Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.

090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

EXECUTIVE SUMMARY
1.0 BACKGROUND
As a consequence of liberalization and rapid socio-economic development in India,
opening of various central/state undertakings and bank offices, there has been tremendous
growth of economic activities in the urban centers. This has resulted in a spurt of freight
and passenger transport activities. National Highway Authority of India (NHAI) has
decided to take up the development of various National Highways.

National Highways Authority of India (NHAI) has taken up the up-gradation of existing 2-
lane road to 4 lane with paved shoulder configuration of Bhavnagar – Talaja section of
NH-8E from Km 7.090 (design chainage km 6.945) to Km 53.585 (design chainage Km
54.990) in the State of Gujarat. This project stretch length is 48.045 Km.

2.0 PROJECT ROAD & SALIENT FEATURES


2.1 The present project consists of following road stretches as indicated in Table – 1.1:

Table – 1.1: Project Stretch

Sl. No. Road Name/No. From (km) To (km) Length (kms)

1 NH – 8E 6.945 54.990 48.045

Total Length of Project Roads

The entire project road in its present condition is a two lane road. The layout plan
indicating the project road is presented in Figure – 1.1.
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

Figure 1.1: Layout Plan

2.2 Objectives of Study


The main objective of the present study is to establish technical and environmental &
social viability of the project and prepare Detailed Project Report for upgrading of the
existing 2 lane road to 4 lanes configuration.

3.0 SOCIO ECONOMICS PROFILE


The primary purpose of socio – economic analysis is to provide an overview of the state’s
socio – economic setup and the related status of the project influence area within the
states. The details include the present status, the past performance and the perspective
growth of the economy, population and urbanization. The profile depicts the spatial
distribution of economic activities.
It is observed that over 80 percent of the vehicular traffic on the project corridor originates
or terminates in the State of Gujarat. Therefore, the Socio-economic analysis of the broad
influence area is confined to this state.
Gujarat, for administrative purpose, has been divided 23 districts. The project road Section
mainly passes through three districts of Gujarat, namely Bhavnagar, Amreli and Junagadh.

2
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

All these districts contribute traffic to the project road section in varied proportion. These
districts thus form an immediate influence area of the Project Road. This influence area is
termed as Project influence Area (PIA). This chapter deals with Socio – economic profile
of the immediate PIA. Gross domestic product (GDP) at factor cost at constant (2004-05)
prices in 2009-10 is estimated at Rs. 44, 93,743 crore as against Rs. 41, 62,509 crore in
2008-09 registering a growth of 8.0 per cent during the year as against the growth rate of
6.8 per cent during the previous year. At current prices, GDP in 2009-10 is estimated at
Rs. 61, 33,230 crore as against Rs. 52, 82,086 crore in 2008-09, showing an increase of
16.1 per cent during the year. At constant (2004-05) prices the gross national income at
factor cost in 2009-10 is estimated at Rs 44, 64,854 crore as against Rs. 41, 37,125 crore
in 2008-09 showing a rise of 7.9 per cent during the year. At current prices, the gross
national income in 2009-10 is estimated at Rs. 60,95,230 crore as compared to Rs
52,49,163 crore in 2008-09, showing a rise of 16.1 per cent during the year. The growth
rate of 8.0 per cent in the GDP during 2009-10 has been achieved due to high growth in
transport, storage and communication (15.0%), community, social and personal services
(11.8%), financing, insurance, real estate & business services (9.2%), and manufacturing
(8.8%).
The per capita income (per capita net national income at factor cost) in real terms, i.e. at
2004-05 prices, is estimated at Rs. 33,731 for 2009-10 as against Rs. 31,801 in 2008-09,
registering an increase of 6.1 per cent during the year. The per capita income at current
prices is estimated at Rs. 46,492 in 2009-10 as against Rs. 40,605 for the previous year
depicting a growth of 14.5 per cent.

