DWST-MTHL-QP009 Non-Conforming Item Control Procedure
DWST-MTHL-QP009 Non-Conforming Item Control Procedure
PACKAGE II
REVISION LOG
TABLE OF CONTENTS
1.0 PURPOSE
This procedure is to define the roles, responsibilities and processes surrounding the reporting, recording
and resolving of identified or discovered non-conformances.
2.0 SCOPE
This procedure describes the methodology of controlling non-conforming items found during MTHL
Project package II execution to provide a process for the identification, reporting and documentation of
nonconformities reported or discovered through observation, surveillance, notified inspection at
assembly and erection site.
3.0 DEFINITION
Deviation to the Owner specification is not-acceptable. The disposition of product non-conformities shall
be categorized into four (4) basic types, as follows:
a) Concession : Should be for using alternate method/technique as defined in the original accepted
proposal
b) Rework/Repair : Action on a nonconforming product to make it acceptable for the intended use
4.1 RESPONSIBILITY
All personnel are responsible for identifying and reporting any actual materials, equipment, services,
or processes and that would result in a level of quality outside of accepted or established standards
MUMBAI TRANS HARBOUR LINK PROJECT PACKAGE II
Is responsible for:
- Carrying out Defect Trend Analysis of NCR during first year of project
Is responsible for:
- Identification and reporting of Non-conforming items
Has a responsibility of controlling nonconformities per the accepted disposition of the Non- conform-
ance Report (NCR) for their assigned areas and disciplines.
Is responsible for:
- Preventive action
5.1 Identification
When QC Inspector detects, suspects or is informed of the existence of the non-conforming item, he
shall investigate the non-conformity and report to Project QC Manager.
5.2 Segregation
Once, a non-conforming item is identified by QC Inspector, he shall stop the use or operation of the item
by segregating if possible, and attaching the "Hold" or “Reject” label for guarantee or marking.
Only the QC Inspector shall remove the label/marking once the disposition has been approved and
the corrective action, if required, has been implemented satisfactorily.
The engineer / foreman in charge of the item in Construction Department, Material Management
Department or other Departments are responsible for segregation of the non- conforming item.
QC Inspector shall also ensure that the Non-conforming item has been segregated to the designated
area or identified.
All NCR submissions must be filled out by the originator on the established NCR format.
QC Inspector shall describe the actual condition of non-conformance with back-up data (i.e. documental
evidence or picture and etc.) with the NCR report
Project QC Manager shall decide the necessary disposition action through investigation and discussion
with Construction & Engineering Manager as necessary.
The disposition shall be approved and should include the expected disposition date to be proposed
by Project QC Manager and CONTRACTOR.
When the disposition of NCR is approved, the copies of NCR shall be distributed to QC Inspector,
and relevant parties. Relevant parties (including Responsible Department) will be designated by QC
Manager based upon NCR details.
Correction of the non-conforming item shall be made in accordance with the approved disposition. QC
Inspector shall check the correction, and report the verification result to Project QC Manager when the
correction is completed and verified.
Project QC Manager shall attach the back-up documents, if necessary, to the NCR and close it out with
verification by CONTRACTOR.
MUMBAI TRANS HARBOUR LINK PROJECT PACKAGE II
CONTRACTOR acceptance to the corrective action(s) or correction performed is required to close out
the NCR.
Once the NCR is issued, information related to the NCR shall be registered in the "NCR Register"
Defect trend analysis will be carried out by QC Manager every 3months before Performance Review
Meeting. Sorted cause code will be utilized for quick recall of defect type for analysis purpose.
11.0 APPENDIX
Identification of
Non-Conformance * DTJV/GC finding NC
shall be handled with
Stop the Operation same flow of this.
Segregation
Labelling of Hold/Rej.
NCR Preparation
(Actual Condition)
NCR Disposition/
Registration of NCR
Review/Approvall of
NCR Disposition
Confirm of
Close of NCR
Correction
Review/Approval of
NCR Closure
Distribution of Removal of
Closeout NCR Hold/Reject Label
Implementation
"HOLD LABEL"
"REJECT LABEL"
MUMBAI TRANS HARBOUR LINK PROJECT PACKAGE II
Mismatch of
Proposed Civil drawing Defective Mishandl Approved Inadequate
NCR - Name of the Open/ Actual Date of Rework Cost borne Drawing
NCR/FOR/FIN Rejected/ Agency Completion Rework cost with Workmanship / Transit ing of Improper Inspectio Procedures / Natural Inputs /
S.NO NCR/FOR/FIN No Description Discipline Major / NCR Type Root Cause Details Issued by Vendor / WIP/ Completion of Details of Correction Done Preventive Action by Revision /
Date Rectifiable Responsible date of (Rs.) Mechanical / Materials / Damages items at Storage n Error FQP / QAP Calamity Resources /
Minor Subcontractor Closed Resolution TPL / Subcontractor Modification
Resolution Electrical Equipments sites not followed QA Systems
drawing
1 1 03.06.2016 Curing bunds are not prepared for curing of raft Civil Major Structural Rectifiable Curing done by providing hessain cloth. FQE Closed 03.06.2016 04.06.20169
Document No.:
9
DWST-MTHL-MS-009
10
11
12
13
(Exhibit – 4 : NCR Register)
14
15
16
17
REV.
18
19
1
20
21
22
PAGE
23
Non-Conforming Item Control Procedure
MUMBAI TRANS HARBOUR LINK PROJECT PACKAGE II
15 of 13