4 M.s. bars
12 mm ……………………………….. 29 t
10 mm ……………………………….. 14 t
8 mm ……………………………….. 15 t
A) Materials……………………………….. 1200.00
B) Labour………………………………….. 822.00
Rate per Rft for 10’-0” ht wall ……….. 2022.00 Rft
( A ) MATERIALS
__________________________________________________________________________________
Item Item Measurement Quantity
No .
1 M.s. bars
Footing 2 x 9 x 1.50 x 0.62 16.74
Column 8 x 4.80 x 0.89 34.17
Beam 6 x 2.70 x 0.89 14.41
Ring 35 x 1.40 x 0.39 19.11
Coping 4 x 2.50 x 0.62 6.20
Ring 13 x 1.00 x 0.39 5.07
95.70 @ 32/- . . . . . 3062.00
2 Cement
P.C.C. 1.50 x 1.50 x 0.10 x 3.50 0.787 bags.
R.C.C. 1.20 x 1.20 x 0.15 0.216 cum.
Column 5.00 x 0.30 x 0.30 0.450 cum.
Beam 2.40 x 0.30 x 0.30 0.216 cum.
Coping 2.40 x 0.30 x 0.10 0.072 cum.
0.954 bags
3 Metal ¾”
P.C.C. 1.50 x 1.50 x 0.10 0.225
R.C.C. Footing 1.20 x 1.20 x 0.15 0.216
Column 4.50 x 0.30 x 0.30 0.405
Beam 2.40 x 0.30 x 0.30 0.216
Coping 2.40 x 0.30 x 0.10 0.072
1.134 cum x 880/-… 998.00
4 Sand
P.C.C. 0.225 cum x 0.42 0.094
R.C.C. 0.909 cum x 0.42 0.382
Brick wall 1.350 cum x 0.27 0.365
Plaster 16.20 sqm x 0.0276 0.447
1.288 cum @ 882/- ...1136.00
( B ) LABOUR RATE
__________________________________________________________________________________
Item Item Measurement Quantity /Rate Amount
No .
3 R.C.C.
Footing 4’-0” x 4’-0” 16 sqft
Column 15 Rft
Beam 8 Rft
Coping 8 Rft
47 Rft @ 20/- 940.00
6 Plaster
Wall 2 x 8’-0” x 10’-0” 160 sqft
Patta 4 x 8’-0” 32 sqft
6 x 8’-0” 48 sqft
240 sqft @ 14/-
3360.00
7313.00
Discount 10% ………………………………….( - ) 731.00
For 8’-0” Length ………………………….……….. 6582.00
Per ft length………………………………...Rs. 822/- per Rft
Per sqft …..………………………………...Rs. 82/- per sqft