Professional Documents
Culture Documents
Ssg-Ng01012401-Gen-Aa-5800-00008 - C01 - Project Interface Managment Plan
Ssg-Ng01012401-Gen-Aa-5800-00008 - C01 - Project Interface Managment Plan
SSG-NG01012401-GEN-AA-5800-00008
Revisio
Date Description Originator Checker Approver
n
CONTRACTOR:
Revision Philosophy
Revisions for Review - First issue will be issued at R01, with reason of issue description - Issued
for Review, (with subsequent R02, R03, etc. as required to be used in dependence of review
status received by SPDC). Last issue: A01, A02… with reason of issue description - Issued for
approval, A02 might be reissued in case further modification occurred A02, with reason of issue
description – Re-Issued for approval. When document is considered closed by SPDC, the revision
must be changed to C01, C02….. with reason of issue description - Approved for Construction
Revisions for Design Documentation - First issue will be issued at D01, with reason of issue
description - Issued for Review, (with subsequent D02, D03, etc as required to be used in
dependence of review status received by SPDC). Last issue: C01, with reason of issue description
- Issued for Construction (Final Design) (C02 might be reissued in case further modification
occurred). When document is considered closed by SPDC, the revision must be increased (with no
change on the document itself) and issued , with reason of issue description - Approved for
Construction (Final Design).
Revisions for Purchase - First issue will be issued at P01, with reason of issue description -
Issued for Purchase, (P02, etc to be used in dependence of review status received by SPDC).
Last issue: P03, with reason of issue description - Approved for Purchase (Final Issue) (P0X
might be reissued in case further modification occurred).
Revisions for Information - First issue will be issued at R01, with reason of issue description -
Issued for Information.
Revisions for As built - Documents or drawings revised as “As built” will be issued as Z01, Z02 Z03
etc as required.
Narrative sections revised from previous approved issues are to be noted in the table below and/or
highlighted in the RH margin (using the appropriate revision status).
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the
affected areas and by the use of a triangle containing the revision status.
If a document is cancelled the document will be issued at the next sequential number by adding the
suffixed with a X. For example if R02 is the current revision then 03X will be the Cancelled revision
All revisions to this document must be approved by the relevant Technical authority.
Revision History
2. REFERENCE DOCUMENTS 4
4.0 RESPONSIBILITIES 6
2. REFERENCE DOCUMENTS
Interface Owner A Party that is responsible for developing and managing a specific
(IO) Interface.
Work Hierarchical structure that splits up the project into activities (e.g.
Breakdown Engineering, Construction), in order to monitor and evaluate their
Structure (WBS) progress.
Interface Owners prepare the required documents and manage all aspects of assigned
interfaces. They are responsible for interacting with the interfacing organization and
determine (both as Requester and Receiver) all missing information and the format in
which such information is to be provided.
Physical A Physical Interface arises from the need to coordinate and manage
Interface a physical operation (e.g. flanged coupling, welded joint, cabling)
involving objects/items belonging to COMPANY and objects/items
belonging to other Organizations or vice versa.
Documental A Documental Interface arises from the need to coordinate and
Interface manage Technical Information flows (e.g. Datasheets, Coordinates,
Operating or Design pressures, etc.) from other Organizations
(Contractors and/or Owners) or vice versa, through a document or IT
exchange.
INTERFACE
OPERATING MANAGERIAL
PHYSICAL ORGANIZATIONAL
DOCUMENTAL BUREAUCRATIC
In SSAGS Project, COMPANY and EPC Contractors agreed to have a common Interface
Register where all interface issues and relevant updates are documented. Ownership of
this Register belongs to COMPANY Interface representatives and it is updated at each
interface meeting.
It is the responsibility of the Interface Manager to locate each Interface identified during
the steps described above within a Criticality Matrix like the one shown in Figure 2.
High
EXTERNAL CONSTRAINTS
Low
HL HH
High
LL LH
Interfaces falling within the high External
Constraints Areas (HL and HH as shown in
Figure 2) are managed using the Interface Management Process described in the present
Low INTERNAL CONSTRAINTS
Project Procedure which constitutes the basis of the Project Interface Register. Interfaces
falling within the low-level External Constraint areas (LL and LH in Figure 2) are managed
at discipline level, in accordance with standard COMPANY Procedures.
Subsequently, before classifying the Interfaces, the Interface Manager is responsible for
recording all the interfaces with other Organizations (Contractors and/or Owners) in the
Project Interface Register.
Following Interface classification and IO designation, the Interface Manager issues the
Project IR for all disciplinary functions involved to take action accordingly. A sample IR is
provided in Appendix 1 of this Work Instruction. The Project IR is a dynamic document to
be used during coordination meetings. Interface Manager is responsible for maintaining
and updating the Interface Register and for ensuring correct distribution.
The external interfaces identified as per the above procedure are shared in a joint
meetings led by COMPANY Interface Representatives where all the issues are analysed
and captured in a dedicated Register developed between COMPANY and EPC
Contractors. This dedicated Register is the official Project live document shared amongst
all the stakeholders.
SSG-NG01012401-XXX-XX-6015-0000X
Classification
Status:
Restricted
Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced without prior
written permission from Shell Petroleum Development COMPANY
Revisio
Date Description Originator Checker Approver
n
IO IM PM
CONTRACTOR:
INVOLVED ORGANIZATION
Requester Name and Surname
Receiver Name and Surname
INTERFACE DETAILS
Interface Type
Interface Description
Actions
Acion Number 1 Due Date
Action by
Actual Date
Action Description:
Actions
Acion Number 2 Due Date
Action by
Actual Date
Action Description:
S/No.
DOCUMENTATION INVOLVED/EXCHANGED
INTERFACE ISSUE NO.
S/No. Description of Document Drawing Reference Rev. Mode Date From To
Close Out
Requester Sign Receiver Sign
Date Date