Professional Documents
Culture Documents
BES-L007 Pig LaunchersReceivers
BES-L007 Pig LaunchersReceivers
Engineering Standard
BES-L007
Pig Launchers/Receivers 01 July, 2006
Contents
Page 1 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
REVISION RECORD
Page 2 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
1.1 PURPOSE
This standard defines the minimum requirements for the design, manufacture, assembly inspection, factory
testing, vendor documentation, supply and transport to site of pig launchers/receivers in accordance with this
standard and applicable project documents.
All documents, design calculations, drawings and correspondence provided in relation to this standard shall be in
the English language. All units shall be in accordance with the System Internationale (SI) unless otherwise
specified.
For the purpose of this standard, the following definitions shall apply:
"PURCHASER" means the party or its duly appointed representative, which is contracted to purchase the
materials and/or equipment as described by this standard.
"VENDOR" means the party, which is contracted to manufacture and/or supply, materials, equipment
and services to perform the duties as described by this standard.
NDT Non-Destructive Testing
MT Magnetic Particle Testing
PT Liquid Penetrant Examination
UT Ultrasonic Testing
The pig launchers/receivers shall comply with the requirements of the documents as listed in codes and
standards, project documents and with those referred to “as applicable”.
In case of conflicting requirements from the documents listed, the following descending order of precedence
shall be taken into account:
Page 3 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
ISO 9001 Quality Systems - Model for Quality Assurance in Production, Installation and Servicing
ISO 10474 Steel and Steel Products - Inspection document
ASTM - A694 Carbon and Alloy Steel Forgings for Pipe Flanges, Fittings, Valves and Parts for High
Pressure Transmission Service
ASTM - A370 Mechanical Testing of Steel Products
NACE MR-01-75 Standard Material Requirements for Sulphide Stress Cracking Resistant Metallic Material
for Oilfield Equipments.
Design and manufacture requirements are defined in the documents listed in paragraph 2.0, pig launcher/receiver
data sheet and the specific requirements listed below.
3.1 GENERAL
Pig launcher/receivers are generally located inside the plant area limit and are considered within the scope of the
respective transportation piping code, ASME B31.4/B31.8.
Pig launchers/receivers (including all components) shall be designed and be suitable for continuous outdoor
operation in accordance with site conditions indicated.
The maximum stresses shall be calculated per applicable ASME Code for the design conditions and shall not
exceed the allowable stress based on the design factor. Corrosion allowance shall be as specified in the Purchase
Order or in the design drawings attached to the Purchase Order.
The overall dimensions for pig launchers/receivers shall be in accordance with the drawing specified in the
Purchase Order, or the design drawing attached to the Purchase Order.
Page 4 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
Material of construction shall be in accordance with the attached data sheets. Cylindrical sections shall be made
from seamless or welded pipe. All materials shall meet the requirements of NACE MR-01-75, with hardness
limited to 200 HB.
Materials supplied by VENDOR for piping elements or structural attachments shall conform to the requirements
of the applicable code and shall be traceable to mill certificates. Material selection may be further limited in this
specification or in the Purchase Order. Used or reclaimed materials or materials of unknown specification are
not permitted.
3.3 BARRELS
The internal diameter of the minor barrel should be the same as that of the main line. However, transitions in the
internal diameter due to wall thickness variations greater than 0.095 inch shall be tapered to 1:5 transition taper
to allow for the smooth passage of a pig.
The reducer between the major and minor barrel shall be eccentric with the bottom of the entire barrel at the
same level. Reducers shall have a nominal wall thickness at least equal to the specified nominal wall thickness of
the matching pipe (of equal yield strength) at the large end.
Appurtenances (valves, pig signallers, pressure safety valves etc), except for the end closure, are to be provided
with the pig launchers/receivers only if noted in the purchase order for pig traps.
Blind flanges are to be provided for each nozzle (except the end closure). Blind flanges should be of the same
rating as the flanges.
The pig launchers/receivers shall be equipped with a quick opening closure, designed to allow one man operation
for both opening and closing, with a pressure interlock to prevent opening of the door while the barrel is
pressurized.
The closure shall be designed in accordance with ASME BPV Code Section VIII, Division 1.
The closure fully closed position shall be marked to aid subsequent closure position. The closure shall use a
single replaceable “O” ring as the sealant element. There shall be no leakage of contents of the pig
launchers/receivers prior to disengagement of the locking element and release of the closure.
Optionally, VENDOR shall propose with his bid alternative types of end closures, which shall meet the
requirements in accordance with this specification.
