Professional Documents
Culture Documents
Deedoke-HPP-EMP 2015 v18 Dec2020
Deedoke-HPP-EMP 2015 v18 Dec2020
Author
December 2020
Environmental Management Plan for Deedoke Hydropower Project Final Report
TABLE OF CONTENT
PAGE
TABLE OF CONTENT ........................................................................................................ i
LIST OF FIGURES ............................................................................................................ vi
LIST OF TABLES .............................................................................................................. vi
LIST OF PHOTOS ............................................................................................................vii
LIST OF ACRONYMS ....................................................................................................viii
CHAPTER 1 INTRODUCTION ......................................................................................... 1
1.1 NEED FOR ENVIRONMENTAL MANAGEMENT PLANS ............................ 1
1.2 GENERIC SCOPE OF AN EMP .......................................................................... 2
1.3 ORGANIZATION OF THIS EMP DOCUMENT................................................ 3
1.4 NEED FOR UPDATING THE EMPs .................................................................. 3
CHAPTER 2 PROJECT PROPONENT'S ENVIRONMENTAL AND SOCIAL POLICY
AND COMMITMENTS ...................................................................................................... 5
2.1 ANDRITZ’s POLICY STATEMENT .................................................................. 5
2.2 HIGH TECH CONSTRUCTION TRUST CO., LTD. (HTCT) ........................... 5
2.3 KANSAI ELECTRIC POWER CO., INC. (KANSAI) ........................................ 6
CHAPTER 3 INSTITUTIONAL ARRANGEMENTS ....................................................... 7
3.1 RESPONSIBILITIES OF THE PROJECT PROPONENT .................................. 7
3.2 RESPONSIBILITY OF THE CONTRACTOR .................................................... 8
3.3 RESPONSIBILITY OF MONREC ....................................................................... 8
3.4 RESPONSIBILITY OF STATE/REGION AND DISTRICT AUTHORITIES ... 8
3.5 RESPONSIBILITY OF THE EHS UNIT ............................................................. 9
CHAPTER 4 POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK .................... 10
4.1 CORPORATE ENVIRONMENTAL AND SOCIAL POLICIES ...................... 10
4.1.1 Andritz Hydro................................................................................................. 10
4.2.3 Laws and Regulations Related to Environmental Protection and Social Impact
Management .................................................................................................................. 17
LIST OF FIGURES
PAGE
Figure 1: PDCA cycle for environmental management ................................................................... 2
Figure 2: Application of the EIA’s EMPs ........................................................................................ 4
Figure 3: The main Project construction site and layout plan ........................................................ 68
Figure 4: Base map of the proposed transmission line alignment .................................................. 69
Figure 5: Location of air, noise and vibration sampling stations ................................................... 76
Figure 6: Location of air, noise and vibration sampling stations ................................................... 77
Figure 7: Location of surface water and aquatic ecology sampling stations .................................. 93
Figure 8: Incident resulting in injuries ......................................................................................... 163
Figure 9: Incident resulting in fatality .......................................................................................... 164
Figure 10: Fire and explosion ....................................................................................................... 165
Figure 11: Hazardous chemical/oil spill on water or land ............................................................ 166
Figure 12: Vehicle/equipment accident ........................................................................................ 167
Figure 13: Organization for project construction ......................................................................... 174
Figure 14: Project communities framework ................................................................................. 183
Figure 15: Location of air, noise and vibration sampling stations ............................................... 189
Figure 16: Location of surface water and aquatic ecology sampling stations .............................. 197
Figure 17: Movements of Dashidaira Dam and Periodic Behavior that is the Baseline .............. 205
LIST OF TABLES
PAGE
Table 1: Relevant international Treaties signed by Myanmar ........................................................ 28
Table 2: Governmental organizations and relevant environmental issues ..................................... 33
Table 3: Relevant environmental guidelines and standards ........................................................... 34
Table 4: National environmental quality (Emission) guidelines (2015) ........................................ 34
Table 5: National effluent standards............................................................................................... 35
Table 6: Summary of Project facilities ........................................................................................... 36
Table 7: Impacts during construction phase and mitigation measures ........................................... 37
Table 8: Impacts during Operation Phase and mitigation measures............................................... 62
Table 9: Surface water quality parameters ..................................................................................... 92
Table 10: Budget for occupational health activity........................................................................ 119
Table 11: Summary of integrated health programs for Deedoke HPP ......................................... 120
Table 12: Description of typical measures ................................................................................... 134
Table 13: Training programme for environmental awareness training ........................................ 135
Table 14: Training programme for health and safety awareness training .................................... 136
Table 15: Schedule of job-specific training requirements ............................................................ 137
Table 16: Training register form for recording attendance at training course .............................. 139
Table 17: Summary of Project Land requirements....................................................................... 143
Table 18: Entitlement Matrix ....................................................................................................... 146
Table 19: Outline of site inspection plan for construction ........................................................... 155
Table 20: Information requirements for internal and external communications in environmental
management during construction ................................................................................................. 178
Table 21: Surface water quality parameters ................................................................................. 196
Table 22: Example of Visual Inspection Guideline...................................................................... 206
Table 23: Schematic Threshold and Monitoring Matrix .............................................................. 208
Table 24: Schematic Response and Action Matrix ...................................................................... 209
LIST OF PHOTOS
PAGE
Photo 1: Tree transplant technique ............................................................................................... 115
LIST OF ACRONYMS
CHAPTER 1
INTRODUCTION
Results of an EIA study for a proposed development project will not lead to any
practical outcomes if the proposed mitigation measures and monitoring program are not
implemented in the construction and operational phases of the proposed project. Therefore,
an EIA study will need to extend beyond impact assessment to planning for implementation
of the proposed mitigation measures and monitoring program. In this regard, the results of
the EIA study will need to cover preparation of two environmental management plans
(EMPs): (i) one EMP for implementation by the Contractors in the construction phase; and
(ii) one EMP for implementation by the Project Proponent in the operation phase.
Recognizing this fact, the EIA Procedure requires the EIA study to include preparation of
a Construction phase EMP ( CEMP) and an Operational phase EMP ( OEMP) . The two
EMPs may be presented in Volume 2-EMPs while results of the EIA study are to be
presented as Volume 1-Main EIA Report.
The two EMPs are defined in the EIA Procedure 2015 as follows:
Operational Phase EMP means a detailed and comprehensive EMP for the
operational phase of a Project.Such plan shall present all relevant commitments, Emission
Limit Values, Environmental Quality Standards and other environmental requirements.
The plan shall include a description of the Project operations, installations, and
infrastructure, and shall present an overview of Adverse Impacts, present mitigation
measures together with time schedules, overview maps, images, aerial photos, satellite
images, site layout plans, cross- sections, transects, environmental management and
monitoring plans for each Project site, thematic plans, and management procedures as
appropriate.
The above definitions clearly indicate that the two EMPs required by MONREC
will be comprehensive and have more details than conventional EMPs presented in EIA
reports of the past. This requirement of MONREC is in line with current good EIA
practices.
Therefore, an EMP will need to cover the following subjects: (i) mitigation
measures to be implemented; (ii) arrangements for the implementation of mitigation
measures; (iii) monitoring, evaluating and reporting of the implementation of mitigation
measures to provide feedback information on whether the environmental performance
deviates from the prescribed benchmarks; (iv) corrective actions process if the
environmental performance below the benchmarks, environmental incident response, and
emergency plan; (v) arrangements for operating the EMS, including organizational
structure, responsibilities, documentation, training, communication, and management
review; and (vi) involvement of stakeholders or affected people in environmental
management, including public grievance redress mechanism.
The EIA Guideline 2014 recommends an outline of the EMP in Section 5.2
Generic Content of an EMP and also in Appendix 10-EMP-Table of Contents. The two
outlines are different, thus causing confusion as to which outline should be adopted. This
EMP document is structured to follow the two outlines as appropriate within the
environmental management context of this Project. The essence of each chapter following
this introductory chapter is as follows:
The CEMP and OEMP presented in this Document are based on preliminary
project designs and initial construction plans and schedules. Therefore, the two EMPs
should be considered as framework plans. They are intended to provide framework and
prescribe requirements for the preparation of detailed CEMP and OEMP by the Contractors
(Contractor), e.g. the Civil Works contractor, the Electro-mechanical Works Contractor and
the T-Line Contractor. In this regard, the Project Proponent will require each Contractor to
prepare a detailed CEMP in due course before commencing the construction, and a detailed
OEMP in due course before commercial operation of the hydropower plant.
The Contractors will use the CEMP presented in this Document as the basis to
prepare a detailed CEMP based on the Contractor’s final designs, construction plan and
methods, and construction schedule. The scope and content of the Contractor’s CEMP will
not be less than the scope and content of the CEMP in this Document. The Contractor’s
CEMP shall be contractually binding. During the construction, the Contractor will
implement the Contractor CEMP under the supervision of the Project Manager to be
appointed by the Project Proponent (Owner).
As the Contractors will be responsible for the design, supply, installation, testing,
and commissioning of the hydropower plant and its associated facilities, the Contractors
will use the OEMP presented in this Document as the basis for preparing a detailed OEMP
based on the actual construction, results of plant commissioning, and final operational
procedures. The Power Plant Management Team of the Project Proponent or Owner will
review and revise the Contractor’s OEMP as appropriate to prepare the Owner’s OEMP for
implementation in the operational phase.
For clarity, the application of the EIA’s EMPs as above described is shown as a
diagram in Figure 2. FIGURE 9.1-1: APPLICATION OF THE EIA-EMP
Implement the
Contract- Contract-CEMP Implement the
EIA/CEMP
CEMP through CMS/WI Final OEMP
and FInal O&M
Manuals
CHAPTER 2
PROJECT PROPONENT'S ENVIRONMENTAL AND SOCIAL
POLICY AND COMMITMENTS
Being one of the first major players in energy sector in Myanmar, High Tech
Construction Trust Co., Ltd. (HTCT), a subsidiary of Shwe Taung Group, is a leading
project management and construction company, known for the ability to deliver high-
quality infrastructure projects on time and budget. With a strong commitment to health and
safety, HTCT provides innovative and industry-leading project management, construction
and design services across the Country.
Sustainability has always been at the core of the Group’s strategy. Our activities
are guided by our corporate vision “Inspiring Lives. Sustaining Progress”
KANSAI Electric Power Co., Inc. has the policy statement on project
development and KANSAI will contribute to sustainable development of communities
through fair business activities.
Fundamental Responsibilities
CHAPTER 3
INSTITUTIONAL ARRANGEMENTS
Construction Phase
1) Ensure that the Contractor will update the CEMP presented in this document
to prepare a detailed CEMP based on the results of detailed design, construction plan, and
construction schedule.
2) Establish and operate an environmental and social management system
(ESMS) containing elements outlined in this EMP.
3) Supervise the Contractor closely in implementing the Contractor CEMP as
an integral part of its project implementation management and construction supervision.
4) Submit periodic monitoring report to MONREC as required in the EIA
Procedure 2015.
5) Notwithstanding the periodic monitoring reports to be submitted to
MONREC, keep MONREC and other concerned authorities informed of any serious
environmental events and responses to the events.
6) Conducting periodic audit of environmental and social performances of the
Contractor.
Operational Phase
1) Ensure that the Contractor will update the OEMP presented in this document
to prepare a detailed OEMP based on the results of detailed design, results of
commissioning, and operational manuals.
2) Establish and operate an environmental and social management system
(ESMS) containing elements outlined in this EMP. The ESMS will be part of the
management system of the hydropower plant.
3) Establish an Environment, Health and Safety (EHS) unit within the
organization for operation and maintenance of the hydropower plant. The EHS unit will be
adequately staffed with qualified personnel.
4) Ensure that the Hydro Power Plant Manager will operate the EHS unit to
comply with all EHS requirements prescribed in the ECC.
5) Submit periodic monitoring report to MONREC as required in the EIA
Procedure 2015.
1) Prepare a detailed Contractor CEMP for review and approval by the Project
Proponent. The Contractor CEMP should follow the outline prescribed by the Project
Proponent as proposed in Appendix 3A of this EMP.
2) Implement the mitigation measures during the construction through
construction method statements and work instructions in strict conformance with
environmental conducts prescribed in the Contract.
3) Ensure that all process and environmental control equipment meet all
technical specifications related to their environmental performance.
4) Conduct periodic monitoring and reporting of its compliance with the
environmental and social performance prescribed in the Contract.
5) Ensure that its sub-contractors shall comply with the Contractor CEMP.
6) Consistently update the Contractor CEMP and submit the updated version
to the Project Proponent for approval.
In the construction phase, the Project Proponent will establish an EHS unit
within its project management organization. In the operational phase, the Project Proponent
will establish an EHS unit within the organization for O&M of the hydropower plant and
its associated facilities. Functions and responsibilities of the two EHS units are described
in the CEMP and OEMP.
There are three key groups with responsibility for environmental management
of the Project:
CHAPTER 4
POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK
As ANDRITZ is the lead partner of the Joint Venture, environmental and social
policies of the new corporate to be set up for operating the Project would follow the existing
health, safety, and environmental (HSE) policies of ANDRITZ. ANDRITZ’s corporate
HSE policies were issued by its Management and are applied through its internal
regulations R HY QM 003 and R HY QM 004 to all of its subsidiary business concerns.
The HSE policies are implemented through a Health, Safety and Environmental
Management System (HSES), a sub-system of its corporate integrated management system.
The HSES is described in more detail in the specific HSE-manuals and instructions.
Particularly, the HSES’s Environmental Management System receives ISO 14001:2004
certification.
Environmental Management
Being one of the first major players in energy sector in Myanmar, High Tech
Construction Trust Co., Ltd. (HTCT), a subsidiary of Shwe Taung Group, is a leading
project management and construction company, known for the ability to deliver high-
quality infrastructure projects on time and budget. With a strong commitment to health and
safety, HTCT provides innovative and industry-leading project management, construction
and design services across the Country.
4.1.2.1 Human Rights and Labor Rights Policy
Shwe Taung Group (the Group) is committed to being a good corporate citizen
and contributing to the society of Myanmar within which we operate. Shwe Taung fully
support the United Nation’s Universal Declaration of Human Rights, to which every human
being is entitled. As a company, we utilize the 30 articles from within the Universal
Declaration of Human Rights as a common standard of achievement across all facets of our
work. We acknowledge that the common understanding and compliance to these rights and
freedoms are of the greatest importance.
Shwe Taung also understands and gives full support to the principles of the
International Labor Organization’s (ILO) Core Conventions and Principles. These cover
the areas of freedom of association and common bargaining, the elimination of all forms of
forced or compulsory labor, the effective abolition of child labor and the elimination of
discrimination in respect of employment and occupation.
4.1.2.2 Transparency
Shwe Taung believes that open and transparent communication and feedback are
essential elements of enhancing our relationship with our stakeholders, reducing risk,
sustainable development and improving management of our operational impact on others.
We endeavor to provide a transparent, relevant and fair report on our activities. We
dedicated time and manpower to provide accurate assessments of our procedures and
actions. We communicate on both the progress of our projects and on our CSR activities.
The Group’s philosophy is that the well-being of our company and clients is
dependent on the health and safety or the Group’s workplace. Every precaution reasonable
in all circumstances shall be taken for the protection of all workers. The welfare of the
individual is our greatest concern.
The Group are committed to providing a healthy and safe working environment
for the Group’s employees and any visitors to the Group’s work sites, in order to protect
people and property/physical assets, in accordance with industry standards and in
compliance with legislative requirements.
Sustainability has always been at the core of the Group’s strategy. The Group’s
activities are guided by the Group’s corporate vision “Inspiring Lives. Sustaining Progress”
At Shwe Taung Group, the Group recognize the need to respect the environment
and be cautious when conducting projects that may adversely harm the eco-system and
biodiversity of Myanmar. The Group is actively working towards reducing the Group’s
carbon footprint across all the Group’s operations and continues to develop tools to measure
the outcomes of the Group’s progress in the direction of being more carbon neutral and
environmentally sustainable.
The Group believe that businesses are fully responsible for achieving good
environmental practices and operation in a sustainable manner. The Group is therefore
committed to reducing the Group’s environmental impact and continually improving the
Group’s environmental performance as an integral and fundamental part of the Group’s
business strategy and operating methods.
4.1.2.7 Environment
The detail of Human Rights and Labor Rights Policy, Transparency, Workplace
Health and Safety Policy, Community and Environment; Sustainability Policy and
Environmental, Health and Safety and Environment are described at Appendix 3B in ESIA
Report.
KANSAI Electric Power Co., Inc. has the policy statement on project
development and KANSAI will contribute to sustainable development of communities
through fair business activities.
Fundamental Responsibilities
• Give top priority to ensuring safety.
• Surely Implement CSR.
• Keep changing to accomplish our abiding mission.
KANSAI Electric Power defines and practices the five items outlined right as
our Action Standards for Procurement Activities. KANSAI furthermore utilize business
negotiations, plant visits and the like to explain and promulgate CSR Procurement Policy
to partners.
CSR Action Principles 1 - Safe and Stable Delivery of Products and Services as
Chosen by Customers
CSR Action Principles 2 - Proactive Approach with a View to Creating Ever
Better Environment
CSR Action Principles 3 - Proactive Contributions to Development of Local
Communities
(1) Policy and legal framework which provide the foundation for environmental
management.
(2) Regulations which govern the EIA process, the processing of EIA
documents for the issuance of environmental clearance certificate, and implementation of
the environmental management plans.
(3) Laws and regulations related to environmental protection, environmental
quality standards and social management requirements.
(4) Laws specific to the project site.
The national policy and legal framework will need to agree with international
treaties and agreements which Myanmar is a signatory. In addition, they should be in line
with international standards and guidelines.
The purpose of this law is to promote and safeguard public health and to
take necessary measures in respect of environmental health. The Project Proponent has to
ensure that community and occupational health and safety of the project area is protected
for safeguard public health law under section 3 and 5 of said law.
The Project Proponent has to follow the steps when a Principal Epidemic
Disease or a Notifiable Disease occurs:- under section 4 of said law.
