Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

DAINTREE RESIDENCE - TOP Application Checklist ANNEX A

PARTIAL TOP RPOJECT TITLE


A1839-00012-2017-BP01
PROPOSED TEMPORARY SHOW UNITS AT #01-27, #01-28, #01-29, #01-30 AND #01-31 FOR APPROVED CONDOMINIUM HOUSING
DEVELOPMENT COMPRISING ERECTION OF 12 BLOCKS OF 5-STOREY APARTMENTS (TOTAL: 327 UNITS) WITH BASEMENT
CARPARKS, COMMUNCAL FACILITIES AND 3M WIDE INTEGRATED DRAINAGE RESERVE (URA SALES PARCEL) MK05 ON LOT 09149L
AT TOH TUCK ROAD (BUKIT TIMAH PLANNING AREA)

FULL TOP RPOJECT TITLE


Updated: 2020/06/24
A1839-00012-2017-BP01
PROPOSED CONDOMINIUM HOUSING DEVELOPMENT COMPRISING THE ERECTION OF 12 BLOCKS OF 5 STOREY
APARTMENTS (TOTAL 327 UNITS) WITH BASEMENT CARPARKS, COMMUNAL FACILITIES AND 3M WIDE INTEGRATED DRAINAGE
RESERVE (URA SALES PARCEL) ON LOT (S) 9149L MK05 AT TOH TUCK ROAD

All Consultants & Contractor To Check All The Application, Cert & Clearance To Be Same Project Title As In BCA BP01 Approval
Letter

Target Partial TOP clearance date : dd/mm/yy,


Target Partial TOP application date: dd/mm/yy
Actual Partial TOP 1st inspection date : dd/mm/yy

Items Required for Partial TOP (Extraction from Phase Completion Schedule)
Requirements to Temporary Occupation Permit("TOP") Ready Inspection. A minimum of twelve (12) weeks before respective completion of each phase, the following
arising out of and/or in connection with Phase Completion shall be achieved/submitted by the contractor (and/or his sub-contractors) to enable the Employer to make
Temporary Occupation Permit ("TOP") application to the Building Control Authority ("BCA") for approval:
1. All Registered Inspector's (RI) (Architectural and M&E) inspections completed and RI certificates obtained and submitted to the Employer.

2. All clearances and/or certificates of any required government technical department and authorities obtained (e.g. CBPU clearance, NEA/Pollution Control's
clearance, Fire Certificates and the like) and submitted to the Employer.

3. All submissions of any as-built drawings and calculations required by any authorities and correspondence for clearances (if required) obtained and subm itted to
the authorities

4. All test certificates, Qualified Persons (QP) certificates, authorities' approval letters, label/marks and the like for material used and works installed obtained and
submitted to the Employer.

5. All required Letters of Undertaking submitted to the Employer.

Page 14 of 27
6. All required Certificate of Supervision by the Contractor's and his Sub-Contractors' Qualified Persons (QP) for their construction and installation works submitted
to the Employer.

7. All M&E Installations to be inspected and completed to enable Employer's QP to issue the required Certificate of Supervision.

8. All escape staircases and access routes to be cleaned and clear of any debris and obstacles.

9. All public utilities connected and turned on, including power, water, sewer and telecommunication, SCV. All public utility accounts opened on behalf of the
Employer.

10. All required licenses to be obtained including payment of any fees.

11. Any other works and components in the phase arising out and or in connection with the provision of the contract documents in a respect regardless of the cost.

12. All other compliances, works and materials arising out of and or in connection with any law, regulation or by law including but without limitation to any directions or
stipulation of the Authority relating to the affecting phase completion of the works.

A) Declaration Form BCA-CSC-TOPCSCDQP or BPD_CSC07: ADDP

B) Certificate of Supervision of Building Works (Form BCA-CSC-CSPBW): ADDP

C) Form BCA-CSC-CSPLP or BPD_CSC03 (Certificate of Supervision of Lightning


Protection System): CPG / QJ

D) As-built lightning protection plan and commissioning test report: CPG / QJ

E) Submit Builder's Certificate of Completion of Building Works (form BCA-BE-BRCTBW


or BC-BC): QJ

D) Regularisation of all the ST submission & As-built ST Submission: TWA / QJ

E) Submit As-Built Buildability Score and Constructability Score: ADDP/ TWA / QJ

F) Qualified Person to confirm that the materials used on the exterior of buildings meet the

: QJ / ADDP

Page 15 of 27
G) Submit a copy of Cable Vision Certificates of Cable-readiness, and Certificate of Fibre Readiness. CPG / QJ

H) The AMSL of the as-built height of the building comply with the requirement laid down in the planning conditions by URA & DSTA; Declaration Letter. : QJ

I) A TOP/ CSC clearances issued by Fire Safety & Shelter Department (FSSD)
- RI Inspection: QJ / CPG / ADDP

J) TOP/ CSC clearances issued by NEA


- Confirmation letter that the proposed temporary show units are for viewing purposes only, no sanitary works will be involved. There will be no live discharge of soil
waste from the sanitary toilet facilities from the proposed temporary show units: SETIA

K) BP clearances issued by Land Transport Authority (LTA-Road & Transportation): TWA

L) BP clearances issued by Land Transport Authority (LTA-Vehicle Parking): ADDP

M) BP clearances for this TOP application issued by National Parks Board (NPB): ADDP

N) BP clearances issued by NEA: ADDP

O) Green Mark
- As-built GM score (forms BPD_GM02 +BPD_GM02_Appendix 1) generated via GM e-Filing System
- QP(BP), PE(mech engineer) and PE(electrical engineer), all parties to e-sign and submit via corenet/TOP portal before making an application for TOP or CSC (if TOP
is not applied for). : ADDP / CPG

P) Escape Plan to be mounted on wall of show units (To reflect clearly the show units, emergency escape route, emergency gathering area, etc.: QJ

Some of the criterias for grant of Partial TOP by BCA for showflat units at construction block include followings:-

1) No more cranes at the block of in-situ show units and any adjacent block/s that are within the collapse zone of show unit block ;

2) The superstructure at roof must be completed with no more critical rooftop and external facade structural, m&e and finishing work, such as window installation,
external plastering, water tank etc.. at the block of show units;

3) Safe access from external to showflat units for showflat visitors and temporary parking lots ;

Page 16 of 27

You might also like