PH-05 Restoration Bar Chart Nov 2020

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 26

PH#5 Restoration Gantt chart

Ester Industries Limited

Project Start Date 7/10/2020 (Friday)


Project End Date 1/31/2021 (Sunday)

WBS TASK LEAD

1 Shifting of all scrap, burnt materials from ph#5 heater area Mr. Sandeep Srivastava
1 Testing of RCC column for strengthen. Mr. Sandeep Srivastava

1 Thermax team has to visit site for coil testing , RCA & coil Mr. Sandeep Srivastava
assessment.

1 Dismantling of existing structure (civil structure and new Mr. Deepak Pant
structure erection)
1 Dismantling of thermic fluid pipeline, furnace structure, PA Mr. Sandeep Srivastava
coil,IBH coil
1 Inspection of, testing of old convective coil Mr. Sandeep Srivastava
1 Dismantling of furnace refractory Mr. Sandeep Srivastava
1 Dismantling of furnace , ash Hooper Mr. Sandeep Srivastava
1 Rebuilding of ash Hooper mainframe in RCC slab Mr. Deepak Pant
Erection activities
1 Conveyor belt installation(BC-2) and trial of conveyor to be Mr. Sandeep Srivastava
taken

1 Mr. Sandeep Srivastava

Erection of new ash Hooper on the new RCC frame


1 Erection of main structure on civil platform Mr. Sandeep Srivastava
1 Erection of plenum assembly and IBH coil Mr. Sandeep Srivastava

1 Screw feeder, charcoal feeder installation,chewt fabrication for Mr. Sandeep Srivastava
husk conveying to furnace to be made
1 Erection of MPA & Convective coil on furnace structure Mr. Sandeep Srivastava

1 Erection of inter-connecting pipeline(MPA to convective and Mr. Sandeep Srivastava


IBH)
1 Strengthening of pipeline support to be done Mr. Sandeep Srivastava

1 Mr. Sandeep Srivastava


All drain, air vent valves to be installed as per requirement

1 Expansion tank valves for de-aeration, makeup and overflow to Mr. Sandeep Srivastava
be replaced
1 Expansion tank level indicator, transmitter to be replaced Mr. Sandeep Srivastava

1 DPSL pipeline for MPA,convective,IBH to be fabricated and Mr. Sandeep Srivastava


installed
1 Convective coil all DPSL pipeline to be provided with additional Mr. Sandeep Srivastava
isolation valve at inlet of each instrument
1 Pneumatic testing of complete heater Mr. Sandeep Srivastava
1 Radiography of pipeline joints Mr. Sandeep Srivastava
1 Pneumatic and flushing of pipeline Mr. Sandeep Srivastava
1 Thermic fluid filling in heater circuit Mr. Sandeep Srivastava
1 Construction of furnace refractory Mr. Sandeep Srivastava
1 Inspection of refractory furnace Mr. Sandeep Srivastava
1 Cold circulation & Slow firing of heater Mr. Sandeep Srivastava
Display Week 6

START END DAYS % DONE WORK DAYS


Status as on 03/10/202
0 100% -
0 100% -

0 100% -

Truss fabrication work


completed, erection will be
Mon 8/10/20 Sun 1/31/21 174 90% 125
done after erection of new
convective coil.

Sun 9/20/20 Thu 10/15/20 25 100% 19 MPA structure dismantling is

0 100% -
0 100% - Shifting of refractory bricks a
0 100% -
Sun 9/20/20 Thu 10/15/20 25 100% 19 Pending .

Sun 9/20/20 Wed 9/30/20 10 100% 8 Belt yet not received

Fabrication of ash hopper


completed but due to RCC
Tue 10/20/20 Tue 11/10/20 21 100% 16 rebuilding work is pending
so couldn’t be erected.

Tue 10/20/20 Mon 11/30/20 41 100% 30


Tue 10/20/20 Mon 11/30/20 41 100% 30

Sun 11/01/20 Mon 11/30/20 29 100% 21

Sun 12/20/20 Wed 12/30/20 10 100% 8

Wed 12/30/20 Fri 1/15/21 16 100% 13

Wed 12/30/20 Fri 1/15/21 16 10% 13

Wed 12/30/20 Fri 1/15/21 16 75% 13

Wed 12/30/20 Fri 1/15/21 16 100% 13

Wed 12/30/20 Fri 1/15/21 16 10% 13

Wed 12/30/20 Fri 1/15/21 16 50% 13


Wed 12/30/20 Fri 1/15/21 16 50% 13

Sat 1/16/21 Fri 1/22/21 6 25% 5


Sat 1/16/21 Fri 1/22/21 6 0% 5
Sat 1/16/21 Fri 1/22/21 6 0% 5
Fri 1/22/21 Mon 1/25/21 3 0% 2
Sun 11/15/20 Fri 1/15/21 61 10% 45
Tue 1/26/21 Tue 1/26/21 0 0% 1
Wed 1/27/21 Sun 1/31/21 4 0% 3
Status as on Status as on
Status as on 21/10/2020 Status as on 21/11/2020 04/12/2020 11/12/2020
Completed Completed Completed Completed
Completed Completed Completed Completed

