Professional Documents
Culture Documents
Rate (With Labor Cess) PER Amount: Gebar No.3 ESTIMENT Abst. 1
Rate (With Labor Cess) PER Amount: Gebar No.3 ESTIMENT Abst. 1
Palitana
in Palitana Range of Bhavnagar Division, Bhavnagar.
ABSTRACT
RATE
( With
QTY UNIT ITEM DESCRIPTION Labor
Cess ) PER AMOUNT
ITEM No. 1
Excavation for foundation upto 1.5M
Depth inlcudinng sorting out and
stacking of useful materials and
disposing off the excavated stuff upto
50M Lead. (C) Hard Murrum.
(Mechanised Efforts )
121.00 CuM (R & B SOR : Item. 04/04001C P.23) 147.00
Add 1% Labour Cess 1.47
148.47 CuM 17965.00
ITEM No. 2
Excavation for foundation upto 1.5M
Depth inlcudinng sorting out and
stacking of useful materials and
disposing off the excavated stuff upto
50M Lead. (D) Soft Rock not requireing
Blasting. ( Mechanised Efforts )
50.00 CuM (R & B SOR : Item. 04/04001D P.23 ) 151.00
Add 1% Labour Cess 1.51
152.51 CuM 7626.00
ITEM No. 3
Excavation for foundation upto 1.5 to
3.00M Depth inlcudinng sorting out and
stacking of useful materials and
disposing off the excavated stuff upto
50M Lead. (D) Soft Rocl not requiring
blasting. ( Mechanised Efforts )
36.00 CuM ( R & B SOR : Item. 04/04002D P.24 ) 164.00
Add 1% Labour Cess 1.64
165.64 CuM 5963.00
ITEM No. 4
Providing and laying cement concrete
1:4:8 (1-Cement, 4-Coarse sand, 8-
Hand broken stone aggregates 40mm
nominal size) and curing complete
excluding the cost of formwork in (A)
Foundation and Plinth. ( Upto 10 ton ).
79.00 CuM (R & B SOR : Item. 05/05004 P.32) 1987.00
Add 1% Labour Cess 19.87
2006.87 CuM 158543.00
ITEM No. 5
(ii) Uncoursed Rubble Masonary with
hard stone of approved quality in
foundations and plinth in Cement Mortar
1:5 ( 1-Cement, 5-Coarse sand )
including levelling up etc. complete.
( Upto 10 ton)
31.50 CuM (R & B SOR : Item. 07/07001B P.84 ) 1858.00
Add 1% Labour Cess 18.58
1876.58 CuM 59112.00
Gebar No.3 ESTIMENT Abst. 1
ABSTRACT
RATE
( With
QTY UNIT ITEM DESCRIPTION Labor
Cess ) PER AMOUNT
ITEM No. 6
Providing and laying Cement
Concrete 1 : 2 : 4 ( 1 Cement : 2 Coarse
Sand : 4 Graded Stone Aggregate 20
mm nominal size ) and curing
complete excluding cost of formwork
in (A) Foundation and Plinth. ( Upto 10
ton )
23.00 CuM (R & B SOR : Item. 05/05010A P.34) 3020.00
Add 1% Labour Cess 30.20
3050.20 CuM 70155.00
ITEM No. 7
Providing and laying Cement
Concrete M200 and curing complete
excluding cost of formwork and
reinforcement for Reinforced Concrete
in (A) Foundations, footings, Base of
Columns and Mass Concrete. ( Upto
10 ton )
80.00 CuM (R & B SOR : Item. 05/05024A P.43) 3536.00
Add 1% Labour Cess 35.36
3571.36 CuM 285709.00
ITEM No. 8
Filling available excavated earth
(excluding rock) in trenches plinth, side
or foundations etc. in layers not
exceeding 20cm, in depth consolidating
each disposited layer by ramming and
watering. ( Upto 10 ton )
165.00 CuM (R & B SOR : Item. 04/04006 P.26) 76.50
Add 1% Labour Cess 0.77
77.27 CuM 12750.00
ITEM No. 9
Filling plinth with sand under floors
including watering, ramming,
consolidating and dressing etc.
complete. ( Upto 10 ton )
80.00 CuM (R & B SOR : Item. 04/04007 P.26) 416.00
Add 1% Labour Cess 4.16
420.16 CuM 33613.00
ITEM No. 10
Providing and laying Cement
Concrete M200 and curing complete
excluding cost of formwork and
reinforcement for Reinforced Concrete
in (C) Slabs, landing, shelves, Balconies,
Lintels, Beams, Girders and Cantilever
upto floor two level. ( Upto 10 ton )