Professional Documents
Culture Documents
Safety Pillar Design For Main Galleries in Multi-Slice Longwall Top Coal Caving Method
Safety Pillar Design For Main Galleries in Multi-Slice Longwall Top Coal Caving Method
3, 2015 329
Abstract: Longwall top coal caving (LTCC) is one of the methods used in
thick coal seams. In coal mines where this method is used, some coal is left in
place to be retrieved later in order to prevent damage to the main
galleries. Stresses and strains created by roof layer caving of the panels
advancing towards each other may put pressure on the main galleries. The
amount of this pressure increases with time-dependent consolidation of roof
layers. Sizes of the safety pillars gain importance in order to prevent this
pressure and thus avoid the damages on the supports of the main galleries. In
this research, great deformations creating damages on the supports of the main
galleries of an underground coal mines in Manisa, Soma-Eynez were examined.
Time-dependent deformation amounts were investigated both in situ and with
time-dependent numerical modelling analysis. The results obtained by this
research provide the sizes of the safety pillars in the panels to be produced.
[Received: September 24, 2014; Accepted: December 25, 2014]
1 Introduction
One of the production methods in thick coal seams is the longwall top coal caving
(LTCC) method in which the lower part of the coal seam is taken by a conventional
longwall face and the upper part allowed to cave onto a second conveyor. Very thick
seams can be divided into a number of slices – multi-slice LTCC. In every slice, some
amount of coal is taken from the face and top coal is caved and extracted behind the face.
Since the thickness of the extracted coal is high in this method, significant pressures on
the longwall faces appear after caving of the roof strata. The magnitude of these pressures
depends on the thickness of the coal seam and the limit angles of the layers (Aksoy et al.,
2004). It is possible to calculate the pressures on the faces by analytical methods.
Figure 1 shows the distribution of the stresses on the faces in multi-slice LTCC method
(Whittaker and Pasamehmetoglu, 1981).
As seen in Figure 1, stresses reach peak levels in front of the longwall (1–3 m) and return
to the primary stress conditions 60–80 m behind the longwall. A relief zone occurs in the
gob area between the front abutment and the point where cover load is restored. This is
the case in single slice LTCC. In multi-slice LTCC method, stress conditions are not so
different from the single slice case. Figure 2(a) shows the stress conditions observed
during multi-slice LTCC. In this case, front abutment stresses are located further from the
face. Figure 2(b) shows the stress conditions at the panels advancing towards each other
and positions of the main galleries. Figure 2(c) illustrates the stress states in the case
where the panels advancing towards each other are very close and deformations are
occurring in the main galleries.
(a)
(b)
(c)
332 C.O. Aksoy et al.
Pillar design, however, is very important considering the proper mining production. A
careful survey of literature published on the general pillar design theories helps to
broadly categorise the approaches used by different researchers for their pillar design
theories in the following categories (Mark and and Iannacchione, 1992), namely,
1 empirical approach
2 mechanics-based approach
3 numerical modelling approach.
efficient tool and it generates results which can be very realistic depending on the quality
of the inputs and detailing of the model (Peng, 1986; Kripakov, 1981). At present,
various techniques in pillar design methods are available and the results obtained from
them vary considerably even for the same problem. This can be summarised in Figure 3
which illustrates the comparison of five empirical formula, three analytical and two
numerical techniques. In the late eighties and early nineties some research initiatives
were noticed where pillar stability long after mining started making its way into pillar
design research and as a result some research papers were published. For all of these
research initiatives, the main driving force was to minimise the surface subsidence caused
by the sudden failure of the pillars from an abandoned underground mine. So it became
important to study the long-term stability of coal pillars in great detail. From the
discussions above, it is evident that all of these pillar design methods generate an answer
for a particular instance given the required inputs and that remains constant no matter at
what stage of the pillar life the strength calculation is done. This is because none of these
methods has incorporated any time-dependent criteria, which is found to be very obvious
from the field observations.
The main reason for increasing pressure on the pillars in the multi-slice LTCC
method is the subsidence caused by caving. The protection of the main galleries which
will remain in use for a long time is very important. For this reason, time-dependent
performances of the safety pillars should be addressed, including the movements of the
roof layers.
In this study, support problems in the main galleries due to approaching panels were
examined in an underground coal mine in which multi-slice LTCC method was applied.