Completed Completed Completed Completed

Column
Column strengthening work is Column strengthening work is Column strengthening
strengthening work is
under progress under progress work is under progress
under progress

Completed Completed Completed Completed

Completed Completed Completed Completed


Completed Completed Completed Completed
Completed Completed Completed Completed
Work is under progress Completed Completed Completed

Belt jointing is under progress Completed Completed Completed

Work is under
After completion of point no 9 Work is under progress progress Completed

Material awaited Material awaited Material awaited Completed


Material awaited Material awaited Material awaited Completed

Material awaited Material awaited Material awaited Erection is under progress

Material awaited Material awaited Material awaited Material awaited

Material awaited Material awaited Material awaited Material awaited

Valve replacement
Valve replacement work is under Valve replacement work is work is under Valve replacement work is
progress under progress under progress
progress
Valve replacement
Valve replacement work is under Valve replacement work is Valve replacement work is
progress under progress work is under under progress
progress
Material awaited Material awaited Material received Material received

Material awaited Material awaited Material awaited Material awaited


Material awaited Material awaited Material awaited Material awaited

Under progress
Status as on Status as on
26/12/2020 12/01/2021
Completed Completed
Completed Completed

Completed Completed

Parlin , sheet installtion Sheet installation is under


work is under progress. progress

Completed Completed

Completed Completed
Completed Completed
Completed Completed
Completed Completed

Completed Completed

Completed Completed

Completed Completed
Completed Completed

Erection is under
Completed
progress

Material awaited Completed

Material awaited Completed

Under progress

Valve replacement Under progress


work is under progress

Valve replacement
work is under progress Completed

Under progress

Material awaited Under progress


Material awaited Under progress

Under progress

Under progress
Bought out Item List PH-
S.No Material Code Material Description Qty Unit
1 3000037056 Convective coil 1 Lot
2 3000039571 Membrane Pannel Assembly 1 Lot
3 3000021154 Bellow Seal Valve 6'' 2 Nos
4 3000021153 Bellow Seal Valve 4'' 2 Nos
5 3000021152 Bellow Seal Valve 3'' 2 Nos
6 3000011878 Bellow Seal Valve 2'' 10 Nos
7 3000011877 Bellow Seal Valve 1'' 30 Nos
8 3000021245 Bellow Seal Valve 1/2'' 50 Nos
11 3000013339 Aluminium Cladding 22 gauge 600 Kg
12 3000029818 FIRE DOOR 480X375 HOLE C/C,PN-PXX0240006 12 nos
13 3000015981 Conveyor Belt 190 mtr
14 3000030301 SCREW GI 8X13MM LONG FOR INSULATION 20 Pkt
15 1000000074 SANTOTHERM-66/THERMINOL-66 76336 KG
16 3000000317 MS Plate 6mm 4 ton
17 3000031651 Conveyor Gearbox 2 nos
18 1000000203 Badarpur Sand 50 ton
19 3000028458 SS rod 6mm dia. 100 Kg
20 3000040151 EGB Damper with actuator 3 nos
21 3000030748 AIR COOLED PACKAGE UNIT 11TR 1 Nos
22 3000017347 Window AC 2TR 1 nos
23 3000031376 Air Nozzle 890 nos
24 3000026652 FIRE BRICKS IS-8 SIZE 230x115x76 MM 22,000 EA
25 3000030107 BRICKS FIRE HA 60% SIZE 230x115x76 MM 3,000 EA
26 3000007884 BRICKS FIRE INSUL. SIZE 230x115x76 MM 9,500 EA
27 3000030108 TILES IS-8 SIZE 457x150x76 MM 6 EA
28 3000030109 TIE BRICK SIZE 230x230x75 MM 135 EA
29 3000030110 BRICKS FIRE S/A 60% SIZE 230x115x76/63MM 238 EA
30 3000030111 BRICKS FIRE S/A 60% SIZE 230x115x76/51MM 76 EA
31 3000030112 BRICKS FIRE SKEW SIZE 115x115x115x60 MM 38 EA
32 3000030113 BRICKS FIRE S/A SIZE 230x115x76/51 MM 28 EA
33 3000030114 BRICKS FIRE S/A SIZE 230x115x76/63 MM 82 EA
34 3000030115 BRICKS FIRE SKEW SIZE 115x115x115x60 MM 80 EA
35 3000030116 BRICKS FIRE E/A HA 60% 230x115x76/63 MM 34 EA
36 3000030117 BRICKS FIRE S/A 60%SIZE 230x115x76/70MM 180 EA
37 3000030118 BRICKS FIRE SKEW SIZE230x230x115x76/63MM 16 EA
38 3000030119 BRICKS FIRE E/A SIZE 230x115x76/63 MM 490 EA
39 3000030120 BRICKS FIRE E/A SIZE 230x115x76/70 MM 1,730 EA
40 3000030121 BRICKS FIRE SKEW SIZE 230x230x115x60 MM 145 EA
41 3000030122 BRICKS FIRE IS-8 MPA SEAL 230x165x76 MM 170 EA
42 3000030123 BRICKS FIRE IS-8 MPA SEAL 115x165x76 MM 170 EA
43 3000030124 CERAMIC BLANKET MAKE LLOYD INSULATION 10 BOX
44 3000026660 MILL BOARD 1 X 1 MTR 5 MM THICK 105 EA
45 3000015981 Conveyor belt 200 mtr
46 3000017792 Vulcanizing Compound 2 Kg
49 3000000357 Bamboo 20feet long 25 Nos
50 3000026671 Challey wooden 20 Nos
51 3000002071 Rope coire(jute) 6 to 10 mm dia 15 Kg
52 3000039572 IBH Assembly 1 EA
53 3000019824 SCREW FEEDER,P240200303,THERMAX 2 EA
54 3000040757 PLENUM CHAMBER,VTAIF100/330 1 EA
55 3000040758 FURNACE STRUCTURE,VTAIF100/330 1 SET
56 3000040759 CHARCOAL/SAND FEEDER,VTAIF100/330 2 EA
57 3000040765 INSTRUMENTATION,HEATER 1 SET
58 3000040766 MCC PANEL&BAG FILTER,VTAIF 100 1 EA
59 3000040767 PLC PANEL,THERMAX,VTAIF 100 UNIT 1 EA
60 3000040768 VALVE,F/INST ISOLATION 1 SET