The Project Proponent has to ensure that the head of the household or any
member of the household shall report immediately to the nearest health department or
hospital when any of the events occurs such as rat fall, outbreak of a Principle Epidemic
Diseases, and outbreak of a Notification Disease, under section 9 of said law.
The Project Proponent has to prevent and control the spread of a Principal
Epidemic Disease, the Health Officer may undertake the following measures, under section
11 of said law:-
The Project Proponent has to know the punishment and control of explosive
substances under section 4 and 5 of this law.
This law states clearly that employers have to take care of employees’
benefits, security and welfare, especially benefit from injury and occupational diseases
during pre-construction and construction phase. This law is therefore related to
occupational health and safety (OHS) of employees under section 15 (a) of said law.
The Project Proponent has to prepare and keep records and lists correctly of
worker's daily attendance, appointment of new workers, employing worker by changing of
work, termination, dismissal and resignation, promotion and paying remuneration, under
section 75(a) of said law.
The Project Proponent has to inform the relevant township social security
office if changes in number of workers and establishment, change of employer, change of
business, suspension of work, and close-down of work, and employment injury, decease
and contracting diseases during construction phase under section 75(b) of said law.
The Project Proponent has to ensure that the person in charge shall do the
following: under section 9 of said law:
(a) Keep the captain and mark referring that it is a non-smoking area at the
place mentioned in section.
(b) Arrange the specific place where smoking is allowed as mentioned in
section 7, and keep the caption and mark also referring that it is a specific place where
smoking is allowed
(c) Supervise and carry out measures so that no one shall smoke at the non-
smoking area
(d) Accept the inspection when the supervisory body comes to the place for
which he is responsible
The Factories Act (1951) is relevant to the OHS issue of this Project. This
Act describes about health, safety, welfare, special applications and extensions, working
hours of adults, employment of young persons, punishments and procedure which related
the project during construction and operation phase. The Project Proponent has to follow
all of the section which is related with project as described in the factories act.
The Project Proponent has to follow: (b) The investor may appoint of any
citizen who is a qualified person as senior manager, technical and operational expert, and
advisor in his investment within the Union. (c) The investor shall appoint only citizens for
works which does not require skill. (d) The investor shall appoint skilled citizen and foreign
workers, technicians, and staff by signing an employment contract between employer and
employee, in accordance with the labor laws and rules, under section 51(a), (b), (c) and
(d) of said law.
The Project Proponent has to insure the types of insurance stipulated in the
provision of the rules at any insurance enterprise which is entitled to carry out insurance
businesses within the Union of under section 73 of said law.
The Project Proponent has to explain the detail of project and cooperate with
the national races who resided in the project area, under section 5 of said law.
The Project Proponent has to follow the directive of the Department of Fire
Bridge to reserve fire brigade, and provide fire safety equipment to protect the emergency
and accident plan for public who resided in the project area, under section 25 of said law.
The Project Proponent has to follow law describes about any registered
engineer, graduated technologist and technician should abide by the rules, procedures,
orders, directives and should abide by the ethical principles that stipulated by the council
under section 31 (a) and (b) of said law.
The Project Proponent has to follow that no one shall perform any
engineering and technological work which are specified as being dangerous to the public
by a rule enacted under this law, without having received a registration certificate issued
by the council, except for engineers appointed in a government department or an
organization in the performance of their duties, under section 37 of said law.
The Project Proponent has to follow the city of Mandalay Development Law
for BOT contract and commit for transfer at exact period.
This law states which related to the Project are described in Section 18, 21
(a), 22 (a), 26 (a, b), 27, 40, and 68 as follows:
The Project Proponent has to ensure that the license holder can engage in
electric power generation and distribution only after having received the electrical hazards
safety certificate from the chief inspector, under Section 18 of law.
The Project Proponent has not to fails to comply with the following under
Section 21 of law for complying with the law, rules, regulations, procedures, orders and
directions or the specified quality standards and norms, be responsible in accordance with
the law if any person or organization is affected or suffers a loss as a result.
The Project Proponent has to hold the responsibilities with the following
under Section 22 of law.
The license holder shall be responsible in accordance with the law if any
person or organization is affected or suffers a loss due to his negligence in performance
The Project Proponent has to ensure that the license holder must comply
with under Section 26 of law.
The project has to ensure that the license holder and the authorized person
must inform the chief inspector and the relevant department in charge immediately if an
electrical hazard has accidentally occurred when generating, transmitting, distributing or
consuming electric power, under Section 27 of law.
The Project Proponent has to ensure that the license holder comply with the
rules, norms and procedures issued by the ministry and accept necessary inspections by the
relevant government departments and organizations, under Section 40 of law.
The Project Proponent has to ensure that, if the license holder negligent or
irresponsible of persons who assigned by him has caused injury, disability or death by
electrocution or fire, these aggrieved person has the right to request compensation from the
license holder as follows: under Section 68 of law.
The Project Proponent has to follow the detail section of motor vehicle rules
to avoid the negative impact of air and noise pollution, occupation health and safety, and
socio-safety for who lived near the project area, under this Law.
The Project Proponent should announce local community to follow the law
for road safety and should explain to workers, vehicle drives should follow the law of motor
vehicle to avoid road accident, air and noise pollution during pre-construction and
construction phases that described at section 51, 52, 54, and 57 of said law.
The Project Proponent has to follow all of the functions relating to any
petroleum and petroleum product by issuing licence to vehicles, vessels and barges that
carry any petroleum and petroleum product, determining period, form , conditions, means
of applying for licence, permitting authority and fees to be assessed, determining and
supervision on ports for vessels and barges that carry out import, export, and transport by
water in accord with procedures, taking action, as necessary, in accordance with the
existing laws if it occurs spill or accident in carrying out import, export, transport, and sale
and distribution of petroleum and petroleum product by water and determining procedures
and conditions to be abided by in carrying out transport business except transport by
pipeline under section 9 of said law.
The Project Proponent has to follow the issuing licence for the right to store
for the storage tanks and warehouses, issuing transport permit for the vehicles, vessels and
barges that shall carry any petroleum and petroleum product, determining the period, form
and terms and conditions, manners of applying licence, permitting authority and fees to be
assessed, for licence under subsection (a) and permit under subsection (b) and even if it
occurs environmental impacts in carrying out petroleum and petroleum product business
activities, taking action, as necessary , in accordance with the existing laws of on-site
inspection and also determining, in coordination with ministries concerned, procedures and
conditions relating to standard and quality of storage tanks and warehouse, and tanks of
vehicles, vessels and barges that carry any petroleum and petroleum product of under
section 10 of said law.
The Project Proponent has to follow the descriptions of the Petroleum Rules
which are related with Deedoke Hydropower Project under chapter 3 and 4 of said law.
The Project Proponent has to ensure that obtained any license shall not
violate the conditions contained in the license of under section 7 of said law.
The Project Proponent has responsibility for carrying out the acquisition and
distributing compensation but the funds for compensation are to be provided by the
company acquiring the land. Compensation must be paid at market value with adjustments,
including for crops, The Land Acquisition Act 1894 provides the basis for the Government
of Myanmar to acquire land for public and other purposes and addresses processes for
required notice; procedures for objecting to acquisition; land valuation methods; the
process for taking possession of land; the process for appeals; and rules for the temporary
occupation of land. The Land Acquisition Act 1894 sets out a process for the acquisition of
land as follows:
a. preliminary investigations on the land and procedure for notification of,
and objections to be raised by, persons interested in the land (Article
5A);
b. agreement between the company and the Government is to be disclosed
in the National Gazette;
c. notice is to be given to the public (Article 42);
d. notices are to be posted publicly in the locality of the land (Article 4
(1), Article 9 (1)).
e. notice to the occupier of the land must be given (Article 9 (3), but only
once there is a declaration of intended acquisition.
Although there are provisions for objections to the land acquisition (Article
5A (1)), the President’s decision on the objection is final (Article 5A. (2)), giving wide
discretionary powers to the President. A 2011 amendment to the Land Acquisition Act 1894
changed the rate of compensation from ‘market value’ to ‘’the market value of the land or
three years average value of a similar land which exists surrounding it; whichever is more.
The Land Acquisition Act 1894 permit the Government to use compulsory
acquisition to acquire land for public purposes and for business purposes. The Land
Acquisition Act 1894 defines neither purpose in detail, leaving landholders vulnerable to
losing their land through arbitrary processes.
The Project Proponent has to follow the rights available to those in rural
areas in a limited manner in principle, it is important to reiterate that without either a deed
of title or legal registration of rights in land, those residing or using the land in question are
effectively without rights to the land concerned under statutory law. Because it is estimated
that only 15% or less of all farmers can show a land registration document, and the fact that
many in the rural sectors of the country live under customary land law arrangements that
are not adequately protected under domestic laws, it is clear that farmers, shifting
cultivators and villagers in rural, upland and ethnic areas are tremendously vulnerable to
abuses of their land rights and to land acquisition and subsequent displacement.
The Project Proponent has to control motor vehicles which shall effect
compulsory Third Party Liability Insurance with the Myanmar Insurance of under section
15 of said law.
The Project Proponent has to operate an enterprise which may cause loss to
State-owned property or which may cause damage to the life and property of the public or
which may pollution to the environment shall effect compulsory General Liability
Insurance with the Myanmar Insurance of under section 16 of said law.
The Project Proponent has to follow and allow the leave and holidays act
which is related with all employers.
The Project Proponent has to follow the Labor Organization Law for
protecting the rights of the worker, to have good relations among the workers between
employer enable to form and carry out the labor organizations systematically and
independently. The followings describe in the Labor Organization Law which is related
with the Project under the section 17, 18, 19, 20, 21, and 22 of said law.
The Project Proponent has to follow the duties of the employer which
specified that the minimum wages should to pay for the worker who works for the Project
during pre-construction, construction and operation phases in section 12 and 13 (a), (b),
(c), (d), (e), (f) and (g) of said law.
The Project Proponent has to ensure that a person desirous of any of the
followings within the specified area of an ancient monument shall apply to get prior
permission to the Department, constructing a building which is not consistent with the
terms and conditions stipulated according to the region by the Ministry near and at the
surrounding of an ancient monument under section 15(h) of said law.
The Project Proponent has to ensure that no one shall carry out any of the
following acts which is assumed to cause damage to an ancient monument within the
specified area of an ancient monument or of a listed ancient monument without a written
prior permission; (f) discarding chemical substance and rubbish which can affect an ancient
monument and the environment under section 20(f) of said law.
C. Law Related to Ecological Concerns
Myanmar Forest Policy (1995)
The Project Proponent has to follow Myanmar Forest Policy of land use,
protection and management, forest regeneration and afforestation and identified strategies
/ actions in the short, medium and long term for developing Deedoke Hydropower Project.
The Forest Law (2018)
The Forest Law (2018) was enacted on September, 20. The Law includes
certain objectives to ensure long-lasting forest management and sustainable development.
It is directed towards implementation of the forest policy and environmental conservation
policy and endeavors to reduce the occurrence of natural disasters in line with international
standards.
The Law sets out two types of permit that are to be obtained for carrying out
the below stated business activities: 1) Extraction of forest produce; and 2) Establishment
of wood-based industry.
The permit for establishment of wood-based industry can be obtained from
the relevant Forest Officer for the purpose of carrying out activities involving sawmills,
sawpits, tongue-in-groove mills, plywood mills, veneer mills or wood-based industries.
For any specified forest land and forest-covered land at the disposal of the
Government, anyone who wishes to carry out any development work or intends to
implement any economic scheme shall obtain the prior approval of the Ministry and of the
Director-General or the concerned forest officer.
The Law provides for tougher penal provisions including imprisonment
and/or fines for any non-compliance, in line with the Government’s objective of conserving
the country’s dwindling forests.
The Farmland Law (2012)
The Project Proponent has to respect of application of use the farmland by
other means for the interests of the public under section 30 (a) and (b) of said law.
D. Laws Related to Freshwater Environments
Laws related to freshwater environments are described in different sectoral
laws under two ministries, the Ministry of Livestock and Fisheries and MONREC. For the
Freshwater Fisheries Law (1991), the detail of laws can described as follow:
is an organization of the World Bank Group. They are also adopted by most development
organizations such as the Asian Development Bank. It should be noted that the guidelines
and standards recommended by the World Bank and IFC, especially those related to
environmental pollution, also gave due consideration to the guidelines and standards of the
EPA and WHO.
IFC’s standards and guidelines relevant to this Project are described in two
documents:
The second document provides general guidelines for environmental, health and
safety (EHS) for development projects.
Essential requirements in the two IFC documents pertaining to this Project are
summarized below.
IFC prescribes eight Performance Standards to which its clients will need to
comply throughout the investment life of IFC. The eight performance standards (PS) are:
The eight PSs cover all environmental and social aspects of development
projects.
PS2 requires the client to: (i) formulate and implement human resources
policies and procedures appropriate to its size and workforce that set out its approach to
managing workers consistent with the requirements of this Performance Standard and
national law; (ii) provide reasonable working conditions and terms of employment; (iii)
treat migrant workers on substantially equivalent terms and conditions to non-migrant
workers carrying out similar work; (iv) establish grievance mechanism; (v) refrain from
using child labor and forced labor; and (v) provide a safe and healthy work environment,
taking into account inherent risks in its particular sector and specific classes of hazards in
the client’s work areas, including physical, chemical, biological, and radiological hazards,
and specific threats to women. These requirements will also be applied to workers of the
contractors through effective contractual arrangements between the client and the
contractors.
PS3 requires the client’s project to: (i) efficiently use energy and water; and
(ii) use best available techniques (BAT) in pollution control.
This PS requires the client to: (i) evaluate the risks and impacts to the health
and safety of the Affected Communities during the project life-cycle; and (ii) establish
preventive and control measures consistent with good international industry practice
(GIIP), such as in the World Bank Group Environmental, Environmental, Health and Safety
Guidelines (EHS Guidelines) or other internationally recognized sources. The requirements
are elaborated in the PS document. Some of the requirements, such as hazardous materials
management, are similar to those in PS3. In essence, safety aspects to the communities and
operators will need to be fully considered in engineering design, construction and
operations of all Project facilities, including support facilities or infrastructure. Health risks
will also be included.
PS6 requires the ESIA to consider direct and indirect project-related impacts
on biodiversity and ecosystem services and identify any significant residual impacts. As a
matter of priority, the client should seek to avoid impacts on biodiversity and ecosystem
services. When avoidance of impacts is not possible, measures to minimize impacts and
restore biodiversity and ecosystem services should be implemented. Given the complexity
in predicting project impacts on biodiversity and ecosystem services over the long term,
the client should adopt a practice of adaptive management in which the implementation of
mitigation and management measures are responsive to changing conditions and the results
of monitoring throughout the project’s lifecycle.
PS7-Indigenous Peoples
PS8-Cultural Heritage
PS8 requires the client to: (i) protect cultural heritage from the adverse
impacts of project activities and support its preservation; and (ii) promote the equitable
sharing of benefits from the use of cultural heritage. The ESIA will need to identify sites
of cultural heritage and assess their value or importance at the community, provincial and
national levels.
It should be noted that all the eight PSs are in line with the Government’s
policy and regulations. For this Project, PS7 is not relevant for the following reasons:
According to the field survey in April 2015, all villagers living within the
project affected area are of Burmese ethnic. They are the majority of the country. Although
only very few villagers are not Burmese, they are well integrated into the communities.
Furthermore, the Project development will not create any impacts on cultural practices of
the locals.
Environment covering: (i) air emissions and ambient air quality; (ii) energy
conservation; (iii) wastewater and ambient water quality; (iv) water conservation; (v)
hazardous materials management; (vi) waste management; (vii) noise; and (viii)
contaminated land.
Occupational Health and Safety covering: (i) general facility design and
operation; (ii) communication and training; (iii) physical hazards; (iv) chemical hazards;
(v) biological hazards; (vi) radiological hazards; (vii) personal protective equipment; (viii)
special hazard environments; and (ix) monitoring.
Community Health and Safety covering: (i) water quality and availability;
(ii) structural safety of project infrastructure; (iii) life and fire safety (L&FS); (iv) traffic
safety; (v) transport of hazardous materials; (vi) disease prevention; and (vii) emergency
preparedness and response.
The EIA process for this Project will be administered by the central ECD in
coordination with the regional ECD and various government organizations at the regional,
township, and district levels.
4.3.2 Sectoral Framework/Mechanism
Natural Resources
Banned Pesticides
Toxic chemicals
Natural Disaster
Water Pollution
Environment in
Environmental
Water Supply
Environmental Issues
Air Pollution
Biodiversity
Solid Waste
Forest and
Education
Factory
Energy
Desert
Governmental Organizations
CHAPTER 5
SUMMARY OF IMPACTS AND MITIGATION MEASURES
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Noise Increase ambient noise level at the • Major construction activities which generate loud noise should
construction site, quarry site and be limited to only during the day time. Activities that are necessary to
communities near the material be carried out at night time will need approval of the site engineers,
transportation routes. and will need to have adequate noise control equipment or measures.
• Speeds of vehicles in the construction site will not be more than
40 km/hr.
• Noise performance requirements of construction equipment will
need to be clearly stated in contract specifications.
• Temporary sound barriers or shielding should be installed for
non-mobile equipment.
• Contractors will be required to regularly monitor ambient noise
levels at the receptors, particularly during the noise generation period
such as piling.
• The construction environmental management plan will need to
include an efficient complaints redress procedure and an efficient
corrective action procedure to address the non-compliance of noise
performance.
