BQ Sheet

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 22

RE RESOURCES ENTERPRISE

Reg. No. JR0062494-H


NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

: CADANGAN MEMBINA 1 UNIT RUMAH KEDIAMAN 1 TINGKAT JENIS KEKAL DI ATAS LOT 2493, JALAN TELOK KEMANG,
Project KAMPUNG TELOK KEMANG, MUKIM JALAN BAKRI, 84000 MUAR, DAERAH MUAR, JOHOR
Area 795 sqf
Date : 14th OCTOBER 2020 SUMMARY
ITEM DESCRIPTION PAGE AMOUNT

KERJA-KERJA PILING 6,087.10

KERJA SUBSTRUKTUR Err:509

KERJA STRUKTUR BANGUNAN -

KERJA BUMBUNG -

PINTU DAN TINGKAP -

KEMASAN LUARAN -

KEMASAN DALAMAN -

KERJA-KERJA ELEKTRIK 3,300.00

KERJA-KERJA SISTEM PEMBENTUNGAN 1,000.00

KERJA-KERJA SALURAN PAIP 1,000.00

TABLE TOP 3,000.00

KERJA-KERJA LUAR BANGUNAN -

JUMLAH KESELURUHAN Err:509

Dalam Ringgit Malaysia:

Tempoh Siap:

Disediakan oleh:

............................................

Summary
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA-KERJA PILING

Piling
Bakau 75mm x 10ft panjang piling nos 216 9.20 1,987.20

Pile Cap (1.0m x 1.0m x 600mm depth)


Konkrit G25 m3 10.8 300.00 3,240.00
Tetulang untuk konkrit
Y12mm kg 121 5.50 665.50
Acuan konkrit m2 4.32 45.00 194.40

carried to collection 6,087.10

Disediakan oleh: Diluluskan oleh:


Page 2 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA SUBSTRUKTUR

Asas Pad (1.0m x 1.0m x 600mm depth)


Korek Tanah untuk isi asas pad m3 Err:509 Err:509
50mm Hadkor m2 0 -
Konkrit G25 m3 Err:509 300.00 Err:509
Tetulang untuk konkrit
Y12mm kg 67 5.50 368.50
Acuan konkrit m2 0 45.00 -

Column Stump (125mm x 300mm x 350mm high)


Konkrit G25 m3 0 300.00 -
Tetulang untuk konkrit
Y12mm kg 23 5.50 126.50
R6 link c/c 200mm kg 2 5.50 11.00
Acuan konkrit m2 0 45.00 -

Rasuk Bawah (125mm x 450mm)


Korek Tanah untuk isi rasuk bawah m3 - -
50mm Hadkor m2 - -
Konkrit G25 m3 300.00 -
Tetulang untuk konkrit
Y12mm kg 5.50 -
R6 link c/c 200mm kg 5.50 -
Acuan konkrit m2 45.00 -

Lantai Bawah (125mm depth)


Konkrit G25 m3 300.00 -
BRC A7 m2 -
Hardkor m2 - -
Lapisan kalis lembap m2 -

carried to collection Err:509

Disediakan oleh: Diluluskan oleh:


Page 3 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA STRUKTUR BANGUNAN

Tiang
Konkrit m3 -
Tetulang untuk konkrit kg -
Acuan konkrit m2 -

Lantai Atas
Konkrit m3 -
BRC kg -
Acuan konkrit m2 -

Tangga
Konkrit m3 -
Tetulang untuk konkrit kg -
BRC kg -
Acuan konkrit m2 -

Dinding
Dinding batu ____ m2 -

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 4 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA BUMBUNG

Kerangka Bumbung
Kerangka Bumbung m2 -

Penutup Bumbung
Penutup Bumbung m2 -
Lapisan kalis lembap m2 -
Penebat Aluminium m2 -

Saliran Air Hujan


Gutter m -
Paip Saliran air hujan m -
SPAH Tank nos 1 -

Papak Bumbung (125mm tebal)


