JJM CONSTRUCTION CO., INC.

General Contractor . Engineers . Designers


De Quiroz Compound, 3626 Buhay na Tubig, Imus, Cavite
Cell. Nos. 09189256281, 09089574920, Tel No. (046) 683-2838

SUMMARY OF ACCOMPLISHMENT REPORT


DATE COVERED: As of April 15, 2021

WORK TOTAL QUANTITY COMPLETED BALANCE/S Remarks


DESCRIPTION
PERIMETER FENCE
Fabrication of Grilles 48pcs. 45pcs. 3pcs. On going fabrication
Cornering Interior 48spans 21spans 27spans
Cornering Exterior 48spans 17spans 31spans
Groove Interior 48span 21spans 27spans On going but as of april 13
up to now no manpower
c/o Johnny Miscala
Groove Exterior 48spans 8spans 40spans
Wall Finishing Interior 48spans 23spans 25spans
Wall Finishing 48spans 23spans 28spans
Exterior
Concreting of column 49pcs. 40pcs. 9pcs. Waiting for the delivery of
phenolic for formworks.
CHB Laying and 47spans 47spans 0 Completed
Plastering
RETAINING WALL
CHB Laying 217lm 214lm 3lm Due to abandoned
Meralco post
Plastering Exterior 217lm 211lm 6lm On going
Plastering Interior 217lm 202lm 15lm On going
Finishing 217lm 179m 48lm On going
INSTALLATION OF GRILLES (Justice Hall)
Fabrication 71pcs. 5pcs. 66pcs. Waiting for the delivery of
materials.
Installation 71pcs. 0 71pcs. Waiting for approval of
connection detail.
Painting 71pcs. 0 71pcs. Waiting for the delivery of
materials for painting.
WHEEL STOPPER
Fabrication 207pcs. 180pcs. 27pcs. On going
Installation 207pcs. 0 207pcs. Waiting for the delivery of
concrete epoxy.
STREET LIGHT
Pedestal 27pcs. 15pcs. 12pcs. The balances proceed
together the roadway and
parkings.
Installation of street 27pcs. 14pcs. 13pcs. Installation will proceed if
Light post the balance pedestals are
already done.
Installation of Bulb 27pcs. 12pcs. 15pcs.
MANHOLE
Installation of 44pcs. 7pcs. 37pcs. Waiting for the delivery of
Manhole Cover materials.
Installation of Ladder 44pcs. 4pcs. 40pcs. On going
rung
ROADS
Area A and 20% There’s a lot of obstruction
Commercial like stock file of
Preparation of Sub 30% 20% scaffolding,materials, etc.
Base Course of other contractor.
Preparation of Base 20% 0%
Course
Formworks 10% 0%
Concrete Pouring 40% 0%
Area B 100%
Preparation of Sub 30% 30%
Base Course
Preparation of Base 20% 20% completed
Course
Formworks 10% 10%
Concrete Pouring 40% 40%
Area C 94%
Preparation of Sub 30% 28%
Base Course
Preparation of Base 20% 19% On going
Course
Formworks 10% 9%
Concrete Pouring 40% 38%
Area D 100%
Preparation of Sub 30% 30%
Base Course Completed
Preparation of Base 20% 20%
Course
Formworks 10% 10%
Concreting 40% 40%
PARKINGS
Area A 18%
Preparation of Sub 30% 5%
Base Course
Preparation of Base 20% 3%
Course
Formworks 10% 2%
Concrete Pouring 40% 8%
Area B 50%
Preparation of Sub 30% 15%
Base Course
Preparation of Base 20% 10%
Course
Formworks 10% 5%
Concrete Pouring 40% 20%
Area C 97%
Preparation of Sub 30% 30%
Base Course
Preparation of Base 20% 19%
Course
Formworks 10% 9%
Concrete Pouring 40% 39%
Area D 100%
Preparation of Sub 30% 30%
Base Course
Preparation of Base 20% 20% Completed
Course
Formworks 10% 10%
Concreting 40% 40%
SIDEWALK
Area A 20% Waiting for the delivery of
Preparation of Sub 30% 20% rebars
Base Course
Spreading of gravel 20%
beeding
Formworks 10%
Concrete Pouring 40%
Area B 42%
Preparation of Sub 30% 25%
Base Course
Spreading of gravel 20% 10%
beeding
Formworks 10% 7%
Concrete Pouring 40%
Area C
Preparation of Sub 30%
Base Course
Preparation of Base 20%
Course
Formworks 10%
Concrete Pouring 40%
Area D
Preparation of Sub 30%
Base Course
Preparation of Base 20%
Course
Formworks 10%
Concreting 40%
DRAINAGE
Installation of 95% 5% Waiting for the delivery of
Concrete Pipe RCP

CURB and GUTTER


Area A 0
Area B 0
Area C 50%
Area D 0

Prepared by:

Galicano Acejo Jr.


JJM-QAQC