P.R & P.O Details for restorag


Materials P.R. & P.O Details
S.N Item Code Item Description Unit Qty

1 3000014411 CABLE 3.1/2COREX185MM2 PVC INS 1100V ARM MTR 250


2 3000020227 CABLE ALUMINIUM 3.5X120 MM2 (UOM-MTR=Ea MTR 350
3 3000000423 CABLE ALU ARMOURED 3.5X50MM SQ 1.1 KV GR MTR 450
4 3000000422 CABLE ALU ARMOURED 3.5X35MM SQ MTR 510
5 3000013366 CABLE CU. PVC INSULATED 4X10MM2 MTR 100
6 3000012839 CABLE CU.ARMOURED 4COREX6MM2 MTR 900
7 3000000434 CABLE CU. ARMOURED 4X4 MM SQ.COPPER MTR 100
8 3000000433 CABLE CU. ARMOURED 4X2.5 MM SQCOPPER MTR 700
9 3000000431 CABLE CU. ARMOURED 4X1.5 MM SQPVC INSU. MTR 1,900
10 3000018657 CABLE COPPER ARMOURED 3 X 1MM2 MTR 500
11 3000021009 CABLE 3COREX1.0MM2-1.1KV GRADE FLX.BORE MTR 500
12 3000022777 CABLE TRAY 300X100X2.5MM GI PERFORATED MTR 50
13 3000021041 CABLE TRAY 200X50X2.5MM GI PERFORATED MTR 50
14 3000021040 CABLE TRAY 100X50X1.6MM GI PERFORATED MTR 50
15 3000021039 CABLE TRAY 50X50X1.6MM GI PERFORATED MTR 50
16 3000022784 CABLE TRAY COVER GI 305X15X2.5 MM MTR 50
17 3000022783 CABLE TRAY COVER GI 205X15X2.5 MM MTR 50
18 3000022780 CABLE TRAY COVER GI 55X15X1.6 MM MTR 50
19 3000022781 CABLE TRAY COVER GI 105X15X1.6 MM MTR 50
20 3000021052 COUPLER PLATE 50X210X3+NUT,BOLT & WASHE EA 150
21 3000015172 STRIP G.I. 50X6MM KG 300
22 3000000452 STRIP G.I. 25X3MM KG 300
23 3000012336 LIGHTING DISTRIBUTION BOARD 63 AMP 3TPN EA 1
24 3000033113 LDB SPN DOUBLE DOOR REF. NO-8GB32102RC16 EA 1
25 3000001127 LOAD CONTACT (MCB) THREE POLE-63A EA 6
26 3000001125 LOAD CONTACT (MCB) THREE POLE 32A EA 3
27 3000018483 MCB 20 AMP THREE POLE EA 2
28 3000001120 LOAD CONTACT (MCB) 1POLE 25A EA 4
29 3000001121 LOAD CONTACT (MCB) 1 POLE 10AMP EA 12
30 3000001117 LOAD CONTACT (MCB) 1POLE 6A EA 12
31 3000012342 PLUG & SOCKET WITH MCB 32 AMP 5PIN TPN&E EA 5
32 3000001667 LUG ALU.CRIMPING EYE 185MM2 CAT NO. 119 EA 24
33 3000001665 LUG ALU.CRIMPING EYE 120MM2 CAT NO. 119 EA 20
34 3000031386 LUG ALUMINIUM 50MM2 CAT NO. 119-224 EA 30
35 3000001660 LUG ALU.CRIMPING EYE 35MM2 EA 12
36 3000030573 LUG COPPER 6 MM2 CAT NO. 319-544 EA 200
37 3000032149 LUG COPPER 4.0MM2 CAT NO.319-389 EYE TYP EA 200
38 3000032147 LUG COPPER 2.5MM2 CAT NO.319-541 EYE TYP EA 200
39 3000032145 LUG COPPER 1.5MM2 CAT NO.319-538 EYE TYP EA 200
40 3000015447 END SLEEVE 6.0MM2 P.NO-61801810 EA 200
41 3000015446 END SLEEVE 4.0MM2 P.NO-61801780 EA 200
