Requirement of Materials Mandir Compound Wall ( Excluding Gate )

1 Cement ……………………………….. 3500 bags.

2 Sand ……………………………….. 28000 cuft

3 Metal ¾” ………………………………. 25000 cuft

4 M.s. bars
12 mm ……………………………….. 29 t
10 mm ……………………………….. 14 t
8 mm ……………………………….. 15 t

5 Bricks ……………………………….. 1,40,000 Nos.


Estimate for compound wall for one panel of 2.40 m.

Rate per Rft

A) Materials……………………………….. 1200.00
B) Labour………………………………….. 822.00
Rate per Rft for 10’-0” ht wall ……….. 2022.00 Rft

Costing For Mandir Compound

1 Front ( Excluding Gate ) 470 Rft @ 2022/- Rs. 9,50,340/-


2 North side 450 Rft @ 2022/- Rs. 9,09,900/-
3 South side 543 Rft @ 2022/- Rs.10,97,946/-
Rs.29,58,186/-
Architect’s Fees ………………. 3.15% Rs. 93,182/-
Contingencies ……………….. 2% Rs. 59,163/-
Rs.31,10,531/-

Costing For Bungalow side

1 North side 640 Rft @ 2022/- Rs.12,94,080/-


2 South side 568 Rft @ 2022/- Rs.11,48,496/-
3 East side 210 Rft @ 2022/- Rs. 4,24,620/-
Rs.28,67,196/-
Architect’s Fees ………………. 3.15% Rs. 90,316/-
Contingencies ……………….. 2% Rs. 57,344/-
Rs.30,14,856/-
Estimate for compound wall for one panel of 2.40 m.

( A ) MATERIALS
__________________________________________________________________________________
Item Item Measurement Quantity
No .

1 M.s. bars
Footing 2 x 9 x 1.50 x 0.62 16.74
Column 8 x 4.80 x 0.89 34.17
Beam 6 x 2.70 x 0.89 14.41
Ring 35 x 1.40 x 0.39 19.11
Coping 4 x 2.50 x 0.62 6.20
Ring 13 x 1.00 x 0.39 5.07
95.70 @ 32/- . . . . . 3062.00
2 Cement
P.C.C. 1.50 x 1.50 x 0.10 x 3.50 0.787 bags.
R.C.C. 1.20 x 1.20 x 0.15 0.216 cum.
Column 5.00 x 0.30 x 0.30 0.450 cum.
Beam 2.40 x 0.30 x 0.30 0.216 cum.
Coping 2.40 x 0.30 x 0.10 0.072 cum.
0.954 bags

Brick wall 2.40 x 0.30 x 0.30 0.216


2.40 x 0.23 x 2.40 1.324
1.540 x 1.35 = 2.08 bags.

Plaster 2 x 2.40 x 3.00 14.40 Sqm


2.40 x 0.30 0.72 sqm
6 x 2.40 x 0.075 1.08 sqm
16.20 x 0.16 = 2.59 bags.
5.62 bags @ 300/- ………… 1687.00

3 Metal ¾”
P.C.C. 1.50 x 1.50 x 0.10 0.225
R.C.C. Footing 1.20 x 1.20 x 0.15 0.216
Column 4.50 x 0.30 x 0.30 0.405
Beam 2.40 x 0.30 x 0.30 0.216
Coping 2.40 x 0.30 x 0.10 0.072
1.134 cum x 880/-… 998.00

4 Sand
P.C.C. 0.225 cum x 0.42 0.094
R.C.C. 0.909 cum x 0.42 0.382
Brick wall 1.350 cum x 0.27 0.365
Plaster 16.20 sqm x 0.0276 0.447
1.288 cum @ 882/- ...1136.00

5 Bricks 1.54 cum x 500 770 Nos. @ 3.50 ….2695.00


9578.00
Rate per R.ft. …………………… 1200/- per R.ft.
Estimate for compound wall for one panel of 2.40 m.

( B ) LABOUR RATE
__________________________________________________________________________________
Item Item Measurement Quantity /Rate Amount
No .

1 Excavation 5’-0” x 5’-0” x 4’-0” 100 cuft @ 11/- 1100.00

2 P.C.C. 5’-0” x 5’-0” 25 sqft @ 8/- 200.00

3 R.C.C.
Footing 4’-0” x 4’-0” 16 sqft
Column 15 Rft
Beam 8 Rft
Coping 8 Rft
47 Rft @ 20/- 940.00

4 M.s. bar binding as above 47 Rft @ 15/- 705.00

5 Brick masonry 8’-0” x 9’-0” 72 sqft @ 14/- 1008.00

6 Plaster
Wall 2 x 8’-0” x 10’-0” 160 sqft
Patta 4 x 8’-0” 32 sqft
6 x 8’-0” 48 sqft
240 sqft @ 14/-
3360.00
7313.00
Discount 10% ………………………………….( - ) 731.00
For 8’-0” Length ………………………….……….. 6582.00
Per ft length………………………………...Rs. 822/- per Rft
Per sqft …..………………………………...Rs. 82/- per sqft