Vibration Increase vibration at the construction site, • Contractor will prepare a blasting plan to reduce ground
quarry site and communities near the vibration and air pressure to the acceptable levels. The blasting plan
material transportation routes. will be reviewed for approval by the supervision engineers of the
Project Proponent.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Topography, Geology To minimize the landslide and slope • Perform detailed subsurface investigations to clearly identify any
and Seismology failures caused by the earthwork excavation problem layers, and totally remove these zones during construction to
activities could damage the project prevent stability problems; if this is not possible, make improvements
properties, and pose a health risk to the in these layers.
construction workers. • Design the appropriate slope for areas of high potential of sliding
and align the direction of excavation or slope surface perpendicular or
some degrees with major joints/fault zone,
• Use slope design with a high safety factor to prevent sliding,
• Where necessary, reservoir banks should be graded to reduce
erosion and slumping potential,
• Construction equipment used outside the reservoir zone should
be of a type that will cause minimum damage to soils with low
bearing capacity and soft rock layers underneath,
• Install special devices to build up rock strength and to improve
stability such as line concrete on excavated rock surface, insert rock
bolts and rock anchors, restore vegetable (if possible),
• Perform groundwater monitoring program and use de-watering
(drainage) holes if necessary.
Erosion and Soil erosion occurs naturally depending on General Mitigation Measures
Sedimentation many factors among erosivity of the rain, • Minimize the area of land clearance, and retain vegetation in
erodibility of the soil, slope length and riparian and other suitable locations to minimize erosion of the river
steepness, crop practice and conservation banks;
practice. Prior to construction, the factor • Carefully monitor land clearance activities throughout the pre-
(crop practice) on which soil erosion construction phase to ensure that vegetation is not cleared beyond
depends is increased, because the clearing pre-defined project boundaries;
of the construction would remove • Install drainage control structures at suitable locations to divert
protective vegetative cover. It is anticipated clean runoff away from disturbed area;
that until the construction site is covered
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Erosion and by all project’s facilities or re-vegetation, • Install settling ponds to avoid turbid water caused by construction
Sedimentation soil loss would be greater than existing activities to flow out to the river;
(Cont’d) condition. • Cover spoil bank slopes by sodding with stockpiled topsoil, and
rehabilitate a surface drainage system to keep slope stability and to
avoid erosion;
• Progressively do re-vegetation of disturbed area as soon as
practicable, to facilitate long term stabilization;
• Regularly monitor suspended sediments and sedimentation rates
at key locations upstream and downstream of project facilities, during
construction, to confirm the extent of impacts and implement suitable
management responses; and
• Strictly implement the mitigation measures for solid waste
management and surface water quality.
Clearing of vegetation
• The extent of areas to be cleared will be minimized as far as
practical.
• The use of existing cleared areas will be maximized.
• Clearing of sites will be undertaken in the sequence that sites are
required for construction.
• Progressive revegetation of exposed areas will take place as soon
as practical following completion of construction works in that area.
Suitable species for revegetation will be used.
• If construction works are temporarily stopped in an exposed area
(for longer than 14 days), temporary stabilization of exposed surfaces
will be undertaken.
Exposed areas
• All areas required to be disturbed will be clearly identified and
the boundaries marked on the ground
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Erosion and • Areas not required to be disturbed will be retained in their
Sedimentation original condition.
(Cont’d) • Rip-rap, or similar, will be installed at the inlet and outlet of
culvert, if necessary, to prevent scour erosion.
• Retention of existing vegetation along watercourses will be
maximized to reduce flow velocities and to minimize erosion.
• ‘Clean’ runoff from undisturbed areas will be diverted away from
the construction site and into established watercourses.
• Runoff from disturbed areas will be directed into sediment
trapping or filtering devices.
• Silt fences or vegetative fences should be installed along the top
of river banks to intercept any sediment migrating in runoff toward
the river.
• Sediment collection facilities such as a settling pond should be
periodically cleaned up to keep its function.
• Sediment collection devices will be sized to collect and treat run-
off from the site as appropriate.
• Turbidity of the water discharged from the settling pond will be
periodically monitored, and function of the settling basin should be
secured.
• All discharge from sediment collection devices will pass through
a vegetative or silt filter, prior to release to an established
watercourse.
• All erosion and sediment controls will be visually inspected at
least once a week during the dry season and every 24 hours during the
wet season to ensure their ongoing effectiveness. Any required
remedy or replacement works will be undertaken within 24 hours of
detection.
• The results of the inspections will be recorded and reported to the
Project Proponent.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Erosion and • At least one month prior to the anticipated commencement of the
Sedimentation wet season, a review of the effectiveness and adequacy of the existing
(Cont’d) erosion and sediment controls will be made and any necessary
modification and/or augmentation of controls carried out.
Spoil disposal area establishment
• Long term spoil placement sites will be managed in accordance
with the Contractor’s CESMMP.
Temporary stockpile establishment
• Temporary topsoil stockpiles will be developed.
• Silt fences or vegetative fences will be constructed downstream of
stockpiles to control runoff where necessary.
Use of access roads by construction vehicles
• Access to and within construction sites will be limited to
designated access roads and internal haul roads.
Flood Impact from flood is not major problem in • The Project Proponent will daily inform the Contractors of the
construction phase but in operation phase; river flow data available at the Yeywa Hydropower Plant. The
the impact mitigation device e.g. flood Contractors should analyze the data and reflect it to their flood
warning system has to be put in place since warning and counter measures. Information of the flood warning will
construction phase. be delivered to the Project Proponent and the upstream and
downstream communities.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Surface Water Quality Increased turbidity of river water due to in- • Reduce the submerged biomass to the maximum extent by means
river construction activities and river bed of pre-impounding clearing
excavation or dredging. Degradation of • Minimize earth works as much as possible in direct contact with
river water quality due to inappropriate the river.
management of construction wastes and
domestic waste from site. • Install sedimentation ponds for drainage water from quarries and
other construction.
• Vegetation removal should be limited only in the construction
areas.
• The site preparation activities, including land clearing and site
filling and compaction, should be carried out after taking counter
measures to avoid the problem of surface runoff with high turbidity
discharging into the surrounding paddy field or nearby drainage
channels, if exist.
• To prevent contamination of the surface runoff, potential
contamination sources will be covered with roof. The surface runoff
would contain only suspended solids washed out from the open area.
• Construct a temporary drainage system to collect the surfaced
runoff from the construction area to avoid the discharge of surface
runoff to avoid erosion in the surrounding area.
• Toilet wastes will be discharged into a septic tank (or more than
one septic tank).
• Prevent truck cleaning, lorries, and other equipment used for
preparing, transporting or applying concrete in the river.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Aquatic Ecology Monitor the implementation of mitigation • Use of best practice to avoid/minimize releasing sediment load
measure to ensure the minimum impacts on into the river, e.g. using nylon screens to minimize sediment from
surface water quality and aquatic ecology. steep slope releasing to the river.
• Using of illegal fishing gear anywhere along the river in
construction area should be prohibited.
• Waste water and contaminated water from construction areas and
worker camp site must be treated before discharge to Myitnge River.
• Survey of fish species composition in the project area in both
upstream and downstream must be implemented. Furthermore, the
effect on fish migration or some effects during construction phase on
the fish spawning ground should have been studied.
• Additional survey to identify the spawning and nursing ground in
the tributaries upstream must be implemented. That are should be
protected as the conservation area and fishery activity must be
prohibited
Material Storage Area Best practice for material storage is the • Fuel oil and lubricants storage areas will be suitably bunded and
method to prevent the problem for material constructed to minimize the potential for leaks
and equipment to the human and • Spill containment equipment will be available at the unloading
environment. Moreover, the method can pad for use in the event of spillage
minimize the source of impact to human • Ignition sources will be strictly controlled and limited to avoid a
and environment. fire
• Appropriate firefighting materials and equipment will be
available to suppress fires
• For solid waste, separate each type of wastes and collect solid
waste in appropriate and safety container for recycling where
facilities are available. Any surplus to the recycling activity will be
disposed of at an approved waste disposal site.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Material Storage Area • Mobile equipment must be maintained, cleaned, and stored in the
(Cont’d) suitable warehouse with contain the roof, close container, or covered
with tarpaulin to protected wind and rain.
• Storage of hazardous material will be in designated, clearly
marked area, and far from the waters source.
• Material Safety Data Sheets (MSDS) must be located in close
proximity to all areas where hazardous materials are handled and
inventory is to be made available to regulatory agencies upon request.
• Domestic waste will be gathered and stored in closed containers
to prevent the escape of windblown materials and will be clearly
labeled as permitted waste.
• Paper, steel and metal scrap, cardboard, wood and tires will be
collected separately and offered for recycling where facilities are
available.
• Training and enforce the project staff to operate following to the
regulation and plan.
Excavated Soil More concentration of excavated soil • Excavated soil should be transported to the spoil bank on the left
Disposal Site without proper management may cause and/or right bank quickly after excavated.
runoff problem during the rainy season, • Ensure maximum utilization of excavated soil for the construction
which can change the surface water quality purpose
of the surrounding water resources such as
suspended solid. Therefore, the mitigation
and monitoring for excavated soil is set to
manage excavated soil, protect the runoff,
prevent soil erosion problem, and minimize
damage due to the spoilage of excavated
soil.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Camp Site During pre-construction and construction Surface Water Quality
activities, the other region worker will be • Set up the appropriate sanitary toilet for workers and at least 150
required. The construction camp needs to m from the waterway.
be set up and can generate waste, which • Set up wastewater treatment system at every construction camp to
can make the effect to water, aquatic meet water quality standard prior to discharge to receiving water
ecosystem, and the source of vector borne. body or retention pond.
Therefore, appropriate management of
camp site is needed to minimize any impact Solid Waste
on water quality, aquatic ecosystem, and • Set up waste collection system in the construction camps and
health. coordinate with local authority to dispose such waste properly.
• Prepare garbage bins or containers with covers for garbage
collection at the workers’ campsites and construction area. Also,
inform concern local authorities or sub-contractors that gets
permission from government section to collect and dispose garbage.
• Solid waste disposal procedures will comply with solid waste
management regulations, as well as any additional disposal facility
requirements.
• Separate each type of wastes and collected solid waste in
appropriate and safety container for recycling where facilities are
available. Any surplus to the recycling activity will be disposed of at
an approved waste disposal site.
• Prohibit dumping waste in watercourse or wildlife habitat.
• Hazardous wastes will be collected and disposed of in accordance
with the appropriate regulatory requirements.
• Prohibit burning waste in construction area and worker camp site.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Camp Site (Cont’d) Personnel Health
• Workers’ camp site shall consist of living facilities with housing,
canteen, sanitary facilities for all workers accommodated within the
camp.
• Ventilation of building within the camp area shall be in
accordance with the Applicable Laws and Standards.
• Canteen and residential quarter shall be equipped with mosquito
net.
• Camp sanitation facilities should be provided and inspected.
• Fire-fighting equipment and portable fire extinguishers shall be
provided for all building.
• Train and educate staff in EMP/EIA requirements and conditions.
Training is to be carried out in the three main areas;
• General environmental awareness, including rules and regulations
to be followed on construction sites and workers’ camp.
• General health and safety awareness, including an AIDS/HIV and
STD awareness program
• Job-specific training for workers with responsibility for high risk
activities that could have adverse impacts on the environment and
humans.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Transportation During the construction phase, the major • Inform concerned authorities of Pyin Oo Lwin and Kyaukse
impacts on the traffic will be due to the Township, and local people about the project construction activities
transportation of removal biomass waste plan.
removal, construction materials, • Strictly enforce drivers in following traffic regulations during
construction workers, machinery and transporting material, workers, and equipment during project
supplies for workers on the site. In construction.
addition, increase number of vehicles may • The speed of truck should not exceed 40 km/hr.
increase impact on road damage and
• Repair the damaged road surface where this caused by project
accident on passer and local villagers who
transportation at least after finished site clearance and construction
locate near access road. In order to alleviate
activities. This management should be cover in CSR program.
and mitigate the impacts on transportation
route and traffic volume, management plan • Cover material by canvas during transportation to prevent falling
on transportation shall be developed and and spreading of material.
implemented. • Provide sufficient traffic signs and easily observed signs to
clearly indicate site construction zone.
• In case of accident, the concerned sections must promptly follow
the Construction Emergency Response Plan.
• Test alcohol and drug use on drivers before transportation.
• Avoid operation of trucks at night.
• The used/operated truck should be checked annually.
• Establish a vehicle washing facility to minimize the quantity of
material deposition on public roads.
• Establish a checkpoint at the project gate to ensure the vehicles
leaving the project site are following the measures prescribed to
reduce dust emissions.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Water Use The major impact during construction • Prepare sufficient and appropriate water tanks to collect water for
phase came from water requirement for worker consumption.
workers and construction activities. In • Prepare sufficient potable water for workers.
addition, the village related to project sites • Avoid use of shallow well for worker consumption since it is main
is lack of water for drinking and domestic water source for nearby villages
consumption (especially in dry seasons, 3-5
months). Main water sources for both
drinking and domestic use in all villages
are shallow wells and collected rainwater.
Therefore, setting and checking on
management of water supply for worker
and construction activities to minimize
impacts in term of water use disturb to
local people nearby project sites.
Solid Waste Solid waste will be generated from • Prepare garbage bins or containers with covers for garbage
activities associated with the Project, the collection at the workers’ campsites and inform concerned local
main types of solid waste include; solid authorities or agencies that get permission from government section
waste from the construction workers and to collect and dispose garbage
solid waste from the construction activities. • Prohibit open burning wastes in worker campsite and project area.
Solid waste from construction workers are • The biomass wastes should be separated into usable timber and
domestic waste such as garbage, glass, and woods
food waste, etc. For the solid waste from • The separated timbers and woods will be sold based on the
the project activities is biomass from site concerned laws and regulations.
clearance activities during pre-construction • The unusable wastes will be disposed of a disposal area or landfill
phase, and wood, scrap steel and metals, site to be selected by contractors with approval of the concerned
and erosion control materials during authority.
construction phases. The management of • For used oil and chemicals, they will collect at a temporary
solid waste is very important. If not warehouse before sending back or disposed by contractors or inform
properly controlled and disposed of, waste concerned authorities to dispose used oil and chemicals.
can be unsightly and cause human health
and safety concerns.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Solid Waste (Cont’d) • Prepare garbage bins or containers with covers for garbage
collection at the workers’ campsites and construction area. Also,
inform concern local authorities or sub-contractors that gets
permission from government section to collect and dispose garbage.
• Solid waste disposal procedures will comply with solid waste
management regulations, as well as any additional disposal facility
requirements.
• Separate each type of wastes and collected solid waste in
appropriate and safety container for recycling where facilities are
available. Any surplus to the recycling activity will be disposed of at
an approved waste disposal site.
• Prohibit dumping waste in watercourse or wildlife habitat.
• No construction materials or debris are allowed to become
waterborne. Any materials/debris that enters the aquatic environment
must be removed immediately and disposed of in an approved
manner.
• All temporary structures, piles, false works, debris, cofferdams
etc. will be removed from the waterway upon completion of the work.
• Hazardous wastes will be collected and disposed of in accordance
with the appropriate regulatory requirements.
• Prohibit burning waste in construction area and worker camp site.
Hazardous Materials Hazardous material will be used for this • Preparation of emergency plan for all material used or store onsite
project such as lubricant, oil, and hydraulic the plan will cover planning, response and training measure for
fluid. Hazardous materials are cause of various scenarios.
adverse effect to both human health and • Hazardous materials use will only handle be by personnel who are
environment. Therefore, the mitigation and trained and qualified in the handling of these materials and in
monitoring plan are required for controlling accordance with the manufacturer’s instructions and government
use of hazardous materials and suitable regulations.
management for hazardous wastes.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Hazardous Materials • Storage of hazardous materials will be in a designated, clearly
(Cont’d) marked area, and be at least 30 m from any watercourse.
• There will be no smoking within any hazardous materials storage
area.
• Disposal of hazardous materials will be in accordance with
applicable regulations in effect at the time of disposal.
• Maintenance and cleaning of mobile construction equipment will
not be carried out near residential properties, on the dam, or within 30
m of any watercourse and with no potential for POL materials to
enter the watercourses.
• Material safety data sheets (MSDS) must be located in close
proximity to all areas where hazardous materials are handled and
inventory is to be made available to regulatory agencies upon request.
• Personal Protection equipment must be prepared in the site.
• Ensure all vehicles and heavy equipment are equipped with a spill
kit for using in the accident situation.
• All containers, hoses and nozzles will be free of leaks. All fuel
nozzles will be equipped with functional automatic shut-offs.
• Training all workers to follow to the emergency responsible plan.
Biomass Clearance This project implementation cannot avoid • Project optimization to minimize vegetation losses and preserve
logging activities due to the project must do forest
clearance of the tree and vegetation for • Logging activities must be doing only in the proposed project area
construction the dam site and access road. • Logging and log selling process will be based on the concerned
Therefore, the plan to control logging laws and regulations and conducted by concern authorities only
activities must be set to minimize the • Restore the clearance area after complete construction phase
problem from logging activities. • Set the compensation for paying to the agriculture area that
getting impact from the project
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Tree Species The development of Deedoke Project will • Survey focuses on near threatened tree species and tree with
Transplanting be carried on within forest area where tree cultural significant at the appropriate size.
cutting cannot be avoided. • Trees to be transplanted are marked with color tag.
Occupational Health Occupational health problems, injuries, and • Inspection of a medical care unit, its screening and caring of
accidents may occur during construction important infectious diseases among workers, necessary services and
activities due to workers’ carelessness, records.
machinery malfunction, or inadequately • Inspection of machinery maintenance records, occupational health
training. Therefore, stringent management and safety records of workers.
and monitoring programs are required to • Inspection of construction camp’s sanitation and living
reduce these injuries, accidents, conditions.
occupational health problems, and fire • Inspection of accident prevention measures such as traffic sings,
hazards. use of seat belts, alcohol consumption.
• Screening among all dam workers and personnel by taking blood
examination for malarial infection. Cases found must be radically
treated.
• Chest radiography for workers to detect tuberculosis should be
conducted. And cases detected must be closely under surveillance and
treated.
• Single dose treatment for helminthic infection for all workers and
families should be implemented.
• Any suspected case of sexually transmitted diseases (STD) should
be adequately treated and followed-up with practical health
education.
• Conduct safety training courses and rehearsal for the workers, to
prevent and reduce work accidents.
• Controlling pests primarily through environmental methods.
When environmental methods alone are not effective, the use of
pesticides shall be considered. Information for proper use of
pesticides should be also provided.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Occupational Health • Adequate measures to address mosquito control, including dengue
(Cont’d) fever control.
• Pesticides shall be handled, stored, disposed of, and applied
according to acceptable standards accepted by the World Bank
Operational Policy (OP) 4.09, Pesticide Management.
• Ensure the continued safe disposal of all solid waste and sewage.
• Implement fly, insect and other pest control at construction camp
sites and in the project area.
• Surveillance, investigate and document all disease outbreaks
within the workforce. Using the epidemiologic approach.
Consultation should be available.
• The construction camps shall have an adequate supply of potable
water compliant with WHO criteria and Applicable Laws.
• Ventilation of buildings within the camp areas shall be in
accordance with Applicable Laws and Standards.
• Canteen and residential quarter shall be equipped with mosquito
net and screen.
• Camp sanitation facilities should be provided and routinely
inspected. Any occurrence of water-borne diseases should be
epidemiological studied. Local and provincial health agencies are
good sources for advice.
• Implement regular surveillance and inspection on occupational
hazard, equipment and protective device.
• Minimize dust, noise, air pollutants by strictly implement the
mitigation plans of air quality and noise.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Occupational Health • Prepare and enforce the wearing of safety protection equipment or
(Cont’d) devices to prevent accident or reduce severity such as eye glasses,
safety shoes, ear muffs, safety belts, protective clothing and helmets
with regular inspection.
• Provide adequate proper material and equipment used in
construction activities in order to increase effective working and
decrease the risk of causing accidents or injuries.
• Provide appropriate information and health education to the
workforce on prevention of diseases, including, malaria, diarrhea,
food poisoning, STD, AIDS and tuberculosis.
• Providing emergency treatment and first aid for major
accident/injuries and also emergency patient transfer. An ambulance
shall be also provided. Connection can extend to neighboring
countries.
• Effective public relations activities and social cooperation is
necessary with special attention on community leaders and young
adults.
• Recording of water-borne diseases, accident, dengue fever,
malaria, STD, tuberculosis, and violence should be done and analyses
for future prevention or reduction.
Community Health The extent of the three health programs At this stage, Deedoke project proposes the Community Health
proposed for the Deedoke project are Management Program will consist broadly of:
summarized in the table below. The three • constructing alternative domestic water sources for households
programs are integrated however will be and villages who lost their existing sources
implemented by different parties whose • monitoring and surveillance of vector population possibly
responsibilities will be further defined affected by the water levels
closer to detailed design stage when • monitoring and surveillance of nutrition status
contracting arrangements are better • development of outbreak preparedness
defined.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Construction • Site Decommissioning
Supporting Structures • Decommissioning Hazardous Material & Removal
Dismantling • Hazardous Waste Management & Decommissioning
• Non Hazardous Solid Waste Management & Removal
• Sanitary & Septic Waste Management & Removal
• Concrete Batching & Cleaning
• Site Cleaning and Maintenance Operations
Chance Find Although no significant archaeological • Ensure that all construction workers receive a Physical Cultural
sites have been identified in the project Resource awareness program upon arrival at site. Training will
concerned areas, it is possible that during include identification of Physical Cultural Resource and their
site clearance, earth moving, quarrying and responsibility in terms of the Chance Find Procedure for Physical
excavation for construction of foundation Cultural Resource.
of dam and power house archaeological • Construction workers will be informed of the rules of not stealing
objects or archaeological deposits be or trading historic artifacts
discovered and damaged. • Include in the code of conduct a rule about not buying or trading
physical cultural objects.
Compensation To reduce the social impacts on villagers in Compensation Principle and Policy
the affected villages in the construction Compensation is defined by ADB1 as “Money or payment in
area and related facilities area and along the kind to which the people affected are entitled in order to replace the
transmission line. lost asset, resource or income”. Compensation is also defined
similarly by IFC2 as “Payment in cash or in kind for an asset or a
resource that is acquired or affected by a project at the time the asset
needs to be replaced”.
This RAP adopts a general principle that the people affected will
not be worse off compared to the pre-project level. Based on this
principle and ADB’s safeguard policy guidelines, the following
compensation policy is recommended:
1
ADB Handbook on Resettlement (1998)
2
IFC Handbook for Preparing a Resettlement Action Plan
Deedoke HPP EMP Page 56
Environmental Management Plan for Deedoke Hydropower Project Final Report
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Compensation • For Group 1-PAPs: who will permanently lose part of their
(Cont’d) land and crops for construction of hydropower components, the
Project will provide adequate cash compensation at full replacement
cost for the lost land and crops prior to construction.
• For Group 2-PAPs: who will lose part of their land which is
under contour 80 m a.s.l. due to inundation during project operation,
the Project will provide cash compensation for the loss of land.
• For Group 3-PAPs: who will permanently lose land and
crops due to installation of transmission line support towers. Direct
compensation in cash to individual PAPs in Group 3 will be provided.
• For Groups 4-PAPs: who own the land under transmission
line with in 45.72 meter right-of-way and their right on land use will
be limited i.e., they cannot build house or plant perennial tree with
height greater than 3 meters. Cash will be paid to PAPs to
compensate for the limited right on land utilization.
Eligibility
Eligibility will be determined using two criteria: cut-off date and
possession of Land Use Right Certificates (LURCs).
Cut-off Date: The cut-off date has not yet been determined. The
cut-off date should be the date at which the PAPs are officially
informed of the intention of the Government to acquire their land.
The PAPs will be informed of the cut-off date. Any people who use
or settle in the land area to be acquired for the Project after the cut-off
date will not be entitled to compensation and/or assistance under the
RAP.
LURCs: The eligibility for compensation to PAPs in Group 1,
Group 2 and Group 3 for land loss will be determined by the
possession of LURCs or a claim that is recognizable under national
laws. Persons who do not have LURCs or any recognizable claims to
their land will not be eligible for compensation for land but will be
entitled to compensation for their affected assets upon land and
limited right on land use.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Livelihood Restoration The Project Affected Persons (PAPs) are (a) Promote agricultural product with in home lot:
people in the nearby villages of the four For villagers in the construction site and upstream area who lose
land categories whose land will be used by their farmland, production within home lot is one of mitigation to
the Project. Most of them would own the bring them food stuff and the surplus can be sold for addition income
land although some may be users of the as well.
four types of land requirements.
Examples of home lot production are mushroom cultivation,
growing kitchen garden and green edible fence. Activities to promote
home lot productions are;
• Setting up production group
• Providing Fund for initiate activities
• Technical supports
• Training
• Marketing support/coordinate
(b) Livestock Raising
Develop commercially successful and sustainable Animal
Husbandry by:
• Improving cattle, pig and poultry raising
• Promotion of forage crops
• Improving veterinary techniques
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Community The Project Affected Persons (PAPs) are (a) Public Health Support
Development people in the nearby villages of the four • Provide equipment for health service and sanitary condition
land categories whose land will be used by improvement in the Hnget Gyi Thaik, Thayet Pin, Ma Gyi Inn,War Net
the Project. Most of them would own the village, Yeywa and Jongywa.
land although some may be users of the
• Organize activities to enhance health and sanitation by educating
four types of land requirements.
villagers on health care and diseases prevention for people of all ages.
(b) Education Support
• Upgrading of existing facilities and capacity;
• Provision of educational materials and equipment;
• Scholarships for students;
(c) Provision of Basic Infrastructure
• Water pumping system and groundwater well to alleviate impact
from turbidity of water due to construction activities in river bed.
• Provision of bus or boat for convenient transportation during
construction period
• Safety signs installation or barriers provided for community
safety
During operation of the hydropower plant, inundation of low lying areas along the river
banks will be the main permanent environmental and social impact mainly compensated during the
construction phase. The mitigation measures will include: (i) further assistance in livelihood
restoration of PAPs and community development and (ii) various environmental management and
monitoring measures. Table 8 presents brief information on the impacts and mitigation measures.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Noise The project activities during operation • Speeds of vehicles in the project site will not be more than 40
phases may cause potential impact to the km/hr.
environment and human. • The project proponent will be required to monitor ambient noise
levels at the receptors.
Vibration The project activities during operation • The facility is not expected to generate vibration noticeable
phases may cause potential impact to the outside of it.
environment and human.
Flood The project activities during operation • Installation of flood warning system. A flood warning system in
phases may cause potential impact to the case of critical flood is planned for warning to immediate upstream
environment and human. and downstream people and communities. The system will be
designed in cooperation with the plant operator of the Yeywa
Hydropower Plant and government authorities responsible for
monitoring water levels and meteorological data within the Lower
Myitnge river basin. The system will include the possibility to raise
alarms via a public annunciation system.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Surface Water Increased turbidity of river water due to in- • Water quality, the amount of suspended solid and its chemical
Quality river project activities. Degradation of river parameters should be monitored annually.
water quality due to inappropriate management
of wastes and domestic waste from site.
Aquatic Ecology Increased turbidity of river water due to in- • Survey of fish species composition in the project area in both
and Fishery river project activities. Degradation of river upstream and downstream must be implemented. Furthermore, the
water quality due to inappropriate management effect on fish migration or some effects during construction phase on
of wastes and domestic waste. the fish spawning ground should have been studied.
Solid Waste Solid waste will be generated from activities • Prepare garbage bins or containers with covers for garbage
associated with the Project, the main types of collection at the workers’ campsites and inform concerned local
solid waste Solid waste from workers are authorities or agencies that get permission from government section
domestic waste such as garbage, glass, and to collect and dispose garbage
food waste, etc. The management of solid • Prohibit open burning wastes in project area.
waste is very important. If not properly • The separated timbers and woods will be sold based on the
controlled and disposed of, waste can be concerned laws and regulations.
unsightly and cause human health and safety • The unusable wastes will be disposed of a disposal area or
concerns. landfill site to be selected by the project proponent with approval of
the concerned authority.
• Used oil and chemicals will be collected at a temporary
warehouse before being disposed by project or concerned authorities
informed to dispose them.
• Prepare garbage bins or containers with covers for garbage
collection at the workers’ project area. Also, inform concern local
authorities that gets permission from government section to collect
and dispose garbage.
• Solid waste disposal procedures will comply with solid waste
management regulations, as well as any additional disposal facility
requirements.
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Solid Waste • Separate each type of wastes and collected solid waste in
(Cont’d) appropriate and safety container for recycling where facilities are
available. Any surplus to the recycling activity will be disposed of at
an approved waste disposal site.
• Prohibit dumping waste in watercourse or wildlife habitat.
Livelihood The Project Affected Persons (PAPs) are (a) Promote agricultural product with in home lot:
Restoration people in the nearby villages of the two land For villagers in the construction site and upstream area who lose
categories whose land in the construction and their farmland, production within home lot is one of mitigation to
pondage area will be used by the Project. Most bring them food stuff and the surplus can be sold for addition
of them would own the land although some income as well.
may be users.
Examples of home lot production are mushroom cultivation,
growing kitchen garden and green edible fence. Activities to
promote home lot productions are;
• Setting up production group
• Providing Fund for initiate activities
• Technical supports
• Training
• Marketing support/coordinate
(b) Livestock Raising
Develop commercially successful and sustainable Animal
Husbandry by:
• Improving cattle, pig and poultry raising
• Promotion of forage crops
• Improving veterinary techniques
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Livelihood (c) Fishery
Restoration (Cont’d) • Provision of training on aquaculture or fish pond raising, cage
culture.
• Set new equilibrium on newly river pondage area,
introducing of fish into river pondage area. Recommended releasing
species should be replication of herbivorous species, omnivorous
species and carnivorous species. The recommended for herbivorous
species are such as Rohu and allied (Labeo spp), Cirrhinus mrigala
for example. The omnivorous species are such as silver barb
(Barbonymus gonionotus), the Sweetlips minnow (Osteochilus
hasselti) and walking catfish (Clarias batrachus). The carnivorous
species are such as snakehead (Channa spp.), Wallago attu, Ompok
spp. and Bagrids catfish (Mystus spp.)
(d) Off-farm occupation
• For increasing the chance and efficiency for villagers to work
in this project, preparing villagers to have skill and experience to work
is needed. Sample of occupation that villagers can occupy are
construction worker, carpenter, gardener, guard, light machine repair,
trader, driver, food cooking, etc. Activities to prepare PAPs for off-farm
occupation are;
- To facilitate training by practice
- To set up vocational education
- To coordinate with contractor for PAPs employment
• Woman training for supplementary income. Activities to
prepare are;
- Food processing/preservation
- Promotions of edible fencing/home lots garden
Environmental and
Social Issue / Impacts Mitigation Measures
Impacted Area
Community The Project Affected Persons (PAPs) are (a) Public Health Support
Development people in the nearby villages of the two land • Provide equipment for health service and sanitary condition
categories whose land in the construction and improvement in the Hnget Gyi Thaik, Thayet Pin, Ma Gyi Inn, War Net
pondage area will be used by the Project. Most village, Yeywa and Jongywa.
of them would own the land although some
• Organize activities to enhance health and sanitation by
may be users.
educating villagers on health care and diseases prevention for people of
all ages.
(b) Education Support
• Provision of educational materials and equipment;
• Scholarships for students;
CHAPTER 6
CONSTRUCTION PHASE EMP
6.2 MAPS
Project construction will take place at two sites: (i) main site where the dam,
power house and support facilities, including the access road, will be constructed; (ii)
transmission line corridor where the transmission line will be constructed. The construction
sites for the transmission line is long and narrow with a corridor of not more than 50 m for
the transmission line. Figure 3 is a base map of the main construction site and the site
layout plan. Figure 4 shows the transmission line alignment. The maps also show locations
of sensitive receptors near the construction sites.
This EMP detail the relevant objective, legal requirements, mitigation measures,
monitoring program, performance specifications, implementation schedule, responsibilities
for implementation, and budget. This EMP will be developed prior to the start of
construction works and during the course of the Project when construction works requiring
more detailed environmental planning are identified and will be subject to the review
procedure. The following EMPs will be developed for the Project;
1) Objective
2) Context
Increases in air pollutants caused by fugitive dust from rock blasting, site
excavation quarrying operation and emissions from operation of trucks and heavy
construction equipment.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
5) Monitoring Programs
Parameters
• Wind speed and direction
• PM-10 (1 yr)
• PM-10 (24 hr)
• PM-2.5(1 yr)
• PM-2.5 (24 hr)
• Ozone (8 hr daily maximum)
• NO2 (1 yr)
• NOx as NO2 (1 hr)
• SO2 (24 hr)
• SO2 (10 minute)
Location (Figure 5)
Construction Site
Transmission Line
• Four times per year and each sampling must be conducted for 5
consecutive days.
Transmission Line
1) Objective
• To minimize the adverse impacts caused by the projects construction
activities in the dam construction site. and quarry site and related facilities including
transmission line.
• To monitor the performance of the management action or mitigation
measures and assess compliance with the applicable standards.
2) Context
Increase ambient noise level at the construction site, quarry site and
communities near the material transport routes.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Public Health Law (1972)
5) Monitoring Programs
Parameters
• LAeq 1 hr (Daytime)
• LAeq 1 hr (Nighttime)
• LAmax
• L90
Location (Figure 5)
Construction Site
Quarry Site
• Station 3: Located at Thayetpin Primary School, Thayetpin
village, Kyaukse Township
• Station 4: Located at Quarry Site, Thayetpin village, Kyaukse
Township
Transmission Line
• Station 5: Located near Tower 48, Sun Ye village, Sintgaing
Township
• Station 6: Located between Tower 72 and Tower 73, Taung Yin
village, Sintgaing Township
Frequency
• Four times per year and each sampling must be conducted for 5
consecutive days.
Transmission Line
Methodology
• International Organization for Standardization (ISO1996) for noise
level measurement.
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
Transmission Line
Monitoring of noise at 2 stations approximately costs 600
USD/time (or 300 USD/station/time). The monitoring must be conducted one time in
construction tower period and must be conducted for 5 consecutive days. Total budget
approximately costs 3,000 USD.
1) Objective
• To minimize the adverse impacts caused by the projects construction
activities in the dam construction site. and quarry site.
• To monitor the performance of the management action or mitigation
measures and assess compliance with the applicable standards.
2) Context
Increase vibration at the construction site, quarry site and communities near
the material transport routes.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
5) Monitoring Programs
Parameters
• Vibration or PPV measured
Location (Figure 5)
Construction Site
Quarry Site
• Station 3: Located at Thayetpin Primary School, Thayetpin
village, Kyaukse Township
• Station 4: Located at Quarry Site, Thayetpin village, Kyaukse
Township
Transmission Line
• Station 5: Located near Tower 48, Sun Ye village, Sintgaing
Township
• Station 6: Located between Tower 72 and Tower 73, Taung Yin
village, Sintgaing Township
Frequency
Construction Site
• Four times per year and each sampling must be conducted for 5
consecutive days.
Transmission Line
Methodology
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
Construction Site
Transmission Line
Monitoring of vibration at 2 stations approximately costs 600
USD/time (or 300 USD/station/time). The monitoring must be conducted one times in
construction tower period and must be conducted for 5 consecutive days. Total budget
approximately costs 3,000 USD.
1) Objective
• To minimize the adverse impacts caused by the projects construction
activities in the dam construction site.
• To monitor the performance of the management action or mitigation
measures and assess compliance with the applicable standards.
2) Context
To minimize the landslide and slope failures caused by the earthwork
excavation activities could damage the project properties, and pose a health risk to the
construction workers.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Public Health Law (1972)
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Public Health Law (1972)
Clearing of vegetation
• The extent of areas to be cleared will be minimized as far as practical.
• The use of existing cleared areas will be maximized.
• Clearing of sites will be undertaken in the sequence that sites are
required for construction.
• Progressive revegetation of exposed areas will take place as soon as
practical following completion of construction works in that area. Suitable species for
revegetation will be used.
• If construction works are temporarily stopped in an exposed area (for
longer than 14 days), temporary stabilization of exposed surfaces will be undertaken.
Exposed areas
• All areas required to be disturbed will be clearly identified and the
boundaries marked on the ground
• Areas not required to be disturbed will be retained in their original
condition.
• Rip-rap, or similar, will be installed at the inlet and outlet of culvert, if
necessary, to prevent scour erosion.
• Retention of existing vegetation along watercourses will be maximized
to reduce flow velocities and to minimize erosion.
• ‘Clean’ runoff from undisturbed areas will be diverted away from the
construction site and into established watercourses.
• Runoff from disturbed areas will be directed into sediment trapping or
filtering devices.
• Silt fences or vegetative fences should be installed along the top of river
banks to intercept any sediment migrating in runoff toward the river.
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
2) Context
The project activities during construction phase may cause potential impact
to the environment and human.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• Public Health Law (1972)
- Carry out investigation after flooding to mark high water line and
document the maximum flooding condition. All information collected can be used to justify
the need for improving the accuracy of flood modeling.
5) Monitoring Programs
Parameters
• Water level at construction site
Location
• Construction site
Frequency
Methodology
• Monitoring an operation of a stream gauging station.
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• Install sedimentation ponds for drainage water from quarries and other
construction sites.
• The site preparation activities, including land clearing and site filling
and compaction, should be carried out after taking countermeasures to avoid the problem
of surface runoff with high turbidity discharging into the surrounding paddy field or nearby
drainage channels, if exist.
• Toilet wastes will be discharged into a septic tank (or more than one
septic tank) with a hydraulic retention time of about 5 days.
• Prevent truck cleaning, lorries, and other equipment used for preparing,
transporting or applying concrete in the river.
5) Monitoring Programs
Parameters to be monitored
Frequency
Seven times per year during the construction phase (monthly monitoring
during Wet Season (June-October) and quarterly monitoring during Dry Season).
Methodology
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
5) Monitoring Programs
Parameters to be monitored
• Phytoplankton
• Zooplankton
• Benthos
• Fish species
Frequency
Methodology
Benthos
Fish Species
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
• To collect the material in the safety storage or container to prevent the
accident, and adverse effect to environment and human.
2) Context
Best practice for material storage is the method to prevent the problem for
material and equipment to the human and environment. Moreover, the method can
minimize the source of impact to human and environment.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
5) Monitoring Programs
Parameters to be monitored
• Record of accident related to Leak or Spill of Fuel Oil, Lubricant, and
Hazardous Material
Location
• Material Storage Area
Frequency
• Monthly
Methodology
• Record as monthly basis
6) Performance Specifications
No accidents and adverse effect to environment and human by the release
or spill of fuel oil, lubricant, or hazardous material.
7) Implementation Schedule
Throughout construction phase.
8) Responsibilities
Developer and Contractor.
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractors.
1) Objective
• To manage excavated soil, reduce the runoff and soil erosion problem.
• To minimize damage due to spoilage of excavated soil.
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• Excavated soil should be transported to the spoil bank on the left and/or
right bank quickly after excavated.
5) Monitoring Programs
6) Performance Specifications
• Efficiency of disposal area to collect excavated soil during site
construction.
• Minimize the impacts on surface water quality and aquatic ecology that
locate nearby disposal area.
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
Solid Waste
Personnel Health
Parameters to be monitored
Solid Waste
• Amount of Solid Waste
• Types of Solid Waste
• Waste Management
Personnel Health
• Camp Site Facility
• Training Program Implementation
Location
• Camp site
Frequency
• Monthly
Methodology
• Record as monthly basis
6) Performance Specifications
• National Environmental Quality (Emission) Guidelines (2015)
7) Implementation Schedule
Throughout construction phase.
8) Responsibilities
Developer and Contractor.
9) Budget
1) Objective
• The plan covers potential sources of environmental hazards caused by
transmission line construction activities. These are water pollution, noise and dust
problems, erosion, etc.
2) Context
The construction require access to the tower location and more generally to
the ROW for tower erection and line stringing. During the construction phase, the small
amounts of land acquisition in the transmission line which is not given significant impact.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• Where such landscapes cannot be avoided, the legs of the tower will be
designed to minimize the amount of excavation required to stabilize the structures on
slopes. Construction will only proceed during dry conditions.
(e) Traffic and Noise
• Transportation of material should take place only in daytime. If
construction during evening is required, the local people shall be consulted at least one
week in advance.
• The Contractor(s) shall post warning signs and manage traffic to protect
the public and its workers. Dirt roads should be sprayed with water in dry and windy
conditions. Temporary access paths shall be decommissioned once construction completed.
• Monitoring of noise as well as vibration and air quality will be
conducted in two specific areas where towers are the closest to communities (see specific
plans above).
(f) Water and Wetland Protection
• Location of towers will be adjusted to avoid streams and wetlands.
• Existing drainage systems, both natural and man-made, will be
maintained by building appropriate structures such as bridges, culverts etc.
• To avoid contamination of streams and groundwater by oils from heavy
equipment, sump oils will be stored in drums or containers, and then brought to companies
licensed to manage such waste.
(g) Wildlife Protection
• Strict rules against wildlife hunting, poaching and trading. Non-
compliance will be penalized.
(h) Oil Management
• The substations shall be equipped with structures to collect any
accidental release of oil form transformers and capacitors. An emergency plan shall be
prepared for the event of major releases.
• New and used oil has to be stored in a contained area with concrete
floor.
5) Monitoring Programs
• The Developer will self-regulate their environmental performance and
reports will be drafted by the Contractor.
• Based on the self-assessment, the Project’s representative will be
responsible for auditing at regular intervals. Independent auditing of compliance should be
made four times per year.
6) Performance Specifications
• Number of complaints filed through the complaint response channel.
7) Implementation Schedule
8) Responsibilities
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractor.
1) Objective
2) Context
During the construction phase, the major impacts on the traffic will be due
to the transportation of waste removal, biomass removal, construction materials,
construction workers, machinery and supplies for workers on the site. In addition, increased
number of vehicles may increase impact regarding road damage and accident on road users
and local villagers who locate near access road. In order to alleviate and mitigate the
impacts on transportation route and traffic volume, management plan on transportation
shall be developed and implemented.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Motor Vehicle Rules (1987)
5) Monitoring Programs
• Number of complaints filed through the complaint response channel.
• Number of Transportation Trip at project access road (2 times/year).
• Accidents related to Transportation activity at project access road
(Everyday) and results will be included in monthly report.
6) Performance Specifications
• Number of complaints filed through the complaint response channel.
• Number of accident and injured related to the transportation activity.
7) Implementation Schedule
8) Responsibilities
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractors.
1) Objective
• To ensure on sufficient of water supply for construction workers and
construction activities.
• To minimize impacts in term of water use disturb to local people nearby
project sites.
2) Context
The major impact during construction phase come from water requirement
for workers and construction activities. In addition, the village related to project sites is
lack of water for drinking and domestic consumption (especially in dry seasons, 3-5
months). Main water sources for both drinking and domestic use in all villages are shallow
wells and collected rainwater. Therefore, setting and checking on management of water
supply for worker and construction activities to minimize impacts in term of water use
disturb to local people nearby project sites.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Electricity Law (2014)
• The Conservation of Water Resources and Rivers Law (2006)
5) Monitoring Programs
• Number of complaints filed through the complaint response channel.
6) Performance Specifications
• Number of complaints filed through the complaint response channel.
7) Implementation Schedule
8) Responsibilities
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractors.
1) Objective
• To manage the solid waste with appropriate methods to minimize the
source of adverse effect to human health.
2) Context
Solid waste will be generated from activities associated with the Project, the
main types of solid waste include; solid waste from the construction workers and solid
waste from the construction activities. Solid waste from construction workers are domestic
waste such as garbage, glass, and food waste, etc. For the solid waste from the project
activities is biomass from site clearance activities during pre-construction phase, and wood,
scrap steel and metals, and erosion control materials during construction phases. The
management of solid waste is very important. If not properly controlled and disposed of,
waste can be unsightly and cause human health and safety concerns.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Electricity Law (2014)
• The Forest Law (1992)
• The separated timbers and woods will be sold based on the concerned
laws and regulations.
• The unusable wastes will be disposed of a disposal area or landfill site
to be selected by the contractor with approval of the concerned authority.
• For used oil and chemicals, they will collect at a temporary warehouse
before sending back or disposed by contractors or inform concerned authorities to dispose
used oil and chemicals.
• Prepare garbage bins or containers with covers for garbage collection
at the workers’ campsites and construction area. Also, inform concern local authorities or
sub-contractor that gets permission from government section to collect and dispose
garbage.
• Solid waste disposal procedures will comply with solid waste
management regulations, as well as any additional disposal facility requirements.
• Separate each type of wastes and collected solid waste in appropriate
and safety container for recycling where facilities are available. Any surplus to the
recycling activity will be disposed of at an approved waste disposal site.
• Prohibit dumping waste in watercourse or wildlife habitat.
• No construction materials or debris are allowed to become waterborne.
Any materials/debris that enters the aquatic environment must be removed immediately
and disposed of in an approved manner.
• All temporary structures, piles, false works, debris, cofferdams etc. will
be removed from the waterway upon completion of the work.
• Hazardous wastes will be collected and disposed of in accordance with
the appropriate regulatory requirements.
• Prohibit burning waste in construction area and worker camp site.
5) Monitoring Programs
• Daily checking amount of Solid waste generated during construction
phase and results will be include in monthly reports.
6) Performance Specifications
• Amount of Solid waste generated during pre-construction and
construction phases.
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
• To reduce the problem from hazardous material and to prevent the
impact from hazardous material to human health and environment, and controlling problem
due to spillage situation.
2) Context
Hazardous material will be used for this project such as lubricant, oil, and
hydraulic fluid. Hazardous materials are cause of adverse effect to both human health and
environment. Therefore, the mitigation and monitoring plan are required for controlling use
of hazardous materials and suitable management for hazardous wastes.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Electricity Law (2014)
5) Monitoring Programs
• Daily site inspection includes observation of the collection and storage
of hazardous material in a construction site and the results will be included in monthly
reports.
• Report immediately to the relevant authorities any incident in term of
accident from hazardous material leak to environment on effect to worker.
6) Performance Specifications
• Amount of hazardous material.
• Accident from hazardous material.
7) Implementation Schedule
8) Responsibilities
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractors.
1) Objective
• To minimize the vegetation losses within the proposed project area as
low as practicable
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• The Forest Law (1992)
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
• Mitigation Measures and Monitoring Program: Included in
construction cost by Contractors.
1) Objective
• To reduce impact on biodiversity and cultural resources.
• To set procedure and methodology for tree transplanting, from the
proposed project area to supporting area with high survival.
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
machine or crane with rope instead of iron string at two lifting points’ bottom and middle
of tree. All of activities should be done cautiously to prevent root ball broken which may
lead to tree mortality while waiting to be planted. For small tree lifting, small root ball can
be lifted by labor with wood fixing at bottom of tree.
5. In case that nursery area is far and truck is used for transporting; small
tree can be laid down in vertical direction and big trees may be transported by 2 or 3
trees/trip and only be placed in horizontal direction with their root balls being laid to the
front of truck.
6. Due to tree root system is growing within limited area where water and
nutrient absorption are not enough for tree growing; these may cause tree mortality or
dormancy. The transplanted tree must be kept in maintainer with good condition. Therefore,
plan of tree transplanting site preparation must be done rapidly.
7. For transplanting pit preparation, tree transplanting pit should be fitted
with root ball of each tree and also the depth of pit should cover all of tree root ball. The
reserved materials are existing soil mixed with organic and chemical fertilizers (15-30-15)
for keeping tree adapting in new condition rapidly.
8. Tree transportation from nursery area to planting site should be
carefully done; root ball must be always kept in good condition in hemp sack to prevent
soil broken.
9. Tree lifting in planting pit, especially big tree size, should be done with
small crane or back-hoe in the same procedures as tree root cutting activities. Hemp sack
should be remained for root ball to allow it fertilized. Tree stem must be in natural
horizontal direction, and fully fill up with soil mixed organic fertilizer in pit.
10. High and big trees may be fallen down by windstorm due to weak root
system, therefore, the supporting wood for tree are needed. The building methods for
supporting wood are available in many types which can be suitable adopted for different
tree sizes, height, and tree forms, including planting sites and supporting materials. The
general methods are as follow:
10.1 For supporting tree of small size, diameter 8-12 cm. and 4 m long,
woody pile can be used. Stick pile into soil parallel with transplanting tree 1-2 piles and
also use rope inserted in hose tie with tree stem. Use iron string to tie between wooden pile
and rope with medium tightness as shown in Photo 1, or use supporting pile with diameter
8 cm. and 3-4 m long as 3 sides supporting type as shown in the same photo.
10.2 To support tree with bigger size but less in height (under 10 m), stronger
supporting piles should be used. Use wooden piles with diameter 12 cm. and 5-6 m long
each to support between middle of the tree and ground as 4 sides type as shown in Photo
1.
10.3 To support tree with bigger size, high crown and many branches, it
needs stronger pile than other methods. Therefore, the method as in Topic 10.2, should be
strengthened with iron-string between the big branch or upper the tree stem as shown in the
same photo.
11. Transplanted tree should be kept in good conditions that is free from
weed and applied with chemical fertilizer, formula 15-30-15, 2-3 weeks/time to keep root
system being in high growth. After 3 months, if the tree has not wilted symptom, and having
sprout leave, it indicates that root system is in good condition and can absorb nutrients and
water normally. However, supervisor should always maintain tree supporters until the
transplanted tree grows up and can support itself, which may take 1-2 years up depending
on tree conditions.
5) Monitoring Programs
Location
Trees will be transplanted from the proposed project construction area.
Methodology
Developers will prepare a report in order to submit to the Ministry of
Forestry.
6) Performance Specifications
The Performance Specifications or target are within National Environmental
Quality (Emission) Guidelines (2015).
7) Implementation Schedule
Before construction period at least one year in pre-construction phase and
should be done in wet season.
8) Responsibilities
Developers will take responsibility to implement towards this plan.
9) Budget
The budget for tree transplanting will be included in construction cost.
Cotter Pin
1) Objective
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Public Health Law (1972)
5) Monitoring Programs
Parameter:
6) Performance Specifications
• Total Recordable Injury Frequency Rate (TRIFR)
• Lost Time Injury Frequency Rate (LTIFR)
• Medical Treatment Injury Frequency Rate (MTIFR)
• Duration rate
• Incident rate
7) Implementation Schedule
The extent of the three health programs proposed for the Deedoke HPP are
summarized in the table below. The three programs are integrated, however will be
implemented by different parties whose responsibilities will be further defined closer to
detailed design stage when contracting arrangements are better defined.
Project
Health Programs Regional
Workers
Objectives
• Prevent and Mitigate effects of Constructions and of Operation
of the Deedoke Dam
• Prevent and Mitigate impacts of the population influx (workers
& camp-followers)
• Preventive and curative measures ensuring Health and Safety of
the workforce
• Improve the health situation of the local Population
Period
• 2019 - 2022 Construction (Reservoir Filling)
• 2022 - 2027 Operation of Deedoke Dam
Target Groups
• PAPs due to inundation
• People living in main transportation corridors & access roads
• Camp followers
• Work Camps (Workforce)
Geographical Concentration
• Hnget Gyi Thaik and Thayet Pin
• Ma Gyi In, Gwe Bin, Pan, Kabyu, Salin, Kyaung Ywa, Kyaung
Pone, Thanekthae, Yeywa, Thayet Pin
• Access roads & Camp area
• Workers camp
The Objectives of the Community Health Management Program are the following:
The projected Time Frame for the Community Health Management Program is
6 years. It will start at least 6 months prior to the expected day of the financial close. This
will allow time to prepare (capacity building, purchase of equipment, infrastructure works)
and to be ready before big numbers of workers and camp-followers arrive. The program
will end 3-4 years after the dam has started to operate. Continuous monitoring for long term
effects might be required after the 8-year period.
During the first four years the program will emphasize possible effects resulting
from construction, construction related activities and from the concentration of people
(workers and camp-followers). Afterwards the accent will shift to mitigation and
monitoring of the possible adverse health effects resulting from the changes in water levels
and qualities.
The mitigating activities will address the expected health effects identified in the
Health Impact Assessment and are grouped by Environmental Health Area.
Most of the planned activities will be directly implemented by the public health
institutions of the target areas at district and provincial level. Other activities as surveys,
specific trainings, social marketing and policy development will require the support of
national health program departments at union level, non-governmental organisations and
training institutions.
Most of the planned activities are included in the different vertical national health
program policies. Therefore, the Community Health Management Program will facilitate
and strengthen all national (vertical) health programs that may be in place including:
• Curative Care
• Malaria
• Dengue
• Tuberculosis
• Sexual Transmitted Infections
• HIV/AIDS
• Soil transmitted helminths
• Extended Programme of Immunization
• Maternal Health Care
• Nutrition and micronutrients
• Sanitation
• Clean water supply
• Utilization of iodised salt
• Vitamin A distribution
The Community Health Management Program will limit its activities to:
− constructing alternative domestic water sources for households and
villages who lost their existing sources
− monitoring and surveillance of vector population possibly affected by
the water levels
− monitoring and surveillance of nutrition status
− development of outbreak preparedness
The program will focus first on sub programs that, if executed appropriately, are
designed to mitigate the potential health impacts of the project as identified in the ESIA.
For reasons of quality, continuity, effectiveness and efficiency the health institutions will
implement most of the service delivery activities in an integrated and comprehensive
way.
PIA/TG #2 Inundation Zones (Hnget Kyi Thaik, Ma Gyi In, Gwe Bin, Pan, Kabyu,
Salin, Kyaung Ywa, Kyaung Pone, Thanekthae, Yeywa and Thayet
Pin)
PIA/TG #3: Transportation Corridor (access roads, main roads into project
construction site and quarry) villages namely Hnget Kyi Thaik, Ma Gyi
In, Gwe Bin, Pan, Kabyu, Salin, Kyaung Ywa, Kyaung Pone,
Thanekthae, Yeywa and Thayet Pin
followers. This area will be affected by increased road traffic and concentration of people
and changes in water levels and quality.