42 3000015445 END SLEEVE 2.5MM2 P.NO-61801760 EA 200
43 3000015444 END SLEEVE 1.5MM2 P.NO-61801710 EA 200
44 3000014696 END SLEEVE 1.0MM2 P.NO-61721890 EA 200
45 3000000523 CABLE GLAND SIBG 1619 EA 40
46 3000000526 CABLE GLAND SIBG 2125 EA 24
47 3000000527 CABLE GLAND SIBG 2925 EA 12
48 3000000528 CABLE GLAND SIBG 2932 EA 4
49 3000000529 CABLE GLAND SIBG 2938 EA 6
50 3000000530 CABLE GLAND SIBG 3638 EA 4
51 3000000533 CABLE GLAND SIBG 4251 EA 4
52 3000020274 CABLE GLAND 5451 EA 12
53 3000032154 PVC CABLE GLAND M16X1.5 WITH CHUCK-NUT EA 12
54 3000032155 PVC CABLE GLAND M20X1.5 WITH CHUCK-NUT EA 12
55 3000032156 PVC CABLE GLAND M25X1.5 WITH CHUCK-NUT EA 12
56 3000012167 CABLE TIE 300 MM X 7.6MM (PVC) EA 2,000
57 3000012168 CABLE TIE 200 X 4.7 MM KP-140B EA 2,000
58 3000036243 CABLE TIE 250MM X4.8MM BLACK NYLON EA 2,000
59 3000022865 NUT & BOLT GI 8X15MM KG 20
60 3000003892 WASHER MS 10 MM KG 5
61 3000015893 M.S. MACHINE SCREW WITH NUT 3/16" X 1" EA 500
62 3000016865 DRILL BIT 2.5MM HSS EA 10
63 3000018786 DRILL BIT 3MM HSS EA 10
64 3000003473 DRILL BIT 3.5MM PS EA 10
65 3000003474 DRILL BIT 4MM HSS EA 10
66 3000003640 THREADING TAP SET 3/16 BSW EA 4
67 3000012487 DRILL BIT M6X50MM FOR BOSCH HAMMER DRIL EA 20
68 3000012486 DRILL BIT M6X75MM FOR BOSCH HAMMER DRIL EA 10
69 3000012488 DRILL BIT M10X75MM FOR HAMMER DRILL M/C EA 10
70 3000029035 HAMMER DRILL BIT 12 MM EA 10
71 3000029950 CUTTING WHEEL 105X16X1.2MM (THICKNESS) EA 50
72 3000001333 PHASE TESTER 500 VOLT EA 20
73 3000037583 TUBE LIGHT FITTING FOR 4 FEET LED TUBE EA 40
74 3000029755 LIGHT FITTING 36W LED TYPE 600X600 MM EA 8
75 3000032015 LED BEAM/FLOOD LIGHT SSK-BLS-40W EA 6
76 3000032017 LED STREET LIGHT 40W SSK-ST-40W (S) EA 10
77 3000030353 LED TUBE 18/20 WATT, 230V, 1200MM EA 60
78 3000020079 MOTOR 3 PHASE 1.5KW 950RPM 100L FRAME EA 2
79 3000000675 MOTOR 2.2KW/3HP 1500RPM SQUIRREL CAGE EA 1
80 3000027467 RUBBER MAT ROLL 1MTRX10MTRX2MM FOR 1.1 EA 2
81 3000000272 ANGLE M.S.-50X50X6 MM LENGTH-3MT=14KG Ton 0.5
82 3000030718 JUNCTION BOX 400X500X200MM EA 1
83 3000013976 DIN RAIL CHANNEL NS-35/7.5 PERFORATED EA 5
84 3000036612 MCCB,3POLE,100A,55KA,3VA1110-5ED32-0AA0 EA 1
85 3000029347 POWER CONTACTOR TY-3RT2027-1AL20 EA 2
86 3000029748 MPCB 5.5-8.0 AMPS, 3RV2011-1HA10 EA 2
87 3000001127 LOAD CONTACT (MCB) THREE POLE-63A EA 5
88 3000001125 LOAD CONTACT (MCB) THREE POLE 32A EA 2

