07-3, Foot Path Est, Qsce, Od 88

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

11/19/2014

Quantity Surveying & Cost Estimation 10

QUANTITY SURVEYING &


COST ESTIMATION
CE-372
Nov-14 Composite Rate – Example

COMPOSITE RATES
2

 Schedule rates based on quantities from approved


drawings are worked out for different items of a single job
and are added together to give a single composite rate for
all items.

 It gives composite cost per unit length/area/volume etc.

 Total cost of the composite work can be found by


multiplying unit composite rate by total quantity.

 Examples: Composite rates for Roof Insulation, Steel Grills,


Road , Footpaths, Floors etc.
CE-372 Quantity Surveying & Cost Estimation Nov 14

1
11/19/2014

JOB RATES
3

 It is like composite rates but its unit is per number or each


instead of per unit area/volume as in composite rates.

 For jobs that are independent and contains many minor


items/details, separate estimates/taking off sheets are
prepared and job rate for the whole “job” is worked out.
Consolidated Job rate is then used in main estimate for
costing and its detail workings are also attached with the
main estimate.

CE-372 Quantity Surveying & Cost Estimation Nov 14

JOB RATES
4

 Job rates are prepared for specific jobs based on approved


drawings whose number is also mentioned in the job rate.

 Particular Job Rate can only be applicable to any other


project if same drawings of that job are being used in the
other project also.

 Job Rates preparation saves time and efforts of the


estimators.

 Examples: Job rates for Septic Tanks, Soakage Wells,


Soakage Pits, Valve pits , OHWTs, UGWTs etc.
CE-372 Quantity Surveying & Cost Estimation Nov 14

2
11/19/2014

Problem-4: Misc Estimates


5

 Prepare a Composite Rate of a Footpath 5’-0”


wide and 100 ft long from the drawing.

CE-372 Quantity Surveying & Cost Estimation Nov 14

Problem-4: Section of Typical Footpath

PCC KERBSTONE
350 x 300 x 150 mm

GL GL / FRL

PCC PAVER STONES 50 mm THICK

50 mm THICK SAND BED

P.C.C (1:4:8) 3 “ THICK

COMPACTED EARTH

6 CE-372 Quantity Surveying & Cost Estimation Nov 14

3
11/19/2014

Problem-4: Kerbstones - MES Specifications

Kerb Stones:- The Kerb Stones shall have min 28 days Cylinder
Compressive Strength of 21 MPa (3000 psi). It shall be cast
using Plant Mix Concrete with proper shuttering and compaction
arrangements to ensure strength, finish and quality. The Kerb
Stones are marketed in various sizes, shapes and qualities.
However, for the purpose of this Schedule, the rates have been
worked out for following specifications of Kerb Stones given in
Table 3-8:-
TABLE - 3-8
S.No Size Dropper Top Chamfered Strength
Size and Specifications of Common Kerb Stones
(mm) (mm) (mm) (mm) MPa (psi)

1 450 x 300 x 160 125 10 21.0


150 (3000)
2 350 x 300 x 160 110 10 21.0
150 (3000)
7
CE-372 Quantity Surveying & Cost Estimation Nov 14

Problem-4 : Footpath COMPOSITE RATE


1. PCC Kerbstone

Length: 100 ft (30.478 Mtr)


Providing and laying pre cast PCC Kerb stone size
350 x 300 x 150mm incl setting jointing and pointing in
CM (1:4) all as specified.

2 / 100’-0” = 200 rft 2 x sides


= 60.96 mtr

S.I No.03-80 @ Rs. 316.58/Mtr = Rs. 19298.72

4
11/19/2014

Problem-3 : Footpath COMPOSITE RATE


2. PCC Paver Stones

Length: 100 ft Width: 5’-0” ( Between 2 Kerbstones)


Providing and laying cement concrete paving stone 50mm
thick in any colour as in floors, drive way walk way etc any
pattern and any shape (hydraulically compressed) laid and
jointed in sand including 50mm thick sand bed as laying
coarse all as specified.

1 / 100’-0” x 5’-0” = 500 Sft


= 46.45 Mtr

S.I No.12-21 @ Rs. 748.21/Mtr = Rs. 34754.35

Problem-4 : Footpath COMPOSITE RATE


3. Sub Floors PCC (1:4:8)
{{{

[[[[

Length: 100 ft Width: 5’-0”

Providing and laying cement concrete 1:4:8 laid under


floors using crushed or broken stone all as specified.
.
1 / 100’-0” x 5’-0” x 0’-3” = 125 Cft
= 3.54 Cum

S.I No.12-03 @ Rs. 2971.06/Cum = Rs. 10517.55

10

5
11/19/2014

Problem-4 : Footpath COMPOSITE RATE


4. Compacted Earth Filling {{{

[[[[

Length: 100 ft Width: 5’-0”


Earth filling as in Ordinary or hard soil ,filling in foundation,
pipe trenches, shafts, wells, independent holes, under floors
or around plinth etc, 1.5 M below or above Ground Level
(GL), with spoil obtained from excavation in trenches/over
areas within 10m including watering and compaction in
150mm layer and dressing to required profile and shape.

1 / 100’-0” x 5’-0” x 0’-9” = 375 Cft


= 10.62 Cum

S.I No.01-15 @ Rs. 96.56/Cum = Rs. 1025.47


11

Problem-4 : Footpath 5’-0” wide Priced BQ


Ser Description of Item Qty Unit Rate Amount

1. P/L pre cast PCC Kerbstone size 60.96 Mtr 03-80 19298.72
350x300x150mm incl setting jointing Rs.316.58
and pointing in cm 1:4 all as spd.

P/L cement concrete paving stone 12-21 34754.35


2. 46.45 Sqm
50mm thick in any colour as in floors, Rs.748.21
drive way walk way etc any pattern and
any shape (hydraulically compressed)
laid and jointed in sand including 50mm
thick sand bed as laying coarse all as
specified.
P/L cement concrete1:4:8 laid under 12-03 10517.55
3. 3.54 Cum
floors using crushed or broken stone all Rs.2971.0
as specified. 6
Earth filling as in Ordinary or hard soil 01-15 1025.47
4. 10.62 Cum
including watering and compaction in Rs.96.56
150mm layer and dressing to required
profile and shape all as specified.
65596.09
12
Rate per Mtr = Rs.65596.09/30.478 = Rs. 2152.25