Time-dependent performance of the safety pillars was investigated by numerical
modelling. According to the results obtained, sizes of the safety pillars for the next
production panels were designed.
Soma is a region where coal mining has been done for more than 100 years. Surface and
underground coal mining have been almost inter-twined. Eynez region, where this study
was carried out, is generally underground coal mining region of Soma district.
The lignite deposit of South-Western Turkey contains a series of north-east/
south-west trending Tertiary basins. The Miocene deposits rest unconformably on
Mesozoic-base rocks. Pliocene deposits rest conformably on the Miocene and contain
two poorly developed lignite seams designated as KP1 and KP2. The stratigraphy of the
Soma region is summarised in the general stratigraphic column shown in Figure 4
(Aksoy, 2002). Underground coal production is conducted in Neogene aged sedimentary
rocks to the west of Eynez village. The Soma-Eynez basin contains two thick Miocene
lignite seams designated as KM2 and KM3 in Figure 4. As a result of the coal production
at a depth of 200 m, large-scale subsidence cracks observed as 2–2.5 m opening widths
on the surface during the studies. In the KM2 coal bed, the seam ranges in thicknesses
from 25 to 35 m, with an average extractable thickness of about 28 m (Aksoy et al., 2004;
Inci, 1998).
334 C.O. Aksoy et al.
In the first layer, 2 m of coal is extracted and by this way, cracking of roof strata can
be provided. In the second and third layers, however, approximately 8 m of coal seam is
extracted behind the support and 2 m of it is taken from the face (Figure 5).
Coal excavation is done by drilling and blasting; hydraulic props and steel caps are used
as supporting material. Transportation of coal and other material is carried out by chain
conveyor in the face and band-conveyor is used in the main roads. Average panel length
is 1,000 m, total mine opening is 12 km. Daily and annual production rates are
11,000 tonne and 3.5 million tonne, respectively. Underground transportation length is
9,400 m (7,700 m with belt-conveyor and 1,700 m with chain conveyor)
Figure 7 Support damage at the main galleries, (a) before 60 m distances between D1 and D2
panel (b) wall damage on right main gallery after 60 m distance between D1 and D2
panels (c) wall damage on left side main gallery after 60 m distance between D1 and D2
panels (d) roof damage after 60 m distance between D1 and D2 panel (see online version
for colours)
(a) (b)
(c) (d)
Numerical modelling methods are commonly used in a lot of problems in civil and
mining industry, including determining the size of pillars. The results obtained by
correctly constructed numerical models give rise to results very close to real life cases.
As it is mentioned before, multi-slice LTCC method has been used in this underground
coal mine. A part of the coal is caved behind the support in this method. Therefore, some
stress and deformation changes occur in the roof strata. In order to determine appropriate
pillar size, the mining method must be properly implemented in the numerical model.
The most important problem in this case is definition of the gob material. There are lots
of methods to model the gob material in the caving method (Vakili and Hebblewhite,
2010; Yasitli and Unver, 2005; Xie et al., 1999). One of the most efficient methods is the
one that defines equations of the time-dependent elasticity module of the gob material as
(Xie et al., 1999):
2.3Cr
κ* ≈ (3)
2.3(1 + e)
Cα
μ* = (4)
2.3(1 + e)
where Cc, Cr and Cα are consolidation parameters of rock. Also, the Poisson of this type
of analysis is an elastic constant not a pseudo-elasticity constant as used in
Mohr-Coulomb.
Nicholson and Bieniawski Palmstrom, Palmstrom and Singh Barton Hoek and Diederichs
⎛ RMR ⎞ Emass = 5.6 RMi0.375; 1
Ei ⎡ ⎜ ⎟ ⎤ ⎛ 1− D / 2 ⎞
Rock
E mass = ⎣ 0.0028 RMR 2 + 0.9 e ⎝ 22.82 ⎠ ⎦ (1 > RMi > 0.1) Emass = 7 Rmi0.4 E mass = E i ⎜ 0.02 + ⎟
E mass = 10 Qc 3 ⎝ 1 + e (60 +15 D − GSI ) /11 ⎠
Formation
100 (1 < RMi < 30)