Bought out item list of Primary He


S. NO Material code Item Description Qty Price/ unit
1 3000020105 PROX.SWITCH CR30-15AO DIA:30MM CAP.TYPE 6 1700
2 3000025522 DP TRANSMITTER RANGE 0-2000MMWC+2BRKT 1 37333
3 3000009548 LEVEL SWITCH MAGNETIC 40YWP / ABB/SDW 4 8750
4 3000021678 PRESSURE TRANSMITTER PIT-3301 1 26100
5 3000030219 CABLE 3CORE X 1.5MM2 COPPER COND.ARMOU 2000 80
6 3000030217 CABLE 2CORE X 1.5MM2 COPPER COND.ARMOU 1000 70
7 3000000431 CABLE CU. ARMOURED 4X1.5 MM SQPVC INSU. 2000 65
8 3000030220 CABLE 2CORE X1.5MM2 Cu.COND.K-TYP COMPE 1000 80
9 3000000523 CABLE GLAND SIBG 1619 250 41.44
10 3000021789 LUG CU. FORK TYPE 1.5MM2 P.NO-JFT-913 500 5
11 3000001651 LUG COPPER PIN TYPE 1.5MM SQCAT-CP9 500 0.58
12 3000009279 TUBE SS 1/2" (12MM) 500 386.25
13 3000039328 TUBE ADOPTER (MALE THREAD),1/2'' 200 200
14 3000009155 ADOPTOR S S 1/2"(M)X1/2"OD WITH NUT 100 149.35
15 3000009184 ELBOW SS 1/2"ODX1/2"(M)" 100 98.09
16 3000009252 TEE EQUAL 1/2"X1/2"X1/2" 50 112.5
17 3000002471 BALL VALVE SS SCREWEND 1/2"X1/2"(F)NPT 50 280
18 3000012409 NIPPLE 6" SS SIZE 1/2" NPT(M) BOTH SIDE 50 77.11
19 3000002438 SOCKET 1/2" SS316 NPT(F)X50MM LNTHBOTH 50 257
20 3000022641 SYPHON CS AS PER TAG NO. FOR NEW PROJ. 20 796.33
ht out Item List PH-05
PR No PO No Arrival Date Valuation Remark
8000070116 1000065812 20.12.2020 Rs. 19,766,250.00
8000070116 1000065812 20.11.2020 Rs. 4,400,000.00
8000070116 1000065812 28.09.2020 Rs. 150,000.00
8000070116 1000065799 28.09.2020 Rs. 96,000.00
8000070116 1000065799 28.09.2020 Rs. 50,000.00
8000070116 1000065799 28.09.2020 Rs. 240,000.00
8000070116 1000065799 28.09.2020 Rs. 296,880.00
8000070116 1000065799 28.09.2020 Rs. 356,885.00
8000070116 1000065299 06.04.2020 Rs. 108,000.00
8000070116 1000065812 28.08.2020 Rs. 240,000.00
8000070116 Rs. 190,000.00
8000070125 1000065390 05.05.2020 Rs. 6,000.00 Received
8000070116 Rs. 6,564,960.00 Order not placed
8000070116 1000065714 05.06.2020 Rs. 180,000.00
8000070116 1000065902 25.06.2020 Rs. 40,000.00
8000070116 1000065697 10.06.2020 Rs. 260,000.00
8000070125 1000065390 05.05.2020 Rs. 20,000.00
8000070116 1000066383 25.10.2020 Rs. 590,940.00
8000070125 Rs. 120,000.00
8000070125 Rs. 35,000.00
8000070116 1000065812 28.08.2020 Rs. 1,068,000.00
8000070116 1000065649 Rs. 1,086,800.00
8000070116 1000065649 Rs. 270,750.00
8000070116 1000065649 Rs. 189,525.00
8000070116 1000065649 Rs. 1,140.00
8000070116 1000065649 Rs. 10,901.25
8000070116 1000065649 Rs. 21,479.50
8000070116 1000065649 Rs. 6,859.00
8000070116 1000065649 Rs. 1,263.50
8000070116 1000065649 Rs. 1,383.20
8000070116 1000065649 Rs. 4,050.80
8000070116 1000065649 25.06.2020 Rs. 2,660.00
8000070116 1000065649 Rs. 3,068.50
8000070116 1000065649 Rs. 8,892.00
8000070116 1000065649 Rs. 1,216.00
8000070116 1000065649 Rs. 24,206.00
8000070116 1000065649 Rs. 85,462.00
8000070116 1000065649 Rs. 11,020.00
8000070116 1000065649 Rs. 7,267.50
8000070116 1000065649 Rs. 5,652.50
8000070116 1000065649 Rs. 8,550.00
8000070116 1000065649 Rs. 24,937.50
8000070065 1000065594 20.06.2020 Rs. 200,000.00
8000070065 1000065295 23.04.2020 Rs. 3,400.00
8000070125 1000065389 30.05.2020 Rs. 10,000.00
8000070125 1000065389 30.05.2020 Rs. 7,600.00
8000070125 1000065389 30.05.2020 Rs. 1,350.00
8000070563 1000065812 20.11.2020 Rs. 1,800,000.00
8000070563 1000065812 28.08.2020 Rs. 1,023,500.00
8000070718 1000065812 28.08.2020 Rs. 270,000.00
8000070718 1000065812 28.08.2020 Rs. 571,000.00
8000070718 1000065812 28.08.2020 Rs. 182,500.00
8000070718 1000065812 28.09.2020 Rs. 1,540,000.00
8000070718 1000065812 15.10.2020 Rs. 2,224,000.00
8000070718 1000065812 15.10.2020 Rs. 2,106,000.00
8000070718 1000065812 28.09.2020 Rs. 380,000.00