Branch connections shall either be welded, forged or extruded. Reinforcing pads required by the specified code
shall be fully welded and shall be provided with a vent hole. The vent hole shall be tapped with a 3 mm-6 mm
pipe thread. The tapped hole shall be filled with heavy grease.
All flanges and branch fittings shall be forged carbon steel fittings with the same specified yield strength as the
pipe.
Page 5 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
3.6 SUPPORTS
The pig launchers/receivers shall be provided with saddle supports. Permanent saddles shall be used to support
and restrain pig launchers/receivers and these shall be designed to carry the weight of the pig launchers/receivers
system filled with water together with the weight of the pigs. Details of saddle supports should be provided to
PURCHASER for designing foundations.
Structural steel used for non pressure containing parts shall be equivalent to ASTM A36, S-1 or better.
The supports under the barrel shall be of the sliding type to compensate for expansion of the unrestrained part of
the pipeline.
3.7 FABRICATION
3.7.1 GENERAL
Fabrication of pig launchers/receivers shall be in accordance with the applicable design code (ASME
B31.4/B31.8) and in compliance with the following specific requirements:
Cutting of carbon steel piping shall be preferably carried out by mechanical means. When flame cutting is
employed, the end shall be ground sufficiently back in order that the bevels are clean and free from defects. All
bevelled ends during fabrication shall be subjected to a 100% UT lamination check and MT when flame cut. End
bevels shall conform to ASME B16.25.
Holes for the attachment of fittings shall be made using drills or a hole saw. Use of flame cutting is prohibited.
Holes shall be drilled prior to welding the fitting.
3.7.2 WELDING
All welding procedures, qualification of welders and welding procedure qualifications, design and preparation of
joints, inspection and testing, standards of acceptability of welding, repairs and radiography shall be fully in
accordance with API 1104 or ASME BPV Code Sec. V and ASME BPV Code Sec. IX, and shall be documented
before fabrication commences.
Single-welded butt joints are permitted for circumferential joints and shall be 100% radiographically tested.
Vendor shall provide ultrasonic tests where radiography produces questionable results.
In the event that welds performed on any forging cannot be 100% radiographed, 100% UT or wet MT shall be
utilised.
UT is required on the shell material where locally reinforced fittings are to be welded. Prior to welding all weld
ends are also to be checked using ultrasonic inspection.
3.7.3 NOZZLES
All nozzles shall be flanged, welding neck type in accordance with ASME B16.5. Facing shall be raised face.
All flanged connections shall be bored full length to match pipe thickness.
Connection neck shall be inserted through the vessel wall. “set on” attachment is not permitted.
All nozzles shall be flush with the inside diameter of the vessel.
All sharp surface protrusions and all weld splatter shall be removed (flush) prior to blast cleaning, to ISO 8501-1
Grade 2 ½.
Page 6 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
The launchers/receivers shall be painted with primer only. All bare surfaces shall be coated with two coats of
alkyd primer. Either the first or second coat shall be tinted with 1 or 2% of black alkyd enamel to ensure that the
two full coats are applied. Both primer coats must be applied by brushing and must be well worked into the
surface. The minimum dry film thickness of each finish coat shall be 25 microns (1mil).
Final coats shall be applied by PURCHASER. Primer shall be applied following satisfactory completion of shop
testing and all functional tests.
Third Party Inspection is required for witnessing and certification for non-destructive and other testing and
examination.
The PURCHASER reserves the right to inspect material, manufacturing process, testing etc. Such inspection
does not relieve the VENDOR of the responsibility of suitable design and workmanship.
VENDOR shall submit to PURCHASER a detailed Inspection and Test Plan (ITP) for approval with scheduled
activities and acceptance criteria, before start of manufacturing.
UT shall be in accordance with ASME BPV Code Section V, Articles 5 & 23.
X - Ray shall be in accordance with ASME BPV Code Section V, Articles 2 & 22.
MT shall be the wet method and in accordance with ASME BPV Code Section V, Article 7 & 25.
Results shall be reviewed, interpreted, and evaluated in accordance with the following criteria:
If the pig launchers/receivers are provided with welded reinforced attachments, telltale holes shall be provided in
order to test with dry air at 5 barg pressure and checked with foam agent for leaks. This shall be carried out prior
to the final hydrostatic pressure test.
Hydrostatic pressure tests shall be carried out by VENDOR at a test pressure based on a fibre stress of 90% of
the specified minimum yield strength (SMYS) in the shell or at the applicable test pressure listed in ASME
B16.5, whichever is the lower.
