Professional Documents
Culture Documents
Cec603 24
Cec603 24
Session: 2020 – 21
Semester: Even
Disclaimer: The study materials/presentations are solely meant for academic purposes and they
can be reused, reproduced, modified, and distributed by others for academic purposes only with
proper acknowledgements.
The study materials utilised in making the present presentation/text material are as follows:
1. Environmental Engineering (Vol. I & II) – by – Punmia, Jain & Jain [Laxmi Publications (P) Ltd,
New Delhi] (Henceforth mentioned as Ref1)
2. Environmental Engineering (Vol. I & II) – by – S. K. Garg [Khanna Publishers, Delhi] (Henceforth
mentioned as Ref2)
----------------------------------------------------------------------------------------------------------------
Part - 24
Part – 24
It gives the same discharge & loss of head in the complex system.
Equivalent pipes –
Prob. Given the pipe layout shown, determine the length of an equivalent pipe of 450mm dia.
Q = 10 m3/min
Pipe Diameter, mm Head loss, m/1000m
600 0.9
350 13
300 30
450 4
For BC –
For CD –
Then, total head loss in the pipe system = 1.08 + 7.15 + 18 = 26.23 m.
Prob.
A system of pipes as shown in the figure carries a total flow of 10m3/min. Find the total head loss in
the system between A & E. Take C = 100.
Q = 2 m3/min
Pipe Diameter, mm Head loss, m/1000m
250 3.75
200 12.0
215 8.25
hL = 8 m/1000m
Pipe Diameter, mm Flow, m3/min
200 1.75
215 2.0
Q = 3.75 m3/min
Pipe Diameter, mm Head loss, m/1000m
350 2.2
Q = 10m3/min
Pipe Diameter, mm Head loss, m/1000m
350 12.0
400 7.0
Soln.
For a flow of 2m3/min, from nomograph, for a head loss of 8.25m/1000m, diameter of pipe =
215mm.
The objectives of detection & prevention of waste in water distribution system pipelines are –
(i) Preservation of hygienic quality of water in the distribution mains, &
(ii) Providing conditions for adequate flow through pipelines.
The total lift or the total dynamic head (TDH) against which the pump is to operate is given by ---
Where, HST => total static head (or, lift) i.e. the elevation difference between the pumping source &
the point of delivery;
HL = > total head loss (including losses through valves, bends & other fittings, through the
suction & delivery pipe);
HV => velocity head, (v2/2g) at the discharge head. It is sometimes neglected in computing
power requirements of pumps.
Velocity of flow, v = Q/A = Q/(π x d2/4), where Q = > discharge , A = > area of flow i.e. pipe c/s area &
L => length of pipe.
= f’ x L x Q2 / (3.025 x d5)
= f x L x Q2 / (12.1 x d5).
If W kg is the weight of water lifted by H m. in 1 sec , then work done by the pump ---
= W x H kg-m/sec
= Q x w x H kg-m/sec, where Q => flow in m3/s & w = unit wt. of water, in kg/m3.
Then Brake Horse Power (B.H.P.) = (Q x w x H) / (75 x ղp), where ղ p = efficiency of pump.
If the pump is driven by electric motors, then electric horse power (E.H.P) is ---
= B. H. P. /(ղ e . ղ p)
= (Q x w x H) / (75 x ղ e x ղ p)
= (Q x w x H)/(75.ղ)
Prob. A city has a population of 150,000. Water is to be supplied @ 160 lpcd. If the static lift of the
pump is 40 m. , calculate the E.H.P. of the motor. The rising main (i.e. the pipe through which water is
sent from the source, through a pump, to a reservoir usually located at a higher R.L. than the source)
is 300m long & has a dia. = 50cm. Assume that motor efficiency = 85%, pump efficiency = 60%, f = 0.04
(almost a standard value) & peak hour demand = 1.5 times the average demand.
Soln.
Then peak hourly (i.e during the peak time or, simply the peak value) demand = 1.5 x 0.278 m 3/s
= 0.417 m3/s.
Hf = f x L x Q2 /(12.1 x d5)
= 5.52m.
= 0.417 x 4 / [π x (0.5)2]
= 2.12 m/s.
Then HV = v2/2g
= 2.122 / (2 x 9.81)
= 0.23m.
Then, H = HST + HL + HV
= 40 + 5.52 + 0.23
= 45.75m
= 498.76 H.P.
Prob. Water is to be lifted from a tube well to an overhead tank. Find the E.H.P. of pumping units for
the following data:
Depression head during pumping = 4m; [ this is sort of water level in the sump, that is to be
considered in calculating the total head
R.L. of bottom of the overhead tank = 220.50m; [ please draw a sketch of R.L. values for better
understanding of the level differences
Soln.
= 0.195m ≈ 20cm.
= 48m.
Hf = f x L x Q2 /(12.1 x d5)
= 3.72m.
= 0.20m.
= 59.34.
Thus, adopt 3 units @ 20 HP with an extra 20 HP unit as standby [This is a typical idea of field
provision. This may not be important from exam point of view.]