3.1 Project Appreciation


3.1.1 Climate
The study region experiences moderate temperatures with high-level of humid conditions.
The coastal nature and tropical location ensures moderate temperatures throughout the
year. Monsoon season starts in mid June and end in September. It has a maximum of 42°C
during summer months and minimum of 10°C during winters.
3.1.2 Terrain
The Project stretches pass through plain and rolling terrain.

3
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

3.1.3 Land Use


The land use pattern along the project road is mainly agricultural. Barren land has also
been observed in certain areas of project stretch. The project road traverses adjacent to
many villages and towns.
3.1.4 Environmental Aspects
The existing highway is widening to 4 lane with paved shoulder. The existing road passes
mostly through agriculture areas with building and private properties on both sides of the
road at discrete locations. This aspect has been in view while proposing cutting and filling
on the existing road so as to cause the least possible disturbance to the harmony between
proposed levels of the road and the levels of the existing buildings and internal roads.
However, the widening / up-gradation of the project road will result in overall
improvement of quality of environment in the surrounding region. During construction,
local environment impact is unavoidable.
3.1.5 Alignment
The alignment has been designed for a speed of 100 km per hour.
The vertical gradient is maintained up to 2.5% in compliance with IRC specifications.
3.1.6 Improvement of the Existing Road Geometrics
The Bypasses and Realignments proposed along the project highway are indicated in table
below.

4
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

Table 1.2: Improvement of the Existing Road Geometrics


Existing Design
Chainage (Km) Chainage (Km)
Sr. Length Length
TCS Remarks
No. (Km) (Km)
From To From To

New Alignment –
1 8.587 11.047 2.46 8.442 11.116 2.674 TCS- 3
Proposed Bypass for Budhel

New Alignment – Proposed


2 14.631 16.968 2.337 14.706 17.247 2.541 TCS- 3
Bypass for Kobadi
New Alignment – Proposed
3 20.118 22.808 2.690 20.431 23.867 3.436 TCS- 3
Bypass for Bhandaria
New Alignment – Proposed
4 28.613 31.113 2.500 29.752 32.377 2.625 TCS- 3
Bypass for Tansa
New Alignment – Proposed
5 32.855 33.952 1.097 34.122 35.329 1.207 TCS- 3
Bypass for Rajpura
New Alignment – Proposed
6 39.121 41.024 1.903 41.273 42.13 0.857 TCS- 8
Bypass for Trapaj
New Alignment – Proposed
7 49.700 53.585 3.885 50.790 54.990 4.200 TCS-8
Bypass for Talaja

3.1.7 Proposed Road Cross-Sections


The widening of highway section to 4 lanes with paved shoulder shall be as indicated in
the Table 1.3.
Table 1.3: Proposed Widening

Existing Chainage Design Chainage


Sr. No Section Proposal
From To From To
1 Bhavnagar – Talaja 7.090 53.585 6.945 54.990 4 - lanes

Based on condition and widening requirement of the project road, different types of cross
sections have been proposed.

3.1.8 Existing Structures


From the inventory of Structures, it is noted that there is no major and minor bridge on the
project road. List of Structures present along the project length are described below.
The total number of structures on the Site is indicated below:
a) No. of Major Bridges - 01
b) No. of Railway Over Bridges - Nil
c) No. of Grade Separators - Nil

5
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

d) No. of Minor Bridges - 23


e) No. of Slab Culverts - 41
f) No. of Box Culverts - 01
g) No. of Pipe Culverts - 07
3.1.9 Bus Shelters and truck Lay-byes
The total number of bus shelters and truck lay byes on the Project highway is noted below:
a) No. of Bus Shelters LHS -03
b) No. of Bus Shelters RHS -02
c) No. of Truck Lay-byes -Nil
3.1.10 Toll Plaza
There is no existing Toll Plaza and one New Toll Plaza Proposed at Km. 17.873.

4.0 ENGINEERING SURVEY & INVESTIGATIONS


4.1 Classified Traffic Volume Count at Mid-Block
Various Engineering Surveys and Investigation were conducted for the Feasibility Study
Report preparation. These include Inventory and condition survey of Road and pavement,
Alignment Study, Topographic Survey, Pavement investigations, Sub grade
Investigations, Soil and Material Investigations, Inventory and Condition Survey for
Bridge and cross Drainage Structures.
Information about traffic is indispensable for any highway project since it is the basis of
design of pavement, fixing the number of traffic lanes, design of intersections and
economic appraisal of the project, etc.

Traffic studies at Mid-Blocks are conducted at different locations in the Year 2016 for
classified traffic volume count after a detailed site investigation.

The Mid-Block locations for Bhavnagar – Talaja Section are listed below:

6
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

1. At Km 17.873 on NH -8E (Mid-Block counts for 3 days 24 hours) – Jan 2016

Average Daily Traffic at Toll Plaza-1 Km. 17.873


Bhavnagar Mahuva to
Mode of Vehicle to Mahuva Bhavnagar Total
CAR/ Jeep/ Van/ LMV 1750 1770 3520
LCV/ LGV/ Mini Bus 697 678 1375
Bus/ Truck (2 Axle) 537 574 1111
Fast Moving Vehicles

3 Axle Commercial
Vehicle 321 369 690
MAV/ HCM/ EME (4 to 6
Axle) 649 643 1292
Oversized Vehicle (7 or
more axle) 2 2 4
Two Wheeler 2169 2029 4198
Auto Rickshaw/ 6 Seater 389 374 763
Tractor 7 6 13
Tractor + Trailer 98 97 195
Slow Moving

Bicycle 8 7 15
Vehicles

Cycle Rickshaw 0 0 0
Hand Driven Vehicle/
Bullock Carts/ Horse
Carts 0 1 1
PCU's Vehicles

Motorised 6619 6542 13161


Non Motorised 8 8 16
Total 6627 6550 13177
Motorised 10127 10259 20386
Non Motorised 4 12 16
Total 10131 10271 20401

7
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

The axle load survey data have been analyzed to arrive at the VDF values for each
category of vehicles. The following VDF values have been arrived for various categories
of vehicles.
Table – 1.6: Vehicle Damage Factor

Type of Vehicle VDF Values


Bus 0.81
LCV 1.10
2 – Axle 2.21
3 – Axle 4.93
4 – Axle 3.80
5 – Axle 3.21

4.2 IMPROVEMNET PROPOSALS AND DESIGN


4.2.1 Cross Section Details
Various Types of Typical Cross Section have been developed for the project length based
on the guidelines given in IRC Codes. These are outlined in below Table 1.7.
Table 1.7: Summary of Cross Sections

Sr. Type of Cross Description


No Section
1 TCS – 1 Typical cross section of 4-lane without service road (New Construction)

2 TCS – 2 Typical cross section of 4-lane highway with service road

3 TCS – 3 Typical cross section of 4-lane without service road (New Construction)

4 TCS – 4 Typical cross section of 4-lane without service road (Eccentric widening)

5 TCS-5 Typical cross section of 4-lane without service road (New Construction)

6 TCS – 6 Typical cross section of 4-lane without service road (New Construction)
7 TCS – 7 Typical cross section of 4-lane Flyover/Underpass with slip road
8 TCS – 8 Typical cross section of 4-lane Flyover/Underpass with slip road
9 TCS – 9 Typical cross section of 6-Lane Flyover / Underpass with Slip Road
10 TCS – 10 Typical cross section of 6-Lane Flyover / Underpass with Slip Road

4.2.2 Pavement
This section provides pavement structure proposed for the improvement of the project
road. The entire stretch of project highway has rigid pavement.
 Pavement Structure for New Construction

8
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

The pavement compositions proposed for new construction of rigid pavement for
widening it to 4 lanes are indicated in Table 1.8.
Table 1.8: Pavement Composition for New Construction

Section Bhavnagar – Talaja

Stretch Km 6.945 - Km 54.990


4 Lane with Paved
Carriageway Configuration
Shoulder
PQC 300
DLC
Pavement 150
Composition GSB 230
SG with CBR 8 % 500

9
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd .

5.0 BRIDGES AND STRUCTURES


The proposed bridges are listed below in Table 2.1, Table 2.2, Table 2.3, Table 2.4, Table 2.5 and Table 2.6.
Table 2.1: Widening/Repair/Rehabilitation of Major Bridges

Existing Design Bridge / Proposed Proposed Span Total Length Total width Remarks
Chainage Chainage structure Structure arrangement (c/c of bridge of structure
Sl. No
Location Location No. configuration of bridge)
(Km) (Km) (m) (m) (m)

Existing 240 8.3 Existing bridge shall be retained


1. 49.593 50.687 50/2 bridge 10x24 (Existing) (Existing) after carrying out necessary,
retained repairs and rehabilitation works.

Table 2.2: Reconstruction of existing major Bridges

Existing Design Bridge / Proposed Proposed Span Total Length Total width Remarks
Chainage Chainage structure Structure arrangement (c/c of bridge of structure
Sl. No
Location Location No. configuration of bridge)
(Km) (Km) (m) (m) (m)
NIL

Table 2.3: Construction of additional major bridges

Sl. No
Existing Design Bridge / Proposed Total Length Total width Remarks
Chainage Chainage structure Structure Proposed Span of bridge of structure
arrangement
Location Location No. configuration (c/c of bridge)
(Km) (Km) (m) (m) (m)
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd .

New New 4 Lane bridge on LHS


1. 42.342 42.331 -
4 Lane bridge (2x27.3)+(1x9.1) 63.7
2x12.5
side on Trapaj bypass
with footpath proposed for main
carriageway
New 2 Lane bridge on RHS
2. 49.593 50.687 50/2 New proposed for main
2 Lane bridge 10x24 240 12.5 carriageway

Table 2.4: Widening /Repair & Rehabilitation of Existing Minor Bridges

Existing Design Proposed Span


Bridge / Proposed Total Length Total width
Chainage Chainage arrangement (c/c
Sl. No structure Structure of bridge of structure Remarks
Location Location of bridge)
No. configuration (m) (m)
(Km) (Km) (m)
Existing bridge shall be retained after
8.4 carrying out necessary repairs and
Existing Bridge to
(Existing) rehabilitation works and shall be
1. 49.183 50.267 50/1 be widened to 2 3x7 21
12.5 widened to 2 Lane for main carriage
lane Bridge
(after widening) way on LHS

Table 2.5: Reconstruction of existing minor Bridges

Existing Design Proposed Span


Bridge / Proposed Total Length Total width
Chainage Chainage arrangement (c/c
Sl. No structure Structure of bridge of structure Remarks
Location Location of bridge)
No. configuration (m) (m)
(Km) (Km) (m)

NIL

11
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd .

Table 2.6: Construction of Additional Minor Bridges


Sl. No
Existing Design Bridge / Proposed Total Length Total width Remarks
Chainage Chainage structure Structure Proposed Span of bridge of structure
arrangement
Location Location No. configuration (c/c of bridge)
(Km) (Km) (m) (m) (m)
New
6 Lane bridge New 6 Lane bridge proposed
1. - 10.158 -
for Main carriageway on
1 x 6.0 6 2x16.0 Budhel bypass
New 6 Lane bridge proposed
2. - 10.594 - New for Main carriageway on
6 Lane bridge 1 x 6.0 6 2x16.0 Budhel bypass

New 6 Lane
3. - 11.268 -
bridge
1 x 10.4 10.4 2x16.0 New 6 Lane bridge proposed
for main carriageway

4. 20.148 20.440 - New 6 Lane New 6 Lane bridge proposed


bridge 1x12.3 12.3 2x16.0 for main carriageway
New 6 Lane bridge proposed
5. - 22.317 - New 6 Lane 10 x 6.0 for Main carriageway on
bridge 60 2x16.0 Bhandaria bypass
New New 6 Lane bridge proposed
6. 23.148 24.221 24/1
6 Lane bridge 1x10.8 10.8 2x16.0 for main carriageway
New 6 Lane bridge proposed
7. 24.146 25.227 25/1 New for main carriageway
6 Lane bridge 1x7.8 7.8 2x16.0

8. 25.245 26.312 26/1 New New 6 Lane bridge proposed


6 Lane bridge 1x10.2 10.2 2x16.0 for main carriageway
New New 6 Lane bridge proposed
9. 26.064 27.155 27/1
6 Lane bridge 1x11.4 11.4 2x16.0 for main carriageway
New
10. 26.585 27.672 27/2 6 Lane bridge New 6 Lane bridge proposed
1x6.8 6.8 2x16.0 for main carriageway
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd .

Sl. No
Existing Design Bridge / Proposed Total Length Total width Remarks
Chainage Chainage structure Structure Proposed Span of bridge of structure
arrangement
Location Location No. configuration (c/c of bridge)
(Km) (Km) (m) (m) (m)
New 6 Lane bridge proposed
for main carriageway on
11. - 30.126 -
New 6 Lane 10 x 6.0 Tansa bypass
bridge 60 2x16.0
New 6 Lane bridge proposed
12. - 30.330 - New 6 Lane for Main carriageway on
bridge 5 x 7.6 38 2x16.0 Tansa bypass
New New 6 Lane bridge proposed
13. 31.966 33.224 32/2
6 Lane bridge 1x7.8 7.8 2x16.0 for main carriageway
New
14. 32.674 33.938 33/2 6 Lane bridge New 6 Lane bridge proposed
1x6 6 2x16.0 for main carriageway
New New 6 Lane bridge proposed
15. - 34.126 - 6 Lane bridge for main carriageway on
1x6 6 2x16.0 Rajpara realignment
New 6 Lane bridge proposed
for Main carriageway on
New Rajpara realignment
16. - 34.938 -
6 Lane bridge
3 x 6.0 18 2x16.0

New New 6 Lane bridge proposed


17. - 34.991 - 6 Lane bridge for Main carriageway on
3 x 6.0 18 2x16.0 Rajpara realignment
New
18. 35.56 36.934 36/1 6 Lane bridge New 6 Lane bridge proposed
1x6 6 2x16.0 for main carriageway

19. 35.723 37.113 36/2 New New 6 Lane bridge proposed


6 Lane bridge 1x6.7 6.7 2x16.0 for main carriageway

20. 36.486 37.858 37/2 New New 6 Lane bridge proposed


6 Lane bridge 1x6.2 6.2 2x16.0 for main carriageway
13
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd .

Sl. No
Existing Design Bridge / Proposed Total Length Total width Remarks
Chainage Chainage structure Structure Proposed Span of bridge of structure
arrangement
Location Location No. configuration (c/c of bridge)
(Km) (Km) (m) (m) (m)
New New 6 Lane bridge proposed
6 Lane bridge for Main carriageway on
5 x 5.8 29 2x16.0 Trapaj bypass
21. - 41.138 -
New New 4 Lane bridge proposed
4 Lane bridge for Main carriageway on
5 x 5.8 29 2x10.8 Trapaj bypass
New 6 Lane bridge proposed
New
22. - 41.346 -
6 Lane bridge
for Main carriageway on
2 x 5.6 11.2 2x16.0 Trapaj bypass
New
23. 41.383 42.494 42/1 6 Lane bridge New 4 Lane bridge proposed
1x10.2 10.2 2x12.5 for main carriageway

24. 45.065 46.165 46/1 New New 4 Lane bridge proposed


2 Lane bridge 1x6.4 6.4 2x12.5 for main carriageway

25. 47.22 48.323 48/1 New New 4 Lane bridge proposed


2 Lane bridge 1x6.8 6.8 2x12.5 for main carriageway
Additional New 2 Lane bridge proposed
26. 49.183 50.267 50/1 2 Lane bridge for Main carriageway on RHS
3x7 21 12.5
New New 4 Lane bridge proposed
27. - 53.67 - 4 Lane bridge 10 x 4.9 for Main carriageway on
49 2x12.5 Talaja bypass