A big influx of people is expected, ± 300 workers and between 300 and 1,000
camp-followers (families and service providers). Some of the workers will be Myanmar,
others will come from neighbouring countries (China, Thailand and etc) and from distant
places as Australia, Austria, Japan and etc.
The project with the support of the Myanmar government will try to control
movements of workers and camp-followers. Efforts will be made to educate and change
behaviour on different risk behaviours (promiscuity, hygiene, IBN, etc.). The project will
provide the required sanitary facilities and domestic water supplies. Workers could be
screened for certain contagious diseases. Nevertheless, changes of outbreaks of contagious
or vector-borne disease are very real. This could be outbreaks of classical diseases as
cholera, dysentery, malaria, dengue, etc. but also outbreaks of new emerging diseases such
as SARS and bird flu. Therefore, the project plans to develop and support a provincial
Infectious Disease Detection System and Outbreak Preparedness. The infectious disease
detection system is described in the chapter “Monitoring and Surveillance”. Not knowing
which diseases might cause outbreaks the programme will reserve an immediately
accessible fund allowing emergency purchases of inputs required in case of an outbreak.
Certain items will be purchased preliminary, they are protective clothing, rapid skin
thermometers and dengue spraying equipment.
Respiratory Diseases
In the townships of Kyaukse and Pyin Oo Lwin all activities will be supported.
In the camp-follower camps, the villages near to the work camp and the transportation
corridor will be covered by the promotional and preventive activities, the Contractors
responsible for those villages will benefit from the treatment, training and monitoring
activities.
Geographical location:
In the townships of Kyaukse and Pyin Oo Lwin all activities will be supported.
In the camp-follower camps, the villages near to the work camps and the transportation
corridor will be covered by the promotional and preventive activities, the Contractors
responsible of those villages will benefit from the treatment, training and monitoring
activities. Monitoring and surveillance, and outbreak preparedness will cover all
Townships.
corridor will be covered by the promotional and preventive activities, the Contractors
responsible of those villages will benefit from the treatment, training and monitoring
activities. Monitoring and surveillance will take place in all townships.
Food, Soil and Water borne diseases
Geographical location:
In the townships of Kyaukse and Pyin Oo Lwin all activities will be supported.
In the camp-follower camps, the villages near to the work camps and the transportation
corridor will be covered by the promotional and preventive activities, the Contractors
responsible of those villages will benefit from the treatment, training and monitoring
activities. Monitoring and surveillance will take place in all townships.
Nutrition and micronutrients related issues
Geographical location:
In the townships of Kyaukse and Pyin Oo Lwin all activities will be supported.
In further away townships only Monitoring and Surveillance activities will be
supported. However, if the monitoring shows an increase in malnutrition or micronutrient
deficiencies due to the project the Deedoke HPP will support the treatment of these cases.
Accidents/injuries, chemical exposures and poisoning
Geographical location:
In the townships of Kyaukse and Pyin Oo Lwin all activities will be supported.
In the camp-follower camps, the villages near to the work camps and the
transportation corridor will be covered by the promotional and preventive activities, the
Contractors responsible of those villages will benefit from the treatment, training and
monitoring activities. Monitoring and surveillance will take place in 2 townships along the
transportation corridor.
Psychosocial
In the Kyaukse and Pyin Oo Lwin townships, all activities will be supported.
Monitoring and surveillance will take place in 2 townships along the
transportation corridor.
Cultural Health Practices
Geographical location:
In the Kyaukse and Pyin Oo Lwin townships, the utilization of traditional
medicine will be monitored at village level.
Description:
Prevent or reduce the discharge of pollutants in the environment from material delivery
and storage by minimizing the storage of hazardous materials on-site, storing materials
in a designated area, installing secondary containment, conducting regular inspections,
removing hazardous material after use and training employees and subcontractors.
This management practice covers HazMat delivery, storage and handling.
Description
Prevent or reduce discharge of pollutants to the land, groundwater, in storm water from solid waste or
construction demolition (C&D) waste by providing designated waste collection areas, separate
containers for recyclable waste materials, timing collection of waste and recyclable materials with each
stage of the construction project, and properly training subcontractors and employees.
Risks if no Application of this MANAGEMENT PRACTICE
• Pollution of land, rivers and air
• Development of pests and vectors
• Impacts on health
Suitable Application: & Criteria
The following steps will help keep a clean site and reduce risks of pollution:
• Provide adequate number of rubbish bins on each site.
• Select designated waste collection areas on-site and provide for waste separation in compliance
with procedure to be developed at detailed design. Collection areas on site will be clearly
indicated by signs in Myanmar and in English.
• Locate containers in a covered area and/or in a secondary containment. Provide an adequate
number of containers with lids or covers that can be placed over the container to keep rain out
or to prevent loss of wastes when it’s windy.
• Collect site trash daily, especially during rainy and windy conditions.
• Salvage or recycle any useful material.
• Erosion and sediment control devices tend to collect litter. Remove this solid waste promptly.
• Make sure that toxic liquid wastes (used oils, solvents, and paints) and chemicals (acids,
pesticides, additives, curing compounds) are not disposed of in dumpsters designated for
construction debris.
• Arrange for regular waste collection before containers overflow. If a container does spill, clean
up immediately.
• Make sure that construction waste is collected, removed, and disposed of only at authorized
disposal areas.
• Train employees and subcontractors in proper solid waste management.
Management of the waste disposal site (WDS)
• Ensure WDS is totally fenced and access controlled
• Control weekly conditions of WDS.
• Ensure burning of waste does not threat forest (fire) and residences (smoke). Ensure burning
complies with conditions detailed in Sub-Plan 7 (Emission and Dust Control), and particularly
that only safe waste (Group A1-Combustible Solid Waste) are bu.
• Ensure Record of Waste Placement in the WDS is properly filled in accordance with form
presented in SP 12-Appendix 12-6.
Description
Prevent or reduce the discharge of pollutants to rivers and streams from sanitary/septic waste by
providing convenient, well-maintained facilities, and arranging for regular service and disposal.
Risks if no Application of this MANAGEMENT PRACTICE
Biological pollution of rivers and streams;
Contamination risk for local population and workers.
Suitable Application: & Criteria
Permanent camps should be equipped with septic tank facilities.
Temporary camps should be equipped with pit latrines.
Permanent workers’ sites for Deedoke project will be equipped with a wastewater treatment
facility.
• Septic tanks should be inspected regularly, and any observed overflow must be reported
immediately to the Camp Manager. In this event, sceptic tank will be emptied and the
traces of overflow cleaned to avoid stagnant contaminated water in camp.
• Septic tanks should be emptied regularly to prevent overflowing and sludge transported
for treatment to any appropriate facility in the area
• If delivery of sludge to a treatment facility is not possible, disposal of sludge will be
done in the solid waste disposal site, together with the putrescible waste (food waste).
• When temporary camp is closed, latrine superstructures will be dismantled and removed
and the pits will be carefully filled with earth and compacted.
• Water quality of treatment facility outflow should be checked regularly to ensure
efficient operation of the facility.
Maintenance
• Inspect facilities regularly.
• Arrange for regular waste collection.
Description
Prevent or reduce the discharge of pollutants to storm water from concrete waste by performing
on-site washout in a designated area, by treating batching plant effluents and training employees
and subcontractors.
Description
Prevent or reduce the discharge of pollutants to river and streams from vehicles and equipment
by washing in designated, contained areas only, eliminating discharges to the storm drain by
infiltrating, and training employees and subcontractors.
Prevent or reduce the discharge of pollutants to storm water from vehicle and equipment
maintenance by running a “dry site”. This involves performing work in designated areas only,
providing cover for materials stored outside, checking for leaks and spills, containing and
cleaning up spills immediately, and training employees and subcontractors.
Risks if no Application of this MANAGEMENT PRACTICE
Soil and water pollution;
Occupational and public safety if vehicles are not appropriately maintained.
Suitable Application: & Criteria
Cleaning of vehicles and equipment:
• When washing on-site, use designated wash areas to prevent wash water contact with
storm water, creeks, rivers, and other water bodies. The wash area can be sloped for
wash water collection and subsequent infiltration into the ground.
• Use as little water as possible to avoid having to install erosion and sediment control
for the wash area.
• Use phosphate-free, biodegradable soaps.
• Educate employees and subcontractors on pollution prevention measures.
Maintenance of vehicles and equipment:
Keep vehicles and equipment clean; don’t allow excessive build-up of oil and grease.
• If maintenance must occur on-site, use designated areas, located away from drainage
courses, to prevent the run-on of storm water and the runoff of spills.
• Maintaining vehicles and equipment outdoors or in areas where vehicles or equipment
fluids may spill or leak into the ground can pollute storm water. If you maintain a large
number of vehicles or pieces of equipment, consider using an off-site repair shop.
• Always use secondary containment, such as a drain pan or drop cloth, to catch spills or
leaks when removing or changing fluids.
• Place a stockpile of spill clean-up materials where it will be readily accessible.
• Use adsorbent materials on small spills rather than hosing down or burying the spill.
Remove the adsorbent materials promptly and dispose of properly.
• Regularly inspect on-site vehicles and equipment for leaks, and repair immediately.
• Check incoming vehicles and equipment (including delivery trucks and employee and
subcontractor vehicles) for leaking oil and fluids. Do not allow leaking vehicles or
equipment on-site.
• Segregate, recycle or dispose of wastes, such as greases, used oil or oil filters, cleaning
solutions, automotive batteries, hydraulic, and transmissions fluids. All these products
are classified as Hazardous waste and must be disposed of accordingly
• Automotive batteries can be stored for recycling but acid contained must be drained
and stored in an appropriate container on a Hazardous Waste Temporary Storage Area.
• Train employees and subcontractors in proper maintenance and spill clean-up
procedures
Description of Measures
All workers will complete the training programs contained in Table 13 and Table 14
below.
Participants in job-specific training will be identified as required in Table 15 on the
basis of their skills and capacity to undertake the training.
All training sessions will be conducted in Myanmar language for Myanmar personnel
and as appropriate for foreign staff. All written materials will be provided in Myanmar
language and other languages as appropriate.
A training register will be maintained that will contain details of the following:
i. Name of training session
ii. Date of training session
iii. List of attendees and signatures
iv. Name of trainer
A sample format for the training register is contained in Table 16.
At completion of each relevant training course, each participant will be issued with a
certificate of successful completion. A copy of the certificate will also be placed on
each participant’s employment file. A sample format for certificate to be developed.
The Owner Engineer will implement a rolling program of refresher courses in
environmental and health and safety awareness issues through the use of ‘tool-box’
sessions at construction sites. The program will aim to visit every construction site for a
2-hour session at least one time within a 6-months period.
During audits of the construction areas, workers knowledge of environmental, health
and safety issues will be examined.
Workers who have undergone job-specific training will be examined every 6 months in
relation to their knowledge and skills and subject to re-training as required. Records of
examination results and any re-training will be kept as part of the training register (refer
Table 16).
All new employees will complete relevant training (in accordance with Table 13, Table
14 and Table 15) prior to commencement of any activities on the construction site.
The key messages from the training sessions will be produced in poster and leaflet form
in Myanmar language. Posters will be displayed prominently in construction work
camps and construction areas and leaflets will be distributed to staff on a regular basis.
Table 14: Training programme for health and safety awareness training
3
Note that workers with regular exposure to these issues or responsibility for these activities will receive
specific training.
4
Note that participants will receive this training and will carry out these functions in addition to their
regular work tasks. These positions are not full-time designated positions but will be used on an ‘as-needs’
basis.
5
Note that participants will receive this training and will carry out these functions in addition to their
regular work tasks. These positions are not full-time designated positions but will be used on an ‘as-needs’
basis.
Table 16: Training register form for recording attendance at training course
TRAINING COURSE
NAME
TRAINING COURSE
DATE
TRAINING
INSTRUCTOR
LOCATION
ATTENDEES
Name Signature
Course Opening Course Closing
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
1) Objective
The objectives of the plan are to ensure that any chance – find physical
cultural resources that might be identified during pre-construction and construction period
are dealt with in an appropriate manner and there is no theft or destruction of physical
cultural resources.
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
• To reduce the social impacts on villagers in the affected villages in the
construction area and related facilities area and along the transmission line.
2) Context
Hydropower Component
Hpa Lan Pin Kone / Inn Hpa Lan Pin Kone / Inn
Kone / Ka Toe / Shan Kan Kone / Ka Toe / Shan Kan
Hnget Gyi Thaik / (North) / Shan Kan (South) (North) / Shan Kan (South) /
Hnget Gyi Thaik / Thayet Pin / Yeywa / Thayet Pin / Yeywa /
Nearby Villages Ma Gyi Inn / Gwebin / / Sun Ye (North) / Sun Ye Sun Ye (North) / Sun Ye
Ma Gyi Inn Kyaungywa Kyaungywa
Pein (South) / Kyauk Kone / (South) / Kyauk Kone /
Ywar Thit / Taung Yin / Ywar Thit / Taung Yin /
Na Be Pin Na Be Pin
Private land Private land Private land Private land 49 Towers in private land
48.07 38.34 55.19 66.82 Private land (%) 71 (Est.)
(%) (%) (%) (%) (67%)
Land Ownership
Government Government Government Government 24 Towers in Government Government
51.93 61.66 44.81 33.18 29 (Est.)
land (%) land (%) land (%) land (%) land (33%) land (%)
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• The Land Acquisition Act (1894)
• The Lower Myanmar Town and Village Act (1899)
• Village Act (1908)
• The Land Purchase Act (1941)
• The Requisition (Emergency Provisions) Act (1947)
• Law Safeguarding Peasant Rights (1963)
• The Constitution of the Republic of the Union of Myanmar (2008)
• The Farmland Act (2012)
• The Vacant, Fallow and Virgin Land Act (2012)
• The Foreign Investment Act (2012)
6
ADB Handbook on Resettlement (1998)
7
IFC Handbook for Preparing a Resettlement Action Plan
Eligibility
Eligibility will be determined using two criteria: cut-off date and possession
of Land Use Right Certificates (LURCs).
Cut-off Date: The cut-off date has not yet been determined. The cut-off date
should be the date at which the PAPs are officially informed of the intention of the
Government to acquire their land. The PAPs will be informed of the cut-off date. Any
people who use or settle in the land area to be acquired for the Project after the cut-off date
will not be entitled to compensation and/or assistance under the RAP.
LURCs: The eligibility for compensation to PAPs in Group 1, Group 2 and
Group 3 for land loss will be determined by the possession of LURCs or a claim that is
recognizable under national laws. Persons who do not have LURCs or any recognizable
claims to their land will not be eligible for compensation for land but will be entitled to
compensation for their affected assets upon land and limited right on land use.
Entitlement Matrix
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
The project developers will implement the plan and report to Compensation
Supervision Committee of Regional and District
Entitled Persons Type and Level of Impacts Number of Households Compensation Policy Implementation Issues
Group 1-PAPs
• Those with LURCs or recognizable • Loss of land, trees and crops, • To be determined • Cash Compensation: The PAPs will • The compensation should be
claims on the right to use land. and immovable assets due to construction receive full compensation. provided prior to construction.
of hydropower components • The cash compensation will cover: (i)
land loss at current market price or
replacement cost; (ii) loss of trees and
crops.
• Those without LURCs or • Loss of land, trees and crops, and • To be determined • Similar to PAPs with LURCs except
recognizable claims on the right immovable assets. they will not be entitled to
to use land. compensation for land loss.
Group 2-PAPs
• Those with LURCs or recognizable • Land loss due to inundation during • To be determined • The PAPs will be considered as Group • The compensation should be
claims on the right to use land. project operation 1-PAPs. The PAPs will receive provided prior to project operation.
compensation for the land loss and
structures, trees and crops on the lost
land.
• Those without LURCs or • Land loss due to inundation during • To be determined • The PAPs will be considered as Group • The compensation should be
recognizable claims on the project operation 1-PAPs and can receive cash provided prior to project operation.
right to use land. compensation for the entire loss
excluding land.
• Group 3-PAPs
• Those with LURCs or recognizable • Land loss due to installation of • The PAPs will receive cash • The compensation should be
claims on the right to use land. transmission line support towers. compensation for the entire lost land provided prior to transmission line
- 49 HHs (LURC status not and crops. installation.
• Those without LURCs or • Land loss due to installation of yet known) • The PAPs will receive cash • The compensation should be
recognizable claims or the right to transmission line support towers. compensation for only trees and crops provided prior to transmission line
use land. on the lost land. installation.
• Group 4-PAPs • Right on land use beneath transmission • At least 49 HHs (plus • The PAPs will receive cash • The compensation should be
line within 45.72-meter right-of-way will some additional HHs compensation as opportunity cost to provided prior to transmission line
be limited. TBD) compensate for the limited right in land installation.
use.
10) Budget
C1 Compensation
A. Land Compensation
Categories of Land Total Area, acres Cost, USD/acre Total Cost, USD
L1L,L1R, L2R, L2L 428.66 8,974 3,846,794.84
L3 2.51 3,846 9,653.46
Total 3,856,448.30
C2 Compensation
A. Land lease
Total area 250 acres
Lease rate, USD/acre 385 per year
Total annual lease 96,250 USD
Or a lump sum amount 5,065 USD/acre
Total lump sum amount 1,266,250 USD
Perennial Tree:
100 mango trees 120 USD/1 tree
100 banana clumps 25 USD/ 1 clump
Total Compensation
(100x120)+(100x25) 14,500 USD
1) Objective
• To Enhance or at least restore the quality of life for Project Affected
Persons.
• To extent possible, prevent or minimize adverse social impacts.
• Mitigate all possible remaining adverse social impacts.
