Professional Documents
Culture Documents
Vol II Tech Spec Htls Package 158
Vol II Tech Spec Htls Package 158
Vol II Tech Spec Htls Package 158
BIDDING DOCUMENTS
FOR
Combined package of following Replacement of existing ACSR conductors by HTLS conductor including
Supply of all Materials/Equipments and Erection (Including Civil Works) of all Materials/Equipments, Testing
and Commissioning and buy back of released materials on Total Turnkey basis.
A: Replacing the existing 66kV DC Coyote ACSR conductor by High Temperature
Low Sag conductor (HTLS) between 220/66/11kV Hebbal station and 66/11kV
ITI sub station for a distance of 14.334kms. in Bangalore East Taluk,
Bangalore Urban District on Total Turnkey Basis.
B: Replacement of the existing Lynx conductor by High Temperature Low Sag
(HTLS) conductor suitable for Coyote in the existing 66kV Peenya-
Brindavan SC line for a distance of 3.0kms. in Bangalore North Taluk,
Bangalore Urban District on Total Turnkey Basis.
537456407.doc Page 1
THIS CONTAINS THE FOLLOWING VOLUMES
537456407.doc Page 2
Karnataka Power Transmission Corporation Limited
BIDDING DOCUMENTS
FOR
Combined package of following Replacement of existing ACSR conductors by HTLS conductor including
Supply of all Materials/Equipments and Erection (Including Civil Works) of all Materials/Equipments, Testing
and Commissioning and buy back of released materials on Total Turnkey basis.
A: Replacing the existing 66kV DC Coyote ACSR conductor by High Temperature Low
Sag conductor (HTLS) between 220/66/11kV Hebbal station and 66/11kV ITI sub
station for a distance of 14.334kms. in Bangalore East Taluk, Bangalore Urban
District on Total Turnkey Basis.
B: Replacement of the existing Lynx conductor by High Temperature Low Sag (HTLS)
conductor suitable for Coyote in the existing 66kV Peenya-Brindavan SC line for
a distance of 3.0kms. in Bangalore North Taluk, Bangalore Urban District on
Total Turnkey Basis.
VOLUME- II
TECHNICAL SPECIFICATIONS
---------------------------------------------------------------------------------------------------
ISSUED BY:
The Chief Engineer, Electricity, Tel: 080-2274744, 2120905
Tendering & Procurement, Fax: 0091-080-2212456
Kaveri Bhavan
Bangalore:560 009
537456407.doc Page 3
SECTION – I
(VOLUME – II)
537456407.doc Page 4
VOLUME-II
SECTION-I
1.0 GENERAL
2.0 SCOPE
5.0 DRAWING
537456407.doc Page 5
VOLUME – II
SECTION–I
1.00 GENERAL:
537456407.doc Page 6
standard equipments provided, shall be inter-changeable with one
another.
Similarly, all services as may be necessary for the execution of the
Contract though they may not have been specifically detailed in the
Technical Specifications, unless specifically excluded, shall be
furnished by the Contractor.
1.2 Equipment Performance Guarantee:
The performance guarantee of the equipment under the scope of the
contract has been detailed in the Technical Specifications. These
guarantees shall supplement the general performance guarantee
provisions covered under General Conditions of Contract.
Liquidated damages for not meeting performance guarantees during
the performance and guarantee tests shall be assessed and
recovered from the Contractor as detailed in Special conditions of
Contract. Such liquidated damages shall be in addition to damages,
if any, payable under any other clause of Conditions of Contract,
Special Conditions of Contract.
1.3 Engineering Data:
The furnishing of engineering data by the Contractor shall be in
accordance with the schedule for each set of equipment and
materials as specified in the Technical Specifications. The review of
the data by the Engineer will cover only general conformance of the
data to the specifications and documents, interfaces with the
equipment and materials provided under the Specifications, external
connections and of the dimensions which might affect plant layout.
This review by the Engineer may not indicate a thorough review of all
dimensions, quantities and details of the equipment and materials,
any device or item indicated or the accuracy of the information
537456407.doc Page 7
submitted. This review and/or approval by the Engineer shall not be
considered, by the Contractor, as limiting any of its responsibilities
and liabilities for mistakes and deviations from the requirements,
specified under these Specifications and Documents.
All engineering data submitted by the Contractor after final process
including review and approval by the Engineer shall form part of the
Contract Documents and all the works performed shall be in strict
conformity with these specifications unless otherwise expressed in
writing by the Engineer.
1.4 Drawings:
All drawings submitted by the Contractor including those submitted
at the time of Bid shall be in sufficient detail to indicate the type,
size, arrangement, material description, Bill of Materials, weight of
each component, break down for packing and shipment, the external
connections, fixing arrangements required, the dimensions required
for installation and inter-connections with other equipment and
materials, clearances and spaces required for installation and inter-
connections between various portions of equipment and any other
information specifically requested in the Specifications.
Each drawing submitted by the Contractor shall be clearly marked
with the name of the Owner, the unit/scheme designation, the
specifications title, the specification number and the name of the
project/scheme. If standard catalogue pages are submitted, the
applicable items shall be indicated therein. All titles, noting,
markings and writings on the drawing shall be in English. All the
dimensions shall be in metric units.
The drawings submitted by the Contractor shall be reviewed by the
Engineer within four (4) weeks and shall be modified by the
537456407.doc Page 8
Contractor if any modifications and/or corrections are required by
the Engineer. The Contractor shall incorporate such modifications
and/or corrections and submit the final drawings for approval. Any
delay arising out of failure by the Contractor to rectify the drawings
in time shall not alter the contract schedule.
The drawings sent for approval to the Engineer shall be in
quadruplicate. One print of such drawings will be returned to the
Contractor, by the Engineer marked ‘Approved/ Approved with
corrections’ or resubmit with corrections as noted. The Contractor
shall thereupon furnish to the Owner such number of prints of
approved drawings as may be mutually agreed upon between the
Owner and the Contractor and one reproducible original of the drawings,
after incorporating all corrections. The Contractor shall supply soft copy of
all such drawings in 3½” Floppy diskettes / CD for easy reproduction
later.
1.5 Inspection, Testing And Inspection Certificate:
The Engineer, his duly authorized representative and/or an outside
inspection agency acting on behalf of the Owner shall have, at all
reasonable times, access to the Contractor’s or its Sub-vendor’s/Sub-
Contractors’ premises or works and shall have the power, at all reasonable
times to inspect and examine the equipment materials and workmanship
of the works during its manufacture or prior to despatch and if part of
equipment and materials is being manufactured or assembled at other
premises or works, the Contractor shall obtain for the Engineer and for his
duly authorised representative, permission to inspect as if the equipment
and materials were being manufactured or assembled on the Contractor’s
own premises or works.
1.6 Packaging And Transportation:
537456407.doc Page 9
All the equipment and materials shall be suitably protected coated,
covered or boxed and crated to prevent damage or deterioration during
transit, handling and storage at Sites till the time of erection, the
contractor shall be responsible for any loss or damage during
transportation, handling and storage due to improper packing.
While packing all the equipment and materials, the limitations from the
point of view of availability of Railway wagon sizes in India should be taken
account of.
The Contractor shall also give due consideration to the
encumbrances, infringements etc., likely to be encountered during
the transportation of the equipment to the site and shall, at his own
cost, make all arrangements as may be necessary to ensure smooth
and safe movement of the goods to the site.
The Contractor shall at its own cost carry out investigation to select
the route and the mode to be adopted for transportation of the
goods.
1.7 Protection:
All coated surfaces shall be protected against corrosion, erosion,
abrasion, impact, discolouration and any other damage. All exposed
threaded portions shall be suitably protected with either a metallic or
a non-metallic protecting device. The parts that are likely to suffer
damage by elements of nature especially those transshipped across
the seas, shall also be properly treated and protected in a suitable
manner.
2.00 SCOPE:
2.1 The general scope of the work involved is the total / partial turnkey
construction of 220kV, 110kV and 66kV lines which includes supply
of tower parts and other materials, erection, testing and satisfactory
commissioning of the lines as per Technical Specifications.
537456407.doc Page 10
2.2 The details of the lines with point of connection and termination, the
approximate length of the lines, the voltage class of the lines is
indicated in the Technical Specifications.
The contractor shall supply the towers and extension pieces as per
Detailed Technical Specifications for transmission line tower –
Section-III (Volume-II).
2.3.3 Overhead Line Power Conductors:
537456407.doc Page 11
The static ground wire or earth wire conductor shall be got
manufactured and supplied as per the detailed technical
specification Section–V (Volume-II) titled “Detailed Technical
Specification for Ground wires” attached here to.
2.3.5 Power Line Conductor Insulators:
The line erection which includes soil investigation, soil testing for
tower foundations, stub assembly, stub setting, concreting of
foundations, back filling and curing, assembly of tower
537456407.doc Page 12
superstructure, pave out of conductors, hoisting of insulators,
stringing and tensioning of power and ground wire conductors, fixing
of conductor accessories, fixing of tower accessories etc testing and
commissioning of the lines and handing over of lines shall be as per
the detailed technical specification Section-X(A) titled “Stub setting
and casting of foundations” and Section–X(B) titled “Erection,
installation, testing and commissioning of lines” attached here to.
3.00 APPLICABLE STANDARDS:
5.00 VOID
537456407.doc Page 14
g) Configuration
i. Single Circuit Delta Right Right
angled angled
Triangle triangle
537456407.doc Page 15
The Weight spans for 220 kV/110kV/66kV DC towers considered in
the design which is being supplied to the successful contractor is as
follows:
‘DB’, ’DC’, 480 -480 288 -288 412 -412 247 -247
‘DD’
537456407.doc Page 16
SECTION – II
(VOLUME – II)
TECHNICAL SPECIFICATIONS
FOR
537456407.doc Page 17
VOLUME-II
SECTION-II
1.0 GENERAL
3.0 ROUTING
4.0 SURVEYS
5.0 PROFILE
537456407.doc Page 18
VOLUME – II
SECTION – II
1.00 General:
3.00 Routing:
KPTCL has got done the detailed surveys of the lines. The tower profiles
and tower spotting data will be furnished to the successful bidder along
with the topo extract of the area through which the lines have to pass
through. This is to enable the contractor to carryout a walk over
survey / route inspection / check survey of the detailed surveys got
done by KPTCL. In case the contractor finds upon verification that the
detailed surveys got done by KPTCL is not feasible for execution, then
the contractor shall conduct detailed survey afresh for the stretches
where the alignment is not feasible and the size shall be approved by the
Engineer. The detailed surveys to be so got done by the contractor shall
537456407.doc Page 19
follow the guidelines as enumerated here below in the succeeding
paragraphs.
The scope of check survey also includes preparation of route alignment
map as per check survey, tower profiles and tower schedules and
obtaining approval of the concerned engineer.
The route shall be aligned preferably close to an all weather road. This
is to ensure accessibility to the line both during construction and later
during line patrolling and maintenance. The routing shall also confirm
to the following clauses from 3.1 to 3.11.
3.1 Railway Crossings:
River crossing towers shall be located in the straight reaches of the river,
since the flow in these reaches is uniform without much stress on the
flood banks. The clearances as stipulated in the latest I.E. Rules for
both navigable and non-navigable rivers shall be strictly followed. The
same is also indicated in transmission manual, Chapter-4 of CBIP.
3.3 Telecommunications:
537456407.doc Page 20
Parallelism:
The angle of crossing above the telecom lines shall as far as possible be
900 and in no case less than 600. No guarding is required to be
interposed between power and telecom lines.
A minimum vertical clearance of 3.05mt shall be maintained between
the lowest power conductor and the telecommunication circuit in
respect of 220 kV, respectively (as per CBIP, Chapter-4).
3.4 Plantations:
It is necessary to avoid coconut, areca nut, rubber and other cash crop
plantations. If it is not possible to avoid such plantations, then the line
shall cut across the corner or the thinnest belt of such plantations.
3.5 Marshes and Back Waters:
537456407.doc Page 21
It is desirable to cross National and State Highways at 90 0 and in any
case not less than 600. Towers to be located at the crossing span should
be located such that one tower is close to the Road nearer by about
30 M to 40 M. Besides the crossing span shall be reduced to 80% of the
ruling span.
The vertical clearance shall be as stipulated in I.E. Rules but further
enhanced by another 0.3 M so as to ensure better safety and clearances
between tractors, trailers, trucks and lorries loaded with huge packages.
Thus a clearance of 7.8 M shall be maintained between the lowest
conductor and the top surface of the Road. The towers on either side of
National and State Highways shall be with double suspension / tension
strings and shall be tension type towers. The maximum span shall be
250 m.
3.8 Aerodromes:
537456407.doc Page 22
The routing of the line in the vicinity of defence (I.A.F. installations) shall
follow the following stipulations.
1. Within 805 M of Radar and
No structure of any height
Wireless Receiving Stations.
2. Between 805 M and 3200 M Structure of not more than
24.4 M height
3. Between 1375 metres and An angle of less than 10 9
3200 mtrs from the perimeter min from Aerodrome outer
of the air field perimeter to the top of the
structure.
4. Within flying funnel area of an - Do -
air field up to 1373 M from the
nearest end of the runway.
537456407.doc Page 23
The line shall preferably be routed away from buildings, huts by at least
15 M. But where this is inevitable the following vertical and horizontal
clearances shall be maintained.
220 kV 110 kV 66 kV
1 Vertical 5.49 M 4.58 M 3.97 M
2 Horizontal 3.66 M 2.75 M 2.14 M
3.11 Miscellaneous:
4.1 Reconnaissance:
The detailed survey involves final theodolite alignment along with chain
survey and levelling.
The final alignment shall be fixed very precisely from angle point to
angle point. Pegs or concrete blocks/pillars shall be driven in to the
ground with only 5 cm projecting at each and every angle point. They
537456407.doc Page 24
may be painted yellow with identification nos. if necessary, for easy
location. These pegs/blocks shall be prevented from damage or
disturbance by stone Cairns. If the stretch between two angle points is
very long then intermediate pegs at an interval of say 1 KM or 0.5 KM
shall be driven into the ground.
The chain survey and levelling shall be conducted either simultaneous
with final theodolite alignment or after completion of final theodolite
alignment. In either case the chain survey and levelling shall follow the
final theodolite alignment. The following details shall be incorporated in
the chain survey and levelling field book.
1) Centre line of the proposed line.
4) Roads.
537456407.doc Page 25
14) Railway track.
The level shall be taken at frequent intervals, to show the actual contour
of the centerline. Every terrain and change in levels must be shown. If
the ground is fairly level then levels must be taken at 30-M intervals.
Wherever there are slopes cross sectional levels must be taken at right
angles at suitable intervals of 5.0 M and 10.0 M to ensure adequate
clearance of the conductor on the higher slope side.
In hilly regions with peaks and valleys, survey shall be adopted by using
theodolite and levelling staff whereby both the distances and levels at
various points are measured.
5.0 Profile:
537456407.doc Page 26
Number of wires whether service, phone, carrier, distance of adjoining
pole and angle – numbers on pole if any. The angle of crossing should
not be less than 600 otherwise the telephone line has to be deviated.
Height of top most wires from the ground has to be shown in the
levelling sheets to check adequacy of clearance.
MWL position of bank and height. The bottom of the foundation of the
tower has to be above hydraulic gradient.
537456407.doc Page 27
5.7 Buildings, Huts, Etc.
h) Clearances expected for the line over the tracks for the line.
6.0 Tower Spotting:
KPTCL will furnish the necessary sag – template and tower spotting
charts to the successful bidder on a blue print. The Contractor shall
prepare the same on an acrylic/plastic sheet and submit one copy to the
Engineer for verification of profiles.
The tower location shall be marked on the profile using the owner
supplied sag – template and tower spotting chart. The following points
shall be taken into consideration while spotting the tower locations.
