Professional Documents
Culture Documents
Indo Rock 2013 - Weak Dyke in Rock Storage Cavern - Final Paper
Indo Rock 2013 - Weak Dyke in Rock Storage Cavern - Final Paper
ABSTRACT: This Paper deals with a mafic fractured dyke of about 30m thick and more than 500m length
encountered during construction of a large underground storage cavern in India. The geological and
geotechnical problems associated with this dyke and the challenges encountered during the investigation and
construction stage are presented in this paper. The fractured dyke is in general perpendicular to the cavern
alignment but it offsets suddenly about 50m from the original orientation and encountered in one of the caverns
in parallel orientation for about 50m and dips steeply towards the wall of the cavern and possesses stability
problems in the cavern wall. The probe hole drilled inside the cavern wall shows that these dykes are extended
up to a distance of 10 m behind the cavern wall. Borehole televiewer (BHTV) was also conducted in the water
curtain boreholes drilled above the cavern to study the geometry of the shifted dyke in the intermediate cavern
pillar. Unwedge and FEM studies were conducted to ascertain stability of cavern from wedge sliding as well as
wall stability. Special supports were recommended based on the analyses and investigations. Now the cavern is
fully excavated in this zone and the extensometer readings show the cavern condition is stable.
1 INTRODUCTION
The rock cavern project under study is a strategic crude oil storage project under construction in west coast
of India near Mangalore. The project consists of four U shaped caverns of 30m height, 20m width and about
700m length (See Fig.1). Each U shaped cavern consists of inlet and outlet shaft at the open ends for crude oil
movement through pipelines. The cavern is seated about 60m below the ground and is excavated through two
access tunnels; one for each 2 U shaped caverns. The caverns are placed about 100m inter-distance. Each leg of
U shaped cavern is having about 30m width of rock pillar and above each U shaped cavern, water curtain
system is developed to contain oil and gas using Hydro-geological confinement.
Water curtain system consists of a water curtain tunnel parallel to and 20 m above the cavern and a series of
water curtain boreholes drilled perpendicular to the tunnel while extending cover of about 20m beyond both
sides of U shaped caverns. These boreholes are pressurized with water during water curtain tunnel construction
to prevent lowering of water table during cavern excavation below. As a matter of fact, the water curtain
systems should work properly atleast 50 m ahead of cavern excavation to prevent de-saturation in rocks near
cavern which will be difficult to re-saturate once de-saturated leaving air traps and air bubbles risky for stored
oil and gas to leak in future.
Since the water curtain tunnel is excavated before cavern excavation, this acts as a pilot tunnel exposing the
actual geology to be encountered during cavern excavation. As the caverns are 30m height, they are excavated
in four stages; top gallery and 3 benches each of about 7-8m in height.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
Fig.3 Geological model showing 30m thick dyke as geological hotspots of the project
During cavern heading excavation, sudden change in the position of the dyke TD5 was observed in one of
the storage caverns (See fig.4). The dyke offsets about 50m from the original orientation and encountered in the
shifted position in one of the caverns. But their orientation was same. The shifting could have taken place in the
rock pillar between the two adjacent storage caverns. To confirm this, 3 water curtain boreholes drilled in this
rock pillar just above the observed shifted dyke was examined with BHTV. It revealed that the shifting in dyke
does occur in the rock pillar and the orientation of dykes, which were split in to numerous dyke swarms, were
found to be both perpendicular as well as parallel to the cavern alignment. The parallel orientation of the dyke
swarms along with its steep dip towards north wall in one of the caverns was found to be critical. The fracture
zone FR4 found along either direction of the TD5 dyke seems unchanged in orientation and got overlapped with
parallel alignment of dyke in this zone. This zone in north wall of cavern was physically found to be fractured
and crushed with silty clay infilling and was classified as rock class V where as in south wall of the cavern, no
shifting in dyke was found and the dyke remains perpendicular to the cavern wall and is classified as class IV.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
A close study on the northwall geology and BHTV studies suggest that the offset of the dyke is ductile and
at the offset, it locally splits into number of small dykes (dyke swarms) and some of them runs parallel to the
cavern orientation for about 50m and some of them runs perpendicular to the cavern same as original dyke but
overlapped with similarly oriented fracture zone. Thus the overall geology in this area are quite complex (See
Fig.4). Also the shifting in dyke could have caused by dyke TD3 which is intersecting this TD5 dyke at this
same location. Another possibility could be that this dyke was emplaced on pre-existing fracture system and
during emplacement dyke found its own way along the weaker zone explaining the ductile mechanism observed.