O Details for restorage of P.H # 5 ( Electrical)

P.O Value
P.R No P.R Date P.O No Arriving Date
(Rs.)

1000065593 15.06.2020

8000070085 29.03.2020

28,750.00 10.06.2020
20,000.00 10.06.2020
10,700.00 10.06.2020
8,000.00 10.06.2020
22,500.00 10.06.2020
8000070086 29.03.2020 1000065568 12,500.00 10.06.2020
4,550.00 10.06.2020
7,250.00 10.06.2020
4,050.00 10.06.2020
18,450.00 10.06.2020
19,650.00 10.06.2020
2,495.25 05.09.2020
1,527.75 25.07.2020
5,813.10 05.09.2020

8000070087 29.03.2020 1000066220


1,792.98 25.07.2020
8000070087 29.03.2020 1000066220 1,195.32 25.07.2020
480.48 25.07.2020
1,441.44 25.07.2020
1,441.44 25.07.2020
11,088.00 30.04.2020
474.00 25.07.2020
242.80 25.07.2020
157.20 25.07.2020
42.36 25.07.2020
1,406.00 25.07.2020
1,094.00 25.07.2020
962.00 25.07.2020
892.00 25.07.2020
412.00 25.07.2020
342.00 25.07.2020
358.00 25.07.2020
164.00 25.07.2020
1000066061
168.00 25.07.2020
8000070106 30.03.2020 1,895.60 25.07.2020
1,518.24 25.07.2020
1,305.24 25.07.2020
402.96 25.07.2020
604.44 25.07.2020
731.28 25.07.2020
1,321.60 25.07.2020
4,361.04 25.07.2020
319.20 25.07.2020
397.44 25.07.2020
546.00 25.07.2020
4,800.00 20.07.2020
1000066062 2,000.00 20.07.2020
2,600.00 20.07.2020
1,600.00 30.04.2020
350.00 30.04.2021
750.00 25.07.2020
120.00 25.07.2020
125.00 25.07.2020
185.00 25.07.2020
265.00 25.07.2020
8000070109 30.03.2020 1000066225
2,176.00 25.07.2020
3,000.00 30.04.2020
1,500.00 30.04.2020
2,100.00 30.04.2020
2,300.00 30.04.2020
900.00 25.07.2020
802.40 25.07.2020
13,600.00 20.7.2020
11,600.00
8000070110 30.30.2020 1000066145 7,500.00
1000066141 12,700.00 15.07.2020
1000066145 21,000.00 20.7.2020
1000066328 11,520.00 25.10.2020
8000070112 30.03.2020
1000066192 11,526.00 25.07.2020
8000070138 02.04.2020
8000070139 02.04.2020