6.3 Span:
The number of consecutive spans between the section points shall not
exceed 15 spans or 5 KM in plain country and 10 spans or 3 KM in hilly
terrain Section-A point shall be taken to comprise of a tension point
with ‘B’ type or ‘C’ type tower.
537456407.doc Page 29
6.4 Extensions:
The profile sheets duly spotted, along with tower schedules indicating
type of towers, type of foundations, wind span, angle of deviation, river
or road crossing and incorporating other details as in Clause 5.0 shall
be got approved from the owner before execution.
537456407.doc Page 30
it is necessary to have the pit centres peg marked. The contractor shall
prepare the route alignment maps, tower schedules and tower profiles
and submit the same to the owner for approval.
*****
537456407.doc Page 31
SECTION – IIIA
(VOLUME – II)
TECHNICAL SPECIFICATIONS
FOR
537456407.doc Page 32
VOLUME-II
SECTION-IIIA
1.0 SCOPE
2.0 STANDARDS
3.0 STATUTORY REQUIREMENTS
4.0 MATERIALS
5.0 TOWER DESIGNS
6.0 TOWER TYPES AND FABRICATION / ERECTION MARK
7.0 FABRICATION
8.0 DRILLING AND PUNCHING
9.0 GALVANIZING
10.0 FASTERNERS: BOLTS, NUTS AND WASHERS
11.0 TOWER ACCESSORIES
12.0 PACKING
13.0 TOWER FOUNDATIONS
537456407.doc Page 33
VOLUME – II
SECTION–IIIA
1.00 SCOPE:
2.00 STANDARDS:
Notwithstanding anything contained in the succeeding clauses the
fabrication, galvanising and supply of towers and tower accessories shall
537456407.doc Page 34
conform to the following Bureau of Indian Standard Specifications (BIS
or IS) with their latest amendments thereof:
IS 209
Code of practice for use of structural steel in
IS 800
Building construction
Use of structural steel in overhead transmission line
IS 802 (Part-1/Sec-1) – 1995
towers
IS 802 (Part-2) – 1977 Fabrication, Galvanising, Inspection and Testing
Dimensions for rolled steels, beams, columns,
IS 808 – 1989
channel and angle sections
IS 1239 – 1968–Part-I Mild Steel Tubes
Hexagonal head bolts, screws and nuts of product
IS 1363 (Part – 3) – 1992
grade C.
Mechanical properties and test methods for nuts
IS 1367 (Part – 6) – 1980
with specified loads
IS 1367 (Part – 13) – 1985 Hot dip galvanised coatings on threaded fasteners
IS 1573 – 1986 Electroplated coatings of Zinc on iron and steel
IS 1730 – 1989 Dimensions for steel plates, sheets strips and flats
IS 2062 – 1992 Steel for general structural purposes
IS 2551 – 1982 Danger Notice Plates
Methods of testing of uniformity of Zinc coating on
IS 2633 – 1972
Zinc coated articles
Single coil rectangular section spring washers for
IS 3063 – 1972
bolts, nuts and screws
IS 3757 – 1985 High strength structural bolts
Code of practice for high strength bolts in steel
IS 4000 – 1992
structures
Hot dip zinc coatings on structural steel and other
IS 4759 – 1984
allied products
Code of practice for design installation and
IS 5613 (Part-2/Sec-I)–1985 maintenance of overhead lines (Part-2 – Lines above
11 kV and up to and including 220 kV)
IS 5624 – 1970 Foundation bolts
IS 6610 – 1972 Heavy washers for steel structures
IS 6623 – 1985 High strength structural nuts (first revision)
IS 6639 – 1972 Hexagonal bolts for steel structures
Hardened and tempered washers for high strength
IS 6649 – 1983
structural bolts and nuts (first revision)
Structural steel – Micro-alloyed (Medium and high
IS 8500 – 1992
strength qualities) (First revision)
IS 10238 – 1982 Step bolts for steel structures
IS 12427 – 1988 Transmission line tower bolts
537456407.doc Page 35
3.0 STATUTORY REQUIREMENTS:
537456407.doc Page 36
Design of Normal Towers and +3M & +6M Body extensions along with
FOUNDATIONS are not in the scope of this specification. However,
KPTCL has standardized 220kvD/C, 110KvD/C and 66Kv D/C towers
of M/s. Kalpataru make for all the ongoing works of EHV transmission
lines in the state. The Structural drawings along with the BOM and also
the foundation drawings of the towers will be furnished to the successful
bidder and he shall make the proto type assembly of each type tower
and offer the same for proto inspection by the purchaser. The mass
fabrication shall be taken only after the approval of proto assembly.
However, in case, other types of towers or extension pieces (+9M or
+12M or +15M Etc.,) other than the ones furnished , the successful
bidders shall prepare such design/drawings as per IS 802-1977 and
submit the same for approval. The loading trees of the normal tower, if
required, will be furnished to the bidder for the above purpose.
537456407.doc Page 37
130x130x10
110x110x10
110x110x10
100x100x7 110x100x8
100x100x7
100x100x6 75x75x5 150x150x12
110x110x8
90x90x6 70x70x5 130x130x10
100x100x10
80x80x6 80x80x6 110x110x8
Sizes of 70x70x5
65x65x5 100x100x6 90x90x8
90x90x6
Steel 70x70x5 65x65x5 90x90x6
80x80x6
5 Section 50x50x4 65x65x4 75x75x5
75x75x5
used in 55x55x5 60x60x4 70x70x5
65x65x5
mm 55x55x4 75x75x6 65x65x5
60x60x4
45x45x4 55x55x4 55x55x4
55x55x4
45x30x4 90x90x6 50x50x4
45x45x4
60x60x4 50x50x4 45x45x4
50x50x4
65x65x4 75x75x6
45x30x4
45x45x4
45x30x4
537456407.doc Page 38
II A : WEIGHT OF 110 kV DC TOWERS & BODY EXTENSIONS IN KG
537456407.doc Page 39
II B : WEIGHT OF 110 kV MC TOWERS & BODY EXTENSIONS IN KG
110 kV MC 110 kV MC
110 kV MC ‘MA’
Sl ‘MC’ ‘MD’
N Super Bolt & Super Bolt & Super Bolt &
Structure Nuts Structure Nuts Structure Nuts
1 Normal
6900.81 312.186 12402.32 422.259 17279.96 511.553
Tower
2 +3M
863.56 32.509 1543.28 44.990 2012.79 49.100
Extn.
3 +6M
1737.28 67.698 2900.80 96.064 3749.51 105.390
Extn
4 +9M
1761.04 66.648 3008.24 96.106 3888.25 105.256
Extn
5 Stub 362.12 4.768 817.44 7.536 1039.36 10.560
45x45x4
45x45x4
45x45x5
45x45x5
50x50x4
50x50x4
50x50x5
50x50x5
55x55x4
45x45x4 55x55x5
55x55x5
45x45x5 60x60x5
60x60x5
50x50x5 65x65x5
65x65x5
50x50x4 65x65x6
65x65x6
55x55x5 70x70x5
75x75x6
Sizes of 60x60x5 75x75x5
80x80x6
65x65x6 75x75x6
Steel 90x90x6
75x75x6 80x80x6
5 Section 90x90x7
80x80x6 90x90x6
used in 90x90x8
90x90x8 90x90x7
mm 100x100x7
100x100x7 90x90x8
110x110x10
110x110x8 100x100x7
130x130x8
110x110x10 110x110x10
130x130x10
130x130x10 130x130x10
130x130x12
130x130x12 130x130x12
150x150x12
150x150x12
150x150x16
150x150x16
150x150x18
200x200x16
200x200x16
200x200x20
537456407.doc Page 40
III A WEIGHT OF 66 kV DC TOWERS & BODY EXTENSIONS
66 kV DC 66 kV DC 66 kV DC 66 kV DC
‘DA’ ‘DB’ ‘DC’ ‘DD’
Sl.Sl. No. Super Bolt & Super Bolt & Super Bolt & Super Bolt &
Structure Nuts Structure Nut Structur Nuts Structur Nuts
e.
Normal
1 1225.00 55.00 1540.00 52.00 1757.00 62.00 2288.00 82.00
Tower
+3M
2 285.00 10.00
9 384.00 10.00 394.00 11.00 543.00 15.00
Extn.
+6M
3 604.00 15.00 77100 16.00 852.00 18.00 1212.00 33.00
Extn
S4 Stub 67.00 1.00 105.00 1.00 105.00 1.00 153.00 1.00
110x110x8
100x100x6
80x80x6
90x90x6
90x90x6
75x75x5
80x80x6
60x60x4
75x75x5 75x75x6 100x100x7
65x65x5
70x70x5 65x65x4 60x60x4
S Sizes of 40x40x4
55x55x5 65x65x5 90x90x6
50x50x5
Steel 50x50x5 60x60x4 55x55x4
45x45x5
5 Section 50x50x4 55x55x5 50x50x4
100x100x8
used in 55x55x4 55x55x4 75x75x5
100x100x6
mm 40x40x4 50x50x5 60x60x5
110x60x4
45x45x4 45x45x4 45x45x4
55x55x4
45x30x4 45x30x4 45x30x4
45x30x4
40x40x4
50x50x4
50x50x4
130x130x10
75x75x6
90x90x6
75x75x5
537456407.doc Page 41
III B : WEIGHT OF 66 kV MC TOWERS & BODY EXTENSIONS IN KG
537456407.doc Page 42
IV FOUNDATION VOLUMES FOR 66KV D/C TOWERS
(Common for Normal, +3M, & +6M Body Extension Towers)
Type of Soil/ Tower Concrete Mix. Earth Exvn. Steel Re inf
Foundation Type in CMT/Twr in CMT/Twr in Kg/Twr.
1:2:4 1:3:6
Normal DA 1.54 - 14.2 -
DRY DB 2.08 - 20.6 -
DC 2.64 - 27.65 -
DD 4.03 - 41.07 -
Normal DA 3.5 - 23 -
DB 4.72 0.59 38.79 133
WET
DC 5.82 0.72 52.27 166
DD 8.27 1.11 84.27 219
Partially DA 4.51 0.62 36.99 118
DB 6.48 0.93 57.62 175
Sub-Merged
DC 7.83 1.11 75.84 215
DD 10.46 1.51 111.63 274
Fully DA 6.05 O.8 50.69 154
DB 8.37 1.28 76.89 222
Sub-Merged
DC 9.73 1.46 97.2 240
DD 13.04 1.99 142.83 351
Wet DA 8.84 1.36 74 206
DB 11.94 1.91 110 291
Black Cotton
DC 14.03 2.25 144 382
DD 18.9 3.04 212 593
Dry DA 1.9 - 4.99 41
DB 2.5 - 6.2 44
Fissured Rock
DC 2.6 - 7.91 51
DD 4.03 - 17.97 56
Submerged DA 5.91 - 18.98 44
DB 8.95 - 29.23 50
Fissured Rock
DC 10.87 - 42.45 56
DD 16.5 - 67.79 60
537456407.doc Page 43
V - A : FOUNDATION VOLUMES FOR 110KV D/C TOWERS
(Common for Normal, +3M, & +6M Body Extension Towers)
Type of Soil/ Tower Concrete Mix. Earth Exvn. Steel Re inf
Foundation Type in CMT/Twr in CMT/Twr in Kg/Twr.
1:2:4 1:3:6
Normal DA 2.35 - 23.06 -
DB 3.34 - 35.82 -
DRY
DC 4.42 - 43.77 -
DD 7.70 - 66.27 -
Normal DA 5.08 - 41.53 -
DB 8.54 - 66.64 -
WET
DC 9.41 1.22 92.06 260
DD 12.88 1.56 134.87 427
Partially DA 6.69 1.0 61.94 179
DB 8.38 1.2 90.75 248
Sub-Merged
DC 14.62 2.18 155.52 459
DD 15.97 2.42 171.4 615
Fully DA 8.78 1.39 82.98 241
DB 10.55 1.6 117.5 319
Sub-Merged
DC 14.62 2.18 155.5 450
DD 19.42 3.04 211.6 835
Wet DA 12.34 2.04 117.6 359
DB 15.6 2.52 177.8 558
Black Cotton
DC 20.31 3.2 221.86 738
DD 26.43 4.29 291.0 1276
Dry DA 2.01 - 7.59 46
DB 3.41 - 11.62 56
Fissured Rock
DC 4.5 - 20.08 57
DD 7.74 - 34.0 59
Submerged DA 9.96 - 34.9 51
DB 12.56 - 62.06 61
Fissured Rock
DC 17.95 - 72.21 61
DD 14.56 2.18 102.39 509
537456407.doc Page 44
WET MC 58.9 6.00 390 5100
MD 84.6 7.7 510 8384
Partially MA 28.4 2.9 205 1388
MC 66.7 6.8 450 5832
Sub-Merged
MD 86.0 8.7 575 8676
Fully MA 33.2 3.6 245 1544
MC 75.0 7.7 510 6224
Sub-Merged
MD 105 10 640 9080
Wet MA 33.8 3.6 245 1604
MC 76.0 7.7 510 6468
Black Cotton
MD 96.5 10.0 640 9788
Dry MA 24.2 2.5 130 1252
MC 58.0 6.0 320 4872
Fissured Rock
MD 76.0 7.7 425 8032
Submerged MA 33.8 3.6 185 1608
MC 76.0 7.7 425 6192
Fissured Rock
MD 96.5 10.0 545 9972
Hard Rock MA 13 0 13 396
MC 13.0 0 13 512
MD 14.0 0 14 774
537456407.doc Page 45
VI FOUNDATION VOLUMES FOR 220KV D/C TOWERS
(Common for Normal, +3M, & +6M Body Extension Towers)
Type of Soil/ Tower Concrete Mix. Earth Exvn. Steel Re inf
Foundation Type in CMT/Twr in CMT/Twr in Kg/Twr.
1:2:4 1:3:6
Normal DA 3.54 - 32.15 -
DRY DB 5.33 - 47.8 -
DC 6.82 - 56.66 -
DD 9.37 1.48 109.44 492
Normal DA 6.14 0.76 50.63 167
DB 10.73 1.27 95.43 294
WET
DC 11.0 1.51 111.63 301
DD 17.34 2.66 187.13 806
Partially DA 9.11 1.12 71.29 226
DB 13.6 1.8 130.68 350
Sub-Merged
DC 13.79 2.02 145.32 431
DD 21.07 3.43 236.5 1270
Fully DA 11.88 1.53 94.25 297
DB 16.8 2.38 168.7 498
Sub-Merged
DC 16.86 2.58 181.59 602
DD 26.67 4.25 289.3 1409
Wet DA 14.14 2.24 133.23 461
DB 22.45 3.39 234.4 704
Black Cotton
DC 23.22 3.72 255 985
DD 34.13 5.64 377.6 2134
Dry DA 6.26 - 24.98 47
DB 11.26 - 47.04 59
Fissured Rock
DC 14.19 - 56.84 60
DD 25.83 - 98.36 62
Submerged DA 11.16 1.8 68.92 310
DB 16.92 2.61 125.26 523
Fissured Rock
DC 18.59 2.96 144.56 734
DD 29.69 4.71 249.8 1706
537456407.doc Page 46
ion
Tower
Limit
A & DA 00 to 20 To be used as tangent tower
a) Angle tower with tension insulator string.
b) Tension tower for uplift forces resulting from
a uplift span up to 200 metres.
c) Power line crossing with a suitable body
B and 0 to
0
extension.
DB 150 d) To be used where unbalanced tension
results due to unequal ruling span of 200
metres and 400 metres on each side of
tower.
e) To be used as section tower.
a) Angle tower with tension insulator.
b) To be used where unbalanced tension
results due to unequal ruling span of 200
C and 150 to
metres and 400 metres on each side of the
DC 300
tower.
c) Tension tower for uplift forces due to uplift
span.
a) Complete dead end.
b) To be used for river crossing with longer
D and 300 to wind span.
