Minutes: Contract Works Weekly Meeting N.º: 004: N o Attendees Name Title E-Mail Company Participant
Minutes: Contract Works Weekly Meeting N.º: 004: N o Attendees Name Title E-Mail Company Participant
N
o Attendees Name Title e-mail Company Participant
1 Manfred Hofmann Project Manager manfred.hofmann@auxitec.es JV TPF & Auxitec
2 Viladi Aliyev Deputy Project Manager vidadi.aliyev@auxitec.es JV TPF & Auxitec X
3 Emilio Gimeno K2 Expert emilio.gimeno@auxitec.es JV TPF & Auxitec X
4 Vugar Talibov Project Coordinator vuqar.talibov@atef.az ATEF X
5 Nuri Göksuakar Project Manager nurigoksuakar@yahoo.com ATEF X
6 Didem Atesh Deputy Project Coordinator didem.ates@atef.az ATEF
7 Leyla Aydinova Translator leyla.aydinova@atef.az ATEF X
8 Asker Askerzade DC/AC Coordinator asker_askerzade@atef.az ATEF
9 Yusif Alimov Quality Control Manager alimov.yusif@atef.az ATEF X
10 Anar Maharramov HSE Manager anar.meherremov@atef.az ATEF X
11 Raul Kazimov Local Expert raul.kazimov@auxitec.es JV TPF & Auxitec X
12 Jabir Suleymanli Administration Manager jabir@auxitec.es JV TPF & Auxitec
13 Cemil Agirman Contract Manager cemil@auxitec.es JV TPF & Auxitec X
14 Aysel Bagirova Team assistant aysel.bagirova@auxitec.es JV TPF & Auxitec X
Nesrinaltunboga@proray.com.t
15 Nesrin Altunboga Project Engineer r JV TPF & Auxitec X
16 Canip Gencyuva Project Engineer canipgencyuva@proray.com.tr JV TPF & Auxitec X
Page 2 of 6
Agenda
ACTION
Item DESCRIPTION STATUS
BY
Nº.
1 The meeting was started with the speech of Contractor - ATEF is instructed
PIU Director. He expressed his concern
regarding the execution of the works on time,
especially he requested from the Contractor to
finalize the design works for Section-1 as soon
as possible. Meanwhile, he reminded that the
Contractor shall also proceed with the works in
Section-2 and Section-3.
2 The Consultant has summarized the urgent Contractor
steps to be taken by the Contractor, as the
works are in delay and since there is not a
realistic schedule, it is not possible to know
progress of the works. Accordingly, he
emphasized that submission of the following
documents is crucial for the proper
management and monitoring of the project: