Professional Documents
Culture Documents
Fema 356
Fema 356
Fema 356
1. Rehabilitation requirement
2. General Requirement
3. Analysis Procedure
By:- Binaya Jamarkattel
Roll No :-005
1. Rehabilitation Requirements
1.1 Scope
1.2 Design Basis
1.3 Seismic Rehabilitation Process
1.4 Rehabilitation Objectives
1.5 Target Building Performance levels
1.6 Seismic Hazard
1. Rehabilitation Requirement
1.1 Why we need Rehabilitation?
• Specifies nationally applicable provisions for the rehabilitation of
buildings to improve seismic performance.
• For selecting a rehabilitation objectives and the rehabilitation
process.
1.2 Design Basis
• Provisions of this standards are based on ‘Performance based design
methodology’.
• FEMA 356 is based on FEMA 273 guidelines with limited material
taken from FEMA 274.
• FEMA 356 takes references to many other reports:-
1. FEMA 222A and FEMA 223A – Provision for seismic regulation of new buildings.
2. FEMA 302 and 303 -
3. FEMA 237 – Development of guidelines for rehabilitation of buildings
4. FEMA 172 – NEHRP handbook of techniques for the seismic rehab of existing building
5. FEMA 178 -
6. FEMA 156 and 157- typical cost for seismic rehabilitation of existing building
7. FEMA 275 – planning for seismic rehabilitation: societal issues
8. FEMA 276 – Guidelines for seismic rehabilitation of buildings
1.3 Seismic Rehabilitation Process
• Review Initial Considerations
• Select Rehabilitation Objective
• Obtain As- Built Information
• Select Rehabilitation Method
• Perform Rehabilitation Design
• Verify Rehabilitation Design
1. Redesign Unacceptable Rehabilitation
2. Prepare Construction Documents of Acceptable Rehabilitation
1.4 Rehabilitation Objectives
1. Basic Safety objective
2. Enhanced Rehabilitation Objectives
3. Limited Rehabilitation Objectives
Reduced Rehabilitation Objective
Partial Rehabilitation Objective
1.5 Target Building Performance level
1.5.1 Structural Performance Level and ranges
Collapse Prevention(S-5)
Not Considered(S-6)
1.5 Target Building Performance level
1.5.2 Non-Structural Performance Level and ranges
Immediate
Hazard reduced(N-D)
Occupancy (N-B)
Life Safety (N-C)
1.5 Target Building Performance level
1.5.3 Designation of Target Building Performance Level
Higher Performance
Less loss
Operational (1-A) Very Little Damage (S1+NA)
Immediate
Repairs are minor (S1+NB)
Occupancy (1-B)
Collapse Prevention
The building remains standing, but only
(5-E) Lower Performance
barely; any other damage or loss is
acceptable (S5+NE) more loss
2. General Requirements
2.1 Scope
This chapter deals with the general requirements for:-
• Data collection
• Analysis Procedures
• Methodology
• Strategies
for the design of seismic rehabilitation projects.
2.2 As-Built Information
• Includes configuration of the structural system, types, detailing,
connectivity, material strength and condition of structural elements.
Global Structural
Mass reduction Strategies Strengthening
Where,
Fpx=diaphragm inertial force
Fi = Lateral load applied at floor level I
wi= Portion of the effective seismic weight
3.3 Analysis Procedures
3.3.2 Linear Dynamic Procedure
Basis of the procedure
Modeling and analysis considerations
• Ground motion characterization
Response Spectrum, Site-specific response spectrum, Ground acc. Time history
• Response Spectrum Method
-
• Time History Method
-
Determination of Forces and Deformations.
• Modification of Demands
• Diaphragms
3.3 Analysis Procedures
3.3.3 Non-Linear Static Procedure
Basis of the procedure
Modeling and analysis considerations
• Control Node Displacement
-
• Lateral load Displacement
-
• Idealized Force-Displacement Curve
• Period Determination
Ti= Elastic fundamental Period (in Sec)
Ki= Elastic lateral stiffness of the building in the direction
under consideration
Contd…. Determinations of Forces and Deformations
• General
• Target displacement
Target displacement at each floor level is calculated as,
Where,
C0= Modification factor to relate spectral displacement of equivalent SDOF
C1 = Modification factor to relate expected max inelastic displacement to
displacements calculated for linear elastic response
Te = Eff. Fundamental period of the building
TS = Characteristic period of the response spectrum
R = ratio of elastic strength demand to calculated yield strength coefficient.
3.4 Acceptance Criteria
1. Linear Procedure
Design Forces and Deformations
Deformation-Controlled Actions Force-Controlled Actions
Contd..
1. Linear Procedure
Acceptance criteria for linear procedure
Deformation-Controlled Actions Force-Controlled Actions
Contd..
2. Non- Linear Procedure
Acceptance criteria for non-linear procedure
Deformation-Controlled Actions
Forced controlled actions
Thank You!
FEMA 356
(Federal Emergency Management Agency)
• Bearing capacity qc
qc=3qallow
• For deep foundation
Qc=3Qallow
• Alternatively, for any foundation (deep or shallow foundation)
qc or Qc = 1.5 QG
Where,
QG= Gravity load action
Qallow= Allowable Vertical capacity (dead+live load)
qallow= Allowable bearing pressure (dead+live load)
4.5 Seismic Earth Pressure
4.6 Foundation Rehabilitation
• Soil Material Improvements
• Shallow Foundation Rehabilitation
Addition of new isolated footing
Enlarge the existing footing
Increase bearing capacity
Mitigation of differential lateral displacement
• Deep Foundation Rehabilitation
Steel
• Scope : Rehabilitation of Steel lateral-force-resisting element
• Historical Information: Available construction documents and as-built
information.
• Material Properties and Condition Assessment:
1. Properties of in place materials and components:
o Material Properties
o Component Properties
o Test Method to quantify properties
o Minimum number of tests
o Default properties
Steel
• Scope : Rehabilitation of Steel lateral-force-resisting element
• Historical Information: Available construction documents and as-built
information.
• Material Properties and Condition Assessment:
1. Properties of in place materials and components:
o Material Properties
o Component Properties
o Test Method to quantify properties
o Minimum number of tests
o Default properties
2. Condition Assessment
• Examination of component
• Configuration of structural element
• Identification of non-structural component
• Characterization of soil and foundation
• Identification of adjacent building
Procedure
• If detailed design drawings exist, at least one connection of each
connection type shall be exposed.
• In the absence of construction drawings, at least three primary
connections of each connection type shall be exposed.
Steel Moment Frames
1. Fully Restrained Moment Frames
o Stiffness
Linear static and dynamic Procedure
Axial Area and Shear area Moment Of Inertia Panel Zone Modeling Joint Modeling Connections
* Acceptance Criteria
• Beams:
Acceptance Criteria………………… Contd
• Columns:
Rehabilitation Measures
• Strength of the links may be increased by adding cover plates to the
beam flanges, stiffeners to the web, changing braces configuration
Steel Plate Shear Walls
• General: develops its seismic resistance through shear stress in the
plate wall,
used for Immediate Occupancy and operation of a facility is
mandatory after a large earthquake.
• Stiffness:
• Acceptance Criteria :
• Rehabilitation Measures:
Addition of Stiffeners, encasement in concrete, or addition of
concrete or steel shear walls.
Steel Frame with Infills
• General:
partial or complete infill of reinforced concrete or unreinforced
masonary
Steel Frame with Infills………………….. Contd
• Acceptance Criteria
• Rehabilitation:
addition of stiffeners, encasement in concrete, or the addition of
concrete or steel plate shear walls.
Diaphragms
a) Bare Metal deck Diaphragms: usually used for roofs where, very light gravity loads imposed
• Linear and Non-linear static Procedures
• Strength
• Acceptance Criteria
• Rehabilitation Measures: Adding Shear Connectors, Adding new steel plates to existing frame
components, Adding puddle welds
b) Metal Deck Diaphragms with Structural Concrete Topping : usually used for floor and roofs,
where there are typical floor gravity loads.
• Stiffness: Linear Procedures, Nonlinear Procedures
• Strength
• Acceptance Criteria: Connection capacity of connection should be considered deformed
controlled
• Rehabilitation Measures: Adding Shear Connectors, Adding new steel plates to existing frame
components, Adding diagonal steel bracing
Diaphragms……………………………. Contd
C) Metal Deck Diaphragms with Nonstructural Concrete Topping
d) Horizontal Steel Bracing (Steel Truss Diaphragms)
e) Archaic Diaphragms: Consisting of Shallow brick arches
f) Chord and Collector Elements: reinforcing acts as the chord or
collector, load transfer occurs through bond between the reinforcing
bars and the concrete.
Steel Pile Foundations
• General: wide flange shape or structural tubes , with or without
concrete infill
• Stiffness
• Strength: Flexural demand shall be calculated
• Acceptance Criteria: Incorporated with FEMA 274
• Rehabilitation Measures: driving additional piles near existing
groups, adding a new pile cap to increase stiffness, In most cases, it is
not possible to rehabilitate the existing piles.
Cast and Wrought Iron
• General:
• Stiffness:
• Strength and Acceptance Criteria:
Concrete
1. Scope: Techniques for repair of earthquake-damaged concrete
components are not included in this standard. FEMA 306, FEMA 307, and
FEMA 308
2. Material Properties Based on Historical Information:
Prepared By:
Kalyan Adhikari
MSEQE008
Masonry
• Strength
URM walls Out-of-Plane
• Stiffness – neglected
• Strength – treatment of veneer
• Acceptance Criteria – table 7-5
Condition Assessment
• General
• Scope and Procedure
• Basis for Mathematical Building Model
Knowledge Factor
General Assumptions and Requirements
Stiffness
Strength and Acceptance Criteria
Connection Requirements
Rehabilitation Measures
Wood and Light Frame Shear Walls
Types of Wood Frame Shear walls
• Existing- Single layer horizontal sheathing, Diagonal lumber sheathing,
Vertical wood sliding, Wood sliding over horizontal and diagonal
sheathing, panel sheathing, stucco on studs, Gypsum plaster on wood
lath and gypsum lath, etc.
• Enhanced- Wood structural panel sheathing added to unfinished stud
walls, overlay of existing shear walls, added under existing wall covering
• New
Types of Light Gage Metal Frame Shear Walls
• Existing- Plaster on metal Lath, Gypsum Wallboard, shuttering
• Enhanced
Single Layer Horizontal Lumber Sheathing or Sliding
Shear Walls
• Stiffness
• Strength
• Acceptance Criteria
• Connections
Diagonal Lumber Sheathing Shear Walls
Vertical Wood Sliding Shear Walls
Wood Sliding Over Horizontal Sheathing Shear Walls
Wood Siding Over Diagonal Sheathing
Wood Structural Panel Sheathing
Wood Diaphragms
Types Of Wood Diaphragms
• Existing- Single Straights Sheathing, Double Straight Sheathing,
Single Diagonal sheathing, Diagonal Sheathing with Straight
Sheathing, Double Diagonal Sheathing, Wood Structural Panel
Sheathing, Braced Horizontal Diaphragms
• Enhanced- Wood Structural Panel Overlays on Straight or Diagonal
Sheathing, on Existing wood structural analysis, increased
attachment
• New- New wood structural panel sheathing, New single diagonal
sheathing, new double diagonal sheathing, new braced horizontal
diaphragms
Single Straight Sheathing
Wood Foundations
Types- Wood Pilings, Wood footings, Pole Structures
Analysis, Strength, and Acceptance Criteria
Rehabilitation Measures
• Non-Linear Models
• Dynamic
Presented By:
Er. Girijesh Prasad Sah
M.Sc. in Earthquake Engineering 2076 Batch
Roll No:- THA076MSEQE007
Simplified RehabilItation
“Simplified Rehabilitation” reflects a level of analysis and design that
o Achieves the life safety performance level for the Basic safety
earthquake(BSE) earthquake hazard level, but does not
necessarily achieve the Basic Safety Objective(BSO).
Building Type 8—Concrete Moment Frames(C1)
Repair involves the repair of any damaged parts or members of the component to enable
the component to meet its acceptance criteria; for example, some corroded attachments for a
precast concrete cladding system might be repaired and replaced without removing or
replacing the entire panel system.
4.Bracing
Bracing involves the addition of members and attachments that brace the component
internally or to the building structure. A suspended ceiling system might be rehabilitated
by the addition of diagonal wire bracing and vertical compression struts.
5.Attachment
Attachment refers to methods that are primarily mechanical, such as bolting, by which
nonstructural components are attached to the structure or other supporting components.
Typical attachments are the bolting of items of mechanical equipment to a reinforced
concrete floor or base. Supports and attachments for mechanical and electrical equipment
should be designed according to good engineering principles.
Furnishings and Interior Equipment(Storage Racks): Definition,
Behavior, and Acceptance Criteria
Definition and Scope
Storage racks are usually constructed of metal. Storage racks are generally
purchased as proprietary systems installed by a tenant and are often not under
the direct control of the building owner. Thus, they are usually not part of the
construction contract, and often have no foundation or foundation attachment.
However, they are often permanently installed, and their size and loaded weight
make them an important hazard to either life, property, or the surrounding
structure. Storage racks in excess of four feet in height located in occupied
locations shall be considered when the Life Safety Nonstructural Performance
Level is selected.
Component Behavior and Rehabilitation Methods
Storage racks may fail internally—through inadequate bracing or moment-resisting
capacity—or externally, by overturning caused by absence or failure of foundation
attachments.