DD 600 c) Angle tower with tension insulator.
d) Dead-end with 00 to 150 deviations both on
line and substation side (slack span).
NOTE: The above towers may also be used for longer span with smaller
angle of deviations.
iv) Erection Mark – These shall be done on each member with marking
dies of 16 mm size before galvanizing and shall be legible after
galvanizing. The notation shall be as follows:
A – BB – CC – DDD
A – Owner’s Code – Alphabet – K
BB– Contractor’s Mark – Number
CC – Tower Type Alphabet
DDD – Mark number – Numerical
537456407.doc Page 47
(v) The three phase conductors of the double circuit tower shall be
in vertical formation (I, I, I)
7.00 FABRICATION:
537456407.doc Page 48
7.6 No angle member shall have the two leg flanges brought together by
closing the angle.
7.7 The structure shall be such that all parts shall be accessible for
inspection and cleaning. Drain holes shall be provided at all points
where pockets of depressions are likely to hold water.
7.8 All similar parts shall be made strictly interchangeable. All steel
sections before any work is done on them, shall be carefully levelled,
straightened and made true to detailed drawings, by methods which will
not injure the materials so that when assembled the adjacent matching
surfaces are in close contact throughout. No rough edges shall be
permitted in the entire structure.
8.00 DRILLING AND PUNCHING:
8.1 Before any cutting work is started, all steel sections shall be carefully
straightened and trued by pressure and not by hammering. They shall
again be trued after being punched and drilled.
8.2 Holes for bolts shall be drilled or punched with a jig but drilled holes
shall be preferred. The following maximum tolerance of accuracy of
punched holes is permissible.
a) Holes must be perfectly circular and no tolerance in this respect is
permissible.
b) The maximum allowable difference in diameter of the holes on the
two sides of plates or angle is 0.8-mm i.e., the allowable taper in
punched holes should not exceed 0.8 mm on diameter.
8.3 All burrs left by drills or punch shall be removed completely. When the
tower members are in position the holes shall be truly opposite to each
other. Drilling or reaming to enlarge defective holes shall not be
permitted.
537456407.doc Page 49
8.4 The strain plate holes shall be chamfered properly and sharp edges
removed.
9.00 GALVANISING:
Fully galvanised towers and stubs galvanised from the top up to 300
mm below ground level shall be used for the lines. Galvanising of the
member of the towers shall conform to IS: 2629-1966 and IS: 4759-
1968. All galvanised members shall withstand tests as per IS: 2633-
1972. For fasteners, the galvanising shall be done after all fabrication
work is completed, except that the nuts may be tapped or re-run after
galvanising. Spring washers shall be electro-galvanised as per Grade 4
of IS: 1573-1070.
537456407.doc Page 50
nut and threaded enough to permit firm gripping of the members, but
not further. It shall be ensured that the threaded portion of each bolt
protrudes not less than 3 mm and not more than 8 mm when fully
tightened. All nuts shall fit hand tight to the bolt. Threads of bolts and
nuts shall have a neat fit and shall be such that they can be turned with
finger through out the length of the threads of bolts and they shall be
capable of developing full strength of the bolts.
10.3 Flat and tapered washers shall be provided wherever necessary.
Spring washers shall be provided for insertion under all nuts. These
washers shall be of steel electro-galvanised, positive lock type and as
specified in Bill of Materials.
10.4 The contractor shall furnish bolt schedules giving thickness of
members connected, the nut and the washer, the length of shank, the
threaded portion of bolts and sizes of holes and any other detail of this
nature.
10.5 The bolts shall be of class 5.6 and nuts shall be of property class
5. The ultimate shear stress and bearing stress on bolts shall be 3160
Kg/Sq.cm and ultimate bearing stress shall be as per IS.
10.6 To obviate bending stress in bolts or to reduce it to minimum, no
bolt shall connect aggregate thickness of more than three (3) times its
diameter.
10.7 Bolts at the joints shall be so staggered that nuts may be tightened
with spanners without fouling.
10.8 The minimum bolt spacing and rolled edge distance and sheared
edge distances of sections from the centres of bolt holes to be
maintained are given in Table below:
537456407.doc Page 51
Diameter Hole Minimum Minimum Minimum
of bolts diameter bolt rolled sheared edge
(mm) (mm) spacing(mm) distance distance
(mm) (mm)
16 17.5 40 20 23
12 13.5 32 16 20
Each tower shall be provided with step bolts on one of the main legs, of
not less than 16 mm diameter and 175 mm long, spaced not more than
450 mm apart and extending from about 3.5 metres above the ground
level to the top of the tower. Each step bolt shall be provided with two
nuts on one end to fasten the bolt securely to the tower and button head
at the other end to prevent the feet from slipping away. The step bolts
shall be capable of withstanding a vertical load not less than 1.5 KN and
shall be used as a ladder for climbing. The step bolts shall conform to
IS 10238 and shall have a hexagonal head.
11.2 Anti-climbing devices:
537456407.doc Page 52
a) For the attachment of suspension insulator strings a suitable
swinging hanger on the tower shall be provided so as to obtain
requisite clearance under extreme swinging conditions and free
swinging of the string. The hanger shall be designed to withstand an
ultimate tensile strength of more than 90 KN.
b) For ground wires at suspension towers suitable ‘U’ Bolts strong
enough to withstand the full designed loads shall be provided to
accommodate the hook of the ground wire suspension clamps.
c) At tension towers, horizontal strain plates of suitable dimensions on
the underside of each power cross-arm tip and at the top ground wire
peak shall be provided for taking the ‘D’ shackles of the tension
insulator strings or groundwire tension clamps, as the case may be.
11.4 Caution Plates, Number Plates, Circuit Plates and Bird Guards:
Each tower shall be fitted with Number Plates, Caution Plates (Danger
Boards), Circuit plates and phase plates. These shall be provided at
appropriate level from the ground level (about 2.5 m to 3.5 m from
ground level) so that the man standing at the foot ground tower will be
able to clearly identify the same. These plates shall be 2 mm thick and
vitreous enameled on both back and front.
The letters, figures and the conventional skull and bones on danger
plates are in signal red on the front side. On the number plate, the
number of the tower location preceded by the letters defining the type of
the tower shall be inscribed. Phase plates shall be coloured red, yellow
and blue to indicate the phase of the conductor. The letters on number
plates shall be in red against white background. The number plates
shall confirm to Fig-5 of IS: 5613 (Part-II/Sec-I). Similarly the plates
and circuit plates to Figs. 6 & 7 in the said IS. The danger notice plates
537456407.doc Page 53
shall confirm to IS: 2551. Bird guards shall be of the saw tooth type
and confirm to Fig.10 of IS (5613 Part-II/Sec-I).
11.5 Earth Bonds:
Stub setting templates shall be arranged for by the contractor at his own
cost for all types of towers with or without extensions.
Stub templates for standard towers and towers with extensions shall be
of the adjustable type. All stub templates shall be painted with anti-
corrosive paints. The number of stub templates to be fabricated shall be
decided by the contractor to coincide with the approved erection
programme.
12.00 PACKING:
12.1 The material shall be boxed or bundled for transport as per IS 802 (Part-
II) – Clause – 11 and sub-clauses thereof. However
537456407.doc Page 54
a) Angles shall be packed in bundles securely wrapped four times
around at each and every foot with No. weight of any bundle shall
not exceed approximately 450 Kg and the length of any individual
member not more than 6000 mm.
b) Cleat angles, brackets, filler plates and similar small loose pieces
shall be nested and bolted, together in multiples and securely wired
together through holes, wrapped round at least four times with No.9
SWG wire with ends twisted tightly. Gross weight of each bundle
shall not exceed approximately 70 Kgs.
c) The correct number of bolts, nuts and washers plus 10% excess for
each tower, extensions, cross arms, attachment to cross arms, etc.
shall be packed in heavy gunny bags accurately tagged in accordance
with the contents. 4 number of such bags shall be packed in a solid
box of 22 mm thick lumbered work with paneled ends securely nailed
and further reinforced with 22 mm x 75 mm battens round the sides,
at the ends with 25 mm wire No.18 SWG gauge iron band stretched
entirely around the battens with ends over lapping at least 150 mm.
The gross weight of each box shall not exceed approximately 70 Kgs.
All packaging shall be subject to the approval of the owner.
12.2 Marking of packings:
Each bundle or package shall have the following markings on it.
a) The name designation of the consignee.
b) Ultimate destination as required by the owner.
c) The relevant marks and number of tower members, or reference
number of bolts, nuts and small components like gusset plates,
various attachments, etc for easy identification.
537456407.doc Page 55
The marking shall be stenciled in indelible ink on the top members in
the bundles of tower steel and on wooden boxes or gunny bags
containing smaller components.
Detailed despatch instructions shall be sought for by the contractor
from the owner at least four weeks ahead of the schedule date of
despatch.
537456407.doc Page 56
In respect of Black cotton soil, the foundations shall be designed for wet
conditions only i.e.-for Wet Black cotton soil only. However, for
excavations, payment shall be made based on the rates for Normal dry if
the soil is dry and based on the rates quoted for wet black cotton soil if
the soil is wet.
SECTION – IIIB
(VOLUME – II)
537456407.doc Page 57
TECHNICAL SPECIFICATIONS
FOR
537456407.doc Page 58
VOLUME – II
SECTION–IIIB
(GENERAL)
1.0 Scope:
The scope of the work includes the supply
of 66KV D/C Narrow Base towers which includes the
following
a. Fabrication & Galvanization of steel sections
b. Assembly of proto-type and offer the same for
inspection by KPTCL
c. Supply of 16mm dia Galvanized Bolt & Nuts
conforming to class 5.6 of IS:12427
d. Supply of tower accessories like step bolts.
Hangers, D-shackle, flexible copper bonds,
number plate, phase plate, circuit plate and
danger plate etc.
e. Packing and dispatch
537456407.doc Page 59
after awarding the contract. However the line
diagram showing the configuration, dimensions and
size of steel section of all the three types of
towers are enclosed with the specification.
Foundations:
Technical details
537456407.doc Page 60
BASE WIDTH OF THE NORMAL TOWER
TYPE .
Sl Type of tower
No. NB-DA NB-DC NB-DD
Section
(Wt. In (Wt. In (Wt. In
Kg) Kg) Kg)
Stub
1 150x150x16 - - 498.19
2 150x150x12 - 376.45 -
3 100x100x8 161.80 - 55.18
4 100x100x6 - 41.95 -
65x65x6 17.17 - -
Total
179 418.40 553.37
NORMAL TOWER
1 45x45x5 804.09 330.5 314.03
2 50x50x5 - 606.0 -
3 50x50x6 252.44 - 360.00
4 60x60x5 - - 204.95
5 65x65x6 129.16 274.2 727.11
6 75X75x8 123.78 - -
7 90x90x8 212.63 248.7 245.99
8 100X100X8 226.27 - -
537456407.doc Page 61
9 130x130x10 - 497.2 -
10 130x130x12 - - 551.45
11 150x150x12 - 576.55 -
12 150x150x16 - - 841.16
13 2mm
thickness
plate - 2.36 -
14 4mm
thickness
plate - - 5.43
15 6mm
thickness
plate 42.34 60.00 59.248
16 8mm
thickness
plate 33.64 - -
17 10mm
thickness
plate - 6.0 5.72
18 12mm
thickness
plate - 61.75 112.84
19 16mm
thickness
plate - 46.76 -
Total 1824.39 2710.02 3427.928
STUB SETTING TEMPLATE
1 150X150X16 - - 140.19
2 150X150X12 - 87.04 -
3 100X100X8 40.66 - -
4 65X65X6 - 85.17 94.19
5 45x45x5 8.85 81.11 101.7
Total 200.23 253.32 336.08
+3 M BODY EXTENSION
1 150x150x16 - - 429.03
2 150X150X12 - 325.96 -
3 130X130X10 36.72 -
4 130X130X12 - - 43.62
5 100X100X8 145.00 - -
6 90x90x8 13.65 - -
537456407.doc Page 62
7 65x65x6 - - 166.07
8 50X50X5 - 167.65 -
9 45x45x5 159.91 - 109.35
10 8mm
thickness
plate 14.29 - -
11 12mm
thickness
plate - 33.01 33.01
Total 332.85 563.43 781.08
+6 M BODY EXTENSION
1 150X150X16 - - 859.05
2 150X150X12 - 652.69 -
3 130X130X12 - - 43.62
4 130X130X10 - 36.72 -
5 100X100X8 290.31 - -
6 90x90x8 13.65 - -
7 65x65x6 - - 336.47
8 50X50X5 - 352.78 -
9 45x45x5 330.88 53.46 218.7
10 6mm
thickness
plate - 3.81 -
11 8mm
thickness
plate 4.29 - -
13 12mm
thickness
plate - 33.01 33.01
Total 649.13 1132.47 1490.85
FOUNDATION VOLUMES
537456407.doc Page 64
Code of practice for plain and reinforced
IS 456
concrete.
Code of practice for use of structural steel
IS 800
in building construction
Use of structural steel in overhead
IS 802 (Part-1/Sec-1)
transmission line towers
– 1995
Materials, Loads and Permissible stresses
Fabrication, Galvanizing, Inspection and
IS 802 (Part-2) – 1977
Testing
Dimensions for rolled steels, beams,
IS 808 – 1989
columns, channel and angle sections
IS 1239 – 1968–Part-I Mild Steel Tubes
Hexagonal head bolts, screws and nuts of
IS 1363 (Part – 3) – 1992
product grade C.
Mechanical properties and test methods for
IS 1367 (Part – 6) – 1980
nuts with specified loads
IS 1367 (Part – 13) Hot dip galvanized coatings on threaded
– 1985 fasteners
Electroplated coatings of Zinc on iron and
IS 1573 – 1986
steel
Dimensions for steel plates, sheets strips and
IS 1730 – 1989
flats
IS-Number Particulars
537456407.doc Page 65
Code of practice for design installation and
IS 5613 (Part-2/Sec-I) maintenance of overhead lines (Part-2 –
–1985 Lines above 11 kV and up to and including
220 kV)
IS 5624 – 1970 Foundation bolts
IS 6610 – 1972 Heavy washers for steel structures
IS 6623 – 1985 High strength structural nuts (first revision)
IS 6639 – 1972 Hexagonal bolts for steel structures
Hardened and tempered washers for high
IS 6649 – 1983 strength structural bolts and nuts (first
revision)
Method determination o f weight of zinc
IS 6745
coating Of zinc coated iron and steel articles
IS 10238 – 1982 Step bolts for steel structures
IS 12427 – 1988 Transmission line tower bolts
Reference
/Abbr Name and address from which
eviat the standards are available
ion
BUREAU OF INDIAN STANDARS,
Manak Bhavan,
IS
New Delhi
INDIA
CANADIAN STANDARDS
ASSOCIATION
CSA 178,Rexdale Boulevard
Ontario
CANADA
BRITISH STANDARDS
British Standard Institution
BS
Pentonvile Road
U.K.
537456407.doc Page 66
DEUTSCHES INSTITUTE FIIR NOR
Gurggarafenstrasse 4-10
DIN
Post Fach 1107
BERLIN-30
3.0 MATERIALS:
12.1 ISS steel sections of tested quality in conformity with IS-2062-2006 (for
both MS and HT steel) with dimensional and section properties
conforming to IS 808-1976 Part V & VI shall be used in the design of
tower members, stubs and stub setting templates. No individual member
length shall more than 6000mm. Tower designs shall be made with only
rationalized steel sections. However during fabrication if any particular
section is not available the same shall be substituted by a higher section at
no extra cost. However, design approvals for such substitution shall be
obtained from the purchaser.
537456407.doc Page 67
The other materials to be used in the construction and erection of the tower
are the tower accessories such as number plates, circuit plates, phase
plates, danger boards, earthing materials, anti-climbing devices. These are
detailed separately under supply of tower accessories.
