6/8/2021 6/9/2021

SCHEDULE PEK.EVAKUASI DAYA.REV1


Mulai
ENGINEERING
Drawing General Layout
DRAWING PONDASI SEALING END
Drawing Cross Section Galian
Drawing Layout & Long Section Switchyard 70 kV
Drawing Layout & Long Section GT
PROCUREMENTS
PIPA HDPE
PO
SHIPMENTS
70 kV Power Cable AL/XLPE 1x240mm2
PO
FABRIKASI
SHIPMENTS
Link box with SVL (3 in 1) complete with al acessories (1 Set R,S,T)
PO
FABRIKASI
SHIPMENTS
Link box for earthing (3 in 1) complete with al acessories (1 Set R,S,T)
PO
FABRIKASI
SHIPMENTS
3 kV Earthing Cable 185 mm2
PO

SHIPMENTS
Out door Seiling End 70 kV, for AL/XLPE 1x 240 mm2, complete with clamp and
supporting steel structure (untuk penempatan di kedua sisi).
PO
FABRIKASI
SHIPMENTS
Steel support for outdoor termination
PO
FABRIKASI
SHIPMENTS
Set of clamps, jumper, connectors and accessories for installation
PO
FABRIKASI
SHIPMENTS
CONSTRUCTION
Mobilisasi Demobilisasi Manpower for Termination @7 orang
Mobilisasi Demobilisasi Equipment for Termination
PEK.SIPIL
Pondasi Cable Sealing end
Galian & Pengeboran Bore Pile
Pembesian Bore Pile
Pengecoran Bore Pile
Galian Pondasi Pile Cap
Pembesian Pondasi Pile Cap
Bekisting Pondasi Pile Cap
Pengecoran Pondasi Pile Cap
PEK.ELMEK
Erection Steel support for outdoor termination
Galian Jalur Kabel Tanah
Urugan kembali
Laying and Jointing Pipe HDPE
Laying Cable 70 kV Power Cable AL/XLPE 1x240mm2
70 kV Cable Cleating untuk support kabel di terminasi
Terminating Sealing end ,Out door Seiling End 70 kV, for AL/XLPE 1x 240 mm2, complete
with clamp and supporting steel structure (untuk penempatan di kedua sisi).

Install Set of clamps, jumper, connectors and accessories for installation

Install Link box with SVL (3 in 1) complete with al acessories


Install Link box for earthing (3 in 1) complete with al acessories
Install 3 kV Earthing Cable 185 mm2
Pengujian
6/10/2021 6/11/2021 6/12/2021 6/13/2021 6/14/2021 6/15/2021 6/16/2021 6/17/2021 6/18/2021
6/19/2021 6/20/2021 6/21/2021 6/22/2021 6/23/2021 6/24/2021 6/25/2021 6/26/2021 6/27/2021
6/28/2021 6/29/2021 6/30/2021 7/1/2021 7/2/2021 7/3/2021 7/4/2021 7/5/2021 7/6/2021
7/7/2021 7/8/2021 7/9/2021 7/10/2021 7/11/2021 7/12/2021 7/13/2021 7/14/2021 7/15/2021
7/16/2021 7/17/2021
KERJASAMA OPERASI (KSO)
PLNT - RE

Jl. RE. Martadinata RT. 52 No. 35 Balikpapan - KALTIM 76121 Telepon : (0542) 8506674Facsimile : (0542) 8502918

SCEDHULE PEKERJAAN PENGGAILIAN PONDASI

KEGIATAN 5-Jul-21 6-Jul-21 7-Jul-21 8-Jul-21 9-Jul-21 10-Jul-21 11-Jul-21 12-Jul-21 13-Jul-21 14-Jul-21 15-Jul-21 16-Jul-21 17-Jul-21 18-Jul-21 19-Jul-21 KETERANGAN
PEMBERSIHAN LOKASI
PENGGALIAN
BORPILE
LIBUR
PEMBESIAN
PENGECORAN
PERAPIAN AREA SEKITAR DAN PERALATAN
KETERLAMBATAN
PELAKSANAAN
PEKERJAAN DAPAT
TERJADI KARENA
CUACA YANG BISA
BERUBAH SETIAP SAAT

ESTIMASI WAKTU
YANG LAMA AKIBAT
STRUKTUR TANAH
YANG MUDAH
MENGALAMI LOSNGSOR