Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Running Procedure

VAGT® Rev.:4

voestalpine Tubulars GmbH & Co KG


www.voestalpine.com/tubulars
VAGT®
RS-RP-VAGT-1 Rev.4: Updated Tab.2 on page 11 showing Inspection length for
visual inspection about perfect threads as shown in sketch on page 10;

voestalpine Tubulars GmbH & Co KG


www.voestalpine.com/tubulars
Table of Content
 Table of Content
 VAGT®
 Technical data sheet
 Running and handling
 DryTec®
 Visual inspection and field repair
 Transportation, handling and storage

This document contains the recommended practices for the installation of voestalpine tubulars proprietary connections.
This is not comprehensive and is meant only as general guidance, based on best industry practices.

The user assumes all responsibility for the safe and effective implementation of these practices. Further, it is the user’s
responsibility to provide competent and knowledgeable personnel, as well as appropriate and well maintained equipment.

voestalpine Tubulars GmbH & Co KG


3 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
VAGT ®
 VAGT® is field approved by millions of successfully installed feet

 Gas tight thread connection

 Metal to Metal Seal – The high contact pressure in the seal area
ensures 100% gas tightness

Tubing design Casing design


1.9 – 4.5 inches 5-7 inches
 Internal Shoulder – Reinforces the contact pressure in the seal
30° seal taper 10% seal taper area and acts as a positive make-up stop.
20° shoulder 15° shoulder
1.9“ to 2 7/8“ 8 5 threads per
threads per inch inch  Improved Buttress Thread design – The thread design ensures a
3 ½“ to 4 ½“ 6 10° stabbing
threads per inch flank high stress performance and allows easy make-up even under
3° load flank severe condition.

 Smooth Internal Profile – Minimizes turbulence and also provides


good conditions for internal plastic coating.

voestalpine Tubulars GmbH & Co KG


4 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
Technical data sheet
Dimensions and torque values will be provided
through our datasheet generator:
http://www.voestalpine.com/tubulars/en ->
Customer service -> Datasheet generator

 Torques are valid for dope with friction


factor 1 at room temperature
 Max. torque: optimum +15%
 Min. torque: optimum -10%
 Torques for special clearance couplings on
request
 Special clearance & 20° beveled couplings:
slip type elevator strongly recommended
due to lower load on coupling face

voestalpine Tubulars GmbH & Co KG


5 | March 5, 2020 | Running Procedure – VAGT® – Rev.:4
Running and handling
 Equipment  Prevent corrosion
 Elevator  Drifting
 If collar type – smooth bearing face  Drift on pipe rack – start from box end
 If slip type – clean and sharp dies  Visual inspection
 Derrick  Check each pipe (see page 11)
 Blocks are centered over rotary table  Apply clean and dry protectors
 Power tong  Pipe tally
Correct size and calibrated

 Torque-turn monitoring system
 Running
 Lifting and stabbing
 Pipe handling  Remove pin protectors just before stabbing
 Thread protectors in place
 Clean connection with compressed air
 No hooks to lift pipes
 Check seal area for damages
 No rough handling
 Apply thread compound – pin & box
 Use proper racks
 Preparation Box API-modified running compound with
known friction factor between 0,8 ans 1,2 is
 Cleaning
recommended. Dope shall be applied
 Remove and clean protectors uniform on pin and box (on pin including
 Clean pin and box seal and shoulder)
 Diesel and oil-based products are not recommended as Pin
cleaning solvent
voestalpine Tubulars GmbH & Co KG
6 | March 5, 2020 | Running Procedure – VAGT® – Rev.:4
Running and handling
 Use a stabbing guide  Acceptance
 Lower carefully  Final torque between maximum and minimum
 Maintain good alignment  Use correct friction factor of dope
Friction factor might be affected by extreme
 Make-up 
temperatures.
 Start slowly in high gear with open back-up  Delta torque shall be at least 30 % of actual applied
 If connection jams (torque increases immediately) torque
 Stop and release tong
 See diagram on page 8
 Disengage connection / place back-up on coupling
 Clean connection / visual inspection
 No plastic deformation
 If questionable - set aside  Increase of torque shall be reasonable uniform and
 If o.k. – stab again smooth
 If connection stabs correct
 Increase speed to spin-in (max. 20 rpm)
 Assemble until torque increase
 Stop rotation / close back-up
 Finish in low gear and with speed less than 5 rpm
 Approximately 1 to 2 turns before shouldering