3.0 FABRICATION:
537456407.doc Page 68
3.5 The tower structures shall be accurately fabricated to bolt together easily at
site without any undue strain on the bolts.
3.6 No angle member shall have the two leg flanges brought together by
closing the angle.
3.7 The structure shall be such that all parts shall be accessible for inspection
and cleaning. Drain holes shall be provided at all points where pockets of
depressions are likely to hold water.
3.8 All similar parts shall be made strictly interchangeable. All steel sections
before any work is done on them, shall be carefully leveled, straightened
and made true to detailed drawings, by methods which will not injure the
materials so that when assembled the adjacent matching surfaces are in
close contact throughout. No rough edges shall be permitted in the entire
structure.
4.1 Before any cutting work is started, all steel sections shall be carefully
straightened and trued by pressure and not by hammering. They shall
again be trued after being punched and drilled.
4.2 Holes for bolts shall be drilled or punched with a jig but drilled holes shall
be preferred. The following maximum tolerance of accuracy of punched
holes is permissible.
c) Holes must be perfectly circular and no tolerance in this respect is
permissible.
d) The maximum allowable difference in diameter of the holes on the two
sides of plates or angle is 0.8-mm i.e., the allowable taper in punched
holes should not exceed 0.8 mm on diameter.
4.3 All burrs left by drills or punch shall be removed completely. When the
tower members are in position the holes shall be truly opposite to each
537456407.doc Page 69
other. Drilling or reaming to enlarge defective holes shall not be
permitted.
4.4 The strain plate holes shall be chamfered properly and sharp edges
removed.
5.0 GALVANISING:
Fully galvanized towers and stubs galvanized from the top up to 300 mm
below ground level shall be used for the lines. Galvanizing of the member
of the towers shall conform to IS: 2629-1966 and IS: 4759-1968. All
galvanized members shall withstand tests as per IS: 2633-1972. For
fasteners, the galvanizing shall be done after all fabrication work is
completed, except that the nuts may be tapped or re-run after galvanizing.
Spring washers shall be electro-galvanized as per Grade 4 of IS: 1573-
1070.
6.1 All bolts and nuts shall conform to IS: 6639 –1972 or IS: 12427 – 1988 as
applicable and shall be of approved makes only. All bolts and nuts shall
be galvanized and shall have hexagonal heads and nuts. The heads shall
be forged out of the solid, truly concentric, and square with the shank,
which must be perfectly straight. The following makes are approved:
7. M/s. GKW, Calcutta.
8. M/s. Raj Enterprises, Indore.
9. M/s. Agarwal Industries, Howrah.
10. M/s. Bharat Industries, Howrah.
11. M/s. NEXO Industries, Ludhiana.
537456407.doc Page 70
12. M/s. Indian Steel & Wire Products (ISWP), Jamshedpur.
6.2 Fully threaded bolts shall not be used. The length of bolts shall be such
that the threaded portion will not extend into the place of contact of the
members. All bolts shall be threaded to take the full depth of the nut and
threaded enough to permit firm gripping of the members, but not further.
It shall be ensured that the threaded portion of each bolt protrudes not less
than 3 mm and not more than 8 mm when fully tightened. All nuts shall fit
hand tight to the bolt. Threads of bolts and nuts shall have a neat fit and
shall be such that they can be turned with finger through out the length of
the threads of bolts and they shall be capable of developing full strength of
the bolts.
6.3 Flat and tapered washers shall be provided wherever necessary. Spring
washers shall be provided for insertion under all nuts. These washers shall
be of steel electro-galvanized, positive lock type and as specified in Bill of
Materials.
6.4 The contractor shall furnish bolt schedules giving thickness of members
connected, the nut and the washer, the length of shank, the threaded
portion of bolts and sizes of holes and any other detail of this nature.
6.5 The bolts shall be of class 5.6 and nuts shall be of property class 5. The
ultimate shear stress and bearing stress on bolts shall be 3160 Kg/Sq.cm
and ultimate bearing stress shall be as per IS.
6.6 To obviate bending stress in bolts or to reduce it to minimum, no bolt shall
connect aggregate thickness of more than three (3) times its diameter.
6.7 Bolts at the joints shall be so staggered that nuts may be tightened with
spanners without fouling.
537456407.doc Page 71
The minimum bolt spacing and rolled edge distance and sheared edge distances of
sections from the centres of bolt holes to be maintained are given in Table below:
TABLE –3
(Clause12.02)
Each tower shall be provided with step bolts on one of the main legs, of
not less than 16 mm diameter and 175 mm long, spaced not more than 450
mm apart and extending from about 3.5 metres above the ground level to
the top of the tower. Each step bolt shall be provided with two nuts on one
end to fasten the bolt securely to the tower and button head at the other end
to prevent the feet from slipping away. The step bolts shall be capable of
withstanding a vertical load not less than 1.5 KN and shall be used as a
ladder for climbing. The step bolts shall conform to IS 10238 and shall
have a hexagonal head.
7.2 ANTI-CLIMBING DEVICES:
537456407.doc Page 72
angle pieces with 12 mm x 12-mm notches for accommodating barbed
wire shall be supplied with the towers along with provision for suitable
bolt holes on leg members for fitting the angles. The barbed wire shall
conform to IS-378 (1978). The anti-climbing devices shall in general
conform to Fig-8 of IS-5613 (Part-II/Sec-I).
7.3 INSULATOR STRINGS AND GROUND WIRE CLAMP
ATTACHMENTS:
Each tower shall be fitted with Number Plates, Caution Plates (Danger
Boards), Circuit plates and phase plates. These shall be provided at
appropriate level from the ground level (about 2.5 m to 3.5 m from ground
level) so that the man standing at the foot ground tower will be able to
clearly identify the same. These plates shall be 2 mm thick and vitreous
enameled on both back and front.
537456407.doc Page 73
The letters, figures and the conventional skull and bones on danger plates
are in signal red on the front side. On the number plate, the number of the
tower location preceded by the letters defining the type of the tower shall
be inscribed. Phase plates shall be colored red, yellow and blue to indicate
the phase of the conductor. The letters on number plates shall be in red
against white background. The number plates shall confirm to Fig-5 of IS:
5613 (Part-II/Sec-I). Similarly the plates and circuit plates to Figs.6 & 7 in
the said IS. The danger notice plates shall confirm to IS: 2551.Bird guards
shall be of the saw tooth type and confirm to Fig.10 of IS (5613 Part-
II/Sec-I).
7.6 EARTHING:
Stub setting templates shall be arranged for by the contractor at his own
cost for all types of towers with or without extensions.
537456407.doc Page 74
Stub templates for standard towers and towers with extensions shall be of
the adjustable type. All stub templates shall be painted with anti-corrosive
paints. The number of stub templates to be fabricated shall be decided by
the contractor to coincide with the approved erection programme.
8.0 PACKING:
8.1 The material shall be boxed or bundled for transport as per IS 802 (Part-II)
537456407.doc Page 75
8.2 MARKING OF PACKINGS:
Each bundle or package shall have the following markings on it.
d) The name designation of the consignee.
e) Ultimate destination as required by the owner.
f) The relevant marks and number of tower members, or reference
number of bolts, nuts and small components like gusset plates, various
attachments, etc for easy identification.
The marking shall be stenciled in indelible ink on the top members in the
bundles of tower steel and on wooden boxes or gunny bags containing
smaller components.
The contractor from the owner shall seek for detailed dispatch instructions
at least four weeks ahead of the schedule date of dispatch.
9.0 The bidder shall assess the type and total quantities of the towers, tower
accessories and all other line materials required for completion of the line
and furnish the same in the relevant BPS of specification. The bids will be
evaluated based on the quantity furnished by the bidder. The payment will
be restricted to the quantity so assessed by the bidder. All the materials and
works required for the completion of the above project shall be invariably
furnished in the BPS.
The purchaser reserves the right to order for final quantities at the rates
quoted in the bid, which shall be valid through out the tendency of the
contract.
The unit weight of each type of tower, stubs, and extension pieces shall be
furnished by the bidder. The weight of tower shall mean the weight of the
tower calculated by using the black section (un-galvanized) weight of steel
members of sizes indicated in the approved fabrication drawings and bill
of materials, without taking in to consideration the reduction in weights
due to holes, notch cuttings, bevel cuttings, etc., but taking in to
consideration the weight of special fittings.
21.0 TESTS:
22.0 INSPECTION:
537456407.doc Page 76
22.1 Proto-type assembly:
The proto-type assembly of the complete tower
along with body extensions shall be offered
for inspection by the Engineers of KPTCL and
the mass fabrication shall be taken only
after the successful proto-inspection.
22.2 The supplier shall keep the purchaser
informed well in advance of the commencement
of manufacture, progress of manufacture
thereof and fabrication of various tower parts
at various stages, so that arrangements could
be made for inspection by the purchaser.
537456407.doc Page 77
rejected shall be resubmitted for inspection,
except in cases where the purchaser of his
authorized representative considers that the
defects can be rectified.
537456407.doc Page 78
Schedule – Schedule of Guaranteed Technical
Particulars given in Section DRS
537456407.doc Page 79
SECTION – IVA
(VOLUME – II)
TECHNICAL SPECIFICATIONS
FOR
537456407.doc Page 80
VOLUME-II
SECTION-IV
1.0 SCOPE
2.0 STANDARDS
3.0 PRICIPAL PARAMETERS
4.0 GENERAL TECHNICAL REQUIREMENTS
5.0 TESTS
6.0 INSPECTION
7.0 QUALITY ASSURANCE PLAN
8.0 PACKING AND FORWARDING
TEST PROCEDURES
537456407.doc Page 81
VOLUME – II
SECTION – IVA
TECHNICAL SPECIFICATION FOR POWER CONDUCTOR FOR
TRANSMISSION LINES
1.0 Scope:
1.1 This specification provides for design, manufacture, engineering,
inspection and testing before despatch, packing and delivery F.O.R.
(destination) of aluminium conductors steel reinforced (ACSR) for
overhead transmission purposes specified herein.
537456407.doc Page 82
Sl. Indian International
Title
No. Standards Standards
1 IS: 209 Specification for zinc BS: 3436
IS: 398 Specification for IEC: 209
Part-I to aluminium conductors BS: 215
2 (Part-II)
Part-V (As for overhead transmiss-
relevant) ion purpose
Reels and Drums for
3 IS: 1778 BS: 1559
Bare Conductors
Method of Tensile Testing
4 IS: 1521 ISO/R89
of steel wire
Recommended practice
5 IS: 2629 for Hot Dip Galvanizing of
Iron and Steel
Method of Testing
6 IS: 2633 Uniformity of coating of
zinc coated Articles
Galvanised coating on ASTM A-472
7 IS: 4826 729
round steel wire
Method of Determination
of weight of zinc coating
8 IS: 6745
of zinc coated Iron and BS: 443
Steel Articles
EC grade Aluminium rod
9 IS: 1841 produced by rolling
(second Revision)
EC grade Aluminium rod
produced by continuous
10 IS: 5484
casting and rolling (first
revision)
Methods of determination
of weight of zinc coating
11 IS: 6754
of zinc coated Iron and
steel Articles.
Specification for Drake
12 C-49 CSA
ACSR
537456407.doc Page 83
2.2 The standards mentioned above are available from:
Reference
Name and Address
Abbreviation
British Standards, British Standards
BS Institution, 101, Pentonvile Road,
N-19-ND – UK
International Electro-technical
Commission, Bureau Central de la
Commission, Electro Technique
IEC/CISPR
International, 1 Rue de verembe,
Geneva, SWITZERLAND
537456407.doc Page 84
3.0 Principal Parameters:
3.1 The details of conductor are tabulated below:
26/4.442 30/2.79 26/2.5 mm
mm mm Aluminium
Stranding and wire
Aluminium Aluminium 7/1.9 mm
diameter
7/3.45 mm 7/2.79 mm Steel
Steel (Drake) Steel (Lynx) (Coyote)
a) Number of Strands (Not applicable) (Not applicable)
Steel Centre. 1 1 1
I Steel Layer 6 6 6
I Al. Layer 10 12 10
II Al. Layer 16 18 16
b) Sectional area of
aluminium (Sq.mm) 402.8 183.4 131.7
c) Total sectional area
(Sq.mm) 468.40 226.2 151.6
d) Overall diameter (mm) 28.13 19.53 15.86
e) Approximate weight
(kg/km) 1623.5 844 521
f) Calculated D.C
resistance at 200C 0.0715 0.1589 0.2214
(ohm/km)
g) Minimum UTS (Kg) 14175 7950 4625
h) Modulus of Elasticity
0.773 0.787 0.773
(Kgs/Sq.cm x 106)
537456407.doc Page 85
The details of steel strand are as follows:
i. Minimum breaking
load of strand before 1251 819 403
stranding (Kg)
ii. Minimum breaking
load of strand after 1188 778 383
stranding (Kg)
iii. Minimum weight of
259 230 210
zinc coating (gm/sq.m
537456407.doc Page 86
points rigidly fixed to the wire, the metal being allowed to expand
freely.
4.2.5 Co-efficient of linear expansion: The coefficient of linear expansion
for hard drawn aluminium at 00C has been taken as 0.004/0C has
been taken as 23.0 x 10-6/0C. This value holds good for all practical
purposes over the range of temperature from 0 0C to highest safe
operating temperature.
4.3 Physical constant for Galvanised steel wires:
4.3.1 Density: At a temperature 200C, the density of galvanised steel wire is
to be taken as 7.80 g/cm3.
4.3.2 Co-efficient of Linear Expansion: In order to obtain uniformity in
calculations a value of 11.5 x 10 -6/0C may be taken as the value for
the co-efficient of Linear Expansion of galvanized steel wires used for
the cores of steel-reinforced aluminium conductors.
4.4 Materials:
4.4.1 The conductors shall be manufactured from EC grade aluminium rod
suitably hard-drawn on wire drawing machines. The aluminium rods
used shall comply with IS: 1841 and IS: 5484. The mechanical and
electrical properties of aluminium wire shall comply with the
requirements given in relevant standard.
4.4.2 Galvanised steel wire shall be drawn from high carbon
steel rods produced by either acidic or basic open-
hearth process, electric furnace process or basic
oxygen process. The mechanical and electrical
properties of wire shall comply with the requirements
given in relevant standard. The chemical composition
of high carbon steel wire is given below for guidance
only.
537456407.doc Page 87
Element Percentage Composition
4.4.3 The zinc used for galvanising shall be electrolytic high-grade zinc not
less than 99.95% purity. It shall conform to and satisfy all the
requirements of IS: 209 Galvanizing may be done by hot process.
Natural grease may be applied between the layers of wires.
NOTE: Lithium soap grease corresponding to Grade-II of IS: 7623
(Specification for lithium soap greases) is suitable for such
application.
4.5 Freedom from Defects:
4.5.1 The wires shall be smooth and free from all imperfections such as
spills, splits, slag inclusion, die marks, scratches, pittings, blow-
holes, projections, looseness, overlapping of strands, chipping of
aluminium layers etc and all such other defects, which may hamper
the and mechanical/ electrical properties of the conductor. Special
care should be taken to keep away dirt, grit etc during stranding.
4.6 Wire sizes:
4.6.1 Nominal size:
The aluminium and galvanised steel wires for the stranded conductor
covered by this standard shall have diameters specified in clause 3.1.
The diameter of the steel wires shall be measured over the zinc
coating.
537456407.doc Page 88
4.6.2.1 Aluminium Wires: A tolerance of + 1% is permitted on the nominal
diameter of conductor respectively.
4.6.2.2 Galvanized steel earthwire: A tolerance of + 2% is permitted on the
nominal diameter.
NOTE: In order to maintain the circularity of the wires the tolerance
allowed in 4.6.2.1 and 4.6.2.2 shall apply to both the
measurements at right angles taken at the same cross-section
as per Clause 2.2 of IS:398 (Part-II) (Second Revision with
Amendments 1 to 30).