8000070165 06.04.2020

out item list of Primary Heating -5 (Instrumentation)


Total price PR No PO No PO date Arriving date
10200 1000065458 29.04.2020
37333
35000 1000065457 29.04.2020
26100
160000 1000065465 29.04.2020
70000 1000065465 29.04.2020
130000 1000065465 29.04.2020
80000 1000065465 29.04.2020
10360 1000065394 18.04.2020
2500 1000065394 18.04.2021
8000070140
290 1000065394 18.04.2022
193125 1000065402 19.04.2020
40000 1000065402 19.04.2021
14935 1000065402 19.04.2022
9809 1000065402 19.04.2023
5625 1000065402 19.04.2024
14000 1000065402 19.04.2025
3855.5 1000065376 15.04.2020
12850 1000065402 19.04.2024
15926.6 1000065393 18.04.2020
Delivery status
Not Received
Not Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Not Received
Not Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Not Received
Received
Received

Remarks

Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Not Received
Not Received
Not Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Not Received
Received
Received
Received
Received
Received
Received
Received
Received
Received
Received

Remarks
Conditional assesment of VTAIF - 100
Date 22-Jul-20 Planned
S.no. Activity Start date
1 Ultrasonic thickness testing of convectve coil 1 18-07-2020
2 In situ Metallography of convective coil 1 21-07-2020
3 Hardness testing of convective coil 1 18-07-2020
4 DP testing of convective coil 1 19-07-2020
5 Magnetic particle inspection of convective coil 1 19-07-2020
6 Ultrasonic thickness testing of Outlet Header convectve coil 1 20-07-2020
7 In situ Metallography of Outlet Header convectve coil 1 21-07-2020
8 Ultrasonic thickness testing of convectve coil 2
9 Hardness testing of Outlet Header convectve coil 1 18-07-2020
10 DP testing of Outlet Header convectve coil 1 19-07-2020
11 Magnetic particle inspection of Outlet Header convectve coil 1 19-07-2020
12 Ultrasonic thickness testing of Outlet Header convectve coil 2 24-07-2020
13 In situ Metallography of Outlet Header convectve coil 2 21-07-2020
14 Hardness testing of Outlet Header convectve coil 2 18-07-2020
15 DP testing of Outlet Header convectve coil 2 19-07-2020
16 Magnetic particle inspection of Outlet Header convectve coil 2 19-07-2020
17 In situ Metallography of convectve coil 2 23-07-2020
18 Hardness testing of convectve coil 2 22-07-2020
19 DP testing of convectve coil 2 23-07-2020
20 Magnetic particle inspection of convectve coil 2 24-07-2020
21 Outlet header coil 2 7/23/2020
24 Ultrasonic thickness testing of MPA 23-07-2020
25 Hardness testing of MPA 23-07-2020
26 Destructive testing of MPA 23-07-2020
27 ID fan impeller visual inspection 26-07-2020
28 ID fan impeller hardness testing 26-07-2020
29 ID fan impeller Thickness testing 26-07-2020
30 FD fan impeller visual inspection 26-07-2020
31 FD fan impeller hardness testing 26-07-2020
32 FD fan impeller Thickness testing 26-07-2020
33 ENSG visual inspection 27-07-2020
34 Pnematic testing(inlet + outlet header ) CC 27-07-2020
35 Pre-eliminary report shared by regional team 27-07-2020
36 Conditional assesment report submission by our expert team at HO 05-08-2020
37 Destructive testing of convectve coil 2 23-07-2020
38 Destructive testing of convectve coil 1 23-07-2020
39 Ultrasonic thickness testing of Inlet Header convectve coil 2 24-07-2020
40 In situ Metallography of Inlet Header convectve coil 2 21-07-2020
41 Hardness testing of Inlet Header convectve coil 2 18-07-2020
42 DP testing of Inlet Header convectve coil 2 19-07-2020
43 Magnetic particle inspection of Inlet Header convectve coil 2 19-07-2020
44 Ultrasonic thickness testing of Inlet Header convectve coil 1 24-07-2020
45 In situ Metallography of Inlet Header convectve coil 1 21-07-2020
46 Hardness testing of Inlet Header convectve coil 1 18-07-2020
