Grading Policy
Mid Term = 20 %
Final Term = 60 %
Class participation = 20 %
Assignments = 08 % (3 Assignments)
Quizzes = 12 % (3 Quizzes)
Assignments & Quizzes Schedule
Lectures Availability
www.drqaisarali.com
2
Department of Civil Engineering, University of Engineering and Technology Peshawar
Lecture-01
Introduction
By: Prof. Dr. Qaisar Ali
Civil Engineering Department
UET Peshawar
www.drqaisarali.com
Topics
Examples
3
Department of Civil Engineering, University of Engineering and Technology Peshawar
Objectives
4
Department of Civil Engineering, University of Engineering and Technology Peshawar
Applied Load
Beam will resist the (Demand)
5
Department of Civil Engineering, University of Engineering and Technology Peshawar
50 Tons
Concrete pad
12″
12″
6
Department of Civil Engineering, University of Engineering and Technology Peshawar
50 Tons
12″
12″
Prof. Dr. Qaisar Ali CE-416: Reinforced Concrete Design – II 14
7
Department of Civil Engineering, University of Engineering and Technology Peshawar
iii. 1000/ 765.27 = 1.3 (Capacity is 1.3 times greater than Demand)
iv. 2000/ 765.27 = 2.6 (Capacity is 2.6 times greater than Demand)
8
Department of Civil Engineering, University of Engineering and Technology Peshawar
Doing both.
9
Department of Civil Engineering, University of Engineering and Technology Peshawar
The factors of 1.2 and 1.6 used by ACI 318-14 (Building code
requirements for structural concrete, American Concrete Institute
committee 318) as load amplification factors for dead load and live
load respectively are based on probability based research studies.
10
Department of Civil Engineering, University of Engineering and Technology Peshawar
200 Tons
Concrete pad
12″
12″
Prof. Dr. Qaisar Ali CE-416: Reinforced Concrete Design – II 22
11
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.3
Solution:
Demand in the form of load (P) = 200 Tons = 200 × 2204/1000 = 440.8 kips
Demand in the form of load effects (Stress) = (200 × 2204)/ (12 × 12)
Capacity in the form of strength = 1.5 ksi (less than the demand of 3.0611 ksi).
Increase the strength by using some other material; using high strength concrete,
steel or other material; economical is to use concrete and steel combine.
Example 1.3
Solution:
Let us assume that we want to use steel bar reinforcement of yield strength fy = 40 ksi. Then
capacity to be provided combinedly by both materials should be at least equal to the
demand. And let us follow the Working Stress approach, then:
Therefore,
As = 11.24 in2 (Think on how to provide this much area of steel? This is how compression
members are designed against axial loading).
12
Department of Civil Engineering, University of Engineering and Technology Peshawar
2.0 kip/ft
20″
20′-0″
12″
Beam section
Prof. Dr. Qaisar Ali CE-416: Reinforced Concrete Design – II 25
Therefore, M = ƒI/y
13
Department of Civil Engineering, University of Engineering and Technology Peshawar
ƒ =?
U = 1.4D (5.3.1a) D
14
Department of Civil Engineering, University of Engineering and Technology Peshawar
For ΦMn = Mu
15
Department of Civil Engineering, University of Engineering and Technology Peshawar
Where,
εu = 0.003
16
Department of Civil Engineering, University of Engineering and Technology Peshawar
smax = Avfy/(50bw),
d/2
24 inches
17
Department of Civil Engineering, University of Engineering and Technology Peshawar
ΦVs = Vu – ΦVc
ΦAvfyd/s = Vu – ΦVc
s = ΦAvfyd/(Vu – ΦVc)
18
Department of Civil Engineering, University of Engineering and Technology Peshawar
“Vu” is the shear force at distance “d” from the face of the support.
“ΦVc” and “ΦVc/2” are plotted on shear force diagram.
Prof. Dr. Qaisar Ali CE-416: Reinforced Concrete Design – II 37
Example 1.5
20′-0″
19
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
14″
20′-0″
Beam section
Prof. Dr. Qaisar Ali CE-416: Reinforced Concrete Design – II 39
Example 1.5
20
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
BMD
Example 1.5
For ΦMn = Mu
ΦAsfy(d – a/2) = Mu
21
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
First Trial:
Assume a = 4″
a = Asfy/ (0.85fc′bw)
Example 1.5
Close enough to the previous value of “a” so that As = 4.37 in2 O.K
22
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
200/40000 = 0.005
Example 1.5
Flexural and Shear Design of Beam as per ACI:
Solution:
Step No. 04: Design.
Design for flexure:
εt = Net tensile strain (ACI 21.2.2). When εt = 0.005, Φ = 0.9 for flexural design.
23
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
Bar Placement: 10 #6 bars will provide 4.40 in2 of steel area which is
slightly greater than required.
Example 1.5
For Curtailment and bent up bar details refer to the following figures
provided at the end of this lecture:
Graph A2 and A3 in “Appendix A” of Nilson 13th Ed.
Figure 5.15 of chapter 5 in Nilson 13th Ed.
24
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
Vu = 33.74 kips
Example 1.5
25
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
Example 1.5
Other checks:
26
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
Other checks:
Example 1.5
Flexural and Shear Design of Beam as per ACI:
Step 05: Drafting (Shear Reinforcement)
3.9504 kip/ft
33.74 kips
39.50
kips 20.13 kips
10.06 kips
x1
x2
x1 = (10.06)(10)/(39.50) ≈ 2.5 ft
x2 = (20.13)(10)/(39.50) ≈ 5.0 ft
Note:
As Sd ≈ Smax we will provide sd up to 7.5 ft from
the face of support. Beyond this point, theoretically
no reinforcement is required, however, we will
provide #3 2-legged stirrups @ 12 in c/c.
27
Department of Civil Engineering, University of Engineering and Technology Peshawar
Example 1.5
Flexural and Shear Design of Beam as per ACI:
Step 05: Drafting (Flexural Reinforcement)
3D Model
SketchUp Model
28
Department of Civil Engineering, University of Engineering and Technology Peshawar
Summary
Load Combinations
Summary
29
Department of Civil Engineering, University of Engineering and Technology Peshawar
References
ACI 318-14
Appendix
Exact curtailments lengths for simply supported positive moments (to be measured from face of the support)
30
Department of Civil Engineering, University of Engineering and Technology Peshawar
Appendix
L1 L1 L2 L2
4 3 3 3
L1 L2 L2
8 8 8
L1 L2
Figure: Cutoff for bars in approximately equal spans with uniformly distributed
loads for 50% curtailment