4.7 Joints in Wires:
4.7.1 Aluminium Wires: No joints shall be permitted in the aluminium
wires in the outermost layer of the ACSR Conductor. Joints in the
inner layers are permitted, in addition to those made in the base rod
or wire before final drawing, but no two such joints shall be less than
15 meter apart in the complete stranded conductor. Such joints shall
be made by cold pressure butt-welding.
NOTE: Joints are not permitted in the outermost layer of the
conductor in order to ensure a smooth conductor finish and
reduce radio interference levels and corona losses on the extra
high voltage lines.
4.7.2 Galvanized steel wires: There shall be no joints except those in the
base rod or wire before final drawing, in steel wires forming the core
of the steel-reinforced aluminium conductor.
NOTE: Joints are not permitted in the steel wires after final drawing
in order to avoid reduction in the breaking strength of the
conductor that may occur as a result of failure of the joints.
4.8 Stranding:
537456407.doc Page 89
4.8.1 The wires used in the construction of galvanised steel reinforced
aluminium conductor shall before stranding, satisfy all the relevant
requirements of this specification.
4.8.2 The lay ratio of the different layers shall be within the limits given in
the following tables:
Maximum Minimum
1. ACSR DRAKE
a) Steel Wire 28 18
b) Aluminium
i. 10 Wire layer 14 10
ii. 16 Wire layer 16 10
2. ACSR LYNX
a) Steel Wire 30 20
b) Aluminium
i. 12 Wire layer 21 14
ii. 18 Wire layer 14 11.25
3. COYOTE ACSR
a) Steel Wire 30 20
b) Aluminium
i. 10 Wire layer 21 14
ii. 16 Wire layer 14 11.25
Note: The details of ACSR Coyote and Lynx may be ignored as they are not in the scope.
NOTE: For the purpose of calculation, the mean lay ratio shall be
taken as the arithmetic mean of the relevant minimum and
maximum values given in this table.
537456407.doc Page 90
4.8.3 In all constructions, the successive layers shall have opposite
directions of lay, the outermost layer being right-handed. The wires
in each layer shall be evenly and closely stranded.
4.8.4 In conductors having multiple layers of aluminium wires, the lay ratio
of any aluminium layer shall not be greater than the lay ratio of the
aluminium layer immediately beneath it.
537456407.doc Page 91
5.1.1 Type tests shall mean those tests, as per IS, which are to be carried
out to prove the design, process of manufacture and general
conformity of the material to this specification. These tests shall be
carried out on samples prior to commencement of commercial
production against the order. The Bidder shall indicate his schedule
for carrying out these tests in the offer.
5.1.2 Acceptance Tests shall mean those tests, which are to be carried out
on samples taken from each lot offered for predespatch inspection, for
the purposes of acceptance of that lot.
5.1.3 Routine Tests shall mean those tests, which are to be carried out on
each strand/spool/length of the conductor to check requirements,
which are likely to vary during production.
5.1.4 Tests during manufacture shall mean those tests, which are to be
carried out during the process of manufacture by the supplier to
ensure the desired quality of the end product to be supplied by him.
5.1.5 The norms and procedure of sampling for these tests will be as per
the Quality Assurance Programme to be mutually agreed to by the
supplier and the purchaser as per relevant clause of General
Conditions of Contract.
5.1.6 The standards and norms to which these tests will be carried out are
listed against them. Where a particular test is a specific requirement
of this specification, the norms and procedures of the test shall be as
specified in Annexure-II or as mutually agreed to between the
supplier and the purchaser in the Quality Assurance Programme.
5.1.7 For all type and acceptance tests, the acceptance values shall be the
values guaranteed by the bidder in the “Guaranteed Technical
Particulars”, Volume-III of his proposal or the acceptance value
537456407.doc Page 92
specified in this specification, whichever is more stringent for that
particular test.
5.2 Type tests:
The following type tests shall be conducted once on each
sample/samples of conductor for every 500 KM of production from each
manufacturing facility.
a) UTS test on Stranded Conductor: Ref. Test Procedure
b) Corona extinction voltage test (dry): - do-
c) Radio interference voltage test (dry): - do-
d) DC resistance test on stranded
Conductor : - do-
e) Stress-strain Test : - do-
5.3 Acceptance Tests:
a) Visual and dimensional check on: Ref. Test Procedure
Drum
b) Visual check for joints, scratches :
Etc. and lengths of conductor - do -
c) Dimensional check on steel and :
Aluminium strands - do -
d) Check for lay ratios of various :
Layers - do -
e) Galvanizing test on steel strands : - do -
f) Torsion and Elongation test on : - do -
Steel strands
g) Breaking load test on steel and :
Aluminium strands - do -
h) Wrap test on steel and aluminium:
Strands - do -
537456407.doc Page 93
i) DC resistance test on aluminium :
Strands - do -
j) UTS test on welded joints of :
Aluminium strand - do -
NOTE: All the above tests except test mentioned at (j) shall be
carried out on aluminium and steel strands after stranding
only.
5.4 Routine Tests:
a) Check to ensure that the joints are as per specification.
b) Check that there are no cuts etc on the strands.
c) All acceptance tests as mentioned in Clause 5.3 above shall be
carried out on each coil.
5.5 Tests during Manufacture:
a) Chemical analysis of zinc used : Ref. Test Procedures
For making galvanising
b) Chemical analysis of aluminium : - do -
Used for making aluminium strands
c) Chemical analysis of steel used : - do -
For making steel strands
5.6 Testing Expenses:
5.6.1 The testing charges for the type tests specified shall be indicated
separately in the prescribed schedule.
5.6.2 The Bidder shall indicate the type test charges for each type test
separately. In case the same are not mentioned then the charges are
deemed to have been included in the quoted rates of materials.
5.6.3 In case of failure in any type test, the Bidder is either required to
modify the design of the material or repeat the particular type test
three times successfully at his own expenses. The decision of the
537456407.doc Page 94
purchaser in this regard shall be final and binding. The type tests
are to be conducted irrespective of whether the same have been
conducted earlier or not.
5.6.4 Bidder shall indicate the laboratories in which he proposes to
conduct the type tests. He shall ensure that the tests can be
completed in these laboratories within the time schedule guaranteed
by him in the appropriate schedule.
5.6.5 The entire cost of testing for the acceptance and routine tests and
tests during manufacture specified herein shall be treated as
included in the quoted unit price of conductor, except for the
expenses of the inspector/ purchaser’s representative.
5.6.6 The prices quoted by the bidder towards conductance of type test
shall be taken into consideration for bid evaluation.
5.7 Additional Tests:
The purchaser reserves the right of having at his own expenses any
other test(s) of reasonable nature carried out at supplier’s premises,
at site, or in any other place in addition to the aforesaid type,
acceptance and routine tests to satisfy himself that the material
comply with the specifications.
5.8 Sample Batch for type testing:
5.8.1 The supplier shall offer at least three (3) drums for selection of
samples required for conducting all the type tests.
5.8.2 The supplier is required to carry out all the acceptance tests
successfully in the presence of purchaser’s representative before
despatch.
5.9 Test Reports:
5.9.1 Four copies of type test reports shall be furnished to the Purchaser
within one month of conducting the tests. One copy will be returned
537456407.doc Page 95
duly certified by the purchaser to the supplier within three weeks
thereafter and on receipt of the same supplier shall commence with
the commercial production of the conductor.
5.9.2 Four copies of acceptance test reports shall be furnished to the
purchaser. One copy will be returned, duly certified by the Purchaser
and only thereafter shall the conductor be despatched.
5.9.3 All records of routine test reports shall be maintained by the supplier
at his works for periodic inspection by the purchaser.
5.9.4 All test reports of tests conducted during manufacture shall be
maintained by the supplier. These shall be produced for verification
as and when required for by the purchaser.
5.10 Test Facilities:
5.10.1 The following additional test facilities shall be available at Supplier’s
works:
a) Calibration of various testing and measuring equipment including
tensile testing machine resistance measurement facilities, burette,
thermometer, barometer etc.
b) Standard resistance for calibration of resistance bridges.
c) Finished conductor shall be checked for length verification and
surface finish on separate rewinding machine at reduced speed
(variable from 8 to 16 metres per minute). The rewinding facilities
shall have appropriate clutch system and free of vibrations, jerks
etc with transverse layering facilities.
6.0 Inspection:
6.1 The Purchaser’s representative shall at all times be entitled to have
access to the works and all places of manufacture where conductor shall
be manufactured and the representative shall have full facilities for
unrestricted inspection of the supplier’s works raw materials and
537456407.doc Page 96
process of manufacture for conducting necessary tests as detailed
herein.
6.2 The supplier shall keep the purchaser informed in advance of the
time of starting and of the progress of manufacture of conductor in
its various stages so that arrangements can be made for inspection.
6.3 No material shall be despatched from its point of manufacture before
it has been satisfactorily inspected and tested, unless the inspection
is waived off by the purchaser in writing. In the later case also, the
conductor shall be despatched only after satisfactory testing for all
tests specified herein has been completed.
6.4 The acceptance of any quantity of material shall in no way relieve the
supplier of any of his responsibilities for meeting all requirements of
the specification, and shall not prevent subsequent rejection if such
material is later found to be defective.
6.5 At least 5% of the total number of drums subject to minimum of two
in any lot put up for inspection, shall be selected at random to
ascertain the length of conductor by following method:
“At the works of the manufacturer of the conductor, the conductor
shall be transferred from one drum to another at the same time
measuring its length with the help of a graduated pulley &
Cyclometer. The difference in the average length thus obtained and as
declared by the Supplier in the packing list shall be applied to all the
drums if the conductor is found short during checking.”
7.0 Quality Assurance Plan:
7.1 The Bidder shall invariably furnish following information along with his
offer, failing which his offer shall be liable for rejection.
i) Statement giving list of important raw materials names of sub-
suppliers for the raw materials, list of standards according to which
537456407.doc Page 97
the raw materials are tested, list of tests normally carried out on raw
materials in presence of Bidder’s representative, copies of test
certificates.
ii) Information and copies of test certificates as in (i) above in respect of
bought out material.
iii) List of manufacturing facilities available.
iv) Level of automation achieved and list of areas where manual
processing exists.
v) List of areas in manufacturing process, where stage inspections are
normally carried out for quality control and details of such tests and
inspections.
vi) List of testing equipments available with the Bidder for final testing of
equipment specified and test plant limitation, if any, vis-à-vis the
type, special, acceptance and routine tests specified in the relevant
standards. These limitations shall be very clearly brought out in
schedule of deviation from specified test requirements.
7.2 The supplier shall within 30 days of placement of order submit following
information to the purchaser.
i. List of raw materials sub-suppliers selected from those furnished
along with offer.
ii. Type test certificates of the raw material.
iii. Quality Assurance Plan (QAP) with hold points for Purchaser’s
inspection. The quality assurance plan and Purchaser’s hold
points shall be discussed between the Purchaser and supplier,
before the QAP is finalized.
7.3 The supplier shall submit the routine test certificates of raw material
at the time of routine testing on the conductor.
8.0 Packing & Forwarding:
537456407.doc Page 98
8.1 The Conductor shall be supplied in non-returnable strong wooden
drums provided with lagging of adequate strength, and displacement
during transit, storage and subsequent handling and stringing
operations in the field. The drums shall generally conform to IS:
1778-except otherwise specified hereinafter.
8.2 The drums shall be suitable for wheel mounting and for jetting off the
conductor under a minimum controlled tension of the order of 5 KN.
8.3 The Bidder should submit the proposed drum drawings along with
the bid. However, the same shall be in line with the requirements as
stated herein. After placement of the Letter of Award, the supplier
shall submit four copies of fully dimensioned drawing of the drum he
wished to supply, for Purchaser’s approval before taking up
manufacturing of Conductor. After getting approval from the
purchaser, supplier shall submit 30 more copies of the approved
drawing to Purchaser for further distribution and field use at
Purchaser’s end.
8.4 All wooden components shall be manufactured out of seasoned
softwood free from defects that may materially weaken the component
parts of the drums. Preservative treatment for anti-termite/anti-
fungus (Aldrime/Aldruse) shall be applied to the entire drum with
preservatives of a quality, which is not harmful to the conductor.
8.5 The flanges shall be of two/three ply construction with each ply at
right angles to the other and nailed together. The nails shall be
driven from the inside face flange, punched and then clenched on the
outer face. The tolerance in thickness of each ply shall be + 3 mm
only. There shall be at least 3 nails per plank of ply with maximum
nail spacing of 75 mm. Where a slot is cut in the flange to receive the
537456407.doc Page 99
inner end of the conductor, the entrance shall be in the line with the
periphery of the barrel.
8.6 The wooden battens used for making the barrel of the conductor shall
be of segmental type. These shall be nailed to the barrel supports
with at least two nails. The battens shall be closely butted and shall
provide a round barrel with smooth external surface. The edges of
the battens shall be rounded or chamfered to avoid damage to the
conductor.
8.7 Barrel studs shall be used for construction of drums. The flanges
shall be holed and the barrel supports slotted to receive them. The
barrel studs shall be threaded over a length on either end, sufficient
to accommodate washers, spindle plates and nuts for fixing flanges at
the required spacing. Barrel studs should be tack welded with the
nuts after tightening.
8.8 Normally, the nuts on the studs shall stand protrude of the flanges.
All the nails used on the inner surface of the flanges and the drum
barrel shall be countersunk. The ends of barrel shall generally be
flushed with the top of the nuts.
8.9 The inner cheek of the flanges and drum barrel surface shall be
painted with a bitumen-based paint.
8.10 Before reeling, cardboard or double corrugated or thick bituminised
waterproof bamboo paper shall be secured to the drum barrel and
inside of flanges or the drum by means of a suitable commercial
adhesive material. The paper should be dried before use. Medium
grade Kraft paper shall be used in between the layers of the
conductor. After reeling the conductor, the exposed surface of the
outer layer of conductor shall be wrapped with thin polythene sheet
across the flanges to preserve the conductor from dirt, grit and
*****
TECHNICAL SPECIFICATION
FOR
ACCR HTLS (HIGH TEMPERATURE LOW SAG)
CONDUCTOR
- EQUIVALENT TO ACSR COYOTE
1. GENERAL INFORMATION:
1.0 Preamble:
KPTCL has decided to uprate the following ring mains in Bangalore city by
replacing the existing ACSR COYOTE by equivalent ACCR ( Aluminum
Conductor Composite Reinforced) HTLS (High Temperature Low Sag)
Conductor (which can carry double the current with the same sag at
maximum temperature) on the existing towers. The intermediate supports
(Narrow Base Tower / High Tensile Tubular Mono-Pole) shall be used only in
case of long spans to get the adequate clearances.
The above lines are passing through thickly populated Residential &
Commercial plots along the narrow streets and hence at most care must be
taken by the contractor during Releasing & Stringing of the conductor
without causing any damage to the property. The bidders are advised to
compulsorily carry out the walk-over survey/ route-inspection to
familiarize with the work before quoting. The preliminary and detailed
survey has been conducted by KPTCL and all the necessary data such as
tropo-sheet extract, route profile & tower schedule will be furnished to the
successful contractor.
The existing 66KV D/C towers of the ring mains are designed and
commissioned almost 32 to 40 years back.
The following are the design parameters of the tower:
3.0 Description of High Temperature Low Sag (HTLS) Conductor and its
Technical Requirements
3.1 The HTLS Conductor shall be capable of providing the specified ampacity at
a continuous operating conductor temperature higher than that of the
maximum permissible operating temperature of the existing ACSR COYOTE
Conductor without exceeding the level of maximum permissible sag of the
existing ACSR COYOTE Conductor AT 55 0 C ie., 5.1M for HTLS conductor
for a continuous operating temperature of the conductor .
The physical and operating performance requirements of the transmission
line after its uprating by means of re-conductoring with HTLS conductor are
mentioned below. The bidder shall offer HTLS conductor complying with the
specified requirements. The Bidder shall indicate particulars of the proposed
conductor in the relevant GTP schedule of BPS alongwith calculations to
establish compliance with the specified requirements.
3.2 Current Carrying Capacity / Ampacity Requirements
3.4.1 The HTLS conductor shall meet the following sag tension
requirements for ruling span of 275M
3.4.2 After award of the contract, the Supplier shall submit Sag-Tension
calculations corresponding to various conditions given above for all the
existing spans and spans ranging from 50M to 400M in intervals of 50M.
3.4.3 Besides above, the Supplier shall also furnish details of creep
characteristics in respect of HTLS conductor based on laboratory
investigations/ experimentation (creep test as per IEE1138) conducted on
similar type of conductor and shall indicate creep strain values
corresponding to 1 month, 6 month, 1 year & 10 year creep at everyday
tension & at maximum continuous operating temperature.
3.5 Workmanship
3.5.1 All the conductor strands shall be smooth, uniform and free from all
imperfections, such as spills and splits, cracks, die marks, scratches,
abrasions, rust etc.
3.5.2 The finished conductor shall be smooth, compact, uniform and free from all
imperfections including kinks (protusion of wires), wire cross over, over
riding, looseness (wire being dislocated by finger/hand pressure and/or
unusual bangle noise on tapping), material inclusions, white rust, powder
formation or black spot (on account of reaction with trapped rain water
etc.), dirt, grit etc.
CAPITALISATION OF LOSSES
KPTCL will capitalise the losses as offered by the Bidders commensurate
to the ratings offered by each of them in their “Augmentation
Programme”. The savings in losses will need to clearly demonstrate with
calculations by the bidder. Such loss capitalisation will be averaged by
admitting the loss over 25 years.
= 995.328 x Rac
Differential price evaluation for the conductors offered by the bidders shall
be carried out considering the average ohmic losses calculated as above
and considering Rs.1,52,600 per kW.
The best parameter of loss (lowest ohmic loss for conductor) corresponding
to lowest AC resistance quoted among bidders by any technically
responsive and qualified bidder shall be taken as basis and that quoted by
the particular bidder shall be used to arrive at differential price to be
applied for each bid.
Note All the above tests except (j) shall be carried out on
: Aluminium / Aluminium Alloy and core strands after
stranding only.
BS British Standards,
British Standards Institution
101, Pentonvile Road,
N - 19-ND
UK
5.0 ANNEXURE-A
5.1.0 Tests on Conductor
5.1.1 UTS Test on Stranded Conductor
Circles perpendicular to the axis of the conductor shall be marked at two
places on a sample of conductor of minimum 5 m length between fixing
arrangement suitably fixed by appropriate fittings on a tensile testing
machine. The load shall be increased at a steady rate upto 50% of
minimum specified UTS and held for one minute. The circles drawn shall
not be distorted due to relative movement of strands. Thereafter the load
shall be increased at steady rate to minimum UTS and held for one minute.
The Conductor sample shall not fail during this period. The applied load
shall then be increased until the failing load is reached and the value
recorded.
5.1.2 D.C. Resistance Test on Stranded Conductor
On a conductor sample of minimum 5m length two contact-clamps shall be
fixed with a predetermined bolt torque. The resistance shall be measured
by a Kelvin double bridge or using micro ohm meter of suitable accuracy by
placing the clamps initially zero metre and subsequently one metre apart.
The test shall be repeated at least five times and the average value
recorded. The value obtained shall be corrected to the value at 20 0C as per
IS:398-(Part-IV)/(Part-V). The resistance corrected at 20deg C shall conform
to the requirements of this Specification.
5.1.3 Coefficient of linear expansion for core/core strands
The temperature and elongation on a sample shall be continuously
measured and recorded at interval of approximately 15 degree C from 15
degree C to maximum continuous operating temperature corresponding to
rated current(720A) by changing the temperature by suitable means.
Coefficient of linear expansion shall be determined from the measured
results.
5.1.4 Breaking load test on Aluminium Alloy & Core strands and
D.C Resistance test on Aluminium Alloy wire
The above tests shall be carried out as per IEC: 888/889 and the results
shall meet the requirements of the specification.
*****
TECHNICAL SPECIFICATIONS
FOR
1.0 SCOPE
2.0 STANDARDS
3.0 MATERIALS
SECTION – V
SCOPE:
1.0 This Specification provides for the manufacture, testing before despatch
supply and delivery of 7/3.15mm ground wire 1100 NEWTON/Sq.mm
quality (grade 3 as per IS 12776 of 1989 for the purpose of earthing and
protection of power transmission lines as per the particulars given in
Appendix – I attached. The ground wire shall consist of standard
galvanised steel wires. The other applicable standards are IS-209/2979,
2.0 STANDARDS:
The ground wire shall comply in all respects with the latest edition of IS
12776/1989 (with latest amendments).
3.0 MATERIALS:
The materials offered shall be of best quality and workmanship. The steel
wire (strands) shall be manufactured from steel produced by the suitable
process. The steel wire shall not contain sulphur and phosphorous
exceeding 0.05% each.
The steel wire shall be evenly and uniformly coated with Zinc complying
with IS-209/1979 specification for Zinc (revised)-99.99% grade and zinc
coating shall conform to heavy type coating as per IS-4826/1979
The wire when tested in accordance with the IS-1521 or any one-gauge length
of 100 mm, shall have the minimum-breaking load of strand as specified in
Appendix-I, shall be as follows. The tensile strength of the finished strand
shall not be less than 95% of the aggregate of the single wires.
The successful tenderer shall submit seven copies of stringing charts for
earth wire showing initial and final sags and tensions for various
temperatures and spans. One set of chart shall be in ink or tracing.
TECHNICAL SPECIFICATIONS
FOR
DISC INSULATORS
&
SECTION-VI (A)
TECHNICAL SPECIFICATION FOR DISC / LONG ROD INSULATORS FOR
USE ON TRANSMISSION LINES
1.0 SCOPE
2.0 STANDARDS
8.0 TESTS
9.0 INSPECTION
10.0 DOCUMENTATION
1.0 SCOPE:
1.1 This specification provides for design, manufacture, engineering, inspection and
testing before dispatch, packing and delivery F.O.R. (destination) DISC
INSULATORS / LOG ROD INDULATORS as per technical requirements
furnished in this specification. These insulators are to be used in suspension and
tension insulator strings for suspension and anchoring of conductors on EHV
transmission towers of KPTCL.
1.2 The insulators shall conform in all respects to high standards of engineering,
design, workmanship and latest revisions of relevant standards at the time of offer
and purchaser shall have the power to reject any work or material which, in his
judgement, is not in full accordance therewith.
2.0 STANDARDS
2.1 Except as modified in this specification, the disc insulators shall conform to the
following Indian standards which shall mean latest revisions and amendments.
Equivalent International and Internationally recognized standards to which same
of these standards generally correspond are also listed below:
Sl. Indian
Title International standard
No. Standard
Method for chemical analysis of
1 IS: 206
slab zinc
2 IS: 209 Specification for Zinc BS:3436
Porcelain insulators for overhead BS:137 (I&II)
3 IS:731 power lines with the nominal IEC:274
voltage greater than 1000 V. IEC:383
IS:2071 Method of High voltage Testing
Part(I)
4
Part (II)
Part(III)
5 IS:2121 Specification of Conductors and
Reference
Name and Address
Abbreviation
2.3 Insulators conforming to any other international standards are also acceptable
provided always that such standards are equivalent to or better than the
corresponding standards specified in 2.1 above However in such an event the
salient points of Comparison between the standards adopted and the standards
quoted herein shall be detailed in the appropriate schedule. Two copies authentic
English version of such standards shall be submitted along with the offer.
3.0 PRINCIPAL PARAMETERS:
3.1 Details of disc Insulators:
3.1.1 The insulator strings shall consist of standard discs for a three
phase. 50 HZ, effectively earthed 220 or 110 or 66KV transmission
system in a moderately polluted atmosphere. The discs shall be
cap and pin, ball and socket type.
3.1.2 The Size of disc insulator, minimum creepage distance, the number
to be used in different type of strings, their electromechanical
strength and mechanical strength of insulator string along with
hardware shall be as follows:
Ball pins shall be made with drop forged steel and caps with malleable cast iron. They
shall be in one single piece and duly hot dip galvanized. They shall not contain parts
or pieces joined together, welded, shrink fitted or by any other process from more than
one piece of material. The pins shall be of high tensile steel, drop forged and heat-
treated. The caps shall be cast with good quality black heart malleable, cast iron and
annealed. Galvanizing shall be by the hot dip process with a heavy coating of zinc of
very high purity. The bidder shall specify the grade, composition and mechanical
properties of steel used for caps and pins.
The design of the insulator shells shall be such stresses due to expansion and
contraction in any part the insulator shall not lead to deterioration. Shells with
cracks shall be eliminated by temperature test followed by mallet test. Shells
shall dried under controlled conditions of humidity temperature.
i. The Pin and cap shall be designed to transmit the mechanical stresses to the
shell by compression and develop uniform mechanical strength in the
insulator. The cap shall be circular with the inner and outer surfaces
concentric and of such design that it will not yield or distort under loaded
conditions. The head portion of the pinball shall be suitably designed so that
when the insulator is under tension the stresses are uniformly distributed over
the pinhole portion of the shell. The pinball shall move freely in the cap
socket either during assembly of a string or during erection of string or when a
string is placed in position.
ii. Metal caps shall be free from cracks, seams, shrinks, air holes, blow holes and
rough edges. All metal surfaces shall be perfectly smooth with no projecting
parts or irregularities which may cause corona. All load bearing surfaces
shall be smooth and uniform so as to distribute the loading stresses uniformly.
Pins shall not show any microscopically visible cracks, inclusions and voids.
4.4.4 GALVANISING:
All ferrous parts shall be hot dip galvanized in accordance with IS:2629. The zinc
to be used for galvanizing shall conform to grade Zn 99.5 as per IS-209. The
zinc coating shall be uniform, smoothly adherent, reasonably bright, continuous
and free from impurities such as flux, ash, rust strains, bulky white deposits and
blisters. Before ball fittings are galvanized, all die flashing on the shank and on
the bearing surface of the ball shall be carefully removed without reducing the
designed dimensional requirements.
4.4.5 CEMENTING:
The insulator design shall be such that the insulating medium shall not directly
engage with hard metal. The surfaces of porcelain and coated with resilient paint
537456407.doc Page 147
to offset the effect of difference in thermal expansions of these materials. A zinc
sleeve measuring 5mm thick and 20mm length shall be provided on the pin as
shown in the drawing Section-XII.
The insulator strings shall be formed with standard discs described in this
specification for use on 3 phase, 220/110/66KV, 50 Hz effectively earthed systems
in an with pollution level as indicated in project synopsis atmosphere. Suspension
insulator strings for use with suspension / tangent towers are to be fitted with discs
of 90 KN EMS rating while tension insulator strings for use with Anchor / Tension
towers are to be fitted with discs of 120/90 KN EMS rating.
Suspension Tension
220KV 110KV 66KV 220KV 110KV 66KV
i. Lightning Impulse withstand voltage
(dry) KV peak. 1050 550 325 1050 550 325
ii. Power frequency withstand voltage
(wet) KV r.m.s. 460 230 140 460 230 140
iii. Corona extinction voltage – KV
(rms) 176 - - 176 - -
iv. Max. RIV for complete string
including corona rings, arcing horns, clamps 500 - - 500 - -
etc, at 1.1 times maximum line to ground
voltage (micro-volts)
v. Mechanical failing load for each sting 120 90 90 120 90 90
KN.
vi. No deformation load for each string - - - - - -
Kgf.
vii. Max. voltage across any disc. 13% 13% 13% 13% 13% 13%
4.12.2 Insulator units after assembly shall be concentric coaxial within limits as
permitted by Indian standards
4.12.3 The string design shall be such that when units coupled together there shall be
contact between shell of one unit and metal of the adjacent unit.
5.1.2 Insulator shall have normal sheds/alternate sheds with good self-cleaning properties.
Insulator shed profile, spacing projection etc. shall be strictly in accordance with
the recommendations of IEC-815
5.1.4 The prices of these items shall be considered as included in the price of long rod
insulators.
5.2 The size of long rod insulator, minimum creep age distance, the number to be used
in different type of strings, their electromechanical strength and mechanical
strength of insulator string along with hard ware shall be as follows.
The porcelain used in the manufacture of the shells shall be ivory white,
nonporous, of high dielectric, mechanical and thermal strength, free from internal
stresses, blisters, laminations, voids, foreign matter, imperfections or other
defects which might render it in any way unsuitable for insulator shells.
Porcelain shall remain unaffected by climatic conditions, ozone, acid, alkalis,
zinc or dust. The manufacturing shall be by the wet process and impervious
character obtained by through verification.
Ball pins shall be made with drop forged steel and caps with malleable cast iron.
They shall be in one single piece and duly hot dip galvanized. They shall not
contain parts or pieces joined together, welded, shrink fitted or by any other
process from more than one piece of material. The pins shall be of high tensile
steel, drop forged and heat-treated. The caps shall be cast with good quality black
heart malleable, cast iron and annealed. Galvanizing shall be by the hot dip
process with a heavy coating of zinc of very high purity. The bidder shall specify
the grade, composition and mechanical properties of steel used for caps and pins.
7.1 GENERAL:
i. All raw materials to be used in the manufacture of these insulators shall be
subject to strict raw materials quality control and to stage testing / quality
control during manufacturing stage to ensure the quality of the final end
product. Manufacturing shall conform to the best engineering practices
adopted in the field of extra high voltage transmission. Bidders shall
therefore offer insulators as are guaranteed by them for satisfactory
performance on Transmission Lines.
ii. The design, manufacturing, process and material control at various stages
be such as to give maximum working load, highest mobility, best
resistance to corrosion, good finish, elimination of sharp edges and corners
to limit corona and radio interference voltages.
The design of the insulator shells shall be such stresses due to expansion and
contraction in any part the insulator shall not lead to deterioration. Shells with
cracks shall be eliminated by temperature test followed by mallet test. Shells
shall dried under controlled conditions of humidity temperature.
ii) Metal caps shall be free from cracks, seams, shrinks, air holes, blow
holes and rough edges. All metal surfaces shall be perfectly smooth with no
projecting parts or irregularities which may cause corona. All load bearing
surfaces shall be smooth and uniform so as to distribute the loading stresses
uniformly. Pins shall not show any microscopically visible cracks, inclusions and
voids.
All ferrous parts shall be hot dip galvanized in accordance with IS:2629. The zinc
to be used for galvanizing shall conform to grade Zn 99.5 as per IS-209. The
zinc coating shall be uniform, smoothly adherent, reasonably bright, continuous
and free from impurities such as flux, ash, rust strains, bulky white deposits and
blisters. Before ball fittings are galvanized, all die flashing on the shank and on
the bearing surface of the ball shall be carefully removed without reducing the
designed dimensional requirements.
7.4.1 CEMENTING
The insulator design shall be such that the insulating medium shall not directly
engage with hard metal. The surfaces of porcelain and coated with resilient paint
to offset the effect of difference in thermal expansions of these materials. A zinc
sleeve measuring 5mm thick and 20mm length shall be provided on the pin as
shown in the drawing Section-XII.
7.9 Interchangeability:
The long rod insulator with ball and socket connection shall be of standard
design suitable for use with the hardware fittings of any make conforming to
relevant IS/IEC standards.
8.0 TESTS:
8.1 The following tests shall be carried out on the insulator string
and unit insulators.
b) Thermal mechanical
Performance test : IEC:575
h) Thermal mechanical
Performance test : IEC:575
8.8.4 On the complete porcelain long rod insulator string with hardware
fittings :
i) Power frequency voltage withstand ) IEC-383
test with corona control rings )
and under wet condition )
j) Switching surge voltage withstand )
test under wet condition )
(400KV only) )
8.8.5 All the type tests given under clause No.6.8.1 shall be conducted on Single
suspension and Double tension Insulator strings along with hardware fittings.
The purchaser reserves the right for carrying out any other tests of a reasonable
nature at the works of the supplier or at any other recognized laboratory / research
institute in addition to the above mentioned type, acceptance and routine tests at
the cost of the purchaser to satisfy that the materials complies with the intent of
this specification.
9.0 INSPECTION:
9.1.1 Purchaser and its representative shall at a times be entitled to have access to the
works and to all places of manufacture where insulators are manufactured and the
supplier shall afford all facilities to them for unrestricted inspection of the works,
inspection of materials, inspection of manufacturing process of insulators for
conducting necessary tests and specified herein.
9.1.2 The supplier shall keep the Purchaser informed in advance of the time of starting
and progress of manufacture of insulators in various stages so that arrangements
could be made for inspection.
9.1.3 No material shall be dispatched from its point of manufacture unless the material
has been satisfactorily inspected and tested.
9.2.1 Each disc insulator shall be legibly and indelibly marked with the trademark of the
supplier, the year of manufacture, the guaranteed combined mechanical and
electrical strength in Kilo-Newton abbreviated by ‘KN’ to facilitate easy
identification and proper use.
9.2.2 The marking shall be on porcelain for porcelain insulators. The marking shall be
printed and not impressed and the same shall be applied before firing.
9.3.1 The bidder hereunder shall invariably furnish following information’s along with his
offer, failing which the offer shall be liable for rejection.
i. Statement giving list of important raw materials, names of sub-suppliers
for the raw materials, list of standard, according to which the raw materials
are tested, list of tests, normally carried out on raw material in presence of
Bidder’s representative, copies of test certificates.
ii. Information and copies of test certificates as in (i) above in respect of
bought out material.
iii. List of manufacturing facilities available.
iv. Level of automation achieved and list of areas where manual processing
exists.
v. List of areas in manufacturing process, where stage inspections are
normally carried out in quality control and details of such tests and
inspections.
vi. Special features provided in the equipment to make it maintenance free.
vii. List of testing equipment available with the Bidder for final testing of
equipment specified and test plant limitation, if any, vis-à-vis the type,
special, acceptance and routine tests specified in the relevant standards.
These limitations shall be very clearly brought out in schedule of
deviations from specified test requirements.
9.3.2 The supplier shall within 30 days of placement of order submit the
following information to the owner.
i. List of raw materials and the names of sub-suppliers selected from those
furnished along with the offer.
10.0 Documentation:
10.1 The bidder shall furnish full description and illustrated catalogues of insulators
offered along with the offer.
10.2 TEST REPORTS:
i. Four copies of type test reports shall be furnished to the purchaser’s within
one month conducting the tests. One copy will be return duly certified by
the purchaser’s to the supplier within three weeks there afterwards and
receipt of the same supplier shall commence with the commercial
production of the concern material.
ii. Four copies of acceptance test reports shall furnished to the purchaser’s.
One copy will returned, duly certified by the purchaser’s and only there
after shall the materials be dispatched.
iii. All records of routine test reports shall maintained by the supplier at his
works for periodic inspection by the purchaser’s.
iv. All test reports of tests conducted during manufacture shall be maintained
by the supplier. These shall be produced for verification as and when
requested for by the purchaser.
Under the conditions as specified in (2) above, the insulator string along with
complete hardware fittings shall have a radio interference voltage level below 500
micro volts at one MHz when subjected to 50 Hz AC voltage of 1.1 times
maximum line to ground voltage under dry condition. The test procedure shall be
in accordance with IS:8263/IEC:437
The complete insulator string along with its hardware fitting excluding arcing
horn corona controlling/grading ring and suspension assembly/dead end assembly
shall be subject to a load equal to 50% of the specified minimum ultimate tensile
strength (UTS) which shall be increased at steady rate to 68% of the minimum
UTS specified. The load shall be held for five minutes and then removed. After
removal of the load, the string components shall not show any visual deformation
and it shall be possible to disassemble them by hand. Hand tools may be used to
remove cotter pins and loosen the nuts initially. The string shall then be
reassembled and loaded to 50% of UTS and the load shall be further increased at a
steady rate till the specified minimum UTS and held for one minute. No fracture
should occur during this period. The applied load shall then be increased until the
failing loads reached and the value recorded.
The suspension string shall be tested in suspension mode and tension string in
tension mode itself in laboratory span of minimum 30 meters. In the case of
suspensions string a load equal to 600 Kg. Shall be applied along with the axis of
the suspensions string by means of turn buckle. The insulators string along with
hardware fittings and two sub conductors throughout the duration of the test
vibration dampers shall not be used on the test span. Both the sub-conductors
shall be vertically vibrated simultaneously at one of the resonance frequencies of
the insulator string (more than 10HZ) by means of vibration inducing equipment.
The amplitude of vibration at the antipode point nearest to the string shall be
measured and the same shall not be less than 120.4 being the frequency of
vibration. The insulator strings shall be vibrated for five million cycles then
rotated by 90 deg and again vibrated for 5 million cycles without any failure, after
the test the disc insulators shall be examined for looseness of pins and cap or any
crack in the cement. The hardware fittings shall be examined to fatigue fatter and
mechanical strength test. There shall be no deterioration of properties of hardware
components and disc insulators after the vibration test. The insulators shall be
subjected to the following tests as per relevant standards.
Acceptance Criteria:
An insulator shall be deemed to have met the requirement of this test if, having
been successfully subjected to the ten impulse flashovers, the arithmetic mean of
the three subsequent dry/power frequency voltage flashover values equals or
exceeds 95% of the rated dry power frequency flashover voltage.
a) It has not flash over when the oscillogram or peak voltage indicator shows
a marked reduction in voltage.
or
b) Any one of the subsequent three dry power frequency voltage flashover
value is less than 80% of the value specified.
Failure of any one unit either in the steep wave front or subsequent low frequency
voltage test shall cause for testing on double number of units.
The disc insulator shall be held over a polarized light source and the stress lines
viewed thereon. There shall be no uneven stress distribution in the toughened
glass insulators. This shall be carried out on 100% glass shells.
2.3 Hydraulic Internal Pressure Test on Shells (only for Disc
Insulator):
The test shall be carried out on 100% shells before assembly. The details
regarding test will be as discussed and mutually agreed to by the Supplier and
Purchaser in Quality Assurance Programme.
Where
b) The minimum sample size shall be taken as 20 for disc insulator units and
5 units for long rod units.
c) The individual electromechanical failing load shall be at least equal to the
rated value. Also puncture shall not occur before the ultimate fracture.
2.7 IR Measurements:
IR Measurement shall be carried out by the instrument operating at 1 KV DC. IR
value when measured under fair weather condition, shall not be less than 50 M-
ohm.
The Impact test shall be carried out in accordance with ANSI-C-29.2 Clause 8.2.8
with the following modification.
The breaking point of the pendulum shall be so adjusted that, when released the
copper nose will strike the outer rim of the shell or the most protruded rim of the
shell squarely in direction parallel to the axis of the unit and towards the cap.
The test specimen shall receive an impact of 7 N-m for 120 kN Disc & 10N-m for
160 kN Disc releasing the pendulum.
Similarly using a horizontal scale with veridical slider the radial run out shall be
measured. The slider shall be positioned on the scale to establish contact with the
circumstance of the disc insulator and disc insulator rotated on its future always
maintaining the contact. After one full rotation of the disc the maximum and
minimum position the slider has reached on the scale can be found out.
Difference between the above two readings shall satisfy the guaranteed value for
axial run out.
Crack detection test shall be carried out on each ball and pin before assembly of
disc unit. The supplier shall maintain complete record of having conducted such
tests on each and every piece of ball pin. The bidder shall furnish full details of
the equipment available with him for crack test and also indicate the test
procedure in detail.
TECHNICAL SPECIFICATIONS
FOR
SILICON RUBBER COMPOSITE INSULATOR
SECTION-VI (B)
TECHNICAL SPECIFICATIONS FOR SILICON RUBBER COMPOSITE
INSULATOR FOR USE ON TRANSMISSION LINES
your bid.
1. All the drawings i.e., elevation, side view, plan cross sectional view
shall be submitted.
process and field quality plan with the technical bid. The flow chart
3. The bidder shall have to submit all the Design test and type test
reports for having designed and tested for the offered items. In
5. All the points other than GTP, which are asked to confirm in
7. Please note that the evaluation will be carried out on the strength
8. The bidder shall bring out all the technical deviation/s only as per
(For Supply)
SECTION-VI (B)
TECHNICAL SPECIFICATION FOR SILICON RUBBER COMPOSITE
INSULATORS FOR USE ON TRANSMISSION LINES
1. SCOPE
2. PRE-QUALIFYING REQUIREMENTS.
3. STANDARDS
4. SERVICE CONDITIONS
NSULATORS
COMPOSITE
11. INTERCHANGIABILITY
14. WORKMANSHIP
15. MARKINGS
21. DOCUMENTATION
22. DRAWINGS.
23. DEVIATIONS
24. MAINTENANCE.
SECTION-VI (B)
TECHNICAL SPECIFICATION FOR SILICON RUBBER COMPOSITE
INSULATORS FOR USE ON TRANSMISSION LINES
(120KN & 90KN EMS)
5.0 SCOPE:
1.3 This specification provides for design, manufacture, engineering,
inspection and testing before dispatch, packing and delivery F.O.R.
(destination) of SILICON RUBBER COMPOSITE as per
technical requirements furnished in this specification. These
insulators are to be used in suspension and tension insulator
strings for suspension and anchoring of conductors on EHV
transmission towers of KPTCL.
7.0 STANDARDS
7.1 Except as modified in this specification, the SILICON RUBBER
COMPOSITE insulators shall conform to the following Indian
standards which shall mean latest revisions and amendments.
Equivalent International and Internationally recognized standards
to which same of these standards generally correspond are also
listed below:
Indian
Sl. International
Standa Title
No. standard
rd
International Electro- IEC 60050 –
1 technical Vocabulary Chapter 471
Insulators
2 Method for chemical
IS: 206
analysis of slab zinc
3 IS: 209 Specification for Zinc BS:3436
Composite insulators
for A.C. Overhead
4 power lines with the IEC:61109-
nominal voltage 1992
greater than 1000 V.
Method of High IEC:60060-1 -
IS:207 voltage Testing General
1 definition& test
5 Part(I) requirements.
Part (II) IEC:60060-2 –
Part(III) Measuring
systems.
6 IS:212 Specification of
1 Conductors and
Earth-wire
Accessories for
Reference
Name and Address
Abbreviation
British Standards, British Standards
BS institution, 101, Pentonvile Road, N-19,
ND, UK
International Electro technical
Commission Bureau Central de la
IEC/CISPR Commission Electro Technique
International 1, Rue de verembe Geneva
Switzerland
Bureau of India Standards,
Manak Bhavan,
IS
9, Bahadur Shah Zafar Marg,
New Delhi – 110 001 India
International Organisation for
standardization
Danish Board of Standardization
ISO
Dansk Standardisering Street,
Aurehoegvej – 12 DK – 2900
DENMARK
iii. 39 m/sec in the coastal areas, the Western Ghats and the
plains of northeastern Karnataka ( Bidar, Gulbarga &
Raichur).
TABLE:1
Minimum Electro-
Size of disc creepage No. of mechanical
Sl. Type of
insulator(mm distance of Standard Strength of
No. String
) each disc discs Insulator string
(mm) in KN
220 KV
Double
Tensile
110 KV
Double
Tensile
66KV
Double
Tensile
TABLE -2
viii. Lightning Impulse
withstand voltage 1050 550 325 1050 550 325
(dry) KV peak.
460 230 140 460 230 140
ix. Power frequency
withstand voltage (wet) KV 176 - - 176 - -
r.m.s.
x. Corona extinction 500 - - 500 - -
voltage – KV (rms)
xi. Max. RIV for complete
string including corona rings, 120 90 90 120 90 90
arcing horns, clamps etc, at 1.1
times maximum line to ground - - - - - -
voltage (micro-volts)
xii. Mechanical failing load 13% 13% 13% 13% 13% 13%
for each sting KN.
xiii. No deformation load for
each string Kgf.
xiv. Section length of Silicon rubber Composite insulator string, minimum creepage
distance required, no. of units per string & EMS of each unit is tabulated in Table -3.
Note: The section length of insulators mentioned above is the required length of
insulator corresponding to equivalent length of disc insulator string. The bidder may
offer insulator varying in length with that mentioned above. However, in such a case
the total length of string including hardware fittings shall be within the maximum
and minimum limits specified in the drawing (inclusive of tolerances on hardware and
insulator ) attached to this specification.
6.3 DRAWINGS:
5.2.1 The General arrangement drawings in respect of 220KV, 110KV & 66KV
strings mentioned above are enclosed at the end of this specification. These
drawings are attached only for the information and guidance of the
manufacturer.
5.2.2 The manufacturer shall furnish outline drawing of the insulator and component
drawing of end fittings, Corona control ring indicating all dimensions. All
drawings shall be neatly arranged and all drafting and lettering shall be
standard and legible. Dimensions shall be in SI units. The drawings shall give
the following information.
1) The bill of material indicating quantity, nature grade and reference standard
of the material used for various parts,
2) Technical details like Section length of insulator, dry arcing distance,
creepage distance, ball and socket designation, identification mark on the
insulator.
3) Mechanical characteristics like specified mechanical load (SML) , Routine test
load (RTL) and weight of insulator.
4) Electrical characteristics like One minute Power frequency withstand voltage
under dry and wet conditions, lightening impulse withstand voltage.
Switching surge impulse withstand voltage. Corona inception and extinction
voltage.
5) After award of contract the bidder shall submit 3 sets of drawings to CEE
(P&C) , Kaveri Bhavan , Bangalore, giving details as mentioned above for
7.1 GENERAL:
7.2 Design:
Silicon rubber Composite insulator shall be designed to meet the
high quality, safety and reliability capable of withstanding a wide
range of system and environmental conditions mentioned in
section 3,4 & 5 above. Composite insulators shall consists of Three
Parts, at least two of which are insulating parts:-
7.2.1 Core:
The core shall be glass-fibre reinforced epoxy resin rod (FRP) of high di-
eletric and mechanical strength. Both, glass fibre and Epoxy resin
matrix material shall be optimized in the FRP rod. Process used for
manufacturing should yield a uniform material structure and
optimum control and regulation of the quality-influencing
parameters such as homogeneity and uni-directionality of the
glass fibre across the cross section of the rod. Glass fibers with low
content in alkalies shall be boron free ‘E’glass or Boron free
Electrically corrosion resistance(ECR) glass. Use of resin with
hydrolysis trend due to water penetration should be prevented i. e.
matrix of the FRP rod shall be Hydrolysis resistant. Suitability of Epoxy
matrix as well as interface between matrix and fibres is to be
considered as design parameter to prevent brittle fracture. The FRP rod
should be void free and shall be manufactured through Pultrusion
process and shall not be of draw forming process.
7.2.2 Housing:
The core of the composite insulator shall be completely covered by a
continuous housing consisting of a seamless sheath & -weathershed of
The composite insulators shall be socket and ball type with the
necessary coupling arrangement such that pin shall move freely in the
cap socket either during assembly of a insulators or during erection
of insulators or when a insulators is placed in position but do not get
disengaged while in service under various operating and atmospheric
conditions.
The socket & ball type metal end fittings shall be designed to transmit
the mechanical stresses to the to the core & the end fittings by
compression and develop uniform mechanical strength in the insulator
Material and methods used in the fabrication of metal parts shall be
11.0 INTERCHANGEABILITY:
The composite insulators including the ball socket connections shall be
standard design suitable for use with the hardware fittings of any make
conforming to relevant Indian standards.