P2AB Marl 0.23 1.29 8.92 0.08
P2 Limestone 9.16 32.20 22.69 4.93
P1 Shale and Claystone 1.37 15.35 8.92 0.61
KM3 Coal 0.11 1.29 13.33 0.04
M3 Marl 3.83 15.35 12.12 1.71
M2 Marl 2.26 10.60 9.44 0.90
KM2 Coal 0.24 2.94 5.31 0.08
M1 Marl 4.96 22.23 14.06 2.45
Deformation modulus specified due to some empirical equations
Safety pillar design for main galleries in multi-slice LTCC method
339
340 C.O. Aksoy et al.
friction angle
Poisson ratio
modulus (Ek)
Cohesion (c)
modulus (Ei)
Deformation
Density (d)
Formation
Elasticity
Internal
(kg/m3)
(Φ) (o)
(MPa)
(MPa)
MPa
(v)
Marl (P2AB) 3,000 84.67 0.30 1,900 0.124 6.14
Limestone (P2) 23,000 4,925.23 0.24 2,650 3.60 27.47
Shale and Claystone (P1) 5,000 609.12 0.33 1,900 1.022 15.90
Coal (KM3) 1,500 42.34 0.35 1,700 0.163 9.32
Marl (M3) 14,000 1,705.55 0.27 2,100 0.921 19.53
Marl (M2) 10,000 898.26 0.30 1,950 0.619 16.24
Coal (KM2) 2,000 223.60 0.33 1,650 0.436 12.94
Marl (M1) 15,000 2,450 0.25 2,200 0.885 19.58
Fractured zone - 210,000 0.3 21 0.300 20
A total of 739 days of production progress of D1 and D2 panels were integrated into the
model.
Time-dependent 3D numerical modelling analysis stages achieved for the production
are listed below. Figure 9 shows the schematic view of the production stages.
Figure 9 Cross-section of the D1 and D2 panels (see online version for colours)
Safety pillar design for main galleries in multi-slice LTCC method 341
6 the case in which the distance between D1 panel and safety pillar is 60 m, t = 90 day,
∑ t = 530
7 the case in which the distance between D2 panel and safety pillar is 100 m, t = 61
day, ∑ t = 591
8 the case in which the distance between D1 panel and safety pillar is 20 m, t = 30 day,
∑ t = 621
9 the case in which the distance between D2 panel and safety pillar is 60 m, t = 30 day,
∑ t = 651
10 the case in which D1 panel affects the safety pillar t = 13 day, ∑ t = 664
11 the case in which the distance between D2 panel and safety pillar is 20 m t = 45 day,
∑ t = 709
12 the case in which D2 panel affects the safety pillar t = 30 day, ∑ t = 739
As it is seen in Figure 9, gob material and the state of the roof strata above the coal are
defined as fracture zone and caving zone.
Soma-Eynez underground coal mine and mining activities were integrated into the model.
Stresses and deformations caused by 739 days time-dependent analysis of the production
were investigated step by step. Table 4 illustrates general view of steps and effective
stresses in the model. Moreover, bending moments, axial and shear forces on the main
galleries support predicted in the model are given in Table 5 step by step.
342 C.O. Aksoy et al.
Table 4 General view of steps and effective stress on model (see online version for colours)
5
Safety pillar design for main galleries in multi-slice LTCC method 343
Table 4 General view of steps and effective stress on model (continued) (see online version
for colours)
9
344 C.O. Aksoy et al.
Table 4 General view of steps and effective stress on model (continued) (see online version
for colours)
11
12
Time-dependent efficiency of the safety pillar was investigated for D1 and D2 panels.
Table 5 illustrates that, when the coal production is 100 m away from safety pillar,
bending moments in the supports are between 59.11–71.84 kN/m for D1 side gallery and
58.37–66.57 kN/m for D2 side gallery. However, when this distance is reduced to 60 m,
bending moments increase to 112.32 kN/m for D1 side gallery.
Table 5
condition
Forces and moments on the main galleries supports depending on time and excavation
345
346 C.O. Aksoy et al.
Bending moment on the support of the gallery in panel D2 increases from 66.52 kN/m to
154.93 kN/m over time for 100 m distance of safety pillar. When the distance between
panel D2 and safety pillar is 60 m, bending moment in the gallery at panel D1 and D2 are
863.41 kN/m and 611.50 kN/m, respectively. When panel D1 has reached to the
limit distance to pre-designed safety pillar, panel D2 has been still 60 m away from the
safety pillar. At this moment, bending moment in the gallery at panel D1 and D2 are
1,320.00 kN/m and 873.03 kN/m, respectively. At this stage, although production at
panel D1 was ended, production at panel D1 continued. When the distance between panel
D2 and safety pillar is 20 m, bending moment in the gallery at panel D1 and D2 are
1,510.00 kN/m and 1,260.00 kN/m, respectively. When panel D2 has reached to the limit
distance to pre-designed safety pillar, bending moments in the gallery supports in panel
D1 and D2 are 2,430 kN/m and 2,110 kN/m, respectively.