Konkrit m3
BRC kg
Acuan konkrit m2

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 5 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

PINTU DAN TINGKAP

Pintu
Pintu Utama nos -
Pintu Bilik nos -
Pintu Bilik Air nos -

Tingkap
Tingkap nos -
Tingkap Bilik nos -
Tingkap Bilik Air nos -

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 6 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KEMASAN LUARAN

Dinding Luar
Plastering m2 -
Cat m2 -

Lantai Luar
Rendering m2 -
Jubin m2 -

Siling Luar
Siling Luar m2 -
Fascia m -

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 7 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KEMASAN DALAMAN

Dinding Dalam
Plastering m2 -
Cat m2 -

Lantai Dalam
Rendering m2 -
Jubin m2 -

Siling Dalam
Siling dalam m2 -
Cornice nos -

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 8 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA-KERJA ELEKTRIK

Kerja -kerja pendawaian elektrik termasuk poin soket dan suis L/S 3,300.00

KERJA-KERJA SISTEM PEMBENTUNGAN

Kerja-kerja sistem pembentungan L/S 1,000.00

KERJA-KERJA SALURAN PAIP

Kerja-kerja saliran paip (inlet & outlet) L/S 1,000.00

TABLE TOP

1 set table top dapur 12 kaki L/S 3,000.00

carried to collection 8,300.00

Disediakan oleh: Diluluskan oleh:


Page 9 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : Bill of Quantity
ITEM DESCRIPTION UNIT QTY RATE AMOUNT

KERJA-KERJA LUAR BANGUNAN

Longkang m -
Pejalan kaki m2 -

carried to collection -

Disediakan oleh: Diluluskan oleh:


Page 10 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA-KERJA PILING

Piling
Bakau 75mm x 10ft panjang piling nos 12 18 216.00 216

Pile Cap (1.0m x 1.0m x 600mm depth)


Konkrit G25 m3 1.000 1.000 0.600 18 10.80 11
Tetulang untuk konkrit
Y12mm kg 1.520 10 18 273.60 0.888 243
Acuan konkrit m2 4.000 0.060 18 4.32 4

KERJA SUBSTRUKTUR

Asas Pad (1.0m x 1.0m x 600mm depth)


Korek Tanah untuk isi asas pad m3 1.000 1.000 0.650 3 1.95 2
50mm Hadkor m2 1.000 1.000 3 3.00 3
Konkrit G25 m3 1.000 1.000 0.600 3 1.80 1.8
Tetulang untuk konkrit
Y12mm kg 1.500 10 3 45.00 0.888 40
Acuan konkrit m2 4.000 0.600 3 7.20 7.2

Column Stump (125mm x 300mm x 350mm high)


Konkrit G25 m3 0.300 0.125 0.300 21 0.24 1
Tetulang untuk konkrit
Y12mm kg 1.250 4 21 105.00 0.888 93
R6 link c/c 200mm kg 1.063 2 21 44.63 0.222 10
Acuan konkrit m2 0.850 0.350 21 6.25 6

Rasuk Bawah (125mm x 300mm)


Korek Tanah untuk isi rasuk bawah
Vertical beam
B m3 4.322 0.125 0.350 1 0.19
C m3 7.730 0.125 0.350 1 0.34
E&G m3 7.855 0.125 0.350 2 0.69
F m3 2.009 0.125 0.350 1 0.09
Horizontal beam
1a m3 5.496 0.125 0.350 1 0.24
2 m3 2.748 0.125 0.350 1 0.12
2a m3 2.448 0.125 0.350 1 0.11
3 m3 7.944 0.125 0.350 1 0.35
4 m3 2.748 0.125 0.350 1 0.12
5 m3 5.496 0.125 0.350 1 0.24 2
Konkrit G25 m3 same as korek tanah 2
Tetulang untuk konkrit
Y12mm
Vertical beam
B kg 5.272 4 1 21.09
C kg 8.930 4 1 35.72
E&G kg 8.930 4 2 71.44
F kg 2.834 4 1 11.34
Horizontal beam
1a kg 6.796 4 1 27.18
2 kg 3.748 4 1 14.99
2a kg 3.748 4 1 14.99
3 kg 9.244 4 1 36.98
4 kg 3.748 4 1 14.99
5 kg 6.796 4 1 27.18 0.888 245

