Summary of all Works
Page 2 of 39
Pipe Summary
Page 3 of 39
Civil Work Summary
Page 4 of 39
Electro-Mechanical Summary
Page 5 of 39
Bill No A: General Items
Total
Previous Current Unit Rate Previous Current Contract
Item Description Unit Quantity Quantity Quantity Quantity (Birr) Amount Amount
Total Amount
Amount
A1 Contractor's Mobilization & demobilization
Mobilization of contractor's man power, construction materilas
A1.1 Ls 1 0.85 0.85 600,000 0 510,000 510,000 600,000
and equipment to construction site
Demobilization of contractor's man power, construction
A1.2 Ls 1 0.0 480,000 0 0 0 480,000
materilas and equipment from construction site
Page 6 of 39
Main Line civil works
BILL NO. B-0.4.1 Construction of Valve chambers, crossings and Thrust & anchor blocks for pressure line
River Crossing Type OD 250mm HDPE #2
Previous Current Total Unit Rate Previous Current Contract
B-04.1.0 Description UNIT QNTY
Quantity Quantity Quantity (Birr) Amount Amount Amount
Page 7 of 39
Main Line civil works
Page 8 of 39
ML civil work takeoff
Page 9 of 39
Main Line Trench Excavation
BILL NO. B-03:-MAIN LINE TRENCH EXCAVATION (RAISING AND TRANSMISSION MAIN) EARTHWORK
B-03.1 FROM BH TO BOOSTER STATION 1
Contract Previous Current Total Unit Rate Previous Current Total Contract
B-03.1.1 Earth Work unit
Quantity Quantity Quantity Quantity (Birr) Amount Amount Amount Amount
Page 10 of 39
Main Line Trench Excavation
Page 11 of 39
takeoff Trench Excavation
Page 12 of 39
takeoff Trench Excavation
Page 13 of 39
takeoff Trench Excavation
Page 14 of 39
Page 15 of 39
Page 15 of 39
Page 16 of 39
C-06.1.19 DN 250 flanged gate valve No 1 1 1 7,500 0.0 7,500.0 7,500.0 7,500.0
D-0.6.21 DN 250 dismantling joint No 1 1 1 7,500 0.0 7,500.0 7,500.0 7,500.0
Total of Bill . Construction of rectangular cooling 0.0 618,515.5 618,515.5 1,339,280.3
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 16 of 39
takeoff cooling tank
C-06.1.0EARTH WORK
D-0.6.5MASSONARY WORK
C-06.1.4construct stone massonary trapezoidal
2 25 23 0.7 1.1 73.92 foundation wall of the birka with 700mm at base and
600mm at the top
D-0.6.6construct stone massonary trapezoidal wall
of the birka with 600mm at base and 500mm at the
top
C-06.1.550 cm thick basaltic or equivalent stone
1 25 23 0.25 143.75 Hard core well rolled, consolidated & blinded with
crushed stone
D-0.6.7CONCRETE WORK
C-06.1.650mm thick lean concrete C-10 above the
1 23.6 21.6 509.76
hard core
D-0.6.8Reinforced concrete type C-30 of the base
floor filled into form work and vibrated around
reinforced bar
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 17 of 39
Bar Schedule Cooling
Page 18 of 39
UNDERGROUND TANK 200M3
Page 19 of 39
UNDERGROUND TANK 200M3
Page 20 of 39
UNDERGROUND TANK 200M3
Page 21 of 39
takeoff 200m3
C-03.1.11 Reinforced concrete type C-30 filled into form work &
vibrated around reinforced bar mix ratio should be 1:2:3
Page 22 of 39
takeoff 200m3
C-03.1.16 Parapet
C-03.1.17 Provide and fix formwork to
1 9.7 0.4 C-03.1.18 Base slab
3.142 12.1893795 m2
C-03.1.19 Wall
1 9.1 1.3
1 8.5 1.3