It is clear from the analysis and observations on sites, deformations occurred on the
main gallery supports show dynamic behaviour. Those deformations, forces and moments
acting on the supports reach to critical damage values when the production is closer
certain amount to safety pillars. Another issue here is that, roof strata has been caved over
time and affects to the support in conjunction with coal production.
7 Conclusions
References
Aksoy, C.O. (2002) Numerical Modelling for the Recovery of Protecting Pillars in Soma District,
PhD Thesis, Dokuz Eylul University, Graduate School of Natural and Applied Science,
Izmir-Turkey.
Aksoy, C.O. and Kucuk, K. (2012) The Technical Report on Determination of Huge Deformation
on Support of Inlet and Outler Ventilation Galleries Induced By D1 and D2 Panel of Imbat
Mining Co., pp.1–189, DEU Eng. Fac., İzmir.
Aksoy, C.O., Köse, H., Onargan, T., Koca, Y. and Heasley, K. (2004) ‘Estimation of limit angle by
laminated displacement discontinuity analyses in Soma coal field, Western Turkey’,
International Journal of Rock Mechanics and Mining Science, Vol. 41, No. 4, pp.547–556.
Safety pillar design for main galleries in multi-slice LTCC method 347
Aksoy, C.O., Geniş, M., Aldas, G.G., Özacar, V., Ozer, S.C. and Yılmaz, Ö. (2012a) ‘A
comparative study of the determination of rock mass deformation modulus by using different
empirical approaches’, Engineering Geology, Vols. 131–132, pp.19–28.
Aksoy, C.O., Oğul, K., Topal, İ., Ozer, S.C., Özacar, V. and Posluk, E. (2012b) ‘Numerical
modeling of non-deformable support in swelling and squeezing rock’, International Journal of
Rock Mechanics and Mining Science, Vol. 52, pp.61–70.
Aksoy, C.O., Ozacar, V. and Kantarci, O. (2010) ‘An example for estimation of rock mass
deformations around an underground opening by numerical modeling’, International Journal
of Rock Mechanics & Mining Sciences, Vol. 47, pp.272–278.
Inci, U. (1998) ‘Lignite and carbonate deposition in middle lignite succession of the Soma
formation, Soma coal field, Western Turkey’, Int J Coal Geology, Vol. 37, pp.287–313.
Kripakov, N.P. (1981) ‘Analysis of pillar stability on steeply pitching seam using finite element
method’, BuMines RI, Vol. 8579, p.33.
Mark, C. and Iannacchione, A.T. (1992) Proceedings Workshop on Coal Pillar Mechanics and
Design, Coal Pillar Mechanics: Theoretical Models and Field Measurements Compared, IC
9315, pp.78–93
Peng, S.S. (1986) Coal Mine Ground Control, John Willey& Sons Inc., New York.
Vakili, A. and Hebblewhite, B.K. (2010) ‘A new cavability assessment criterion for longwall top
coal caving’, International Journal of Rock Mechanics & Mining Sciences, Vol. 47,
pp.1317–1329.
Whittaker, B.N. and Pasamehmetoglu, A.G. (1981) ‘Ground tilt in relation to subsidence in
longwall mining’, International Journal of Rock Mechanics and Mining Sciences and
Geomechanics, Vol. 18 , No. 4, pp.321–329.
Xie, H., Chen, Z. and Wang, J. (1999) ‘Three-dimensional numerical analysis of deformation and
failure during top coal caving’, International Journal of Rock Mechanics & Mining Sciences,
Vol. 36, No. 6, pp.651–658.
Yasitli, N.E. and Unver, B. (2005) ‘3D numerical modeling of longwall mining with top-coal
caving’, International Journal of Rock Mechanics & Mining Sciences, Vol. 42 , pp.219–235.