Disediakan oleh: Diluluskan oleh:


Page 11 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA SUBSTRUKTUR (Samb)

Rasuk Bawah (125mm x 300mm) (Samb)


R6 link c/c 200mm
Vertical beam
B kg 1.163 24 1 27.90
C kg 1.163 42 1 48.83
E&G kg 1.163 42 2 97.65
F kg 1.163 12 1 13.95
Horizontal beam
1a kg 1.163 31 1 36.04
2 kg 1.163 16 1 18.60
2a kg 1.163 16 1 18.60
3 kg 1.163 44 1 51.15
4 kg 1.163 16 1 18.60
5 kg 1.163 31 1 36.04 0.222 82
Acuan konkrit
Vertical beam
B (both side) m2 4.322 0.600 2 1 5.19
C (both side) m2 7.605 0.600 2 1 9.13
E (both side) m2 7.730 0.600 2 1 9.28
G (both side) m2 7.855 0.600 2 1 9.43
F (both side) m2 2.009 0.600 2 1 2.41
Horizontal beam
1a (both side) m2 5.496 0.600 2 1 6.60
2 (both side) m2 2.748 0.600 2 1 3.30
2a (both side) m2 2.448 0.600 2 1 2.94
3 (both side) m2 7.944 0.600 2 1 9.53
4 (both side) m2 2.748 0.600 2 1 3.30
5 (both side) m2 5.496 0.600 2 1 6.60 68

Lantai Bawah (125mm depth)


Konkrit G25
Master Bedroom, Bedroom 2 & 3, Kitchen m3 2.923 2.923 0.125 4 34.18
Bath 1 m3 2.923 1.399 0.125 1 0.51
Dining (near living) m3 2.923 2.072 0.125 1 0.76
Dining (infront bath 2) m3 1.399 2.009 0.125 1 0.35
Living m3 2.923 2.986 0.125 1 1.09
Bath 2 m3 1.399 2.009 0.125 1 0.35

BRC A7 (1 layer)
Master Bedroom, Bedroom 2 & 3, Kitchen m2 2.923 2.923 4 34.18
Bath 1 m2 2.923 1.399 1 4.09
Dining (near living) m2 2.923 2.072 1 6.05
Dining (infront bath 2) m2 1.399 2.009 1 2.81
Living m2 2.923 2.986 1 8.73
Bath 2 m2 1.399 2.009 1 2.81 59

Hardkor
Master Bedroom, Bedroom 2 & 3, Kitchen m2 2.923 2.923 4 34.18
Bath 1 m2 2.923 1.399 1 4.09
Dining (near living) m2 2.923 2.072 1 6.05
Dining (infront bath 2) m2 1.399 2.009 1 2.81
Living m2 2.923 2.986 1 8.73
Bath 2 m2 1.399 2.009 1 2.81 59

Lapisan kalis lembap


Master Bedroom, Bedroom 2 & 3, Kitchen m2 3.523 3.523 4 49.65
Bath 1 m2 3.523 1.999 1 7.04
Dining (near living) m2 3.223 2.372 1 7.64
Dining (infront bath 2) m2 1.699 2.609 1 4.43
Living m2 3.523 3.286 1 11.57
Bath 2 m2 1.999 2.609 1 5.22 86

Disediakan oleh: Diluluskan oleh:


Page 12 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA SUBSTRUKTUR (Samb)