Thus geologically the phenomenon is not still well understood whether it is brittle or ductile and which intrusive
dyke is younger one and the fracture zone associated (FR4) is syn-tectonic or post tectonic could be best left to
the structural geology experts.
To ascertain the extent of branched out dyke passing parallel to the cavern, 4 nos. of probe holes of about 15
m length were driven. The probe hole result shows that these dykes are extended upto a distance of 10 m behind
the dyke. However, the persistence, thickness and orientation of each branched dyke rock were still unknown. In
addition, these branched dyke rocks were highly irregular and discontinuous.
At crown, a wedge formed with maximum apex height 4.0 m (Refer table 2), suggests that bolt length
should be at least 1 m more than the wedge apex height. Therefore minimum length of the bolt should be 5.0 m.
Summary of the recommended rock support for the caverns are given in Table 3.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
Table 2 Wedge analysis with dyke orientation obtained during initial investigations
Joint set Location of wedge Apex Unsupported factor of FOS with
Combination Height safety Support
Table 4 Wedge analysis with Shifted dyke orientation in northern wall of cavern
Joint set Combination Location of Apex Unsupported factor FOS with
wedge Height of safety Support
Roof 1 0 Stable
J2-J3-J4
Wall 4.5 0.5 2.7
As the rock mass around this zone is highly fractured, closely jointed and of complex geology, numerical
analysis using Phase2 software was also carried out to access the north wall stability with assumed rock support.
The analysis models were developed from respective surrounding rock mass and geometry of mafic dyke of
about 10m thick placed on the north wall of cavern with the properties of dyke varying from poor to very poor.
Results of the FEM analysis shows that Stress level observed around the cavern are moderate and stable.
Yielded zone varied between 2-3m and is restricted close to central part of north wall of cavern. Limited
yielding of rock bolts was noted. Maximum displacement observed during excavation of bench 2 was estimated
between 4-8 mm. Overall displacement is relatively small and acceptable. Strength factor observed between the
pillars is around 2 and the shear stress is very close to zero. This state ensures the stability of pillar between two
caverns.
The results of the analyses both from unwedge & FEM indicates that there is no cause for concern for
wedge sliding as well as wall stability. However, due to uncertainties based on the fact that the branched dykes
were highly irregular and their persistence, orientation, etc were still unknown, one row of 12 m rock bolt (25
φ) were recommended at both bench 2 and 3 level, which will cross over the dyke zone of about 10m. In
addition shotcrete thickness of 100mm was proposed on north wall. The revised recommended rock supports at
weak dyke zone are shown in Table 5.
To check the integrity of applied recommended systematic rock bolt, pull out test with a load 1.5 times the
design load i.e. 20 MT was performed on 5 rock bolts of 5 m in length on north side of wall. The results of the
pull out test shows a maximum deformation of 4.3 mm at ultimate load and none of the rock bolts were failed at
this load.
INDOROCK 2013: Fourth Indian Rock Conference 29 – 31 May 2013
5 CONCLUSIONS
During cavern heading excavation, a sudden change in the position of Mafic fractured dyke was observed. The
dyke offsets about 50m from the original orientation and encountered in one of the caverns in shifted position.
Shifting could have taken place in the rock pillar between the two adjacent storage caverns where the dyke runs
parallel to the cavern alignment. A Borehole image processing studies (BIPS) were conducted in three boreholes
drilled in the water curtain tunnel just above the observed shifted dyke to confirm this phenomena and also 4
nos. of probe holes of about 15 m length were driven to ascertained the extend of dyke. The probe hole result
shows that these dykes are extended upto a distance of 10 m behind the cavern wall. These branched dyke rocks
were highly irregular and discontinuous and it locally splits into number of small dykes (dyke swarms) and all
of them runs parallel to the cavern orientation for about 50m. As the rock mass around this zone is highly
fractured, closely jointed and of complex geology, wall stability of the cavern in this zone was re-ascertained
using both wedge and numerical analysis. Results of the analyses both from unwedge & FEM indicates that
there is no cause for concern for wedge sliding as well as wall stability. However, as the branched dykes were
highly irregular and their persistence, orientation, etc were still unknown, one row of 12 m rock bolt (25 φ)
were recommended on north wall at both bench 2 and 3 level. The displacement plot of extensometer both from
wall as well as from water curtain tunnel confirms stable conditions.
REFERENCES
1. Barton. N., Lien. R, Lunde, J., 1974, Engineering classification of rock masses for the design of tunnel
support, Rock Mechanics, Vol.6, n°4, pp 189-236.
2. Nanda A., Design and construction of storage caverns, Proceedings of Indian Geotechnical conference,
Dec.13-15, 2012, Delhi.