The length and other dimensions should be such that it should be
substituted by other conventional type Porcelain insulators.
14.0 WORKMANSHIP:
16.0 PACKING:
All insulators shall be packed in strong corrugated box of
minimum 7 ply duly paletted or wooden crates. The gross weight of
17.1 INSPECTION:
Inspection includes the performance of acceptance, type and
design tests. KPTCL reserves the right to carry out design and type
tests to check conformity of the material with the proto type unit
previously approved.
17.2 TESTS:
Insulators offered shall be manufactured with the same
configuration & raw materials as used in the insulators for which
Design & type test reports are submitted. the manufacturer shall
submit a certificate for the same . The design and type test reports
submitted shall not be more than five years old.
No material shall be dispatched from its point of manufacture
before it has been satisfactorily inspected, tested, and necessary
dispatch instructions are issued in writing, except for the cases
where waiver of inspection is granted by competent authority of
the Purchaser, and even in this case also written dispatch
instructions will be issued. Any dispatches before the issue of
Dispatch Instructions in writing will be liable for rejection and
non-acceptance of the materials by the consignee.
The acceptance of any quantity of material shall in no way relieve
the Bidder of any of his responsibilities for meeting all
12 Recovery of -Annexure-A
Hydrophobicity test
All the above type test shall be conducted on Single ‘I’ suspension and
If any one insulator or metal part fails to comply with the sampling
tests, Re-testing procedure shall be as per Clause 7.6 IEC:61109.
c) The bidder should have all the routine and acceptance testing
facilities, in house in accordance with IEC:383 & 61109.
Manufacturers of foreign origin shall, in addition to the above,
also have arrangements in India, either at works of their
authorized representative/licenses or in the NABL lab. like
CPRI, IISC, ERDA etc. for conducting sampling test in
accordance with IEC : 383 & 1109.
ii) Type test certificates of the raw material and bought out accessories.
iii) Quality assurance plan (QAP) with hold points for purchaser's
inspection.
21.0 DOCUMENTATION
21.1 Two sets of type test reports, duly approved by the Purchaser shall
be submitted by the Bidder, before commencement of supply. A
copy of acceptance and routine test certificates, duly approved by
the purchaser shall accompany the dispatch consignment.
21.2 The bidder shall submit the drawings in triplicate for the offered
insulators well within the commencement period for approval. The
manufacturing of the insulator shall be strictly in accordance with
the approved drawings and no deviation shall be permitted without
the written approval of the Purchaser. All manufacturing and
fabrication work in connection with the insulator prior to the
approval of the drawing shall be at supplier’s risk.
21.3 Approval of drawings etc. by the purchaser shall not relieve the
Bidder of his responsibility and liability for ensuring correctness
and correct interpretation of the latest revision of applicable
standards, rules and codes of practices. The insulator shall conform
in all respects to high standards of engineering, design,
workmanship and latest revisions of relevant standards in vogue on
the day of opening of the Technical Bid and purchaser shall have
the power to reject any work or material which in his judgment is
not in full accordance therewith.
21.4 In case the bidders offers Silicon rubber composite insulators
tested and supplied to other utilities , and are in service, the
TECHNICAL SPECIFICATIONS
FOR
SECTION-VII
1.0 SCOPE
2.0 STANDARDS
3.0 MATERIALS
5.0 TESTS
7.0 INSPECTION
8.0 PACKING
1.0 SCOPE:
3.0 MATERIAL:
All ferrous metal parts except those made of stainless steel shall be
protected by hot dip galvanizing. Spring washers shall be electro
galvanized.
All castings shall be free from blowholes and other casting defects such
as cracks etc. The surface shall be as smooth as possible.
i) This shall be suitable for jointing the two ends of the power
conductor. The joint shall have a conductivity of an equivalent
length of the conductor. The joint shall not permit slipping of,
damage to or failure of the complete conductor or any part thereof
at a load of not less than 95% of the ultimate tensile strength of
the conductor. The electrical resistance of the joint after
installation shall not exceed 75% of the measured resistance of the
equivalent length of the conductor.
ii) The components of the joint shall consist of steel and Aluminium
sleeves for joint compression of the steel core conductors and
aluminium conductors respectively. The steel sleeve shall not
crack or fail during compression. The steel sleeve shall be hot dip
galvanized. The Aluminium sleeve shall be manufactured and
extruded out of EC grade Aluminium with a purity of not less than
99.5%. Tapered Aluminium filler plugs shall be provided at the
line of demarcation between compression and non-compression
zone.
ii) The compressed conductor with the repair sleeve shall not permit
damage or failure of the conductor at a load of not less than 95%
of the ultimate tensile strength of the conductor. The electrical
resistance of the repaired portion of the conductor shall not exceed
75% of the measured resistance of an equivalent length of the
conductor.
5.0 TESTS:
a) Visual examination.
b) Verification of dimensions.
c) Tensile strength test.
d) Electrical resistance test.
e) Slip strength test.
f) Bend test.
g) Resilient test.
a) Visual examination.
b) Verification of dimension.
c) Resonance frequency test.
d) Fatigue test.
e) Mass pull off test.
f) Dynamic characteristic test.
g) Damping efficiency test.
h) Clamp slip test.
i) Torque test.
j) Galvanising electroplating test.
k) Magnetic power loss test.
l) Radio interference voltage test.
a) Visual examination.
b) Dimensional verification.
c) Failing load test.
d) Galvanising test.
a) Visual examination.
b) Verification of dimensions.
c) Tensile strength test.
d) Electrical resistance.
e) Slip strength test.
a) Visual examination.
b) Dimensional verification.
7.0 INSPECTION:
8.0 PACKING:
******
TECHNICAL SPECIFICATIONS
FOR
1.0 SCOPE
2.0 STANDARDS
3.0 MATERIALS
7.0 TESTS
1.0 SCOPE:
2.0 STANDARDS:
The fittings and accessories shall comply in all respects with relevant
Indian Standard Specification, IS 2121-1962 and IS 2486 with latest
amendments. The Indian Standards wherever mentioned in this
specification shall mean only the latest edition of the relevant standards
including latest amendments.
3.0 MATERIALS:
4.1 All parts of fittings shall be suitable for use in atmospheric conditions given in Part-
I (General) of Technical Specifications and shall be inherently resistant to
atmospheric corrosion or be suitably protected against corrosion both during storage
and in service.
All ferrous metal parts except those made of stainless steel shall be protected by hot
dip galvanizing. Spring washers shall be electro galvanized.
The threads in nuts and in tapped holes shall be cut after galvanizing and shall be
well lubricated or greased. All other threads shall be cut before galvanizing. The
bolt threads shall be under cut to take care of the increase in diameter due to
galvanising and if required should be return after galvanizing.
All castings shall be free from blowholes and other casting defects such as cracks.
The tension joints shall be so designed that when installed they withstand at least
95% of the minimum-breaking load of the ground wire.
All fittings shall be so designed that the effects of vibration both on the
conductor and the fitting itself are minimized.
iii) The messenger cable of the vibration damper shall be made of high
strength steel with a minimum strength of 136 Kg/mm and
performed in order to prevent subsequent drop of weights in
service. The number of strands in the messenger cable shall be
19. Clamping bolts shall be provided with self-locking nuts
designed to prevent corrosion of the threads or loosening during
service. The messenger cable shall be suitably and effectively
sealed to prevent corrosion.
iv) The damper mass shall be made of hot dip galvanized mild
steel/cast iron or a permanent mould cast zinc alloy. All castings
shall be free from defects such as cracks shrinkage, inclusions and
blowholes etc. The inside and outside surfaces of the damper
masses shall be smooth.
vi) The vibration analysis of the system with and without damper,
dynamic characteristic of the damper shall have to be submitted
by Bidder along with the bid. The vibration analysis and damping
design shall be suitable to the 220-kV/110-kV/66 kV system now
offered for construction.
ii) These clamps shall give adequate area of support without any slip
to the ground wire under normal working tension and vibration
conditions.
iii) The complete tension hardware assembly shall be so designed as
to avoid undue bending in any part of the clamp and shall not
produce any hindrance to the movements of the clamp in
horizontal and vertical direction.
5.1 General:
i) All the equipments shall be of the latest design and shall conform
to the best modern engineering practice adopted in the field of
extra high voltage engineering. The bidder shall offer only such
equipment as are guaranteed for satisfactory and suitable
performance of 220 kV transmission lines.
ii) The design, manufacturing process and quality control of all the
materials shall be such as to give maximum factor of safety,
maximum possible working load, highest mobility, elimination of
sharp edges and corners to limit corona and radio interference
best resistance to corrosion and a good finish.
5.2 Galvanising:
5.3 Castings:
ii) The design of metal parts and their mating surfaces in contact
with power conductors shall be such as to prevent corrosion of the
537456407.doc Page 252
contact surface and to maintain good electrical contact under all
operating conditions.
ii) ‘D’ shackles, clevis ‘U’ bolts, cotter pins and other components
shall be manufactured from drop forged steel conforming to IS
2004/1978 or equivalent thereof.
iii) Bolts, nuts and washers shall be as per IS 1367 and shall be of
reputed makes such as GKW, TATA brands etc.
iv) All split pins shall be of stainless steel.
5.6 Interchangeability:
All components like design shall be interchangeable.
5.7 Compression Markings:
i) Die compression areas shall be clearly marked on components,
which are to be pressure compressed such as Mid-span
compression joints and tension hardwares. The marking shall be
an etched inscription with the words “COMPRESS FIRST” on
components, which are meant for continuous die compression.
Where components are designed for in termiltent die
compressions, the compression and non-compression zones shall
bear etched inscription such as “COMPRESS ZONE” and “NON-
COMPRESSION ZONE” distinctly with etched arrow signs
indicating the direction of compression and knurled marks
showing the end of the zones.
537456407.doc Page 253
ii) All inscriptions etched on metal shall be distinct, legible and shall
not wear out in the course of normal handling.
6.0 BID DRAWINGS:
i) The bidder shall furnish along with the bid the dimensional
drawings of all accessories and hardware’s.
ii) These drawings shall include the following information.
a) Dimensions.
b) Tolerances on dimensions.
c) Material designation used for different components with
reference to standards.
d) Fabrication details such as welds, finishes and coatings.
e) Catalogue or part numbers for each component and the total
assembly with bill of materials.
f) Identification marking.
g) Weight of individual components and total assembled weight.
iii) The assembly drawings shall include the following:
a) Brief installation instructions.
b) Design installation torque for the bolt or cap screw.
c) Withstand torque that can be applied to the bolt or cap screw
without failure of components or parts thereof.
d) Compression dies number with recommended compression
pressure.
e) Relevant technical details of significance.
7.0 TESTS:
******
TECHNICAL SPECIFICATIONS
FOR
1.0 SCOPE
2.0 STANDARDS
3.0 PRINCIPAL PARAMETERS
4.0 GENERAL TECHNICAL REQUIREMENTS
5.0 TESTS
6.0 INSPECTION
7.0 QUALITY ASSURANCE PLAN
8.0 DOCUMENTATION
9.0 PACKING AND FORWARDING
DETAILS OF TESTS
1.0 SCOPE:
Reference
Name and Address
Abbreviation
British Standards, British Standards Institution, 101,
BS
Pentonvile Road, N-19-NO UK.
International Electro technical Commission Bureau
Central de la commission Electro Technique
IEC/CISPR
International, 1, Rue de Verembe Geneva,
SWITZERLAND
IS Bureau of Indian Standards, Manak Bhavan, 9, Bahadur
Shah Zafar Marg, New Delhi-110 001, INDIA
ISO International Organization for Standardization, Danish
Board of Standardization Aurehoegvej-12 DK-2900
Helleprup DENMARK
NEMA National Electric Manufacturers Association 155, East
44th Street New York, NY USA, 10017
4.13 Galvanising:
4.13.1 Galvanizing shall satisfy the tests mentioned in IS: 2633. No
material shall be galvanised until all shop operations have been
NOTE: For electrical tests, the insulator string shall be mounted on a simulated
tower.
5.6.4 All the type tests given under clause No.5.6.1 above shall be conducted separately
on Single/Double Suspension and Single/Double tension insulator string along with
hardware fittings.
5.6.5 The tests specified under clause No.5.6.1 (e) and (f), that is, the voltage distribution
test and corona/RIV (Dry) test shall also be conducted on single suspension pilot
insulator string along with hardware fittings.
5.7 Acceptance Tests/Sample Tests:
5.7.1 On both suspension and tension hardware fittings:
IS: 2486
a) Visual examination
(Part-I)
IS: 2486
b) Verification of dimensions
(Part-I)
c) Galvanizing test/Electroplating
As per
d) Mechanical strength test of welded
Specification
Joint
e) Mechanical strength test for corona control BS: 3288 (Part-
rings/grading rings I)
f) Test on locking devices for ball and socket
IEC: 372(2)
coupling
DETAILS OF TESTS
TECHNICAL SPECIFICATIONS
FOR
SECTION-X(A)
SECTION-X (A)
2.0 Excavation:
2.1 Except as specifically otherwise provided, all excavation for footings
shall be made to the lines and grades of foundation. The excavation
walls shall be vertical and pit dimensions shall be such as to allow a
clearance of not more than 150 mm on all sides from the foundation
pad. All excavation shall be protected so as to maintain timbering,
shoring or casing, if necessary. Any sand, mud, silt or other
undesirable materials, which may have accumulated in the excavation,
shall be removed by the contractor before placing concrete.
3.4 The Owner may get certain foundations such as well type or pile type
constructed through other agencies. However, the contractor shall be
required to set the stubs for the same and coordinate his work with the
other agencies accordingly.
TECHNICAL SPECIFICATIONS
FOR
1.0 GENERAL
4.0 ASSEMBLY
SECTION – X (B)
1.0 General:
The details of the scope of erection work shall include the cost of
labour, and tools and plants like tension stringing equipment and
all other incidental expenses in connection with erection and
stringing work.
The contractor shall be responsible for transportation of all
materials to the site, proper storage and preservation at their own
cost till such time the erected line is taken over the Owner.
Similarly the Contractor shall be responsible for transportation,
proper storage, safe custody, loss or damage of all materials for
incorporation in the lines and shall maintain and render proper
account for all such materials lost or damaged during storage and
erection.
The Contractor shall set up required number of stores along the
line and the exact location of such stores shall be discussed and
agreed to between the contractor and the owner.
If any defects are found in case of hot-dip galvanized members, the
members if acceptable to Owner shall be repaired by applying zinc
rich protection paint.
6.1 General:
The erection of conductors shall be done in 4 stages as follows:
a) Delivery of conductors at site
b) Running out (also called paying out) and stringing
c) Tensioning and sagging, and
d) Clipping-in.
6.5 Jointing:
i) All joints on the earthwire and conductor shall be of
compression type, in accordance with the recommendations
of the manufacturer for which all necessary tools and
equipment like compressors, dies, etc. shall have to be
arranged for by the contractor. Each part of the joint shall
be cleaned by wire brush to make it free of rust or dirt etc.
and properly greased before the final compression is done
with the compressors.
ii) All joints or splices shall be made at least 30 meters away
from the structures. No joints or splices shall be made in
spans crossing over main roads, railways, small rivers etc.
Not more than one joint per sub-conductor shall be allowed
in one span. The compression type fittings used shall be of
self-centering type. Care shall be taken to mark the
6.8 Clipping-in:
Clamping the conductors in positioning, armouring at supports
placing of the dampers and spacers, etc. shall be done in
accordance with the recommendations of the manufacturer or field
personnel or both.
The jumper at the section and angle towers shall be formed to parabolic
shape to ensure minimum clearance requirements. Pilot suspension
insulator strings shall be used where necessary to restrict jumper swing.
Fasteners on all fittings and accessories shall be secured in position, the
security clip also properly opened and sprung in to position.
*****