14
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

6.0 DETAILS OF PROPOSED RAMPS AND OVERPASSES

Entry / exit ramps and Overpasses for the entering into or exiting from the project highway at Start and End point of
proposed bypasses have been proposed at the following locations as mention in Table 2.7.;
Table 2.7: Proposed Ramps and Overpasses
Avg. Skew Angle
Proposed Total width Gradient (Degree)
Sr. Design Proposed (%)
Bypass Span of
No. Chainage Structure
Location arrangement proposed
Location configuration
(c/c of bridge) structure
(Km)
(m) (m)

8.635 2 lane (1 x 60) +


1 Budhel 1X8 4.2
Overpass (1 x 30)
34

10.883 2 lane (1 x 31.2) +


2 Budhel 1X8 4
Overpass (1 x 31.5)
46

Kobadi 15.800 2 lane (1 x 48.6) +


3 1X8 2.9
Overpass (1 x 43.6)
34

Kobadi 17.046 2 lane (1 x 43.3) +


4 1X8 3.9
Overpass (1 x 67.9)
55

Bhandaria 20.618 2 lane (1 x 45) +


5 1X8 2.1
Overpass (1 x 40)
38

15
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

Avg. Skew Angle


Proposed Total width Gradient (Degree)
Sr. Design Proposed (%)
Bypass Span of
No. Chainage Structure
Location arrangement proposed
Location configuration
(c/c of bridge) structure
(Km)
(m) (m)

Bhandaria 23.590 2 lane (1 x 40.2) +


6 1X8 3.67
Overpass (1 x 45)
35

Tansa 29.829 2 lane (1 x 33) +


7 1X8 4
Overpass (1 x 37.1)
44

Tansa 2 lane (1 x 34) +


8 1X8 4
Overpass (1 x 47)
32.167 43

Rajpura 2 lane (1 x 28) +


9 1X8 4
Overpass (1 x 43)
34.340 59

Trapaj 42.110 2 lane (1 x 30) +


10 1X8 4
Overpass (1 x 30)
44

Talaja 51.194 2 lane (1 x 50) +


11 1X8 4
Overpass (1 x 61)
36

Talaja 54.880 2 lane (1 x 40) +


12 1X8 4
Overpass (1 x 40)
45

16
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

7.0 GRADE SEPARATED STRUCTURE


List of Grade separated structure are listed in Table 2.8.
Table 2.8: Details of Proposed Grade Separated Structure (Flyovers)
SI Design Proposed Proposed Total width
No Chainage No. of Intersecting Structure Span arrangement of proposed
Location Roads configuration (c/c of bridge) structure
(Km) (m) (m)

1 40.800 1 6 lane 2 x 15.0 2 X 14.5


Trapaj Bypass Flyover
start

8.0 VEHICULAR UNDERPASS, PEDESTRIAN AND CATTLE UNDERPASSES


List of Vehicular Underpasses are listed in Table 2.9 and Table 3.0.
Table 2.9: Proposed Vehicular Underpasses

Existing Proposed
SI. Design Chainage Proposed
Chainage Size (LXH) Total Width of Structure (m)
No (Km) Structure
(Km) (m)
Budhel
1 9.583 6 lane 12 X 5.5 2 X 14.5 + 3.5
Bypass
Talaja
2 52.750 4 lane 12 X 5.5 2 X 12.5 + 3.5
Bypass

17
Four laning of Bhavnagar – Talaja section of NH-8E from Km 7.090 (design
chainage km 6.945) to Km 53.585 (design chainage Km 54.990) on Hybrid
(Annuity) mode in the State of Gujarat
STUP Consultants P. Ltd.

Table 3.0: Proposed Pedestrian and Cattle Underpasses

Proposed
Existing Design Chainage Proposed
SI. No Size (LXH) Total Width of Structure (m)
Chainage (Km) (Km) Structure
(m)

1 13.341 13.361 6 lane 7 x 4.5 2 X 14.5 + 3.5

2 17.015 17.300 6 lane 7 x 4.5 2 X 14.5 + 3.5

3 36.815 38.177 6 lane 7 x 4.5 2 X 14.5 + 3.5

4 47.820 48.910 4 lane 7 x 4.5 2 X 12.5 + 3.5

9.0 ROB
NIL

18