2) Context
The Project Affected Persons (PAPs) are people in the nearby villages of
the four land categories whose land will be used by the Project. Most of them would own
the land although some may be users of the four types of land requirements.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• The Land Acquisition Act (1894)
• The Lower Myanmar Town and Village Act (1899)
• Village Act (1908)
• The Land Purchase Act (1941)
• The Requisition (Emergency Provisions) Act (1947)
• Law Safeguarding Peasant Rights (1963)
• The Constitution of the Republic of the Union of Myanmar (2008)
• The Farmland Act (2012)
• The Vacant, Fallow and Virgin Land Act (2012)
• The Foreign Investment Act (2012)
For villagers in the construction site and upstream area who lose their
farmland, production within home lot is one of mitigation to bring them food stuff and the
surplus can be sold for addition income as well.
(c) Fishery
• Provision of training on aquaculture or fish pond raising, cage
culture.
• Set new equilibrium on newly river pondage area, introducing of
fish into river pondage area. Recommended releasing species should be replication of
herbivorous species, omnivorous species and carnivorous species. The recommended for
herbivorous species are such as Rohu and allied (Labeo spp), Cirrhinus mrigala for
example. The omnivorous species are such as silver barb (Barbonymus gonionotus), the
Sweetlips minnow (Osteochilus hasselti) and walking catfish (Clarias batrachus). The
carnivorous species are such as snakehead (Channa spp.), Wallago attu, Ompok spp. and
Bagrids catfish (Mystus spp.)
• For increasing the chance and efficiency for villagers to work in this
project, preparing villagers to have skill and experience to work is needed. Sample of
occupation that villagers can occupy are construction worker, carpenter, gardener, guard,
light machine repair, trader, driver, food cooking, etc. Activities to prepare PAPs for off-
farm occupation are;
- To facilitate training by practice
- To set up vocational education
- To coordinate with contractor for PAPs employment
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
The project developers will implement the plan and report to Compensation
Supervision Committee of Regional and District
10) Budget
Estimated Cost
Activity Unit cost (USD)
Construction
period
Livelihood Restoration Program for 3 villages
- Promote home lot production activity (training, 500/village/year 6,750
demonstrate plot, marketing promotion, provide
seed)
- Livestock Raising 500/village/year 6,750
- Fishery 500/village/year 6,750
- Off-farm occupational development 500/village/year 6,750
- (training and technical advice)
Total 27,000
1) Objective
2) Context
The Project Affected Persons (PAPs) are people in the nearby villages of
the two land categories whose land in the construction and pondage areas will be used by
the Project. Most of them would own the land although some may be users of the of land.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• The Land Acquisition Act (1894)
• The Lower Myanmar Town and Village Act (1899)
• Village Act (1908)
• The Land Purchase Act (1941)
• The Requisition (Emergency Provisions) Act (1947)
• Law Safeguarding Peasant Rights (1963)
• The Constitution of the Republic of the Union of Myanmar (2008)
• The Farmland Act (2012)
• The Vacant, Fallow and Virgin Land Act (2012)
• The Foreign Investment Act (2012)
•
Provide equipment for health service and sanitary conditions
improvement in the Hnget Gyi Thaik, Thayet Pin, Ma Gyi Inn, War Net village, Yeywa
and Jongywa.
• Organize activities to enhance health and sanitation by educating
villagers on health care and diseases prevention for people of all ages.
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
The project developers will implement the plan and report to Compensation
Supervision Committee of Regional and District
10) Budget
Estimated
Activity Unit cost Cost (USD)
Construction
period
Community Development Program
Public Health
- Health material and equipment 6 villages, 500 USD/ village/ 13,500
year
- Educate and training 6 villages, 850 USD/year 3,825
Education
- Scholarships 6 villages, 850 USD/year 3,825
- Educational materials and equipment 6 villages, 850 USD/year 3,825
Basic Infrastructure
- Water pumping system
- Safety signs installation or barriers 1 village (Hnget Gyi Thaik) 2,000
provided for community safety
Total 26,975
The Project Proponent and the Contractor will both be involved in environmental
management of the Project construction. The Contractor will select construction methods
or practices that have least environmental impacts, thus meeting environmental
performance targets prescribed in the Contract. During the construction, the Contractor will
implement, under supervision of the Project Proponent, impact mitigation measures
prescribed in the Contract.
The Project Proponent and the Contractor will have to establish and operate their
own environmental management systems (EMS) for the Project construction. The two
EMSs will be related and based on the same information base. The Project Proponent’s
EMS will be focused on monitoring and reviewing environmental compliance at the Project
level as part of the Project management. The Contractor’s EMS will be focused on
environmental management at the task level as part of the construction management. The
two EMSs will therefore be complementary and will enable the Contractor and the Project
Proponent to complete the Project construction with no significant environmental impacts.
The EMS of the Project Proponent will adopt the following procedures:
Before commencing the construction, the Contractor will review and update
existing data on relevant baseline environmental condition, particularly at locations
expected to be affected by the construction.
The weekly inspections will be formal visual inspections in more details than the
daily inspections.
The Contractor’s EHS Manager will be responsible for the daily and weekly site
inspections. The Owner’s EHS Manager will participate in the weekly site inspections, and
occasionally in the daily site inspections.
The monthly inspections will be conducted in more detail than the weekly
inspections. The monthly inspections will also include risk triggers identified in the
environmental risk management plan. The monthly inspections will be conducted jointly
by personnel from both sides, including the Project Managers, the Construction Manager
and the EHS Managers.
The Contractor’s EHS Manager will input all data from completed EIFs as soon
as possible to generate an Environmental Incident Register (EIR). A standard
Environmental Incident Register (EIR) will be controlled by the Contractor’s EHS
Manager. It will contain all environmental incidents occurring on the construction sites of
the power plant, transmission line, gas pipeline, and access road. The EIR will be discussed
regularly at the project environmental performance review meetings. These meetings will
discuss the corrective actions taken, and the preventative measures that have been put in
place.
The Contractor’s EHS Manager will record results of the daily inspections in
daily site inspection notes. The Contractor’s EHS Manager and Construction Manager will
review the daily site inspection notes on a weekly basis to confirm that the checks and
subsequent required works are being carried out, and additional inspections are included as
per construction progress.
For weekly inspections, the Contractor’s EHS Manager will present results of
the inspections in weekly site inspection reports for discussion in the weekly project review
meetings. Both the daily inspection notes and weekly inspection reports will highlight
factors or events that could lead to noncompliance and will need attention of the
Contractor’s Project Manager.
The Contractor’s EHS Manager will prepare monthly site inspection reports as
part of the monthly environmental monitoring reports.
Based on the monthly internal monitoring reports and results of the monthly
review meetings, the Owner’s EHS Manager will prepare a project environmental
monitoring report every six months for submission to MONREC. This report as prescribed
in the EIA Procedure, 2015 (Article 89) will contain the following:
• documentation of compliance with all Conditions;
The monitoring reports should also present the construction progress over the
report period.
6.6.4 Corrective Actions
A. Categories of Non-Compliances
B. Categories of Non-Compliances
The Owner’s EHS Manager will be responsible for identifying and ranking
EHS non-compliances. However, all Project management personnel are encouraged to help
identify EHS non-conformance.
The Owner’s EHS Manager will take actions according to the category of
non-compliances.
For Level A Non-Compliances: The Owner’s EHS Manager will report the
identified non-conformances to the Project Manager with recommendations on corrective
actions and instructions for the Contractor.
For Level C Non-Compliances: The Owner’s EHS Manager will instruct the
Contractor to take appropriate corrective actions.
For Level B and C non-compliances, the Contractor will submit a brief note
on corrective actions to be taken to the EHS Manager and the Resident Engineer, if the
corrective actions are related to change in construction practices.
E. Non-Compliance Report
The EHS Manager will prepare a brief non-compliance report based on the
CAR and reports from the Contractor. The non-compliance report will contain: (i)
information in the CAR; (ii) corrective actions taken by the Contractor; (iii) implementation
period; (iv) results; and (v) recommendation for further actions, if any. The non-compliance
report should be in one or two pages in a Form to be designed.
Non Compliance Report Forms will be verified and closed out by the
originator or his designee. Correspondence referring to a proposed course of action shall
be referenced and attached to the Non Compliance Report Form as appropriate and stored
within the Project Documentation System.
At the request of the Project Proponent, the EIS Consultant prepares this
Emergency Response Plan (CERP) for the construction of Deedoke Hydroelectric Power
Project as part of the EIS study and present as part of the CEMP. It should be noted that the
Contractors will have to be contractually bound to prepare and implement an ERP for
review and approval by the Project Proponent. The CERP must be based on the detailed
design and construction plan, schedule, and methods prepared by Contractors and approved
by the Project Proponent to be part of the contract. Therefore, this CERP prepared as part
of the EIS study can only be considered as an initial ERP with substance at the conceptual
level. The Project Proponent should use this initial CERP to prescribe minimum
requirements for the CERP to be prepared by Contractors before commencing the
construction.
Contractors will further develop this initial CERP to become the final CERP
which will have to be ready for implementation in due course before the construction. To
facilitate its further development by Contractors, this initial ERP adopts the structure of the
final CERP. Contractors will have to fill identified information gaps and add more details
as appropriate.
In line with the above purpose, the CERP presents key emergency incidents,
procedures for responding to the emergency incidents, organization for the management of
CERP implementation, responsibilities of concerned units and persons in the Contractor’s
construction management organization in emergency response, training requirements, and
guidelines for review and updating of the CERP.
The CERP is made available to the Tripartite Committee. The CERP is also
disclosed to the public through the web site of the Project Owner: http:www.____________
(Note: This section is to be prepared by the Contractor based on the detailed design and detailed
construction plan.)
Incidents that are considered emergencies are those that demand quick
response as they are causing serious consequences or are certain to escalate and cause
serious consequences.
(6) Procedures
A. Emergency Communications
B. Notification Procedure
After the emergency incident is verified and its nature is defined, the
EHS Manager will immediately inform the Project Manager (PM). The Project Manager
will activate the HSE for implementation of the CERP. All teams under the HSE will be
immediately deployed to take appropriate actions as prescribed in the Response Procedures.
D. Emergency Evacuation
E. Documentation Procedure
Fire Response
a. Date and time of being notified of the incident
b. Date and time of arrival at the site
c. Exact location of the incident (including GPS coordinates)
d. Magnitude and Location of the fire
e. The extent of smoke observed and direction
f. Activities taken to control the fire
g. Time that the fire is successfully put under control
h. Time cleanup completed and description of cleanup activities
i. Time the team left site
j. Time, name, and nature of other regulatory agencies that have been
notified by the fire response team or that have participated in the
fire control
k. The area impacted by the smoke
(7) Resources
The Contractor has procured or leased all equipment and materials deemed
adequate for effective emergency response during the construction. The Project Manager
shall ensure orderly and systematically storage or installation of the provided resources
ready for immediate use in time of emergency. Emergency equipment must be maintained
through preventive maintenance procedures (inspection and testing) in accordance with the
manufacturer’s recommendations to ensure that equipment is in ready condition for use.
The inspection shall be documented in a field logbook or similar means to be kept in the
project files. Emergency equipment is to include, but not limited to the following:
• Firefighting;
• First Aid;
• Emergency Evacuation;
• Medical and Environmental Emergencies; and
• Other subjects as required.
(9) Drilling
The ERM will ensure that the emergency operations must be rehearsed once
every six months.
The CERP shall be reviewed and amended annually or any time to:
Members of the HSE will refer to the relevant operational manuals in their
implementation of the response procedures in this CERP. The reference operational
manuals include, but not limited to, the following:
6.8.1 Responsibilities
There are three key groups with responsibility for environmental management
of the Project:
Project Proponent
Contractor
• Prepare a detailed Contractor CEMP for review and approval by the Project
Proponent.The Contractor CEMP should follow the outline prescribed by the Project
Proponent as proposed in Appendix 3A.
• Implement the mitigation measures during the construction through
construction method statements and work instructions in strict conformance with
environmental conducts prescribed in the Contract.
• Ensure that all process and environmental control equipment meet all
technical specifications related to their environmental performance.
• Conduct periodic monitoring and reporting of its compliance with the
environmental and social performance prescribed in the Contract.
• Ensure that its sub-contractors shall comply with the Contractor CEMP.
• Consistently update the Contractor CEMP and submit the updated version
to the Project Proponent for approval.
MONREC
MECF/DEC Surrounding
& Others Communitie
Project
Owner
Project
Manager Stakeholder
Management
Administrative ESH
Support Manager
EPC
Contractor
EPC Project
Manager
The Project Management team will support the power plant O&M team
during the transition phase between construction and operational phases. In particular, the
Project Management team is responsible for the sign off construction and post construction
resource consent and designation conditions, handover of environmental monitoring data
and reports and compliance and audit reports before the Project is handed to the O&M
team.
6.8.3 Documentation
The Contractor will ensure that the Project Proponent will have a convenient
access to its documentation system for environmental management. The documentation
system will provide information for environmental audit of the Contractor. Details on the
access to the documentation system and documentation control related to the Project
Proponent will be worked out by the Contractor and presented in its CEMP.
Internal communication will involve: (i) communications within PMO; and (ii)
communications within CPMO; and (iii) communications between PMO and CPMO.
External communication will involve communications between PMO and stakeholders and
the public. Communications between CPMO and stakeholders will need to receive prior
concurrence of PMO.
Internal Communication
External Communication
• scope of construction;
• construction schedule;
• environmental impacts and mitigation measures;
• environmental policy, objectives, and targets;
• environmental management roles and responsibilities;
• legal requirements and environmental quality standards;
• OCEMP;
• CCEMP;
• results of environmental monitoring and performance evaluation;
• hazards and emergency situation; and
• mechanisms for grievance redress, queries, comments, or complaints
from stakeholders
Communications
Information
Internal External
Basic Information
Corporate’s environmental policy on project construction
EIA Report
Owner-CEMP
MONREC’s EHS requirements or conditions attached to the issuance
of ECC
Contractor-CEMP
EHS’s specifications and clauses in the contract
Construction schedule
Project EMS
Project management organization – Owner
Construction management organization – Contractor
Information Generated in EHS Management
Daily, weekly and monthly site inspection reports
Environmental monitoring results
Minutes of project review meetings – EHS
Monthly monitoring reports
Minutes of Tripartite Committee’s meetings
Complaints register and response
Reports on visits by media and stakeholders for environmental
purposes
Environmental incident reports
Corrective action reports
Biannual monitoring reports submitted to MONREC
(2) Responsibilities
Project Proponent
The Contractor
This CEMP will be consistently reviewed and updated by the EMS Manager
or the Project Manager to ensure that it adequately responds to the construction progress
and changes in the construction schedule and methods, if any.
the villages, and 3 represent the Project Proponent. The ECD official should be the
chairperson and the Project Manager of the Project Proponent should serve as secretariat
of the committee. The secretariat will be assisted by the EHS Manager of the Project
Proponent as assistant secretariat of the committee. Representatives of the Contractor
should participate in the committee meetings to support information.
The Project Owner shall within ten (10) days of completing a monitoring report
contemplated in Articles 88 and 89 in accordance with EMP schedule make the report
publicly available on the Project’s website, at a designated public office as agreed with the
Ministry and at the Project offices. Any organization or person may request a digital copy
of a monitoring report and the Project shall, within ten (10) days of receiving such request,
submit a digital copy via email or as may otherwise be agreed upon with the requestor.
The Owner PMO will make arrangements for the disclosure of monitoring
reports in compliance with the above legal requirements. In addition, information on
environmental management will be disclosed to the proposed tripartite committee.
6.9.3.1 Objectives
In the first instance, the grievance management process will seek to resolve
disagreements or stakeholder concerns before they evolve into grievances. This is done
through ongoing engagement with stakeholders throughout the Project, particularly the
PAPs. The resulting informal negotiations and discussions will be conducted in a
transparent manner and will be appropriately documented.
It is anticipated that the Communities Team will be the first point of contact for
villagers to raise grievances (and other issues and concerns).
• The grievance is not valid (e.g. does not relate to the Project). If it is decided
that a grievance is not valid, the grievance will be dismissed and advice of the decision and
the reasons for dismissal will be provided to the complainant in writing (and in person if
required);
• The grievance is a minor issue (e.g. a request for information or
clarification). A response will be provided in writing (and in person if required); and
All grievances will be recorded in the stakeholder database. This will include a
summary of the grievance, the resolution or agreement on proposed actions (between the
Project and the complainant), and monitoring of actions taken in response to the grievance.
In addition, the grievance log will be stored in the database.
Mainly, Project Proponent will appoint the Independent Expert Group and
the Communities Team. The Independent Expert Group will support, coordinate and
manage the compensation process on the ground and will ensure that the compensation
process is in line with international guidelines, particularly those by the World Bank / IFC.
This Independent Expert Group will also supervise the implementation of the project’s
Environmental Management Plans. The Communities Team will be responsible for day-to-
day implementation (Figure 14).
• Endorsing the cut-off date once the census and land and asset inventory
have been completed;
• Attending disclosure meetings with PAPs;
• Reviewing monitoring reports generated during implementation of the
project RAP; and environmental management plans; and
• Negotiate an outcome where the complainant is not satisfied with the
initial response provided by the Communities Team to a grievance. This will involve
engaging with the complainant as well as the Communities Team to reach a mutually
agreeable outcome. It is recommended that minutes from the committee meetings be made
publicly available to enhance transparency in decision-making processes.
(i) A daily cash allowance for assistance with the compensation and
livelihood restoration process;
(ii) Training on their role and responsibilities; and
This will keep reduce the burden on any one village member, enable new ideas
to be injected into the committee and reduce the potential for members to be co-opted by a
particular interest group. Change over should be staggered – so as to preserve institutional
knowledge. It is recommended that committee members be required to sign and adhere to
a Code of Conduct, which sets out criteria for integrity, transparency, objectivity, openness
and accountability. It is recommended that minutes from the committee meetings be made
publicly available to enhance transparency in decision-making processes.
