WMS For Installation of Panel BRD & Capacitor BNK
WMS For Installation of Panel BRD & Capacitor BNK
Method Statement
For
TABLE OF CONTENTS
2. REFERENCES ------------------------------------------------------------------------------------------ 02
3. DEFINITIONS ------------------------------------------------------------------------------------- 02
4. RESPONSIBILITY -------------------------------------------------------------------------------------- 02
7. WORKFORCE ------------------------------------------------------------------------------------- 04
1
PROJECT: KAP-5
1. SCOPE OF WORK:
• This “method statement” covers the nature and type of work for the installation of panel boards
and capacitor bank by CRCC to King Abdullah Bib Abdul-Aziz Project (KAP5).
• This method statement gives guidelines contained herein so as to ensure that the job execution
complies with the requirement of the specifications and the authorities concerned and serves the
intended purpose to satisfactory level.
• This procedure is to be read in conjunction with the relevant ITP, outlining the responsibilities and
the quality verification to be performed by various parties.
2. REFERENCES:
• Contractor’s Quality Control Plan Set for Contract
• Project Specification (7 specifications + MTR).
• Project Health and Safety Plan.
• Approved Drawings.
3. DEFINITIONS:
• MOI: Ministry of interior (Client)
• GIJV: Gesbau Ital 2 Ace Joint Venture (Engineer)
• CRCC: China Railways Construction Corporation (Main Contractor)
• QA/QC: Quality Assurance and Quality Control
• ITP: Inspection and Test Plan
• IR: Inspection Request
• RFI: Request for Information
4. RESPONSIBILITIES:
4.1 Project Manager:
The project manager will have full authority and overall responsibility to manage, supervise. He
will control the works and will have direct responsibility for ensuring safe working practices and
compliance with regulatory authority’s requirements. He will coordinate with the engineers and
the employer representative for execution of the contract scope of works. Implement the project
quality systems to the satisfaction of the project requirements. Review changes and variations to
evaluate impact of those on time and schedule.
2
PROJECT: KAP-5
3
PROJECT: KAP-5
work activities, carrying out inspections and reporting to the CRCC safety department and
carrying out accident and incident investigations.
4.7 Store Controller:
• Review the documents of approved material submittal and verify the items with the packing
list for any shortage or description from approved.
• Responsible for proper storage as per site requirement.
• Verify all documents are forwarded with the item as per the requirement of purchase order.
• The unapproved material shall not be received and stored in store.
6. PRODUCT / MATERIAL:
• Panel Boards / Capacitor Bank and accessories.
• Cable glands.
• Terminal lugs.
7. WORKFORCE:
Construction team will ensure that manpower selected for the specified job is well trained. Tool
box talk shall be carried out before the work commences at site to the involved workers through
the supervisor and foremen in charge the work, under the directives of in charge engineer. The
work procedure and safety precautions should be clearly and concisely explained to the workers
in their own language so it is fully understood.
4
PROJECT: KAP-5
5
PROJECT: KAP-5
• Ensure adequate lighting and adequate space is provided in the working area at night time.
• Ensure that in all areas where there is a risk of falling from height preventative measures will be
taken and identify them.
• Ensure service shaft opening are provided with barricade, tape, safety nets.
• All CRCC tradesmen, operators etc. are qualified and will have licenses and their competency level
issued by CRCC.
• Access/Egress: CRCC will provide scaffoldings assembly with attached step ladder and rubberize
wheel. Platforms will be provided on top of the scaffolding assembly and circulated with tubular
railing at adequate height to protect the workers. Aluminium step ladders will be used in instances
where scaffolding assembly is not permitted in the workplace and for alignment purposes of
installation. Safety personnel should be involved in preparation and approval of scaffolding
assembly and ladders prior to use.
• Lighting Arrangements: Sufficient lighting to the workplace area shall be provided by the
experience electrician under the instruction of his supervisor/foremen. Safety personnel are
involved in the activity to maintain safety measures of temporary electrical wirings installation.
• Emergency Arrangements: In case of any injury or illness which includes electrocution, inform
the Safety Officer/First Aider for appropriate assistance. Depending upon the case the Safety
Officer will inform the relevant parties and move the patient to clinic or other arrangement
prevailing in the project.
• Housekeeping: The Supervisor has the responsibility to ensure the site is kept clean from any
debris. Any material leftovers shall be collected and put into designated disposal box. Unused
materials shall be returned to proper storage in every end of each day work.
10. ENVIRONMENT:
Any hazardous waste generated during specified work shall be segregated and disposed of properly
with support of HSE representative. Any chemical/cleaner used for the job will be kept in a safe
container to avoid spillage on the ground.
All hazardous waste details should be recorded and mentioned in Environment Register.
11. QUALITY ASSURANCE / CONTROL:
The QC Inspector has the fulltime surveillance during the activities to ensure that all works has done
as per this method statement. Any found deficiency shall be immediately corrected based on the
procedure and specification workmanship requirements. To check all necessary documents are
prepared and approved by Engineer.
6
PROJECT: KAP-5
7
PROJECT: KAP-5
• Position the panel boards or capacitor bank in the base foundation at the low voltages room or
where they supposed to be installed as per the latest revision of approved drawing.
• Appropriate lifting equipment shall be used in installation of panel boards for capacitor bank to
ensure that no damage occurs.
• The free stand panel boards or capacitor bank shall be mounted directly on the fabricated steel
frame as per approved drawing.
• Wall mounted panel board shall be fixed by using the support made of C-channel with bolts,
washers and nuts.
• Use approved size of bolt to fix the panel boards for capacitor bank and tighten bolts using nuts
and washers. Capacitor Bank shall be aligned & levelled in accordance with the approved drawing
and manufacturer’s recommendation.
• Cable connected to panel boards or capacitor bank shall be provided with proper support and
strap to ensure that the weight of the cable will not be carried by the equipment.
• All panel boards/MCCs and capacitor bank shall be connected firmly to the main earthing bar as
per approved drawing.
• Perform insulation resistance test for the complete assembly of capacitor bank and panel boards
after the installation.
Cable Termination:
• Engineer/Inspector shall ensure that identification and termination of all power supply cables are
properly tagged. The cable cores and terminal blocks shall be labeled to indicate the Inter-
connection drawings to which they are connected.
• Each terminal and connected wire or cable core shall be marked and identified with suitable and
approved ferrules in accordance with the specification and relevant wiring diagram.
• The correct size of compression type cable lugs, correct crimping dies along with correct crimping
tool shall be used to ensure effective electrical connection.