1 8.5 1.45
3.142 110.5997694 m2
C-03.1.23 Provide, cut, bend and fix in position reinforced steel
bar. All according to structural drawing. Price should include
tying wires
C-03.1.24 Diameter 8 mm plain bar
C-03.1.25 Diameter 10 mm deformed bar
C-03.1.26 Diameter 12 mm deformed bar
C-03.1.27 Diameter 14 mm deformed bar
C-03.1.28 Diameter 16 mm deformed bar
C-03.1.29 Reinforced concrete type C-25 filled into form work and
vibrated around reinforced bar mix ratio should be 1:2:3 for valve
chamber
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 23 of 39
Bar Schedule 200m3
bottom reinforcement
Base Slab
16mm@130mm c/c
D 9.63
so 0.13
cc 35 0.035
ts 350 0.35
I Di Hook Li No of bars L
0 9.63 0.63 10.26 2 20.52
1 9.63 0.63 10.26 4 41.03
2 9.62 0.63 10.25 4 40.98
3 9.60 0.63 10.23 4 40.91
4 9.57 0.63 10.20 4 40.81
5 9.54 0.63 10.17 4 40.69
6 9.50 0.63 10.13 4 40.53
7 9.46 0.63 10.09 4 40.35
8 9.40 0.63 10.03 4 40.13
9 9.34 0.63 9.97 4 39.89
10 9.27 0.63 9.90 4 39.61
11 9.20 0.63 9.83 4 39.30
12 9.11 0.63 9.74 4 38.96
13 9.02 0.63 9.65 4 38.59
14 8.92 0.63 9.55 4 38.18
15 8.80 0.63 9.43 4 37.74
16 8.69 0.63 9.32 4 37.26
17 8.56 0.63 9.19 4 36.74
18 8.42 0.63 9.05 4 36.19
19 8.27 0.63 8.90 4 35.59
20 8.11 0.63 8.74 4 34.94
21 7.93 0.63 8.56 4 34.25
22 7.75 0.63 8.38 4 33.51
23 7.55 0.63 8.18 4 32.71
24 7.33 0.63 7.96 4 31.86
25 7.11 0.63 7.74 4 30.94
26 6.86 0.63 7.49 4 29.95
27 6.59 0.63 7.22 4 28.89
28 6.30 0.63 6.93 4 27.74
29 5.99 0.63 6.62 4 26.48
30 5.65 0.63 6.28 4 25.11
31 5.27 0.63 5.90 4 23.60
32 4.85 0.63 5.48 4 21.92
33 4.37 0.63 5.00 4 20.01
34 3.82 0.63 4.45 4 17.80
35 3.15 0.63 3.78 4 15.12
36 2.26 0.63 2.89 4 11.58
37 0.44 0.63 1.07 4 4.27
1,214.69 16mm
top reinforcement
Base Slab
14mm@130mm c.c
0 9.63 0.10 9.73 2 19.46
Page 24 of 39
Bar Schedule 200m3
Page 25 of 39
Bar Schedule 200m3
Page 26 of 39
Bill No. C- 015.0Toilet At 1000m3, 500m^3 booster station and @ borehole
C-015: CONSTRUCTION OF SOAK AWAY PIT
Previous Current Previous Total Contract
Item DESCRIPTION Unit Qty
Quantity Quantity Amount Amount Amount
C15.3 Clearing of site to remove top soil to a depth of 200 mm m2 12.0 0.00 26.5 0.0 0.0 0.0 318.0
C.15.3 Bulk excavation in ordinary soil to depth of 1.5m m3 15.0 0.00 177.0 0.0 0.0 0.0 2,655.0
C15.4 Bulk excavation in soft rock m3 15.0 0.00 331.0 0.0 0.0 0.0 4,965.0
C.15.4 Bulk excavation in hard rock m3 12.0 0.00 468.0 0.0 0.0 0.0 5,616.0
C15.5 Curt away excavated material m3 42.0 0.00 52.0 0.0 0.0 0.0 2,184.0
C.15.5 Masonry Work 0.00
C15.6 masonar wall with 50cm at the base and 40cm at top m3 35.0 0.00 1,701.0 0.0 0.0 0.0 59,535.0
C.15.6 concerete work 0.00
Reinforced concrete septic cover C30 (Cement 1440 kg/m3) filled into
C15.7 form work and vibrated around reinforced bars, mix ratio should be 1 :2:3 0.00
in
C.15.7 Soak pit top slab m3 2.3 0.00 3,899.0 0.0 0.0 0.0 8,772.8
C15.8 Reinforcement 0.00
Provide, cut, bend and fix in position reinforced steel bar. All according to
C.15.8 0.00
structural drawing. Price shall include tying wires
C15.9 diameter 12 kg 650.0 0.00 69.2 0.0 0.0 0.0 44,980.0
C.15.9 diameter 10 kg 90.0 0.00 66.8 0.0 0.0 0.0 6,012.0
C15.10 diameter 8 kg 80.0 0.00 64.4 0.0 0.0 0.0 5,152.0
C.15.10 Miscellaneous 0.00
Supply and lay 100 mm dia. PVC pipe as shown on the drawing, price
C15.11 m 100.0 0.00 78.0 0.0 0.0 0.0 7,800.0
including excavation of earth and back filling drianage conection
C.15.11 Supply and fix 100x100 mm tee Pcs 4.0 0.00 3,500.0 0.0 0.0 0.0 14,000.0
C15.12 Supply and fix 100 mm dia. PVC ventilation pipe hood shaped covering (cowl) Pcs 2.0 0.00 2,800.0 0.0 0.0 0.0 5,600.0
C.15.12 Supply and fix 40*40cm manhole cover concrete with handling frame pcs 2.0 0.00 1,200.0 0.0 0.0 0.0 2,400.0
Sub Total for Soak Away Pit 0.00 0.00 0.00 169,989.75
CONSTRUCTION OF TOILET
C.15.13 Earth Work
C15.14 Clearing of site to remove top soil to a depth of 200 mm m2 9.0 0.0 0.00 26.5 0.0 0.0 0.0 238.5
C.15.14 Excavation for stone masonry foundation; 0.5 m width and 0.5 m depth m3 3.0 0.0 0.00 88.0 0.0 0.0 0.0 264.0
Cart away and deposit excavated surplus material to a distance not exceeding I m3
C15.15 6.0 0.0 0.00 52.0 0.0 0.0 0.0 312.0
km
C.15.15 fill for the selected material m2 3.0 0.00 50.0 0.0 0.0 0.0 150.0
Page 27 of 39
C15.16 Masonry Work
Supply and place 250 mm thick hard core compacted to receive reinforced floor m2
C.15.16 10.0 14.0 14.00 189.0 0.0 2,646.0 2,646.0 1,890.0
slab
C15.17 Supply and place 500 mm thick hard core for founation wall m2 7.0 28.0 28.00 189.0 0.0 5,292.0 5,292.0 1,323.0
C.15.17 Sub-Total
C15.18 Concrete and Block Work
Reinforced concrete grade C-25 with minimum cement content 1440 kg/m3
C.15.18
cast into formwork and vibrated around reinforcement bars in
C15.19 RC floor tie beam m3 3.0 0.00 3,592.0 0.0 0.0 0.0 10,776.0
C.15.19 RC column m3 1.3 0.00 3,592.0 0.0 0.0 0.0 4,525.9
C15.20 Mass concrete fill on floor slab (100 mm) m3 1.3 0.00 3,592.0 0.0 0.0 0.0 4,490.0
C.15.20 Lintel m3 0.1 0.00 3,592.0 0.0 0.0 0.0 179.6
C15.21 RC roof tie beams m3 2.5 0.00 3,592.0 0.0 0.0 0.0 8,980.0
Provide, fix in position, cut and bend reinforced steel bar. All according to
C.15.21
structural drawing. Price should include tying wires
C15.22 Diameter 8 mm deformed bar kg 120.0 0.00 64.4 0.0 0.0 0.0 7,728.0
C.15.22 Diameter 10 mm deformed bar kg 98.8 0.00 66.8 0.0 0.0 0.0 6,599.2
C15.23 Provide, cut, and fix formwork beam column m2 19.2 0.00 500.0 0.0 0.0 0.0 9,600.0
C.15.23 Block work 0.00
C15.24 20cm HCB block for wall No 250.0 0.00 306.0 0.0 0.0 0.0 76,500.0
C.15.24 Carpentry and Roofing
Supply, assemble and fix in position roof truss price shall include the ml
C15.25 25.0 0.00 28.9 0.0 0.0 0.0 723.7
application of three coats and external anti-termite treatment
Supply and fix purl in in zigba wood size 50 x 70 mm nailed into eucalyptus ml
C.15.25 30.0 0.00 37.1 0.0 0.0 0.0 1,111.5
truss including three coats of anti - termite external treatment
Supply and fix roof cover in G-28 mm corrugated galvanized iron sheet fixed m2
C15.26 into zigba wood purl in with dome headed galvanized nails (purlin and ridge 24.0 0.00 354.0 0.0 0.0 0.0 8,496.0