Lantai Bawah Luar (125mm depth) - Car Porch


Konkrit G25
Bahagian A m3 1.231 3.224 0.125 1 0.50
Tiang (150mm x 400mm) m3 0.150 0.400 0.125 -2 (0.02)
Bahagian B m3 3.048 3.048 0.125 1 1.16
Bahagian C m3 2.115 0.938 0.125 1 0.25 2
BRC A7 (1 layer)
Bahagian A m2 1.231 3.224 1 3.97
Tiang (150mm x 400mm) m2 0.150 0.400 -2 (0.12)
Bahagian B m2 3.048 3.048 1 9.29
Bahagian C m2 2.115 0.938 1 1.98 15
Hardkor
Bahagian A m2 1.231 3.224 1 3.97
Tiang (150mm x 400mm) m2 0.150 0.400 -2 (0.12)
Bahagian B m2 3.048 3.048 1 9.29
Bahagian C m2 2.115 0.938 1 1.98 15
Lapisan kalis lembap
Bahagian A m2 1.231 3.224 1 3.97
Tiang (150mm x 400mm) m2 0.150 0.400 -2 (0.12)
Bahagian B m2 3.048 3.048 1 9.29
Bahagian C m2 2.115 0.938 1 1.98 15
Acuan Konkrit (Sided)
Bahagian A m2 4.586 0.125 1 0.57
Bahagian B m2 3.048 0.125 1 0.38
Bahagian C m2 2.503 0.125 1 0.31 1

KERJA STRUKTUR BANGUNAN

Tiang (150mm x 400mm)


Konkrit G25 m3 0.400 0.150 3.194 21 4.02 4
Tetulang untuk konkrit
Y12mm kg 3.594 4 21 301.90 0.888 268
R6 link c/c 200mm kg 1.313 17 21 468.56 0.222 104
Acuan konkrit m2 1.100 2.744 21 63.39 63

Rasuk Atas (125mm x 450mm)


Konkrit G25
Vertical beam
A m3 2.648 0.125 0.450 1 0.15
B m3 4.272 0.125 0.450 1 0.24
C m3 7.630 0.125 0.450 1 0.43
E m3 8.119 0.125 0.450 1 0.46
G m3 7.780 0.125 0.450 1 0.44
F m3 1.984 0.125 0.450 1 0.11
Horizontal beam
1 m3 7.166 0.125 0.450 1 0.40
1a m3 5.296 0.125 0.450 1 0.30
2 m3 3.593 0.125 0.450 1 0.20
2a m3 2.186 0.125 0.450 1 0.12
3 m3 7.544 0.125 0.450 1 0.42
4 m3 2.648 0.125 0.450 1 0.15
5 m3 5.296 0.125 0.450 1 0.30 4
Tetulang untuk konkrit
Y12mm
Vertical beam
A kg 4.148 4 1 16.59
B kg 5.397 4 1 21.59
C kg 9.055 4 1 36.22
E kg 10.107 4 1 40.43
G kg 9.055 4 1 36.22
F kg 2.959 4 1 11.84

Disediakan oleh: Diluluskan oleh:


Page 13 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA STRUKTUR BANGUNAN (Samb)

Rasuk Atas (125mm x 450mm) (Samb)


Tetulang untuk konkrit (Samb)
Y12mm (Samb)
Horizontal beam
1 kg 8.166 4 1 32.66
1a kg 7.196 4 1 28.78
2 kg 5.443 4 1 21.77
2a kg 4.211 4 1 16.84
3 kg 9.969 4 1 39.88
4 kg 4.148 4 1 16.59
5 kg 7.196 4 1 28.78 0.888 309
R6 link c/c 200mm
Vertical beam
A kg 1.050 16 1 16.80
B kg 1.050 24 1 25.20
C kg 1.050 42 1 44.10
E kg 1.050 47 1 49.35
G kg 1.050 42 1 44.10
F kg 1.050 12 1 12.60
Horizontal beam
1 kg 1.050 38 1 39.90
1a kg 1.050 31 1 32.55
2 kg 1.050 22 1 23.10
2a kg 1.050 16 1 16.80
3 kg 1.050 47 1 49.35
4 kg 1.050 16 1 16.80
5 kg 1.050 31 1 32.55 0.222 90
Acuan konkrit
Vertical beam
A m2 2.648 1.025 1 2.71
B m2 4.272 1.025 1 4.38
C m2 7.630 1.025 1 7.82
E m2 8.119 1.025 1 8.32
G m2 7.780 1.025 1 7.97
F m2 1.984 1.025 1 2.03
Horizontal beam
1 m2 7.166 1.025 1 7.35
1a m2 5.296 1.025 1 5.43
2 m2 3.593 1.025 1 3.68
2a m2 2.186 1.025 1 2.24
3 m2 7.544 1.025 1 7.73
4 m2 2.648 1.025 1 2.71
5 m2 5.296 1.025 1 5.43 68