voestalpine Tubulars GmbH & Co KG


7 | March 5, 2020 | Running Procedure – VAGT® – Rev.:4
Running and handling

voestalpine Tubulars GmbH & Co KG


8 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
Running and handling
 Break-out  High chrome material
 Place back up tong on coupling mill side  Handling
 Set up power tongs to low gear  Avoid metal to metal contact
 Speed shall be less than 10 rpm  Equipment
 Slowly lift the pin out of the box  Use non ferrous low marking dies
 Use weight compensator
 Handle with care / use protectors
 Use non metallic drift
 Clean all pipes  No misalignment
 Visual inspection / page 11  Make-up
 Apply appropriate dope  Start make-up by hand
 Any problems during make-up or break-out should be  Maximum assembly speed 10 rpm
 Final make-up speed max. 5 rpm
reported immediately
 Used equipment, thread compound, torques used, assembly  Thread lock compound
speed, …….  Pin
 Any questionable joint, set aside for evaluation, shall be  Thread lock compound shall be applied on the first
brought to a disposition two-thirds of the threads. No other compound on pin.
 Accepted or rejected  Box
 If rejected it must be properly marked  No thread lock compound on threads. On seal and
shoulder running compound shall be applied.

voestalpine Tubulars GmbH & Co KG


9 | March 5, 2020 | Running Procedure – VAGT® – Rev.:4
DryTec®
 For DryTec only For DryTec only
 No special equipment requested Temperature Friction factor
 Clean with compressed air ( related )
 Standard drift procedure
 Visual inspection -40°C to -15°C -40°F to +5°F 1,28
 Check each pipe (see page 11)
-15°C to +10°C +5°F to +50°F 1,13
 Apply clean and dry protectors. Always
use original protectors. +10°C to +35°C +50°F to +95°F 1,00
 No special running procedure except : No application
of dope +35°C to +60°C +95°F to +140°F 0,84
 Extreme temperature will affect friction Torque/Turn monitoring is required to properly ensure correct make-up of each
 Optimum torque at specific temperatures will be calculated connection with DryTec.
as follow : Optimum torque from data sheet ( at 20°C/68°F) x
The friction factors provided above are for guidance only and cannot represent
temperature related friction factor
all scenarios. To prevent yielding (plastic deformation), it is recommended to start
 Accessories at extreme temperatures with the minimum torque value to determine how the
job-specific conditions are affecting the make-up. If required, torques can be
 If a DryTec pin is made-up with regular box : Apply gradually increased until consistent minimum delta torque as specified is
dope on box achieved.
 If a DryTec box is made upwith a regular pin:
Make-up acceptance shall always be determined based on the criteria outlined
Apply dope on pin and box on pages 8 and 9.

voestalpine Tubulars GmbH & Co KG


10 | March 5, 2020 | Running Procedure – VAGT® – Rev.:4
Visual inspection and field repair
1 Seal
2 Shoulder
3 Cylindrical section
4 Internal bore
5 Perfect thread area
6 Non perfect thread area
7 Coupling face *

* not shown in sketch

voestalpine Tubulars GmbH & Co KG


11 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
Visual inspection and field repair
Pin
Tab.1 Tab.2
Element Area Rust Rust + Pitting Burrs Scratches Dent Inspection length
(measured from Pin End)
Remove with Minor remove with Area of visual inspection of perfect
Seal (a*) 1 Re-cut the pin N/A Re-cut the pin
abrasive fleece abrasive fleece threads

Remove with Grind to smooth surface N/A Grind to smooth surface Grind to smooth surface PIPE OD mm inch
Shoulder 2
abrasive fleece with emery paper with emery paper with file and emery paper
2 3/8 “ 20,2 0,80
Radius between Remove with Grind to smooth surface N/A Grind to smooth surface Grind to smooth surface
1->2
seal and shoulder abrasive fleece with emery paper with emery paper with file and emery paper 2 7/8 “ 27,2 1,07

Edge between N/A N/A Remove with N/A Grind to smooth surface 3 1/2 “ 36,8 1,45
2->4
shoulder and bore emery paper with file and emery paper
4 “ 42,2 1,66
Remove with Remove rust with abrasive N/A Accepted Grind to smooth surface
Cylindrical section 3
abrasive fleece fleece. Pitting is accepted. with file and emery paper 4 1/2 “ 46,6 1,83