cover measured separately)
Supply and fix edge gutter formed in G- 28 flat galvanized metal sheet m
including support brackets 1 mm thick shaped steel plate spaced at a maximum
C.15.26 5.0 0.00 321.0 0.0 0.0 0.0 1,605.0
spacing of 1000 mm c/c and fixed to purl in - price includes metal primer and
two coats of synthetic eName: Eng Abiyot Demissie l paint
Supply & fix diameter 100mm down pipe in G-28 including I mm thick metal m
C15.27 support brackets fixed at a maximum interval of 1000 mm fixed to walls or 15.0 0.00 397.0 0.0 0.0 0.0 5,955.0
columns
C.15.27 Supply and fix 25x 250 mm fascia board to purl in m 9.8 0.00 167.1 0.0 0.0 0.0 1,637.2
C15.28 Supply and fix metal windows size 1x1.8m price includes lock hachs m2 1.8 0.00 5,040.0 0.0 0.0 0.0 9,072.0
Pcs
C.15.28 Supply and fix metal doors size 2.1 Ox1 with figured glass in upper half portion 2.1 0.00 5,880.0 0.0 0.0 0.0 12,348.0
Page 28 of 39
Finishing; finishing work shall include all surface pre-cleaning, polishing
C15.29
and cleaning at the end of finishing
C.15.29 Floor screed in cement mortar 20 mm thick m2 1.8 0.00 109.0 0.0 0.0 0.0 196.2
C15.30 Apply cement mortar pointing to all external cement concrete block wall m2 34.0 0.00 74.0 0.0 0.0 0.0 2,516.0
Apply 3 coats of plastic paint to internal ,externalwalls and synthetic paint to m2
C.15.30 36.0 0.00 47.0 0.0 0.0 0.0 1,692.0
metal doors and windows
C15.31 Electrical Installation
C.15.31 Supply and install the required electrical works LS 1.0 0.00 5,500.0 0.0 0.0 0.0 5,500.0
Sub Total for Toilet 0.0 7,938.0 7,938.0 184,408.8
Total for 1 Toilet including Soak Awey Pit 0.0 7,938.0 7,938.0 354,398.6
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 29 of 39
takeoff toilet@BH
Page 30 of 39
Wet well@BH
Bill No. C- 07 Construction of Artificial Well @ 200m3 underground Booster and at 500m3 rcc ground Booster I
Previous Current Total Unit Rate Previous Current Total Contract
ITEM DESCRIPTION UNIT QNTY
Quantity Quantity Quantity (Birr) Amount Amount Amount Amount
C-07.1 EARTH WORK
C-0.7.2 Site Clearing to remove Top Soil up to 20cm Depth m2 14.4 0.0 0.0 26.5 0.0 0.0 0.0 381.6
C-07.2 Bulk excavation in normal soil to a depth not exceeding 3m m3 20.0 0.0 0.0 303 0.0 0.0 0.0 6,060.0
C-0.7.3 Ditto but in soft rock formation not exceeding 2.5m m3 26.5 0.0 0.0 331 0.0 0.0 0.0 8,771.5
C-07.3 Ditto but in hard rock formation 2m m3 20.0 0.0 0.0 468 0.0 0.0 0.0 9,360.0
Cart away all excavated material, deposit to appropriate distance not
C-0.7.4 m3 66.5 0.0 0.0 52 0.0 0.0 0.0 3,458.0
exceeding 1 km
Provide and fill with suitable selected granular material not
C-07.4 m3 3.0 0.0 707 0.0 0.0 0.0 2,121.0
exceeding 50cm
Provide and fill hard core with hard basaltic or equivalent stone, well
C-0.7.5 compacted and blinded with crushed stone to a finished thickness of m3 7.9 0.0 189 0.0 0.0 0.0 1,493.1
25 cm under the artificial and valve chamber
C-07.5 CONCRETE WORK 0.0 0.0 0.0 0.0 0.0
30cm thick lean concrete C-10 under the artificial base slab and
C-0.7.6 m2 3.6 0.0 180 0.0 0.0 0.0 648.0
valve chamber
Reinforced concrete type C-30 filled into form work and
C-07.6 0.0 0.0 0.0 0.0 0.0
vibrated around reinforced bar
C-0.7.7 Base slab m3 3.2 0.0 3,899 0.0 0.0 0.0 12,632.8
C-07.7 Concrete wall m3 9.9 0.0 3,899 0.0 0.0 0.0 38,600.1
C-0.7.8 Top slab m3 3.6 0.0 3,899 0.0 0.0 0.0 14,036.4
C-07.8 Valve Box m3 5 0.0 3,899 0.0 0.0 0.0 19,495.0
C-0.7.9 Provide and fix formwork to: 0.0 0.0 0.0 0.0 0.0
C-07.9 Base slab m2 6.6 0.0 500 0.0 0.0 0.0 3,300.0
C-0.7.10 Wall m2 39.6 0.0 500 0.0 0.0 0.0 19,800.0
C-07.10 Top slab m2 5.6 0.0 500 0.0 0.0 0.0 2,800.0
Provide, cut, bend & fix in position reinforced steel bar. All
C-0.7.11 according to structural drawing. Price should include tying 0.0 0.0 0.0 0.0 0.0
wires
C-07.11 Diameter 8 mm plain bar kg 80 0.0 64.4 0.0 0.0 0.0 5,152.0
C-0.7.12 Diameter 12 mm deformed bar kg 515 0.0 69.2 0.0 0.0 0.0 35,638.0
C-07.12 ACCESSORIES AND FINISHING 0.0 0.0 0.0 0.0 0.0
Provided and install access ladder constructed out of 1 1/2" dia GS
C-0.7.13 pipe and hooked to the casing as per the drawing; including safety LS 1 0.0 18,400 0.0 0.0 0.0 18,400.0
cages
C-0.7.14 supply and install of steel casing DN600mm m 60 0.0 240 0.0 0.0 0.0 14,400.0
Page 31 of 39
Wet well@BH
Page 32 of 39
takeoff wetwell
Page 33 of 39
Pipe Supply
Page 34 of 39
Main Line Welding & Laying
BILL NO. B-02 : Welding & Laying, of Main line 250mm PN16 HDPE PE100 Pipes & Components of air release valve and washout and pressure line Testing
Previous Current Total Unit Rate Previous Current Total AMOUNT
Item No Description unit Qty
Quantity Quantity Quantity (Birr) Amount Amount Amount ETH
Raising mainline to booster station 1 and from
B-02.1 booster station 1 to Bike Service Reservoir pipe
Welding and Laying
HDPE PE 100 Pipes PN 16/SDR 11 OD 250 mm
B-02.1.1 WP 1,111 0 450 0 0 0 500,000
wellding points
HDPE PE 100 Pipes PN 16/SDR 11 OD 250 mm
m 10,000 0 45 0 0 0 450,000
laying
SUB TOTAL- B-02.1 0 0 0 950,000
B-02.2 Air Release & Washout Fittings
B-02.2 Air Valve FOR OD250 PN16
B-2.2.1 Butwel stub flange DN250 NO 2 0 6,500 0 0 0 13,000
B-2.2.2 Butweld tee DN250*250*110 NO 3 0 7,500 0 0 0 22,500
B-2.2.3 Flanged gate valve DN110 NO 10 0 12,000 0 0 0 120,000
B-02.3 WASH-OUT FOR OD 250 PN16 0
B-02.3.1 Tee DN 250X250X100 NO 3 0 7,500 0 0 0 22,500
B-02.3.2 Flanged gate valve DN100 NO 3 0 12,000 0 0 0 36,000
SUB-TOTAL For B-02.2 and B-02.3 0 0 0 214,000
B-02.4 PRESSURE TESTING AND DISINFECTION
Disinfection of pipelines: flushing with clear water,
filling with water containing 0.15 g/l calcium hypo
B-02.4.1 Ls 1 0 250,000 0 0 0 250,000
chloride, left for 24 hours. This includes supply of all
necessary equipment, chemical and water
SUB TOTAL FOR B-02.4 0 0 0 250,000
Total Carried to Summary FOR BILL NO. B-02 0 0 0 1,414,000
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 35 of 39
Generator & Guard House
Page 36 of 39
Generator & Guard House
C-
Block work 0 0 0 0 0
05.17
C-
20cm thick hallow concrete block for wall m2 1,663 0 306 0 0 0 508,725
05.18
C-
Roof work 0 0 0 0 0
05.19
C- Upper & lower truss member of 10cm dia eucalyptus