47 DP testing of Inlet Header convectve coil 1 19-07-2020
48 Magnetic particle inspection of Inlet Header convectve coil 1 19-07-2020
49 Roof coil hardness+thickness of convecting coil -1
50 Roof coil hardness+thickness of convecting coil -2
51 IBH inletfor
DP test and outlet
IBH header
header + MPI(hardness+thickness) test
test+(hardness & Thickness)test of IBH
52 tubes
53 Chimney grinding for inspection and thickness test
54 DP test for convective coil weld section
F - 100
Planned Actual
End date Start date End date
19-07-2020 18-07-2020 19-07-2020
21-07-2020 7/21/2020 7/22/2020
19-07-2020 7/21/2020 7/22/2020
20-07-2020 NA NA
20-07-2020 7/20/2020 7/20/2020
20-07-2020 7/21/2020 7/22/2020
21-07-2020 7/21/2020 7/22/2020
7/24/2020 7/24/2020
19-07-2020 7/22/2020 7/23/2020
20-07-2020 7/22/2020 7/23/2020
20-07-2020 7/22/2020 7/23/2020
24-07-2020 7/22/2020 7/23/2020
21-07-2020 7/21/2020 7/22/2020
19-07-2020 7/21/2020 7/22/2020
20-07-2020 7/22/2020 7/23/2020
20-07-2020 20-07-2020 20-07-2020
23-07-2020 7/24/2020 7/24/2020
23-07-2020 7/23/2020 24-07-2020
24-07-2020 NA NA
24-07-2020 7/22/2020 7/22/2020
24-07-2020 7/21/2020 20-07-2020
23-07-2020 7/28/2020 7/29/2020
23-07-2020 7/28/2020 7/29/2020
23-07-2020 NA NA
26-07-2020 NA NA
26-07-2020 NA NA
26-07-2020 NA NA
26-07-2020 NA NA
26-07-2020 NA NA
26-07-2020 NA NA
27-07-2020 NA NA
27-07-2020 7/26/2020 7/26/2020
27-07-2020
05-08-2020
26-07-2020 NA NA
25-07-2020 NA NA
24-07-2020 7/25/2020 7/25/2020
21-07-2020 7/25/2020 7/25/2020
19-07-2020 7/25/2020 7/25/2020
20-07-2020 7/25/2020 7/25/2020
20-07-2020 7/25/2020 7/25/2020
24-07-2020 7/25/2020 7/25/2020
21-07-2020 7/25/2020 7/25/2020
19-07-2020 7/25/2020 7/25/2020
20-07-2020 7/25/2020 7/25/2020
20-07-2020 7/25/2020 7/25/2020
7/25/2020 7/25/2020
7/25/2020 7/25/2020
7/26/2020 7/27/2020
7/27/2020 7/27/2020
7/28/2020 7/29/2020
7/29/2020 7/29/2020
Date: 12/01/21
PH#5 -Pending Bullet Points
Target
Sr No Description date
1 Expansion tank platform 15/01/21
2 Building roof sheet fixing 17/01/21
Control room window , door &
3 painting 17/01/21
5 Control room tile installation 20/01/21
6 Heater room flooring 20/01/21
Civil scrap & unwanted civil
7 materials shifting 25/01/21
Main incomer termination from
8 pump room to panel room 13/01/21
ID , FD -2 Nos, RAV-2 Nos, FP, husk
feeder cable laying and
9 termination. 15/01/21
Earthing pit construction &
10 termination for PLC & MCC 16/01/21
False ceiling & Lighting for control
11 room & building shed 18/01/21
DP switch installation for
convective, MPA & IBH coil ( 30
12 Nos) 21/01/21
DP pipe line tapping for
convective coil, IBH, MPA header
13 (30 nos) 18/01/21
Flow transmitter fitment in main
14 line & IBH by pass line. 19/01/21
Main line flow transmitter orifice
15 relocation as per new drg 19/01/21
PT pipe line laying at main heater
16 outlet line 19/01/21
PT fitment in main heater outlet
17 line 22/01/21
RTD instrument fitting ( HTM inlet,
outlet, convective coil both outlet,
18 APH inlet, bag filter outlet. 22/01/21
Both Bed thermocouple fitment &
19 cable laying, termination 23/01/21
FD fan 1,&2- Damper cylinder
fitment/ mounting, cabling,
20 termination
ID fan inlet pressure switch 23/01/21
21 fitment 23/01/21
Screw feeder sensor fitment &
22 cabling 23/01/21
23 Flue gas all three damper cabling. 24/01/21
Expansion tank level transmitter &
24 level switch fitment 24/01/21
Expansion tank level transmitter &
level switch cable laying and
25 termination 24/01/21
26 Refractory work installation 22/01/21
27 Refractory
Radiography dryofcuring
the pipe lines 25/01/21
28 joints
29 Flushing of the pipe lines 15/01/21
30 Pneumatic testing 19/01/21
4 Building structure room painting 15/01/21

25 & 26 /
31 HTM filling and circulation. 01/21
27 to
32 Slow firing 30/1/21
33 Heater will be taken in line 31/01/21

You might also like