The temperature of the pig launchers/receivers material and test liquid shall not be less than 50°F during the
hydrostatic test.
Pressure testing is to be conducted using calibrated test gauges. Test pressures shall be held a minimum of 4
hours.
The end closure will be fully operable after pressure cycles have been applied.
Page 7 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
VENDOR shall establish and maintain a quality assurance system in accordance with ISO 9001 or an approved
equivalent. The PURCHASER shall have the right to undertake such audits as he deems necessary to assess the
effectiveness of the VENDOR’s quality system.
Packaging and handling shall be in accordance with the requirements of BES-A003, Standard for Packing &
Marking together with the specific requirements listed below:
Each piece of equipment having a nameplate as specified by the purchase order and/or equipment data sheet
shall have the nameplate permanently protected during welding, painting and shipping. The following
information shall be stamped on the nameplate.
Connections furnished on the equipment shall be identified and shall be tagged to comply with VENDOR’s
connection table or general arrangement drawing.
Vendor data and document requirements are defined in Appendix 2 and BES-A004, Vendor Data &
Documentation Requirements, together with the specific requirements listed below.
- Three copies of the certified mill test report showing the chemical and physical properties for each item of
material furnished by the VENDOR shall be provided for PURCHASER’s approval.
- A report of results obtained from MT and X-ray of welds indicating all defects were identified and the
disposition of all repairs shall be provided. All original radiographs shall be available to the
PURCHASER for review upon request.
- Weld identification drawings of the fabrication and the weld number for each weld.
- Installation, Operation and Maintenance instructions/manuals covering end closure, and other equipment
supplied in the pig launcher and receiver packages.
- Assembly drawings with corresponding keyed parts lists of all equipment supplied in the pig launcher and
receiver packages.
Page 8 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
Page 9 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
A
B C
N9 N8 N7 N6 N2 N5 N4 N3 N9 N8 N7
N6 N5 N4 N3
E 300 300 300 150 300 300 300
A
I
I
D2
D1 cL N12 N2
N1 cL
I
A N10
355
N11 G
F = = = = 300 H
NOZZLES
N1 Inlet/outlet/pipeline size.
N2 Kicker/bypass connection.
N3 Vent connection. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N4 & N7 Pressure Gauge. 2in connection.
N5 Pressure Safety Valve. 2in connection.
N6 Pig Signaller. 2in connection.
N8 Vent connection. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N9 Purge. 2in connection.
N10 & N11 Drain. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N12 End Closure
NOZZLE DIMENSIONS
SIZE (in) I (mm)
2 150
3 205
4 230
6 305
8 305
Page 10 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
N9 N8 N7 N6 N5 N4 N3 N9 N8 N7
N2R N2L
N6 N5 N4 N3
D 300 300 E 150 300 300 200 100 300
A
K
K
D2
D1 cL N12 N2L
N1 cL
N2R
K
A N10
355
N11 I
F G H 760 300 J
Note
1. Pig launchers/receivers in fixed locations shall be fitted with either nozzle N2R or N2L depending on
their function as launcher or receiver.
2. Mobile launchers/receivers shall be fitted with both nozzles N2R and N2L.
NOZZLES
N1 Inlet/outlet/pipeline size
N2L Kicker/bypass connection for launcher.
N2R Kicker/bypass connection for receiver.
N3 Vent connection. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N4, N7 Pressure Gauge. 2in connection.
N5 Pressure Safety Valve. 2in connection.
N6 Pig Signaller. 2in connection.
N8 Vent connection. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N9 Purge. 2in connection.
N10, N11 Drain. 2in for line sizes up to 12in and 4in for line sizes 14in and larger.
N12 End Closure
NOZZLE DIMENSIONS
SIZE (in) K (mm)
2 150
3 205
4 230
6 305
8 305
Page 11 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
Vendor shall deliver with the Tender the following documents as indicated.
Prequalification information 3
Quality plan 3
List of deviations 3
Dimensional drawings 3
Page 12 of 13
BES-L007
Pig Launchers/Receivers 01 July, 2006
Number of Number of
Weeks after Weeks after Final
Required documents prints for prints for
Award Approval Documents
Approval Final Issue
Dimensional drawings with weights 2 3 2 3 5
Material Certificates 2 3 2 3 5
Manufacturer's Report 2 3 2 3 5
Installation/Operating/Maintenance
2 3 2 3 5
Manual
Spare Parts List (for two year
2 3 2 3 5
operation)
Construction, Start-up &
2 3 2 3 5
Commissioning Spares List
Surface Preparation & Painting
2 3 2 3 5
Procedure
Page 13 of 13