ml 480 0 29 0 0 0 13,896
05.20 wood with 50cm c/c,well seasoned & free of defects
C- Vertical & Diagonal truss member of 8cm dia
ml 350 0 33 0 0 0 11,628
05.21 eucalyptus wood ,well seasoned & free of defects
C- Zigba wood purling 5cm X 7cm fixed to the truss at
ml 350 0 37 0 0 0 12,968
05.22 90cm C/C
C-
Roofing with G-28 corrugated iron sheet m2 65 0 354 0 0 0 23,010
05.23
C- Galvanized sheet gutter G-30 ,150 X150mm, price
m 11 0 321 0 0 0 3,595
05.24 includes brackets and two coats of metal paint
C-
Ditto but down pipes,120 X60mm m 10 0 78 0 0 0 796
05.25
C-
supply & fix 25 X 200mm facial board m 11 0 167 0 0 0 1,871
05.26
C-
Door and window 0 0 0 0 0
05.27
Supply & fix locally made metal window , with all
C- necessary iron monger locks ,mesh for protection & one
m2 3 0 4,704 0 0 0 11,760
05.28 coat of anti rust & two coats of metal paint as per the
drawing 1400mm X1200mm
Supply & fix locally made metal door , with all
C- necessary iron monger locks & one coat of anti rust &
no 3 0 8,400 0 0 0 25,200
05.29 two coats of metal paint as per the drawing 1500mm
X2000mm
C-
Renforcement 0 0 0 0 0
05.30
Steel reinforcement work according to the structural
C-
drawing price includes cutting, bending, tying, & 0 0 0 0 0
05.31
placing in a position
C-
8mm kg 200 0 64 0 0 0 12,880
05.32
Page 37 of 39
Generator & Guard House
C-
10mm kg 120 0 67 0 0 0 8,016
05.33
C-
12mm kg 100 0 69 0 0 0 6,920
05.34
C-
Finishing 0 0 0 0 0
05.35
C-
Plastering in cement sand mortar for internal walls m2 166 0 114 0 0 0 18,924
05.36
C-
plastering & tyrolyn render to the external surface m2 99 0 74 0 0 0 7,326
05.37
C-
Cement screeding in floor m2 27 0 109 0 0 0 2,926
05.38
0 0 0 0 0
C-
Electricity 0 0 0 0 0
05.39
Lights to fed through PVC sheated cable of 2 X 2.5
C- mm2 in thermoplastic conduit of 13.3mm in /under
m 4 0 350 0 0 0 1,400
05.40 surface including junction boxes ,screw type connectors
& flash mounted switches
Flush mounted socket outlet of 16Amp fed through
C- PVC sheathed cable of 3 X2.5mm2 in thermoplastic
no 3 0 250 0 0 0 750
05.41 conduit of 13.5mm in /under surface including junction
boxes ,screw type insulating caps & cover
C- Flouresent lamp laminar type Philips or equivalent
no 3 0 500 0 0 0 1,500
05.42 ,TMS02/240 with 1X40Watt
C-
Supply and fix anchor bolt in the R.C. generator seat No 8 0 1,800 0 0 0 14,400
05.43
Total for BILL NO C-05 Generator and Guard House(9.32x7.6) At Borehole and At Booster I 0.00 16,845.64 16,845.64 852,332.00
Contractor Client
Name: Eng Abiyot Demissie Name:
Signature Signature
Date Date
Page 38 of 39
takeoff generator&guard house
0.5
21.32 m3
C-05.6Masonary
C-05.725 cm thick basaltic or equivalent stone Hard
1 9 6 core well rolled, consolidated & blinded with
crushed stone
0.25 13.5 m3
C-05.8Stone masonry work in cemement Sand
2 9 6
mortar 1:3in ratio in foundation
0.4
0.5 6 m3
For Contractor For Client
Name: Eng Abiyot Demissie Name:
Sign:___________________________. Sign:____________________________.
Date:___________________________. Date:____________________________.
Page 39 of 39