Internal bore 4 Accepted Accepted N/A Accepted Accepted 5“ 50,9 2,00

Perfect thread Remove with Grind to smooth surface Remove with Accepted Grind to smooth surface 5 1/2 “ 52,9 2,08
5
area (b*) abrasive fleece with emery paper emery paper with file and emery paper
5 3/4 “ 54,9 2,16
Non-perfect Remove with Grind to smooth surface Accepted Accepted Grind to smooth surface
6
thread area abrasive fleece with emery paper with file and emery paper 6 5/8 “ 58,2 2,29

7“ 62,9 2,48
a* Minor pitting, dents or scratches may be accepted after approval by voestalpine Tubulars specialist
b* Up to 2 thread-turns may be imperfect if not more than ¼ of a turn is affected. If more than 2 thread-turns / or more
than a half turn in total / are affected, hand-repair may be accepted after approval by voestalpine Tubulars specialist.

Abrassive fleece : 400 / 500 (superfine)


Emery paper : 300 -400 (superfine)
voestalpine Tubulars GmbH & Co KG
12 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
Visual inspection and field repair
Box
Tab.3
Element Area Rust Rust + Pitting Burrs Scratches Dent

Seal (a*) 1 Remove with abrasive fleece Change coupling N/A Change coupling Change coupling General: The phosphated and/or
DryTec-coated surface shall not
Shoulder (a*) 2 Remove with abrasive fleece Change coupling N/A Minor accepted Change coupling
be removed excessively by hand –
Radius between
1->2
Remove with abrasive fleece
Change coupling
N/A
Minor accepted Change coupling repair (except area 3,4 and 7.
seal and shoulder
Minor removal is acceptable as it
Edge between
2->4
N/A N/A Remove with N/A
Change coupling is.
shoulder and bore emery paper

Remove with abrasive fleece


Remove rust with
N/A Accepted Heavier removal can be accepted
Cylindrical section 3 abrasive fleece. Pitting is Change coupling
accepted. after approval by voestalpine
Tubulars specialists. Phosphate
Internal bore 4 Accepted Accepted N/A Accepted Accepted
and/or corrosion protection spray
Perfect thread
5 Remove with abrasive fleece Change coupling
Remove with Accepted
Change coupling should be applied (time for drying
area (b*) emery paper
shall be given).
Minor pitting, after
Non-perfect removal of rust with Accepted Accepted
thread area
6 Remove with abrasive fleece
abrassive fleece, is
Accepted This is as well applicable for the
accaptable DryTec Pin
Coupling face 7 Accepted Accepted Accepted Accepted Accepted

a* Minor pitting, dents or scratches may be accepted after approval by voestalpine Tubulars specialist
b* Up to 4 thread-turns may be imperfect if not more than ½ of a turn is affected. If more than 4 thread-turns /
or more than 2 in total are affected, hand-repair may be accepted after approval by voestalpine Tubulars
specialist
voestalpine Tubulars GmbH & Co KG
13 | March 5, 2020 | Running Procedure – VAGT® - Rev.:4
Transportation, Handling and Storage
(as recommended by API 5C1)

 Transportation
 Load pipe on bolsters and tie down with suitable chains or
straps at the bolsters
 Load pipe with all couplings on the same end of the truck
 Do not overload the truck

 Handling
 Before loading or unloading thread protectors should be in
place
 Do not unload pipe by dropping
 Avoid rough handling which might damage the threads or the
body of the pipe
 When rolling pipe, on the rack, keep pipe parallel and do not
allow pipe to strike the ends
 Do not use hooks to lift pipes

voestalpine Tubulars GmbH & Co KG


14 | March 5, 2020 | Running Procedure - VAGT® – Rev.:4
Transportation, Handling and Storage
 Storage
 At least every six months some of the pin and box thread
protectors should be removed at random and the threads
should be checked for corrosion
 First tier of pipes should be no less than 1,5 feet’s (approximately
0,5m) from the ground 0,5m
 Pipes should properly rest on supports to prevent bending and
damages
 Between the successive layers of pipes you should provide
wooden strips as separators
 Do not stack pipes higher than three meters
 Only use thread protectors that correspond to the threaded
pin/box ends
 Do not mix different pipes in the stack
 All protectors must be secured and should have no damage.
DryTec® protectors shall be checked for proper tightness (hand
tight) when put pipes into storage and at least each 3 months
during storage

voestalpine Tubulars GmbH & Co KG


15 | March 5, 2020 | Running Procedure - VAGT® – Rev.:4
Thank you

voestalpine Tubulars GmbH & Co KG


www.voestalpine.com/tubulars

You might also like