Tangga (150mm thick)


Konkrit G25
Tangga depan m3 3.517 0.235 0.150 1 0.12
Tangga belakang m3 1.220 0.235 0.150 1 0.04 1
Tetulang untuk konkrit
Y12mm
Tangga depan
main rod kg 3.567 2 1 7.13
links kg 0.285 15 1 4.28
Tangga belakang
main rod kg 1.270 2 1 2.54
links kg 0.285 5 1 1.43 0.888 14
Acuan konkrit
Tangga depan m2 3.987 0.150 1 0.60
Tangga belakang m2 1.690 0.150 1 0.25 1

Disediakan oleh: Diluluskan oleh:


Page 14 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA STRUKTUR BANGUNAN (Samb)

Dinding (115mm)
Dinding bata pasir
Vertical wall
B m2 4.272 3.048 1 13.02
W2 m2 1.200 1.200 -1 (1.44)
W5 m2 0.600 0.600 -1 (0.36)
C m2 7.630 3.048 1 23.26
D1 m2 0.900 2.100 -1 (1.89)
E m2 2.748 3.048 2 16.75
F m2 1.984 3.048 1 6.05
D2 m2 0.750 2.100 -1 (1.58)
G m2 7.780 3.048 1 23.71
W1 m2 1.200 1.600 -1 (1.92)
W3 m2 1.200 0.600 -1 (0.72)
F m2 1.984 3.048 1 6.05
D2 m2 0.750 2.100 -1 (1.58)
Horizontal wall
1a m2 5.296 3.048 1 16.14
S1 m2 1.800 2.100 -1 (3.78)
W1 m2 1.200 1.600 -1 (1.92)
2 m2 2.648 3.048 1 8.07
W4 m2 0.600 1.800 -1 (1.08)
2a m2 2.248 3.048 1 6.85
D1 m2 0.900 2.100 -1 (1.89)
3 m2 6.324 3.048 1 19.28
D1 m2 0.900 2.100 -1 (1.89)
D2 m2 0.750 2.100 -1 (1.58)
4 m2 2.648 3.048 1 8.07
5 m2 5.296 3.048 1 16.14
W1 m2 1.200 1.600 -1 (1.92)
D1 m2 0.900 2.100 -1 (1.89) 138

Facade (235mm thick)


Fasad bata pasir
B m2 0.235 2.850 1 0.67
C m2 2.403 2.850 1 6.85
E m2 0.235 2.850 1 0.67
2 m2 0.235 2.850 2 1.34 10
Konkrit G25 m3 2.345 0.235 0.235 1 0.13 1
Tetulang untuk konkrit
Y12mm kg 2.595 2 5.19 0.888 5
Acuan konkrit m2 2.110 0.470 1 0.99 1

Disediakan oleh: Diluluskan oleh:


Page 15 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KERJA BUMBUNG

Kerangka Bumbung (0.75mm Light Weight Zincalume Roof Trusses)


Kerangka Bumbung
Bahagian A m2 7.419 3.742 0.5 2 27.76
Bahagian B m2 11.707 3.742 0.5 2 43.81
Bahagian C m2 5.912 2.982 0.5 -1 (8.82)
Bahagian C m2 3.014 2.982 2 17.98
Bahagian D m2 5.912 2.924 0.5 1 17.29 98

Penutup Bumbung
Penutup Bumbung m2 same as kerangka bumbung 98
Penebat Aluminium m2 same as kerangka bumbung 98

Papak Bumbung (125mm tebal)


Konkrit G25
Bahagian A m3 4.405 1.855 0.125 1 1.02
Bahagian B m3 3.593 3.014 0.125 1 1.35
Bahagian C m3 1.507 3.825 0.125 1 0.72 3
BRC A7 (1 layer) m2 same as konkrit G25 3
Acuan konkrit
Bahagian A (bottom) m2 4.405 1.855 1 8.17
Bahagian A (Sided) m2 8.115 0.125 1 1.01
Bahagian B (bottom) m2 3.593 3.014 1 10.83
Bahagian B (Sided) m2 3.014 0.125 1 0.38
Bahagian C (bottom) m2 1.507 3.825 1 5.76
Bahagian C (Sided) m2 5.332 0.125 1 0.67 27
Lapisan kalis lembap m2 same as konkrit G25 3

PINTU DAN TINGKAP

Pintu
1800mm x 2100mm Aluminium Frame
nos 1 1.00 1
Sliding Door (S1)
900mm x 2100mm Metal Frame Single
Leaf Decorative Solid Timber Panel Door
nos 4 4.00 4
termasuk mengecat pintu kayu dengan 'Sea
Master' (D1)

750mm x 2100mm Metal Frame Single


Leaf UPVC Panel Door termasuk mengecat nos 2 2.00 2
pintu kayu dengan 'Sea Master' (D2)

Tingkap
1200mm x 1600mm Aluminium Frame
nos 3 3.00 3
Casement Tinted Glass Window (W1)
1200mm x 1200mm Aluminium Frame
nos 1 1.00 1
Casement Tinted Glass Window (W2)
1200mm x 600mm Aluminium Frame
Casement Tinted Glass Top Hung Window nos 1 1.00 1
(W3)
600mm x 1800mm Aluminium Frame
nos 1 1.00 1
Casement Tinted Glass Window (W4)
600mm x 600mm Aluminium Frame
Casement Tinted Glass Top Hung Window nos 1 1.00 1
(W5)

Disediakan oleh: Diluluskan oleh:


Page 16 of 22
................................ ................................
Disediakan oleh: Diluluskan oleh:
Page 17 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KEMASAN LUARAN

Dinding Luar
25mm Plastering (1:6 simen mortar)
Vertical wall
B2-B4 m2 4.272 3.048 1 13.02
W2 m2 1.200 1.200 -1 (1.44)
W5 m2 0.600 0.600 -1 (0.36)
facade m2 0.235 2.850 -1 (0.67)
facade m2 2.110 0.235 -1 (0.50)
C4-C5 m2 1.374 3.048 1 4.19
G1a-G5 m2 7.780 3.048 1 23.71
W1 m2 1.200 1.600 -1 (1.92)
W3 m2 1.200 0.600 -1 (0.72)
Horizontal wall
C1a-G1a m2 5.296 3.048 1 16.14
S1 m2 1.800 2.100 -1 (3.78)
W1 m2 1.200 1.600 -1 (1.92)
B2-C2 m2 2.648 3.048 1 8.07
W4 m2 0.600 1.800 -1 (1.08)
facade m2 0.235 2.850 -3 (2.01)
B4-C4 m2 2.648 3.048 1 8.07
C5-G5 m2 5.296 3.048 1 16.14
W1 m2 1.200 1.600 -1 (1.92)
D1 m2 0.900 2.100 -1 (1.89) 71
2 lapisan 'Jotun Weather Shield' basic dengan m2 same as plastering 71

Facade
25mm Plastering (1:6 simen mortar)
B (Vertical) m2 0.705 2.850 1 2.01
B (Horizontal) m2 2.110 0.705 1 1.49
C m2 2.638 2.850 1 7.52
E m2 0.470 2.850 1 1.34
2 m2 0.705 2.850 2 4.02 16
2 lapisan 'Jotun Weather Shield' basic dengan m2 same as plastering 16

