Professional Documents
Culture Documents
CV-0013-002 - Method Statement For Soil Improvement Work
CV-0013-002 - Method Statement For Soil Improvement Work
For REV A2
Soil Improvement
Work
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITY
6. EQUIPMENT
7. GENERAL REQUIREMENT
8. DYNAMIC COMPACTION
9. DYNAMIC REPLACEMENT
1. PURPOSE
This method statement is to describe and explain the methodology involved in soil improvement work
in general, detailing out of the steps to be taken to meet the requirement of MIP06 ONSHORE OIL
FACILITIES PROJECT, Saudi Arabia. The CONTRACTOR reserve his right to adapt the method used
in accordance with the site needs and arrangement.
2. SCOPE
This covers all soil improvement activities. This describes the requirements of quality, HSE, material
and methodology.
3. REFERENCES
All design, engineering, material and construction shall conform to the latest requirements of local &
national standards, regulations and the following reference documents. Latest edition at the time of
contract award shall be applicable.
Any conflicts between the following references shall brought to the attention of the COMPANY for final
decision.
4. DEFINITIONS
COMPANY
CONTRACTOR
5. RESPONSIBILITY
5.4 ENGINEER
- Charge of the construction shall be responsible for completing documentation and
implementation of this procedure.
6. EQUIPMENT
Certified equipment shall be mobilized at site in good running conditions. It shall be double checked
by concerned personnel prior to actual use. The equipment list which is provisional are as follows:
- The Model of each equipment except for DC machine, Vibroflot and the number of equipment
shall be adjusted as per the site condition.
YTQH650B 650T*M
DC machine 3
YTQH450B 450T*M
Vibroflot BJV-75E-377 75KW 2
Crawler crane HITACHI SCX550E 55T 1
Shovel loader CAT-950 3m3 1
Generator Perkins 500KVA 500KVA 1
Bulldozer CAT-D6 20T 1
Excavator CAT 320 20T 1
Tipper truck Volvo FMX 460 25-35m3 15
7. GENERAL REQUIREMENT
7.2 Settlement
- Mat foundation : 50mm
- Isolated and strip footings : 25mm
7.3 Soil Improvement Layout (as per Ground Improvement Design Report in Appendix-4)
8. DYNAMIC COMPACTION
1st phase DC
DC rigs installation
2nd phase DC
Positioning of DC
point
Leveling phase
Dynamic
compaction
Preparation works
Raise hammer
Cycling
Release hammer
Measure hammer elevation
Cycling
8.2.2 Position the dynamic compaction rig and place the hammer at the impact point.
8.2.4 Raise the hammer to design height and release the hook to allow the hammer to
fall down free.
8.2.5 Measure the elevation of the hammer after compaction. If the bottom of the pit is
inclined, level the bottom prior to next compaction. If the pit is too deep to raise
the hammer but there is not significant surface heave, backfill the pit to surface
level and continue compaction.
8.2.6 Repeat procedure (5) and (6) to finish designed times of compaction at one point.
8.2.7 Repeat procedure (3) to (7) to finish compaction for one phase.
8.2.8 Level the ground with bulldozer after completion of one phase compaction.
8.2.9 Measure ground elevation and accordingly adjust compaction parameters for the
next phase compaction.
8.2.10 Repeat procedure (1) to (9) to complete all dynamic compaction work.
Method Statement PAGE 8 OF 15
For REV A2
Soil Improvement
Work
9. DYNAMIC REPLACEMENT
This method combines the advantages from both Dynamic Compaction and Stone Columns
techniques by creating large sized granular columns with high stiffness and internal shear
resistance and overall improvement of mechanical characteristics of the intermediate soil.
The construction sequence could be divided into 6 main steps and detailed explanation shall
be found below:
9.2.1 Mark the position of ramming point and measure the elevation of site.
9.2.2 The crane moves in place and the rammer is placed at the ramming point.
9.2.4 Tamp and record the crater depth of each tamping; When the tamping pit is too
deep for the rammer to be hoisted, Stop tamping and fullfil the tamping pit, record
the quantity of filling; Repeat the process until the design tamping times and
quality control standards are met;
9.2.5 Complete the construction of all tamping point. Tamp from inside to outside or
interlacing if necessary.
9.2.6 After levelling the site, surface compaction in low energy will be carried out to
Method Statement PAGE 9 OF 15
For REV A2
Soil Improvement
Work
desify the loose soil on the surface of the site, and then measure the elevation of
the site after compaction.
10.1.4 Material
Filling Material
Approved material as per SABP-Q-012
Water
Construction Water, Groundwater and Seawater
Method Statement PAGE 10 OF 15
For REV A2
Soil Improvement
Work
The installation sequence could be divided into 5 main steps and detailed explanation shall
be found below:
10.2.2 Surveying
- Mark the location of the stone column as shown in the approved shop drawings
by the site surveyor.
- Positional tolerance for stone column is 150mm.
Safety measure during the execution of work shall be strictly implemented and observed.
CONTRACTOR’s safety team shall by then without excuses to implement the safety rules, regulation
and ensure that all personnel involved in the execution of work with full understating of it.
The following requirement are to be checked regularly but not limited to:
B. Stone Column