks.
- Personnel Reaction : The remaining members of the team or new recruits.
5. Customers cancel contracts, withdraw project sponsorship
- Characteristics: Customers want to terminate the contract or cut off funding for
the project team.
- Appearance time / Frequency : At any time during the project execution phase.
- Causes: Due to many reasons such as customers not satisfied with the work or
products of the project team, or due to uns warranted financial capacity.
- Hedging: There should be strict binding terms in the contract with customers to
prevent them from unilaterally canceling the contract.
- Response method: Try to convince customers to retain the project, and if the
customer resolutely wants to cancel, claim the project money then go find another
potential customer.
- Reaction time : 1 to 2 weeks
- Personnel Response : PM.
6. The project is out of funding
- Characteristics: During the implementation of the project, the PM found that the
remaining amount was not enough to spend on the remaining activities of the
project.
- Appearance time / Frequency : At any time during the project implementation
phase.
- Causes: It may be due to an unsynced cost plan that leads to a rupture of funds
for the project, or because members overs spend, not complying with the plan can
also lead to a fund rupture.
- Hedging: PM needs to agree with the whole team on a clear spending plan,
requires the entire project team to strictly implement, and takes the form of
discipline with members who do not comply with the spending plan.
- Response method: Identify the cause of the project budget deficit, then meet
the whole team to propose a solution. It is possible to minimize activities that are
18
not really important to the project, in case it is difficult for the PM to contact
customers immediately, try to apologize and ask for more funding for the project.
- Reaction time : Immediately.
- Personnel Response : PM
References:
1. Lectures note.
2. A Guide to Project Management Body of Knowledge: PMBOK, by Project
Management Institute.
3. The Toyota Way, by Dr. Jeffrey Liker.
4. Be Fast or Be Gone: Racing the Clock with Critical Chain Project Management,
by Andreas Scherer.
5. Agile Project Management with Scrum, by Ken Schwaber.
6. How Stella Saved the Farm: a Tale About Making Innovation Happen, by Vijay
Govindarajan and Chris Trimble.
7. Some other Vietnamese documents.