Lantai Luar
25mm Rendering
Bahagian A m2 1.231 2.115 1 2.60
Tiang (150mm x 400mm) m2 0.150 0.400 -2 (0.12)
Bahagian B m2 3.048 3.048 1 9.29
Bahagian C m2 2.115 0.938 1 1.98 14

Siling Luar
25mm Plastering celiling (1:6 simen mortar)
Bahagian A m2 1.231 2.115 1 2.60
Tiang (150mm x 400mm) m2 0.150 0.400 -2 (0.12)
Bahagian B m2 3.048 3.048 1 9.29
Bahagian C m2 2.115 0.938 1 1.98 14
Gypsum board ceiling
Bahagian A m2 7.419 0.600 2 8.90
Bahagian B (G) m2 8.363 0.600 1 5.02
Bahagian B (C) m2 3.651 0.600 1 2.19
Bahagian C m2 3.014 0.600 2 3.62
Bahagian D m2 4.712 0.600 1 2.83 23
Fascia
Bahagian A m 7.419 2 14.84
Bahagian B (G) m 9.563 1 9.56
Bahagian B (C) m 3.651 1 3.65
Bahagian C m 3.014 2 6.03
Bahagian D m 5.912 1 5.91 40

Disediakan oleh: Diluluskan oleh:


Page 18 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KEMASAN DALAMAN

Dinding Dalam
Plastering
Bath 1 m2 8.684 3.653 1 31.72
D2 m2 0.750 2.100 -1 (1.58)
W5 m2 0.600 0.600 -1 (0.36)
Bath 2 m2 6.696 3.653 1 24.46
D2 m2 0.750 2.100 -1 (1.58)
W3 m2 1.200 0.600 -1 (0.72)
Master Bedroom m2 11.732 3.653 1 42.86
D1 m2 0.900 2.100 -1 (1.89)
D2 m2 0.750 2.100 -1 (1.58)
W2 m2 1.200 1.200 -1 (1.44)
W4 m2 0.600 1.800 -1 (1.08)
Bedroom 2 & 3 m2 11.732 3.653 2 85.71
D1 m2 0.900 2.100 -2 (3.78)
W1 m2 1.200 1.600 -2 (3.84)
Kitchen m2 11.732 3.653 1 42.86
D1 m2 0.900 2.100 -1 (1.89)
W1 m2 1.200 1.600 -2 (3.84)
Opening m2 1.163 3.253 -1 (3.78)
Living & Dining m2 18.876 3.653 1 68.95
Upper Beam (Dining Area) m2 2.019 0.700 1 1.41
Upper Beam (Opening) m2 1.220 0.700 1 0.85
D1 m2 0.900 2.100 -3 (5.67)
D2 m2 0.750 2.100 -1 (1.58)
S1 m2 1.800 2.100 -1 (3.78)
Opening m2 1.163 3.253 -1 (3.78)
Upper Beam m2 0.125 0.450 -2 (0.11) 257
2 lapisan 'Jotun Emulsion Shield' basic denga m2 same as plastering 247
300mm x 600mm heavy duty non-slipped homogenous tile
Bath 1 m2 8.684 0.900 1 7.82
D2 m2 0.750 0.900 -3 (2.03)
Bath 2 m2 6.856 0.900 1 6.17
D2 m2 0.750 0.900 -3 (2.03) 10

Lantai Dalam
600mm x 600mm homogenous tile (1st Grade)
Master Bedroom, Bedroom 2 & 3 m2 2.933 2.933 3 25.81
Living m2 2.898 2.991 1 8.67
Dining (infront bath 2) m2 1.467 2.019 1 2.96
Dining (near living) m2 2.991 2.077 1 6.21 44