6.11 AUDIT
External EHS audits will be undertaken at the end of first year of the construction
period and at physical completion of the construction. These two audits will be undertaken
by external Environmental Auditing Consultants to review the overall implementation and
effectiveness of the CEMP, related site specific plans, procedures and associated
documentation and overall standard of onsite compliance with legislative requirements.
Audit reports, action plans and any other documentation stemming from the audit
process shall be kept for a minimum of six years. The EHS Manager will be responsible
for site filing of these documents.
CHAPTER 7
OPERATIONAL PHASE EMP
The key objective of the OEMP presented in this section is to establish a clear
operational framework for environmental management during the operational phase of the
Project. The Contractors will then use this OEMP to prepare a more detailed OEMP which
will be based on the detailed designs of the hydropower plant, results of the commissioning,
and O&M details. The detailed OEMP will be reviewed and revised as appropriate by the
hydropower plant O&M team to reflect actual conditions during commercial operation.
7.2 MANAGEMENT AND MONITORING PLANS
This EMP detail the relevant objective, legal requirements, mitigation measures,
monitoring program, performance specifications, implementation schedule, responsibilities
for implementation, and budget. This EMP will be developed prior to the start of Operation
works and during the course of the Project when operation works requiring more detailed
environmental planning are identified and will be subject to the review procedure. The
following EMPs will be developed for the Project;
1) Objective
2) Context
The project activities during operation phase may cause potential impact to
the environment and human.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• Speeds of vehicles in the project site will not be more than 40 km/hr.
• The project proponent will be required to regularly monitor ambient
noise levels at the receptors.
5) Monitoring Programs
Parameters
• LAeq 1 hr (Daytime)
• LAeq 1 hr (Nighttime)
• LAmax
• L90
Operation Site
Frequency
Four times per year and each sampling must be conducted for 5 consecutive
days.
Methodology
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
Project Proponent.
9) Budget
1) Objective
2) Context
The project activities during operation phase are not likely but may cause
potential impact to the environment and human.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
5) Monitoring Programs
Parameters
• Vibration or PPV measured
Dam Site
Frequency
Four times per year during the first year and each sampling must be
conducted for 5 consecutive days.
Methodology
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
Project Proponent.
9) Budget
and each sampling must be conducted for 5 consecutive days. Total budget approximately
costs 12,000 USD.
1) Objectives
• To prevent flood hazard turning into disasters in the project area.
• To reduce flood risk in the project area.
• To avoid any incremental flood impact from project activities
• To monitor the performance of the management action or mitigation
measures.
2) Context
The project activities during operation phase may cause potential impact to
the environment and human.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• Public Health Law (1972)
• Preparing for flood risk: Preparedness activities are intended to achieve a sense
of readiness for the flooding emergency. There are a number of ways to get ready
and ensure preparedness:
• Develop a flood hazard mitigation plan and update it periodically.
• Conduct an emergency exercise to identify deficiencies in the flood hazard
mitigation plan and update it accordingly.
• Utilize emergency warning system; install a flood warning system for
warning to immediate upstream and downstream people and communities.
The system will be designed in cooperation with the plant operator of the
Yeywa Hydropower Plant and government authorities responsible for
monitoring water levels and meteorological data within the Lower Myitnge
River basin. The system will include the possibility to raise alarms via a
public announcement system.
• Make sure drainage structures are cleared to allow water to be intercepted
and conveyed as intended.
• Identify materials needed to respond to flood emergency e.g. pumps, sand
bags and clay for temporary levees, clean-up kits.
• Protecting from flood risk and response for flood: Measures to reduce the
likelihood of flooding affecting people and property and to respond for flood hazard
in the project area include:
• Improving the standard of protection at important location at risks of
flooding.
• Implementing individual property protection.
• Providing immediate assistance such as emergency relief and search and
rescue.
• Recovery and Review:
• Measures for recovery and review include:
• Provide help to communities in the project vicinity affected from flood
hazard.
• Carry out investigation after flooding to mark high water line and document
the maximum flooding condition. All information collected can be used to
justify the need for improving the accuracy of flood modeling.
5) Monitoring Programs
Parameters
• Water level upstream and downstream from project site and at dam site
Location
• Myitnge river level upstream and downstream from the project area and
at dam site.
Frequency
• 12 times per year (Monthly) and on permanent basis during flood risk
periods.
Methodology
• Monitoring operation of stream gauging stations.
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
Project Proponent.
9) Budget
1) Objective
• To minimize the adverse impacts caused by the projects activities at the
project sites.
• To monitor the performance of the management action or mitigation
measures and assess compliance with the applicable standards.
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Public Health Law (1972)
Parameters to be monitored
Surface water quality parameters in operation phase are shown in Table
21.
Frequency
Quarterly monitoring.
Methodology
Figure 16: Location of surface water and aquatic ecology sampling stations
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
Project Proponent.
9) Budget
1) Objective
2) Context
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
5) Monitoring Programs
Parameters to be monitored
• Phytoplankton
• Zooplankton
• Benthos
• Fish species
Frequency
Quarterly monitoring.
Methodology
Benthos
• Collected by Eckman dredge with a grabbing area of 0.25 ft2. Three
grab sampling (0.75 ft2) were performed at each station.
• Each collected samples were observed to identify texture and
composition of sediments and recorded.
• The sediments are washed through a series of wire sieves. Retained
fauna are kept in plastic bottles and preserved in a 5% formalin solution for species
identification and density assessment.
Fish species
• Carried out with local fishing equipment, size of such equipment
including width, length and mesh size would be recorded as same as sampling time. Fish
samples will be preserved and sent to a laboratory for species identification by classification
guidance books (Kottelat, 2001 and Rainboth, 1996).
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
Project Proponent.
9) Budget
1) Objective
• To manage the solid waste with appropriate methods to minimize the
source of adverse effect to human health.
2) Context
Solid waste will be generated from activities associated with the Project, the
main types of solid waste Solid waste from workers are domestic waste such as garbage,
glass, and food waste, etc. The management of solid waste is very important. If not properly
controlled and disposed of, waste can be unsightly and cause human health and safety
concerns.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
• National Environmental Quality (Emission) Guidelines (2015)
• Electricity Law (2014)
• The Forest Law (2018)
5) Monitoring Programs
• Daily checking amount of solid waste generated during operation phase
and results will be included in monthly reports.
6) Performance Specifications
• Amount of Solid waste generated during operation phase
7) Implementation Schedule
8) Responsibilities
Project Proponent
9) Budget
• Mitigation Measures and Monitoring Program: Included in operation
cost by Project Proponent.
1) Objective
• Settlement;
• Deformation;
• Seepage and;
• Cracks
2) Concept
2.1 Settlement
Additional loads by the dam and fluctuation of the reservoir water level
may generate vertical deformation that results in settlement. The vertical deformation
(settlement) would be measured to evaluate the performance of the dam. Settlement may
occur instantaneously as elastic deformation as load is applied.
2.2 Deformation
2.3 Seepage
2.4 Crack
Cracks are likely to occur on concrete structures but basically, they will
not affect the stability of the structures seriously. However, monitoring of major cracks
would contribute for the plant operator to understand dam behavior in light of other
instrumentation results. The cracks will be monitored through visual inspection with crack
scales and the locations of the cracks will be recorded on as-build drawings (“Crack Map”).
The Crack Map will be updated when abnormal behaviors are found during the inspection.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include
4) Management Action
• Monitoring Staff
• Maintenance Manager
• Engineer
• Plant Manager
Normal operation data trends for some instruments may require several
years to develop and the data trends are expected to vary from season to season and with
raising and lowing of the water level in the reservoir, basically during flood events.
5) Monitoring Program
6) Performance Specifications
Figure 17: Movements of Dashidaira Dam and Periodic Behavior that is the Baseline
not critical events for the facility designs of the Deedoke plant and that the frequency of an
emergency acquisition of instrument data should be set up appropriately. During such large
flood events, the hydraulic conditions of the spillway should be observed during the period
along with visual inspection of the dam. Thorough inspections of the dam and
appurtenances should be performed following the floods. Monitoring and Surveillance will
consist of:
•
close visual inspection of the conditions of the dam, abutments and
appurtenance equipment and;
• measurement and assessment of instrument data.
Monitoring
Facility and Inspection Item
Frequency
1. Dam
1a. Concrete Surface (Example)
The concrete surface should be examined to evaluate the
deterioration and continuing serviceability of the concrete.
1b. Cracks
Concrete should be examined for structural cracking shrinkage and
temperature effects or differential movements.
1c. (To be determined specifically later)
2. Instrumentation
Instrumentation that have been installed to measure behaviors of
the structures should be examined for proper function. The
available records and readings of installed instruments should be
reviewed to detect any unusual performance of the instruments or
Monitoring
Facility and Inspection Item
Frequency
evidence of unusual performance of distress of the structure.
3. Reservoir
The features of some areas in the reservoir should be examined to
what extent the water impounded by the dam might cause a risk to
the safety of the dam or to human life or property.
4. Downstream Environment
The immediate downstream of the dam should be examined for
conditions that might impose any constraints on the operation of
the dam or present any hazard to the safety of the dam.
7) Implementation Schedule
8) Responsibility
Project proponent.
9) Budget
Levels A Threshold Level “A” observations or measurements in at Arrange meeting with the Engineer at earliest time;
least [specific numbers will be determined later] categories of Increase monitoring frequency of specific or all instruments
observation depending on location and nature of the monitoring
etc observation;
Increase visual inspection frequency;
Discuss to determine if additional actions are necessary;
etc
Levels B Threshold Level “B” observations or measurements in at (Specific responses and actions will be determined later)
least [ ] categories of observation
etc
Levels C Threshold Level “C” observations or measurements in at
least [ ] categories of observation
etc
1) Objective
Identify potential possible accidental and emergency situations during the
operational period and establish and maintain an emergency preparedness and response
system in the case of (a) Deedoke dam failure, (b) serious equipment failure such as crane
collapse in the powerhouse; (c) structure collapse; (d) fire and explosion; (e) vegetation /
forest fire; (f) personnel fall into the river; (g) accidental release of hazardous materials into
the river; (h) extreme flooding at project site caused by extraordinary release from Yeywa;
(i) serious injury to project personnel, and public in project area caused by project related
equipment; (j) large scale food poisoning in canteen; (k) and security; etc.
2) Impact Locations
3) Legal Requirement
National laws and standards that are most relevant to the management of
this plan include;
• National Environmental Policy (1994)
• Environmental Conservation Law (2012)
• Environmental Conservation Rules (2014)
both by the dam owner and emergency management officials to facilitate timely
notification and evacuation of areas affected by a dam failure or flood condition. These
maps greatly facilitate notification by graphically displaying flooded areas and showing
travel times for wave front and flood peaks at critical locations.
6. Appendices. The appendices contain information that supports and
supplements the material used in the development and maintenance of the EAP.
Coordination
It is vital that development of the EAP be coordinated with all entities,
jurisdictions, and agencies that would be affected by a serious accident or emergency
situation. The finished product should be user friendly as it realistically takes into account
each organization's capabilities and responsibilities.
Coordination with local emergency management officials at appropriate
levels of management is essential to ensure that there is agreement on their individual and
group responsibilities. Participation in the preparation of the EAP will enhance their
confidence in the EAP and in the accuracy of its components. Coordination will provide
opportunities for discussion and determination of the order in which public officials would
be notified, backup personnel, alternate means of communication, and special procedures
for nighttime, holidays, and weekends.
The tasks and responsibilities of the dam owner and the emergency
management officials that would be implemented during an incident need to be as
compatible as possible.
To facilitate compatibility, the dam owner should coordinate emergency
response actions with the local emergency management officials. This should help prevent
over- or under-reaction to the incident by various organizations.
Warning
Planning and implementation of warning system to the population of
hazardous materials release into the river or vegetation/forest fire are the responsibility of
the local officials who are responsible for the safety of the public who live in areas that
would be impacted. The Deedoke dam owner should not usurp the responsibility of the
local authorities responsible for the warning. However, there are recreational facilities,
campgrounds, or residences that are located downstream of Deedoke dam where local
authorities may not be able to issue a timely warning. In such cases, the Deedoke dam
owner should coordinate with local emergency management officials to determine who will
warn these people and in what priority.
Maintaining an EAP
After the EAP has been developed, approved, and distributed, periodic
maintenance must be done to it so that it will not become outdated, lose its effectiveness,
and no longer be workable. The plan must be exercised (verified), by those involved in its
implementation so that they are familiar with their roles and responsibilities, particularly if
emergency response personnel change. The plan must be updated at regular intervals so
that the information contained in it does not become outdated and useless.
Exercising. Emergency incidents at construction sites are common events. Therefore,
training and exercises are necessary to maintain operational readiness, timeliness, and
responsiveness.
5) Monitoring Programs
Preparedness
Preparedness actions should include among others:
• Surveillance and Operation Instructions
• Response at night and during weekends or holidays
• Phone numbers and addresses directory
• Response during periods of darkness or adverse weather
• Alternative systems of communication
• Preventive & Mitigation Actions Instruction
6) Performance Specifications
7) Implementation Schedule
8) Responsibilities
9) Budget
1) Objective
2) Context
The Project Affected Persons (PAPs) are people in the nearby villages of
the two land categories whose land in the construction and the pondage area will be used
by the Project. Most of them would own the land although some may be users:
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include:
For villagers in the construction site and upstream area who lose their
farmland, production within home lot is one of mitigation to bring them food stuff and the
surplus can be sold for addition income as well.
(c) Fishery
• For increasing the chance and efficiency for villagers to work in this
project, preparing villagers to have skill and experience to work is needed. Sample of
occupation that villagers can occupy are construction worker, carpenter, gardener, guard, light
machine repair, trader, driver, food cooking, etc. Activities to prepare PAPs for off-farm
occupation are:
- To facilitate training by practice
- To set up vocational education
- To coordinate with contractor for PAPs employment
5) Monitoring Programs
6) Performance Specifications
10) Budget
Estimated Cost
Activity Unit cost (USD)
Operation
period (1st-3rd)
Livelihood Restoration Program for 3 villages
- Promote home lot production activity (training, 500/village/year 4,500
demonstrate plot, marketing promotion, provide seed)
- Livestock Raising 500/village/year 4,500
- Fishery 500/village/year 4,500
- Off-farm occupational development 500/village/year 4,500
- (training and technical advice)
Total 18,000
1) Objective
2) Context
The Project Affected Persons (PAPs) are people in the nearby villages of
the two land categories whose land in the construction and pondage area will be used by
the Project:
• Group 1-PAPs who are related to L1R and L1L.
• Group 2-PAPs who are related to L2R and L2L.
Most of them would own the land although some may be users.
3) Legal Requirements
National laws and standards that are most relevant to the management of
this plan include;
•
Provide equipment for health service and sanitary condition
improvement in the Hnget Gyi Thaik, Thayet Pin, Ma Gyi Inn, War Net village, Yeywa
and Kyaungywa.
• Organize activities to enhance health and sanitation by educating
villagers on health care and diseases prevention for people of all ages.
5) Monitoring Programs
6) Performance Specifications
7) Implementation Schedule
The project developers will implement the plan and report to Compensation
Supervision Committee of Region and District
10) Budget
Estimated Cost
Activity Unit cost (USD)
Operation
period (1st-3rd)
Community Development Program
Public Health
- Health material and equipment 6 villages, 500 USD/village/ year 9,000
- Educate and training 6 villages, 850 USD/year 2,550
Education
- Scholarships 6 villages, 850 USD/year 2,550
- Educational materials and equipment 6 villages, 850 USD/year 2,550
Total 16,650
7.6 AUDIT
External EHS audits will be undertaken every three years. These audits will be
undertaken by external Environmental Auditing Consultants to review the overall
implementation and effectiveness of the OEMP, related site specific plans, procedures and
associated documentation and overall standard of onsite compliance with legislative
requirements.
Audit reports, action plans and any other documentation stemming from the audit
process shall be kept for a minimum of six years to demonstrate ongoing OSH monitoring
and improvement. The EHS Manager will be responsible for site filing of these documents.
CHAPTER 8
IMPLEMENTATION BUDGET AND SCHEDULE
8.1 BUDGET
Construction Operation
No Plan TOTAL
Phase Phase
Construction Operation
No Plan TOTAL
Phase Phase
8.2 SCHEDULE
The schedule for implementing the CEMP and OEMP will be linked to the
project schedule. After the Contractor completes the detailed designs and detailed
construction plan and schedule, the Contractor should prepare a detailed CEMP within one
month.
The Project Proponent should prepare a detailed OEMP within two weeks after
commissioning of the hydropower plant and its associated facilities.
APPENDIX 3A
OUTLINE OF CONTRACTOR’S ENVIRONMENTAL MANAGEMENT PLAN8
(for guidance only)
1. INTRODUCTION
The introduction of the Contractor’s EMP should include:
• a brief description of the project and the contract
• the contractor’s environmental objectives
• an explanation of the role of the Contractor’s EMP and how it will be used
during construction to achieve the project’s environmental and social (ES)
objectives.
2. ENVIRONMENTAL MANAGEMENT SYSTEM
The contractor shall provide details of the ES management system (ESMS) to
apply during the contract.
The basic elements of the contractor’s ESMS to be detailed are likely to include:
2.1 Contractor’s ES policy
Include a copy of the policy document and an explanation of how the policy will
apply to the project.
2.2 Project organisation chart
An organisational chart showing the reporting/responsibility relationships,
position titles and personnel, including subcontractors, should be included. The personnel
with specific site ES management responsibility should be highlighted.
2.3 Training, awareness and competence
Describe how the organisation training policy will apply to this contract to ensure
that all employees and subcontractors are aware of and adequately trained to discharge their
environmental responsibilities. A specific site briefing prior to commencement of works
shall occur.
2.4 ESMS documentation
Provide documented details of the system, if available, including any manuals,
standard report sheets, checklists, etc.
2.5 Document control
Describe the document control system to apply to the contract.
8
Modified from Appendix A, Contractor’s Environmental Management Plan Guidelines for Construction-
Road, Rail and Marine Facilities, Government of South Australia Government, Revision 2 February 2009