Professional Documents
Culture Documents
Weekly Progress-14 - CAP Solar Project - v0
Weekly Progress-14 - CAP Solar Project - v0
Weekly Progress-14 - CAP Solar Project - v0
NINDY FEBRIANI ANDRI WAHYUDI SINGGIH KURNIAWAN
STATUS CODE : A = Issued for Approval – B = Approved for design/issued for design
CONFIDENTIAL
Prepared by:
PT SELARAS DAYA UTAMA (SEDAYU)
Jl. Sultan Iskandar Muda 12D, Jakarta Selatan 12240
Revision Status
CAP-1901-WP-14
0 A
WEEKLY PROGRESS DOC NO : CAP-1901-WP-14
PERIOD: Sept 2 – 8, 2019
REV :0
CAP SOLAR PROJECT 750kWp
PAGE : 2 of 18
TABLE OF CONTENTS
3. ENGINEERING ACTIVITIES
Not Approve Approved as Not
Submitte
No Master Document List Submitte d (%) Noted Approved
d
d (%) (%)
(%)
(%)
1. Civil Engineering 100 - 100 - -
For more details on the status of master document list, please refer to Appendix 2.
4. QA/QC ACTIVITIES
- Technical Drawing Revision
- Project Management & Operation Revision
WEEKLY PROGRESS DOC NO : CAP-1901-WP-14
PERIOD: Sept 2 – 8, 2019
REV :0
CAP SOLAR PROJECT 750kWp
PAGE : 10 of 18
5. MATERIAL DELIVERY
N
Material Description Status ETD ETA
o
1. Solar Module 44 pallet On Project Site 24 June 2019 25 June 2019
2. Mounting System On Project Site 13 June 2019 14 June 2019
3. Inverter On Project Site 4 July 2019 5 July 2019
4. Solar Cable On Project Site 20 June 2019 21 June 2019
5. Cable Tray On Project Site 20 June 2019 21 June 2019
6. Inverter Shelter On Project Site 11 July 2019 12 July 2019
AC Distribution Board
7. On Project Site 19 July 2019 20 July 2019
& LV Switchgear
6. CONSTRUCTION ACTIVITIES
PE Warehouse (PV Array Side)
- Housekeeping
- Surveyed for placement of water tank positions
- Installation of safetyline permanent
HSE & Fire Station Building
- Performance test of PV system and inverter
- Installation of fences
- Installation of ethernet (LAN)
8. WORK DOCUMENTATION
8.1 FRONT OF SHE OFFICER
Installation of fences
8.3 Performance Test (more details on Appendix 7 – Internal Test and Commissioning Report)