300mm x 600mm heavy duty non-slipped homogenous tile


Kitchen m2 2.933 2.933 1 8.60
Opening m2 1.220 0.115 1 0.14
Bath 1 m2 2.933 1.409 1 4.13
Bath 2 m2 1.409 2.019 1 2.84 16

Skirting
Master Bedroom, Bedroom 2 & 3 m 2.933 4 3 35.20
D1 m 0.900 -1 3 (2.70)
D2 m 0.750 -1 1 (0.75)
Dining & Living m 18.818 1 18.82
D1 m 0.900 -3 1 (2.70)
D2 m 0.750 -1 1 (0.75)
Opening m 1.065 -1 (1.07)
Kitchecn m 2.933 4 1 11.73
D1 m 0.900 -1 1 (0.90)
Opening m 1.065 -1 (1.07)
Opening m 0.115 2 0.23 56

Disediakan oleh: Diluluskan oleh:


Page 19 of 22
................................ ................................
RE RESOURCES ENTERPRISE
Reg. No. JR0062494-H
NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
EMAIL: reresourcesent@gmail.com
PHONE NO: 011-10735990

Project :
Area :
Date : TAKING OFF
ITEM DESCRIPTION UNIT LENGHT WIDTH HIGH DEPTH NOS BIL QTY kg/m TOTAL QTY

KEMASAN DALAMAN (Samb)

Siling Dalam
Siling dalam
25mm Plastering celiling (1:6 simen mortar)
Master Bedroom m2 2.933 2.933 1 8.60
Living m2 2.933 2.991 1 8.77
Dining (near living) m2 2.928 2.077 1 6.08
Dining (infront bath 2) m2 1.404 2.019 1 2.83 26
cornice
Master Bedroom m 2.933 4 1 11.73
Living & Dining (near living) m 16.000 1 16.00
Dining (infront bath 2) m 3.428 2 1 6.86 35
Gypsum board ceiling
Bedroom 2 & 3, Kitchen m2 2.933 2.933 3 25.81
Bath 1 m2 2.933 1.409 1 4.13
Bath 2 m2 1.125 2.019 1 2.27 32

KERJA-KERJA LUAR BANGUNAN

Longkang
front view m 12.720 1 12.72
left side view m 16.118 1 16.12
back view m 7.795 1 7.80
right side view m 9.965 1 9.97 47
kaki lima
A m2 8.733 0.586 1 5.12
B m2 3.223 0.586 1 1.89
C m2 1.524 0.586 1 0.89
D m2 1.582 0.351 1 0.56
E&F m2 3.106 0.586 2 3.64
G m2 0.938 0.586 1 0.55
H m2 7.502 0.586 1 4.40
Tangga belakang m2 1.220 0.235 -1 (0.29)
I m2 8.499 0.586 1 4.98
J m2 3.048 0.586 1 1.79
K m2 0.938 0.586 1 0.55
facade E m2 0.235 0.235 -1 (0.06) 24

Disediakan oleh: Diluluskan oleh:


Page 20 of 22
................................ ................................
RE HOMEWORKS SDN BHD RE HOMEWORKS SDN BHD
Reg. No. 202001037817 (1394138-P) Reg. No. 202001037817 (1394138-P)
Head Office: NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR Head Office: NO. 26, JALAN SINAR BAKRI 3, PUSAT PERNIAGAAN SINAR BAKRI, BUKIT BAKRI, 84200 MUAR JOHOR
Site Office: LOT 1680A, PARIT KADIR DARAT, BUKIT PASIR, 84300 MUAR, JOHOR Site Office: LOT 1680A, PARIT KADIR DARAT, BUKIT PASIR, 84300 MUAR, JOHOR
EMAIL: reresourcesent@gmail.com EMAIL: reresourcesent@gmail.com
PHONE NO: 013-7691228 / 011-10735990 (Admin Office) Taking Off Sheet PHONE NO: 013-7691228 / 011-10735990 (Admin Office) Taking Off Sheet

DESCRIPTION: PAGE: DESCRIPTION: PAGE: